8.1.1
This
Waste Management Implications (WMI) is according to the Section 3.4.8 and
Appendix E1 of EIA Study Brief which specify the requirements of WMI.
8.1.2
The Project
is located on the North of Old Kai Tak Runway. The site is dissected by
existing Kai Tak Tunnel and the new Road D2. The location plan is shown in Figure
8-1-1. the
Project consists of the following buildings:
l Main
Stadium
l Public
Sports Ground, including ancillary areas such as retail area
l Indoor
Sports Centre, including ancillary areas such as retail area
l Hotel
Block, including ancillary areas such as retail area
l Office
Block, including ancillary areas such as retail area
The master layout plan of the Project is shown
in Figure 8-1-2.
8.1.3
The
scope of this study includes identifying the quantity, quality and timing of
the waste arising as a result of construction and operational activities of the
Project based on the master layout plan is shown in the construction phasing
plan, Figure 2-2 and Project programme as shown in Appendix
2A.
8.1.4
This
WMI makes references to relevant WMI of the following EIA reports:
l
Kai Tak Development (No.
AEIAR-130/2009) (KTD EIA)
8.2.1
The
criteria and guidelines for assessing waste management implications are set out
in Annex 7 and Annex 15 of the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM), respectively.
8.2.2
The
following legislation relates to the handling, treatment and disposal of wastes
in the Hong Kong SAR and has been used in assessing potential impacts:
l
Waste Disposal Ordinance (Cap. 354)
l
Waste Disposal (Chemical
Waste) (General) Regulation (Cap. 354C)
l
Land (Miscellaneous
Provisions) Ordinance (Cap. 28)
l
Public Cleansing and Prevention
of Nuisances Regulation (Cap. 132BK)
l
Waste Disposal (Charges for
Disposal of Construction Waste) Regulation (Cap. 354N)
l Dumping at Sea Ordinance (Cap. 466)
l Public
Dumps, WB TC(W) No. 2/1993
l Management
of Dredged/Excavated Sediment, ETWB TC(W) No. 34/2002
l Environmental
Management on Construction Sites, ETWB TC(W) 19/2005
l Trip
Ticket System for Disposal of Construction and Demolition Materials, DEVB TC(W)
No. 6/2010
Waste Management
8.2.3
The
Waste Disposal Ordinance (WDO) prohibits the unauthorized disposal of wastes.
Construction waste is defined as any substance, matter or thing that is
generated from construction work and abandoned, whether or not it has been
processed or stockpiled before being abandoned, but does not include any
sludge, screenings or matter removed in or generated from any desludging,
desilting or dredging works. Under the WDO, wastes can be disposed of only at
designated waste disposal facilities.
8.2.4
Under
the WDO, the Chemical Waste (General) Regulation (1992) provides regulations
for chemical waste control, and administers the possession, storage,
collection, transport and disposal of chemical wastes. The Environmental
Protection Department (EPD) has also issued a guideline document, the Code of
Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992),
which details how the Contractor should comply with the regulations on chemical
wastes.
Dredged Marine Sediment
8.2.5
The
Development Bureau Technical Circulation (Works) No. 34/2002 (ETWB TCW No.
34/2002) sets out the procedure for seeking approval to dredge / excavate
sediment and the management framework for marine disposal of dredged /
excavated sediment. This Technical Circular outlines the requirements to be
followed in assessing the classifying the sediment and explains the marine
disposal arrangement for the classified material.
Construction and Demolition (C&D) Materials
8.2.6
The
current policy related to the disposal of C&D materials is documented in
the WB TCW No. 2/93, ‘Public Dumps’. All inert C&D materials (or public fills)
that are wholly inert, namely public fill, should not be disposed of to
landfill, but taken to public filling areas, which usually form part of
reclamation schemes. The Land (Miscellaneous Provisions) Ordinance requires
that dumping licenses be obtained by individuals or companies who deliver
public fill to public filling areas. The Civil Engineering and Development
Department (CEDD) issues the licenses under delegated powers from the Director
of Lands.
8.2.7
Under
the Waste Disposal (Charges for Disposal of Construction Waste) Regulation,
enacted in January 2006, construction waste delivered to a landfill for
disposal must not contain more than 50% by weight of inert material.
