14.1.1
This chapter presents the implementation
schedule of mitigation measures for the project. Table 14.1 (also contained in Appendix A of the EM&A Manual)
summarizes the details of the recommended mitigation measures for all works
areas. For each recommended mitigation measures, both the location and timing
for the measure have clearly been identified as well as the parties responsible
for implementing the measure and for maintenance (where applicable).
Table 14.1 Environment
Mitigation Implementation Schedule
EIA* |
EM&A Log Ref. |
Environmental Protection
Measures* |
Location/Duration of
measures/ |
Implementation Agent |
Implementation Stage ** |
Relevant Legislation
& Guidelines |
|||
Des |
C |
O |
Dec |
||||||
Air Quality |
|||||||||
3.7 |
A1 |
Good housekeeping to minimize dust generation, e.g. by properly handling and storing dusty
materials |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A2 |
Store cement in shelter with 3 sides and the top covered by impervious
materials if the stack exceeds 20 bags |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A3 |
Cement delivered in bulk should be stored in a closed silo fitted with
an audible high level alarm which is interlocked with the material filling
line and no overfilling is allowed |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A4 |
Loading, unloading, transfer, handling or storage of bulk cement should
be carried out in a totally enclosed system or facility, and any vent or
exhaust should be fitted with an effective fabric filter or equivalent air
pollution control system |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A5 |
Dusty materials (e.g. debris) should be wetted by misting /
water-spraying before any loading, unloading, transfer or transport operation |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A6 |
Any skip hoist for material transport should be fully enclosed by
impervious sheeting |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A7 |
Surfaces where any pneumatic or power-driven drilling, cutting,
polishing or other mechanical breaking operation takes place should be
sprayed with water or a dust suppression chemical continuously |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A8 |
Any area that involves demolition activities should be sprayed with
water or a dust suppression chemical immediately prior to, during and immediately
after the activities to maintain the entire surface wet |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A9 |
Excavation area should be minimized as far as possible |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A10 |
Stockpile of dusty materials should not be extended beyond the
pedestrian barriers, fencing or traffic cones |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A11 |
Excavated or stockpile of dusty material should be covered entirely by
impervious sheeting or sprayed with water to maintain the entire surface wet,
and then removed, backfilled or reinstated where practicable within 24 hours
of the excavation or unloading |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A12 |
Dusty materials remaining after a stockpile is removed should be
wetted with water and cleared from the surface of roads |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A13 |
Properly fitted side and tail boards are necessary for any vehicle with
open load area |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A14 |
While transporting materials that potentially create dust (e.g.
debris), materials should not be loaded higher than side and tail boards, and
should be fully covered by tarpaulin or similar materials which extent at
least 300 mm over the edges of the side and tail boards to prevent leakage. |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A15 |
Limit the maximum vehicle speed within the site to 10km/hr |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A16 |
Haulage and delivery vehicles should be confined to designated roads |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A17 |
Every main haul road should either be: |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A18 |
All on-site unpaved roads should be compacted and kept free of lose materials
as possible |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A19 |
Provide vehicle washing (e.g. wheel washing bay & high pressure
water jet where practicable) at every vehicle exit point for cleaning vehicle
body and wheels |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A20 |
The vehicle washing area and the road between washing area and site
exit should be paved with concrete, bituminous or other hardcores |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A21 |
The portion of any road leading only to construction site that is
within 30m of a vehicle entrance or exit should be kept clear of dusty
materials |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A22 |
Dusty materials on every vehicle's body and wheels should be removed
in washing area before leaving the site |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A23 |