Construction waste delivered to a sorting facility for disposal must contain more
than 50% by weight of inert material, and construction waste delivered to a
public fill reception facility for disposal must consist entirely of inert
material. In accordance with the DEVB TCW No. 6/2010 “Trip Ticket System for
Disposal of Construction and Demolition Materials”, for all contracts that are
expected to generate inert C&D materials (e.g. soil, broken rock, broken
concrete and building debris etc.) requiring disposal from the site, the
Project office shall write to the Public Fill Committee (PFC) through the
Secretary of the PFC to request a designated disposal ground for incorporation
into the tender documents. For contracts where the estimated amount of
non-inert C&D materials (C&D waste) (e.g. timber formwork, other
construction debris, packaging waste, etc.) requiring disposal at landfill
facilities equal to or exceed 50m3, the Project office shall seek
confirmation from the Director of Environmental Protection (DEP) as to whether
landfill facilities will be available for disposal of such materials. The DEP
will designate landfill facilities, if available, for the contract. Where the
estimated amount of non-inert C&D materials (C&D waste) to be generated
from the contract is less than 50m3, the Project office is not required
to apply to DEP for designated landfill facilities which is unlikely for this
Project. However, the Project office should still specify in the tender
documents appropriate landfill facilities (e.g. Outlying Islands Transfer
Facilities managed by the EPD, SENT Landfill at Tseung Kwan O, NENT Landfill at
Ta Kwu Ling and WENT Landfill at Nim Wan).
8.2.8
Enhancement
measures to enhance the management of construction and demolition material, and
to minimize its generation at source include:
l
Drawing up a Construction and Demolition
Material Management Plan (C&DMMP) at the feasibility study or preliminary
design stage to minimize C&D material generation and encourage proper
management of such material;
l
Vetting of the C&DMMP
prior to upgrading of the Project to Category A in the Public Works Programme;
l Providing the contractor with information from the C&DMMP in order to
facilitate him in the preparation of the Waste Management Plan (WMP) and to
minimize C&D materials generation during construction.
8.2.9
Projects
generating C&D materials less than 50,000m3 or importing fill
material less than 50,000m3 are exempted from the C&DMMP. The
ETWB TCW No. 19/2005 “Environmental Management on Construction Sites” includes
procedures on waste management requiring contractors to reduce the C&D
materials to be disposed of during the course of construction. Under ETWB TCW
No. 19/2005, the contractor is required to prepare and implement and
Environmental Management Plan (EMP) and the WMP becomes part of the EMP.
Besides, DEVB TCW No. 6/2010 “Trip Ticket System for Disposal of Construction
and Demolition Materials” promulgates the latest trip ticket system for public
works contracts including capital works contracts, term contracts and design
and build contracts, where C&D materials including waste generated on site
require disposal.
Construction
Impacts
8.3.1
Based
on Master Layout Plan, a method statement for construction and construction
programme is drafted as shown in Section
2.6. The key activities include
l
General Preliminaries, such as
hoarding access roads, temporary utilities, site office and plant set up.
l
Site formation works,
involving site levelling, drainage and permanent access road and utilities, and
formation of access ramps.
l
Foundation, including piled
foundations, pre-boring, pile testing, shallow foundation and pile cap
construction with excavation and lateral supports.
l
Superstructure works.
l
Finishes, such as building
façade, stadium covers, signage etc.
l
Building services and
supporting M&E works.
l
External works such as hard
and soft landscaping, pavement, lighting and road sign and other street
furniture.
l General site clearance.
8.3.2
Based
on the method statement for construction and the construction programme, a
phasing plan is developed as shown in Figure
2-2. The
types of construction waste and C&D materials will be identified. The
quantity, quality and timing of construction waste will be estimated
accordingly, taking into consideration of alternative design schemes and
construction methods, aiming at minimizing the generation of construction
waste.
8.3.3
After
considering the opportunities for reducing waste generation and maximizing
re-use, the types and quantities of waste required to be disposal of as a consequence
shall be estimated and the disposal methods / options of each type of wastes
shall be analyzed.
8.3.4
Based
on the selected option for disposal of both inert C&D materials (or public
fills) and non-inert C&D materials (or C&D waste), some designated landfill
site and public filling areas will have to be identified. Preliminary
construction traffic routes are proposed taking into consideration of feasible
land routes and sea routes by barging and balancing the cut and fill in order
to minimize the generation of inert C&D materials (or public fills) and
maximize the use of inert C&D materials (or public fills) for other
construction works.
8.3.5
The
route for construction traffic from the Project Site to the barging point via
the existing construction route in KTD prior to construction of Road D2 and D3
is shown in Figure 8-3-1. Assuming that Road D2 or D3 will be completed by
Year 2021, but without Central Kowloon Route (CKR), this traffic route will not
be available during the later stage of the Project construction. The
construction route will make use of the alignment of CKR as shown in Figure
8-3-2. If
CKR alignment is not available, construction traffic has to pass through the
Metro Park. It is envisaged that the construction traffic at the later stage of
construction will be greatly reduced as all foundation works, earth works and
structural works should have been substantially completed. The construction traffic
mainly serves the M&E plant delivery, decorative material and disposal of
packaging material and other construction wastes. The frequency of using the
barging route will be substantially reduced.