Regular maintenance of all plant equipment |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A24 |
Throttle down or switch off unused machines or machine in intermittent
use |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A25 |
If the site is adjacent to area where accessible to the public (e.g. road
and service lane etc.), hoarding of not less than 2.4 m high from ground
level should be erected along the adjoining the entire length of that portion
of the site boundary, except for a site entrance or exit. The hoarding should
be well maintained throughout the construction period. |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A26 |
Where a scaffolding is erected around the perimeter of a building
under construction, effective dust screens, sheeting or netting should be
provided to enclose the scaffolding from the ground floor level of the
building, or a canopy should be provided from the first floor level up to the
highest level of the scaffolding |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A27 |
Exposed earth should be properly treated by compaction, turfing,
hydroseeding, vegetation planting or sealing with latex, vinyl, bitumen,
shortcrete or other suitable surface stabiliser within six months after the
last construction activity on the construction site or part of the
construction site where the exposed earth lies |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A28 |
Carry out air quality monitoring throughout the construction period |
Selected representative
monitoring stations |
Contractor |
|
P |
|
|
EIAO-TM |
3.7 |
A29 |
Carry out weekly site inspection to audit the implementation of
mitigation measures |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.7 |
A30 |
Regular watering once per hour on exposed worksites and haul road with
an equivalent intensity of not less than 1.3L/m3 to achieve 91.7%
dust removal efficiency. |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM, APCO |
3.8 |
A31 |
Locate air intake point of hotel outside the exceedance zone of air
pollutant NO2 (at least 5m above ground). |
Parking spaces of MPSC |
Future operator |
|
|
P |
|
EIAO-TM, APCO |
3.8 |
A32 |
Adopt the lower limits of parking provisions for retail area, office
and hotel in the HKPSG as far as practicable to discourage use of cars. The
car parking for coaches, goods vehicles and working/services/emergency
vehicles should be less than 300. |
Parking spaces of MPSC |
Project Proponent/
Contractor |
P |
|
|
|
EIAO-TM, APCO, HKPSG |
3.8 |
A33 |
Provision of electrical vehicle (EV) charging facilities in at least
one-third of the car parking spaces for private cars. Provision of EV
charging enabling facilities in all car parking spaces provided for private
cars. |
Parking spaces of MPSC |
Project Proponent/
Contractor/Future operator |
P |
P |
P |
|
EIAO-TM, APCO |
3.8 |
A34 |
The entry of heavy goods vehicles should avoid peak hours, weekdays
from 7 am to 10 am and from 4 pm to 7 pm, except for major events (i.e. more
than 20,000 persons). |
Parking spaces of MPSC |
Future operator |
|
|
P |
|
EIAO-TM, APCO |
3.8 |
A35 |
Give priority to EV to use the car parking spaces
as far as practicable. |
Parking spaces of MPSC |
Future operator |
|
|
P |
|
EIAO-TM, APCO |
3.8 |
A36 |
Electric vehicles (EV) should be used under normal operation for
vehicles such as electric saloon cars/coaches, if the operator provides
transport services for the staff and/or guests. |
Vehicles managed by
operator of MPSC |
Future operator |
|
|
P |
|
EIAO-TM, APCO |
Hazard to Life |
|||||||||
No mitigation measure is required |
|||||||||
Noise |
|||||||||
5.9 |
N1 |
Adopt good site practice, such as throttle down or switch off
equipment unused or intermittently used between works |
Whole construction site |
Contractor |
|
P |
|
|
NCO, EIAO-TM |
5.9 |
N2 |
Regular maintenance of equipment to prevent noise emission due to
impair |
Whole construction site |
Contractor |
|
P |
|
|
NCO, EIAO-TM |
5.9 |
N3 |
Position mobile noisy equipment in locations away from NSRs and point
the noise sources to directions away from NSRs |
Whole construction site |
Contractor |
|
P |
|
|
NCO, EIAO-TM |
5.9 |
N4 |
Use silencer or muffler for equipment |
Whole construction site |
Contractor |
|
P |
|
|
NCO, EIAO-TM |
5.9 |
N5 |
Make good use structures for noise screening |
Whole construction site |
Contractor |
|
P |
|
|
NCO, EIAO-TM |
5.9 |
N6 |
Use Quality Powered Mechanical Equipment (QPME) and quiet equipment
which produces lower noise level |
Whole construction site |
Contractor |
|
P |
|
|
NCO, EIAO-TM |
5.9 |
N7 |
Erect movable noise barrier of 3m height to shed large plant equipment
(e.g. breaker, backhoe & mobile crane) or hand-held items (e.g. poker,
wood saw, power rammer & compactor) near low-rise NSR. Where necessary,
special design (e.g. with noise absorbing material or bend top) should be
adopted. The barrier's length should be at least five times greater than its
height, and the minimum surface density is 10 kg/m2.