8.3.6
The
depth of basement excavation is compared with the available ground
investigation borelogs in order to assess if sediment removal from excavation
is required.
Operation
Phase Impacts
8.3.7 Based on the Master Layout Plan, various operational activities will be identified. The major activities that generate waste include:
l
Main Stadium: sports
events, performance events, food and beverage, cleaning, repair, maintenance
and renovation.
l
Public Sports Ground:
sports events, public activities, food and beverage, cleaning, repair,
maintenance and renovation.
l
Indoor Sports Centre:
sports events, retails activities, training classes, sports supporting
activities, such as food and beverage, cleaning, repair, maintenance and
renovation.
l
Office block: office
activities, food and beverage, cleaning, repair, maintenance and renovation.
l
Hotel block: guest
accommodation, food and beverage, amenities, retail and hopping facilities,
back of house activities, such as laundry, cleaning, repair, maintenance and
renovation.
l
Transport facilities such
as road and carpark cleaning, crowd control activities, repair and maintenance.
l
Outdoor activities such as planting,
irrigation, cleaning, repair and maintenance.
8.3.8
These
wastes generated are classified as domestic and commercial solid waste referred
to in Appendix 1 of Monitoring Solid Waste in Hong Kong – Waste Statistics for
2014.
Development Parameters
8.3.9
The
development parameters and population of the Project are summarized in Table 8-1.
l This GFA schedule is used to develop the population which
will be used for assessment of waste for operation phase. The area for
assessment of construction waste is further elaborated in Section 8.4.2.
Table
8-1 Development Parameters
and Population Estimation of the Project
Area
|
Use
|
Population
|
Quantities
|
Rate
|
Remarks
|
||||||
Type
|
Estimation
|
Sub-
total
|
No. of seats in sports facility
|
GFA
(m2)
|
No. of Hotel Rooms
|
Sports facility
|
Office Area & Retail Area
|
Hotel
Area
|
|||
Main
Stadium
|
Sports
facilities
|
Spectator
|
50,000
|
|
50,000
|
-
|
-
|
-
|
-
|
-
|
-
|
Permanent
employee (1)
|
30
|
|
-
|
-
|
21/
40,000
|
-
|
-
|
Population
pro-rated from Hong Kong Stadium
|
|||
Temporary
employee (1)
|
5,125
|
|
-
|
-
|
4,100/
40,000
|
-
|
-
|
-
|
|||
Subtotal
|
|
55,155
|
|
||||||||
Public
Sports Ground
|
Sports
facilities
|
Spectator
|
7,000
|
|
7,000
|
-
|
-
|
-
|
-
|
-
|
-
|
Permanent
employee (1)
|
55
|
|
-
|
-
|
21/
40,000
|
-
|
-
|
Population
pro-rated from Tseung Kwan O
|
|||
Temporary
employee (1)
|
475
|
|
-
|
-
|
4,100/
40,000
|
-
|
-
|
-
|
|||
Subtotal
|
|
7,530
|
|
||||||||
Indoor
Sports Centre
|
Sports
facilities
|
Spectator
|
5,400
|
|
5,400
|
-
|
-
|
-
|
-
|
-
|
-
|
Permanent
employee (1)
|
55
|
|
-
|
-
|
21/
40,000
|
-
|
-
|
Population
pro-rated from Queen Elizabeth Stadium
|
|||
Temporary
employee (1)
|
55
|
|
-
|
-
|
4,100/
40,000
|
-
|
-
|
-
|
|||
Subtotal
|
|
5,510
|
|
||||||||
Hotel
Area
|
Residential
|
Resident
|
480
|
|
-
|
-
|
300
|
-
|
-
|
2
x 80%
|
Assume
2 people/room with 80% occupancy
|
Employee
|
300
|
|
-
|
-
|
-
|
1
|
Assume
1 worker/
room
|
||||
Subtotal
|
|
780
|
|
||||||||
Office
Area
|
Commercial
|
Employee
|
800
|
|
-
|
16,000
|
-
|
-
|
1/20
|
-
|
Assume
1 worker/
20m2
GFA
|
Subtotal
|
|
800
|
|
||||||||
Retail
Area
|
Commercial
|
Employee
|
2,280
|
|
-
|
57,000
|
-
|
-
|
1/25
|
-
|
Assume
1 worker/
25m2
GFA
|
Visitor
|
2,105
|
|
-
|
-
|
-
|
-
|
(57,000/13
– 2,280)
|
||||
Subtotal
|
|
4,385
|
|
||||||||
TOTAL
|
74,160
|
|
Construction
Phase
8.4.1 The construction works of the subject development mainly include site formation, underground utility foundation work, basement construction and superstructure construction. The estimated period for the whole construction is 56 months.
8.4.2 According to preliminary civil and structural engineering design and based on total site area of 283,559 m2, the estimated quantities of C&D materials generated from this development is 657,519 m3, including bulking factor of 1.9 for building debris and 1.2 for soil, or 820,719 tonnes with breakdown of waste estimation as shown in Table 8-2 to 8-5.
Table 8-2 Breakdown of Covered Area (Building Footprint) in m2
Item |
Site Area |
Building Footprint (m2) |
Remark |
||
Gross Area |
Deduction |
Net Area |
|||
1 |
Main Stadium |
|
|||
1.1 |
Stadium |
49,084 |
|
||
1.2 |
Field Area in Stadium |
12,960 |
Non building area |
||
1.3 |
Net Area in Stadium |
36,124 |
|
||
2 |
Public Sport Ground |
|
|||
2.1 |
Sport ground |
30,459 |
|
||
2.2 |
Field Area in Public
Sport Ground |
11,393 |
Non building area |
||
2.3 |
Net Area in Public Sport
Ground |
19,066 |
|
||
3 |
Indoor Sports Centre |
34,774 |
34,774 |
|
|
4 |
Hotel |
2,188 |
2,188 |
|
|
5 |
Office cum basement |
Includes 3,100 m2
basement |
|||
5.1 |
Office |
3,532 |
3,532 |
|
|
5.2 |
Basement |
3100 m2 |
|||
Sub-total |
120037 |
95,684 |
|
||
6 |
Podium Deck |
109,639 |
109,639 |
|
|
Total Building
Footprint |
229,676 |
205,323 |
|
Table 8-3 Estimated Quantities of Inert C&D materials
Item |
Description |
Area (Refer to Table
8-2) |
Depth (m) |
Percentage Site
Coverage (%) |
Volume (m3) |
Bulk Factor |
Factored Volume (m3) |
Total* (T) |
(a) |
(b) |
(c) |
(d) = (a)*(b)*(c) |
(e) |
(f) = (d)*(e) |
(g) = (f)*1.3 |
||
1 |
Site clearance (including demolition work
& RC slab 300mm) |
283,559 |
0.3 |
100% |
85,068 |
1.9 |
161,629 |
210,117 |
2 |
Site formation (including open space 400 mm
soil) |
283,559 |
0.4 |
100% |
113,424 |
1.2 |
136,108 |
176,941 |
3 |
Excavation for building sub-structure (piling
+ pilecap + trenches) |
95,684 |
2.0 |
40% |
76,547 |
1.2 |
91,857 |
119,414 |
4 |
Excavation for podium deck (including piling +
utilities) |
109,639 |
1.5 |
40% |
65,783 |
1.2 |
78,940 |
102,622 |
5 |
Excavation for sub-structure above pile cap
(ave.depth (m)) |
205,323 |
1.0 |
40% |
82,129 |
1.2 |
98,555 |
128,122 |
6 |
Excavation of Basement |
3,100 |
6.0 |
100% |
18,600 |
1.2 |
22,320 |
29,016 |
7 |
Total excavated soil/concrete materials |
|
|
|
441,551 |
|
589,409 |
766,231 |
*Density = 1,300 kg/m3 |
Inert C&D materials
include normal excavated soil, rock, sand, demolished concrete rubble, brick,
tile, masonry, asphalt, etc.