Alternatively, acoustic shed, enclosure or silencer (for generator, air
compressor and concrete pump) or acoustic mat (for piling) can be adopted. |
Whole construction site |
Contractor |
|
P |
|
|
NCO, EIAO-TM |
5.9 |
N8 |
Carry out regular site inspection to audit the implementation of
mitigation measures |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM |
5.9 |
N9 |
Carry out noise monitoring throughout the construction period |
Selected representative
monitoring stations |
Contractor |
|
P |
|
|
EIAO-TM |
5.7 |
N10 |
No organized events should be held concurrently in the Main Stadium
and the Public Sports Ground. |
Main Stadium/ Public Sports Ground |
Future operator |
|
|
P |
|
|
5.6.1-5.6.4 and 5.9 |
N11 |
Operational Fixed Noise from Main Stadium |
Main Stadium |
Project Proponent |
P |
|
|
|
NCO, EIAO-TM, Noise
Control Guideline for Music, Singing and Instrument Performing Activities |
5.9 |
N12 |
Operational Fixed Noise from Public Sports Ground |
Public Sports Ground |
Project Proponent |
P |
|
|
|
NCO, EIAO-TM |
5.9 |
N13 |
Operation Noise from Fixed Plants |
Building services and
ventilation systems |
Project Proponent |
P |
|
|
|
NCO, EIAO-TM |
5.9 |
N14 |
Crowd Noise from Dispersion - Crowd management measures should be adopted for major events (i.e.
more than 20,000 persons) which finish at or later than 2230 hours. - Crowd
shall be managed and confined to pre-determined routes, which lead the crowd
towards the future Kai Tak Station & To Kwa Wan Station. For the crowd
moving toward the Kai Tak Station, people will be directed to leave through
or along the ISCB. For the dispersal routes toward To Kwa Wan Station, the
exit from the Project site is designed near the Sung Wong Toi Park. - The
operator should arrange staff members to marshal the dispersion of crowds in
an orderly manner from the Main Stadium all the way to the future Kai Tak
Station & To Kwa Wan Station. Placards should be used to advise attendees
of the events to keep the noise down. No loudspeakers should be used. If any
attendees are found to raise the voice or make any noise beyond control even
after verbal advice by the marshalling staff, the Police should be called in
to restore the situation. |
Main Stadium and pre-determined
routes which lead the crowd towards the future Kai Tak Station & To Kwa
Wan Station |
Future operator |
|
|
P |
|
NCO, EIAO-TM |
5.11 |
N15 |
Operational Noise Monitoring |
Main Stadium/ Public Sports Ground |
Future operator/ Project
Proponent |
|
|
P |
|
EIAO-TM |
5.9 |
N/A |
Planned NSRs (TPN12, TPN13) Planning applications are required for developments on CDA sites and
are subject to Town Planning Board approval. The future developers of the CDA
sites would need to carry out an Environmental Assessment (EA) to support the
planning application. The EA would include the required mitigation measures
so that all noise sensitive receivers at the sites would not be exposed to
road traffic noise levels above the respective criterion. |
The CDA sites facing Sung
Wong Toi Road |
Applicants of the
Planning Application |
P |
|
|
|
HKPSG |
5.9 |
N/A |
Planned NSRs (TPN14) |
The planned Housing Site
facing Sung Wong Toi Road |
The Housing Department |
P |
|
|
|
HKPSG |
Water Quality |
|||||||||
6.7 |
WQ1 |
Practices outlined in ProPECC PN 1/94 Construction Site Drainage
should be adopted. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ2 |
Install perimeter channels in the works areas to intercept runoff from
boundary prior to the commencement of any earthwork |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ3 |
To prevent storm runoff from washing across exposed soil surfaces,
intercepting channels should be provided. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ4 |
Drainage channels are required to convey site runoff to sand/silt
traps and oil interceptors. Provision of regular |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ5 |
Any practical options for the diversion and realignment of drainage
should comply with both engineering and environmental requirements |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ6 |
Minimum distances of 100 m should be maintained between the discharge
points of construction site runoff and the existing WSD saltwater intake and
EMSD cooling water intake. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ7 |
The following good site measures should be adopted for the use of the
existing barging facilities being operated by the MTR SCL Project: |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ8 |
The runoff and wastewater generated from the works areas should be
treated so that it satisfies all the standards listed in the TM-DSS. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ9 |
Reuse and recycling of the treated effluent from construction site
runoff. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ10 |
Weekly site audit should be carried out to check the implementation
status of the recommended water quality impact mitigation measures throughout
construction period. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ11 |
The construction programme should be properly planned to minimise soil
excavation, if any, in rainy seasons. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ12 |