Table
8-4 Estimated Quantities of Non-inert
C&D Materials
Item |
Description |
CFA (m2) |
Total CFA (m2) |
Tonne/CFA (T/m2) |
Weight (T) |
Volume* (m3) |
(a) |
(b) |
(c) |
(d) = (b)*(c) |
(e) = (d)/0.8 |
||
1 |
Main Stadium |
|
112,093 |
0.07 |
7,847 |
9,808 |
2 |
Public sports ground |
|
|
|
|
|
2.1 |
Stadium |
22,033 |
|
|
|
|
2.2 |
Retail |
2,968 |
|
|
|
|
2.3 |
Sub-total |
|
25,001 |
0.07 |
1,750 |
2,188 |
3 |
Indoor Sports Arena |
|
|
|
|
|
3.1 |
Sports ground |
122,811 |
|
|
|
|
3.2 |
Retail |
48,351 |
|
|
|
|
3.3 |
Sub-total |
|
171,162 |
0.18 |
30,809 |
38,511 |
4 |
Hotel block |
|
|
|
|
|
4.1 |
Hotel |
16,837 |
|
|
|
|
4.2 |
Retail |
2,065 |
|
|
|
|
4.3 |
Sub-total |
|
18,902 |
0.13 |
2,457 |
3,072 |
5 |
Office cum Basement |
18,780 |
26,112 |
0.09 |
2,350 |
2,938 |
6 |
Retail |
7,332 |
|
|
|
|
7 |
Open Space |
|
160,000 |
0.01 |
1,600 |
2,000 |
8 |
Podium deck |
|
109,639 |
0.07 |
7,675 |
9,593 |
|
Total |
|
|
|
54,488 |
68,110 |
*Assumed density: 800 kg/m3 |
||||||
Remarks: Advised by the Quantity Surveyor in
Sept 15 Non-inert C&D materials include Timber
formwork, other construction debris,
packaging waste, etc. |
Table 8-5 Estimated Quantities of C&D Materials Generated
Total C&D
materials |
657,519 m3 |
820,719 tonnes |
||
|
(m3) |
% of total volume |
(tonnes) |
% of total weight |
Portion of C&D
materials to be reused on site |
141,945 |
21% |
184,528 |
22% |
Portion of inert
C&D materials (public fill) be disposed offsite |
447,464 |
69% |
581,703 |
71% |
Non-inert C&D materials
(C&D Waste) to be disposed to Landfill |
68,110 |
10% |
54,488 |
7% |
Total volume of C&D Materials |
= 589,409 + 68,110 |
= 657,519 |
m3 |
|
Total weight of C&D Materials |
= 766,231 + 54,488 |
= 820,719 |
tonnes |
8.4.3 The estimated C&D materials are generated in line with the construction programme as shown in Table 8-6.
Table 8-6 Annual
Disposal of C&D Materials During Construction
Year |
Inert
C&D materials (or public fills) (m3) to be disposed of |
Non-inert
C&D materials (or C&D waste) (m3) to be disposed of |
Total
(m3) |
2018 |
178,986 |
- |
178,986 |
2019 |
178,986 |
6,811 |
185,797 |
2020 |
44,746 |
27,244 |
71,990 |
2021 |
35,797 |
30,650 |
66,447 |
2022 |
8,949 |
3,405 |
12,354 |
Total |
447,464 |
68,110 |
515,574 |
8.4.4 The site of the public fill should be identified prior to preparing the Waste Management Plan (WMP). All construction waste should be reused/recycled whenever possible.
8.4.5 The recommended construction waste management strategy is to segregate C&D materials from construction waste. Around 70% of inert C&D materials shall be disposed of at public fill area.
8.4.6 According to the basement layout as shown in Figure 8-4-1, the basement formation level is at -1.0 mPD, the bottom of excavation will be -1.5 mPD, allowing for structures below ground, or depth of 6.5 m below existing ground level. According to available ground investigation information as shown in Figures 8-4-2 and 8-4-3, the top level of marine deposits at borehole no. BH18, see Figure 8-4-2, is 8 m. Therefore, no marine sediments will be excavated. According to BH18, the marine deposits are silty fine to coarse sand which may be used to backfill on site in the case when such soil strata is excavated. However, the chance of encountering marine sediment is very remote as the basement location is on the downstream side of BH18. Though no marine sediment excavation is required, in the case when dredging/excavation of sediment is found required, the Project Proponent is required to observe the requirements of ETWB TC(W) 34/2002 and make submissions to the DASO Authority and Marine Fill committee for consideration prior to starting dredging/excavation if dredging/excavation is found inevitable after exhausting all possible avenues.
General
Refuse
8.4.7 Throughout construction, the workforce would generate refuse comprising food scraps, waste paper, empty containers, etc. Escape of such refuse from the site should not be allowed to occur.
8.4.8 Effective collection and removal of site wastes will be required to prevent waste materials being blown around by wind, flushed or leached into the aquatic environment, and to prevent odour nuisance. The work sites may also attract pests and vermin if the waste storage area is not well maintained and cleaned regularly. Disposal of refuse must be at approved waste transfer or disposal facilities. With the implementation of good waste management practices at the site, adverse environmental impacts would not be expected to arise from the storage, handling and transportation of refuse.
Bentonite
Slurry
8.4.9 Bentonite slurry may be used, depending on the construction method proposed by the Contractor, during pre-boring of piling works. It was estimated that approximately 3,000 m3 of used bentonite slurry may require off-site disposal.
Chemical
Waste
8.4.10 The maintenance and servicing of construction plant and equipment may possibly generate some chemical wastes, for instance, cleaning fluids, solvents, lubrication oil and fuel. Maintenance of vehicles may also involve the use of a variety of chemicals, oil and lubricants.
8.4.11 Chemical wastes arising during the construction phase may pose environmental, health and safety hazards if not stored and disposed of in an appropriate manner as stipulated in the Waste Disposal (Chemical Waste) (General) Regulations. The potential hazards include:
· Toxic effects on the workforce.
· Adverse impacts on water quality and aquatic biota from spills.
· Fire hazards.
8.4.12 Materials classified as chemical wastes will require special handling and storage arrangements before removal for appropriate treatment at the Chemical Waste Treatment Centre at Tsing Yi. Wherever possible opportunities should be taken to reuse and recycle materials. Mitigation and control requirements for chemical wastes are detailed in Section 8.5. Provided that the handling, storage and disposal of chemical wastes are in accordance with these requirements, adverse environmental impacts are not expected to result.
Uncertainties
in Prediction & Evaluation of Environmental Impacts
8.4.13 It is difficult to quantify the amount of general refuse and chemical waste that will arise from the construction activities since it would be highly dependent on the Contractor’s on-site maintenance requirements and the number of plant utilised. However, as a worst case, it is estimated that a factor of 0.65 kg per worker per day of general refuse will be generated. The total quantity of waste generated would thus be estimated 275.25 kg per day, assuming the size of the work force would be a maximum of 145 resident site staff (RSS) and 280 construction workers. Also it is anticipated that the quantity of chemical waste, such as lubricating oil and solvent produced from plant maintenance, would be small and in the order of a few cubic metres (i.e.< 5 m3) in total over the construction period. The amount of chemical waste to be generated would be quantified in the site Waste Management Plan to be prepared by the Contractor.
8.4.14 The construction of the proposed works would require the preparation of a Waste Management Plan (WMP) prior to the commencement of the construction works.
Operation
Phase
8.4.15 According to Monitoring Solid Waste in Hong Kong, Statistics for Hong Kong 2014 (Solid Waste 2014). Municipal wastes include Domestic Waste, Commercial Waste and Industrial Waste. The solid waste generated from the Project consists of domestic waste and commercial wastes but not industrial waste. All activities referred to in Section 8.3.7 generate both domestic and commercial wastes.
8.4.16 The quantities of waste are estimated based on Solid Waste 2014, the average waste generation rates are as follow:
l
Domestic waste 0.89kg / pax / day
l
Commercial waste 0.35kg / pax / day
l Industrial
waste 0.11kg / pax / day
8.4.17 These waste generation rates are based on total waste per capita. Only the hotel residence in the Project Site will likely generate 100% of the domestic waste and all occupants not within sports facilities will likely generate 100% of commercial waste. Other occupants will likely generate a portion of the daily waste within the Project Site while the remaining portion will be generated at their normal place of residence or other working areas outside the Project Site. Thus, weighting factors are assigned to various occupants based on the time spent in the Project as follow:
Table 8-7 Waste
Generation Rates of Occupants
Item |
Area |
Personnel |
Domestic
waste |
Commercial
waste |
||||
Avg. waste generation rate (kg/pax/day) |
Weighting
factor (%) |
Adjusted
rate (kg/pax/day) |
Avg. waste generation rate (kg/pax/day) |
Weighting
factor (%) |
Adjusted
rate (kg/pax/day) |
|||
1 |
Sports facilities |
Spectator |
0.89 |
40% |
0.356 |
0.35 |
25% |
0.088 |
Permanent employee |
60% |
0.534 |
25% |
0.088 |
||||
Part time employee |
40% |
0.356 |
25% |
0.088 |
||||
2 |
Hotel |
Guests |
100% |
0.890 |
100% |
0.350 |
||
Permanent employee |
60% |
0.534 |
100% |
0.350 |
||||
3 |
Office |
Permanent employee |
60% |
0.534 |
100% |
0.350 |
||
4 |
Retail |
Permanent employee |
60% |
0.534 |
100% |
0.350 |
||
Customers |
40% |
0.356 |
100% |
0.350 |
8.4.18 Based on the estimated population waste generation rates and weighing factors, the total domestic waste generated during full operation and at full house sports events, about 35 tpd of municipal solid waste consisting of 27 tpd of Domestic Solid Waste and 8 tpd Commercial Solid Waste will be generated in the Project Site. The breakdown of solid waste generated is shown in Table 8-8.
Table 8-8 Breakdown
of Solid Waste Generated during Operation with Full House Sports
Events
Item |
Area |
Population |
Waste Generation |
||||||||
Domestic |
Commercial |
Municipal |
|||||||||
Type |
Estimation(1) |
Rate(2) (kg/pax/ day) |
Waste (tpd) |
Sub- total
(tpd) |
Rate(2) (kg/pax/ day) |
Waste (tpd) |
Sub- total
(tpd) |
Waste (tpd) |
Sub- total
(tpd) |
||
1 |
Main Stadium |
Spectator |
50,000 |
0.356 |
17.800 |
|
0.0875 |
4.375 |
|
22.175 |
|
Permanent
employee |
30 |
0.534 |
0.016 |
|
0.0875 |
0.003 |
|
0.019 |
|
||
Temporary
employee |
5,125 |
0.356 |
1.825 |
|
0.0875 |
0.448 |
|
2.273 |
|
||
|
|
|
|
19.641 |
|
|
4.826 |
|
24.467 |
||
2 |
Public Sports
Ground |
Spectator |
7,000 |
0.356 |
2.492 |
|
0.0875 |
0.613 |
|
3.105 |
|
Permanent
employee |
55 |
0.534 |
0.029 |
|
0.0875 |
0.005 |
|
0.034 |
|
||
Temporary
employee |
475 |
0.356 |
0.169 |
|
0.0875 |
0.042 |
|
0.211 |
|
||
|
|
|
|
2.690 |
|
|
0.659 |
|
3.349 |
||
3 |
Indoor Sports
Centre |
Spectator |
5,400 |
0.356 |
1.922 |
|
0.0875 |
0.473 |
|
2.395 |
|
Permanent
employee |
55 |
0.534 |
0.029 |
|
0.0875 |
0.005 |
|
0.034 |
|
||
Temporary employee |
55 |
0.356 |
0.020 |
|
0.0875 |
0.005 |
|
0.024 |
|
||
|
|
|
|
1.971 |
|
|
0.482 |
|
2.453 |
||
4 |
Hotel |
Spectator |
480 |
0.89 |
0.427 |
|
0.35 |
0.168 |
|
0.595 |
|
Permanent
employee |
300 |
0.534 |
0.160 |
|
0.35 |
0.105 |
|
0.265 |
|
||
|
|
|
|
0.587 |
|
|
0.273 |
|
0.860 |
||
5 |
Office Area |
Employee |
800 |
0.534 |
0.427 |
|
0.35 |
0.280 |
|
0.707 |
|
|
|
|
|
0.427 |
|
|
0.280 |
|
0.707 |
||
6 |
Retail Area |
Employee |
2,280 |
0.534 |
1.218 |
|
0.35 |
0.798 |
|
2.016 |
|
visitor |
2,105 |
0.356 |
0.749 |
|
0.35 |
0.737 |
|
1.486 |
|
||
|
|
|
|
1.967 |
|
|
1.535 |
|
3.502 |
||
|
Total |
27.284 |
|
8.055 |
|
35.339 |
Construction Phase
8.5.1 In order to minimize construction waste, precast or prefabrication construction shall be adopted as far as applicable. Inert C&D materials (or public fills) will be used to form the ramps and other filling area as far as civil engineering design permits.
8.5.2 The inert C&D materials that can be reused/recycled on site amounting to 141,945 m3, see Table 8-5, while 447,464m3 will be transported to the public fill area by barge through trucks to the barging point. Based on the present construction programme and according to CEDD Public Fill Management, reclamation works for Tung Chung New Town Extension (East) can be considered as alternative disposal outlet for the inert C&D materials (or public fills). If the designated public fill area cannot accommodate these materials, the surplus materials may be transported to Mainland China through Tuen Mun Area 38, which is a fill bank for temporary stockpiling of surplus fill materials. The surplus fill will be reused beneficially in reclamation projects in Mainland China. A detailed C&DMMP to minimize C&D material generation and encourage proper management of such material will be submitted to the Public Fill Committee for approval as stated in Section 8.2.8.
8.5.3 In order to minimize the non-inert C&D waste material during construction, the Contractor have to prepare a waste management plan to encourage material recycling and waste minimization. The non-inert C&D waste materials shall be disposed of at the landfill. The waste materials amounting to 68,110 m3, see Table 8-6, will be transported by barge similar to inert C&D materials (public fills).
8.5.4 It is assumed a truck’s load capacity is approximately 15 tonnes (≈ 8 m3). The maximum number of trucks per year required are as follow:
l Public fill – 178,986/8 = 22,373 truck load
l Landfill –
6,811/8 = 851 truck load
Total = 23,224 truck load
At peak disposal, the monthly truck load is 1,935 (23,224/12) and the daily truck load is about 75 (1,935/26).
8.5.5 Therefore, the entire construction period of 56 months require 64,447 trucks to dispose 515,574 m3 C&D materials.
8.5.6 The construction trucks will follow the route as shown in Figure 8-3-1 or Figure 8-3-2 to the barging point depending on the schedule of the Project construction as shown in Appendix 2A and availability of roads D2 and D3. The hauling of C&D materials shall follow established environmental mitigation measures as stated in Practice Note for Registered Contractors No. 17 “Control of Environmental Nuisance from Construction Sites” issued by the Buildings Department as shown in Appendix 8A covering mitigation measures and good construction practice to avoid construction nuisance for haulage within and outside MPSC site, and in public roads and transfer facilities.
General Refuse
8.5.7 General refuse should be stored in enclosed bins or compaction units separate from C&D materials. A reputable waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D materials. An enclosed and covered area is preferred to reduce the occurrence of 'wind blown' light material.
Bentonite Slurry
8.5.8 Bentonite slurries used in construction works should be reconditioned and reused wherever practicable. The storage silos shall be bunded. Position bentonite storage silos and supply lines shall be placed as far as possible from surface water drains, watercourses or sea. The areas where bentonite is mixed shall be surrounded with a small wall or contain them within a bund and ensure it is contained within working area and does not enter any watercourses, surface water drains or sea. Record of the amount of bentonite used shall be kept for checking in case of quantities of bentonite used is larger than anticipated it is possible that these materials are escaping. Residual used bentonite slurry should be disposed of from the site as soon as possible as stipulated in Clause 8.62 of the General Specification for Civil Engineering Works which states “Bentonite slurry which will not be reused shall be disposed of from the Site as soon as possible.” Residual used dewatered bentonite slurry should be disposed to a public filling area and liquid bentonite slurry if mixed with inert fill material should be disposed to a public filling area.
Chemical Wastes
8.5.9 If chemical wastes were to be produced at the construction site, the Contractor would be required to register with the EPD as a Chemical Waste Producer, and to follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately. Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the waste such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc. The Contractor shall use a licensed collector to transport the chemical wastes. The licensed collector shall deliver the waste to the Chemical Waste Treatment Centre at Tsing Yi, or other licensed facility, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.
Operation
Phase
8.5.10 According to Section 8.4.17, the daily waste generation after full house sports events is about 35 tpd. This quantities of waste may be further reduced by introduction of the following means:
l Minimize unnecessary
waste generation by means of
promotion materials,
such as wider use of information technology and announcements;
l Encourage spectators to
bring along personal containers
for food and drinks and
l Sufficient recycling containers will be provided at suitable locations
to encourage recycling of such waste aluminium cans, plastics and waste paper.
8.5.11 There will still be solid waste to be disposed of after the said waste reduction measures. The refuse will be disposed at approved waste transfer or disposal facilities by refuse collection vehicle. However, the quantities of solid waste to be disposed of is about 35 tpd. Assuming current waste vehicles that can handle 9 ton per load or 240 to 660 litre plastic bins, the envisaged number of truck load is less than four which will not impose significant impact to both land transportation and waste disposal facilities.
8.5.12 In most cases the solid wastes generated from sports or other events have to be stored and waste collection and transference can only be carried out after the vacation of the sports facilities and crowd dispersal. Adequate solid waste storage facilities shall be provided in the Project Site. For provision of waste storage facilities, reference should be made to Practice Notes for Authorized Persons/Registered Structural Engineers/Registered Geotechnical Engineers APP-35 (PNAP No. 98).
8.6.1
Precast
and prefabricated construction shall
be adopted as far as practicable. Reuse and recycle of construction waste
should be implemented as much as possible and construction and operation waste
should be minimized during the design, construction and operation phases. The
Project Proponent should incorporate appropriate contract provisions to arrange
propose re-use of excavated materials in their site clearance and site
formation and excavation work sites as stated in Section 8.5.3.
8.6.2 The Contractor should establish a C&DMMP and submit the Plan to the Public Fill Committee for approval.
8.6.3 Implementation of mitigation measures shall be monitored as specified in the Environmental Monitoring and Audit Manual.