Any exposed soil surfaces should be properly protected to minimise
dust emission. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ13 |
In areas where a large amount of exposed soils exist, earth bunds or
sand bags should be provided. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ14 |
Exposed stockpiles should be covered with tarpaulin |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ15 |
The stockpiles of materials should be placed at locations away from
any stream courses so as to avoid releasing materials into the water bodies. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ16 |
Final surfaces of earthworks should be compacted and protected by
permanent work. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ17 |
Haul roads should be paved with concrete and the temporary access
roads protected using crushed stone or gravel, wherever practicable. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ18 |
Wheel washing facilities should be provided at all site exits to
ensure that earth, mud and debris would not be carried out of the works areas
by vehicles. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ19 |
Good site practices should be adopted to keep the site dry and tidy,
such as clean the rubbish and litter on the construction sites. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ20 |
Adequate temporary site drainage and pumping should be provided, if
necessary. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ21 |
Provide sufficient temporary toilets in the works areas. The toilet
facilities should be more than 30 m from any watercourse. A licensed waste
collector should be deployed to clean the temporary toilets on a regular
basis. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ22 |
Notices should be posted at conspicuous locations to remind the
workers not to discharge any sewage or wastewater into the nearby environment
during the construction phase of the Project. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ23 |
Contractor must register as a chemical waste producer if chemical
wastes would be produced from the construction activities. The Waste Disposal
Ordinance (Cap 354) and its subsidiary regulations in particular the Waste
Disposal (Chemical Waste) (General) Regulation should be observed and
complied with for control of chemical wastes. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ24 |
Any service shop and maintenance facilities should be located on hard
standings within a bunded area, and sumps and oil interceptors should be
provided. Maintenance of vehicles and equipment involving activities with
potential for leakage and spillage should only be undertaken within the areas
appropriately equipped to control these discharges. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ25 |
Clean the construction sites on a regular basis. |
Whole construction site |
Contractor |
|
P |
|
|
WPCO, EIAO-TM |
6.7 |
WQ26 |
Oil interceptor in car parking area shall be designed and constructed
according to Practice Note for Authorized |
Car parking Area |
Project Proponent |
P |
P |
P |
|
WPCO, EIAO-TM, PNAP 124 |
6.7 |
WQ27 |
The chemicals/fuels to be stored on site will be limited to small
essential quantities at any one time.
Any chemicals that may be carried away by water shall be contained in
specific containers and cabinets under shelter and protected from
weather. Any liquid chemical or fuel
shall be contained in hard standing bunded area. The operator shall ensure that only staff
trained in the use and handling the specific chemicals for specific tasks are
allowed to handle the relevant chemicals. |
Whole site |
Future operator |
|
|
P |
|
WPCO, EIAO-TM |
6.7 |
WQ28 |
Good practice should be adopted to clean the rubbish and litter on the
sites so as to prevent rubbish and litter from spreading from the site area.
It is recommended to clean the Project Site on a regular basis. Management
guidelines shall be provided to the management team practically to separate
and remove solids from discharging stormwater system. |
Whole Project site |
Future operator |
|
|
P |
|
WPCO, EIAO-TM |
6.7 |
WQ29 |
For use artificial turf, subject to design and operation
considerations, practically no mitigation measures are required. The duration
of the natural turf on the pitch should be minimized in case of using
occasional natural turf during major events and no pesticides and fertilizers
should be used during the period under normal circumstances. Intercept the
surface water from the turf that may contain residual fertilizers and
pesticides for reuse or treatment if usage of fertilizers and pesticides is
needed. |
Area with Turf |
Future Operator |
|
|
P |
|
WPCO, EIAO-TM |
6.7 |
WQ30 |
The future management of the MPSC should follow Pesticide Ordinance
(Cap 133), Pesticide Regulations (Cap 133A), A Guide to Labeling of
Pesticides, and Safety Guidelines for Storage of Pesticides issued by AFCD
and the LCSD horticultural guidelines on use of turf management and consult
AFCD on pesticides used. |
Area with Natural Turf |
Future operator |
|
|
P |
|
Pesticide Ordinance (Cap 133), Pesticide
Regulations (Cap 133A), A Guide to Labeling of Pesticides, and Safety
Guidelines for Storage of Pesticides issued by AFCD and the LCSD
horticultural guidelines on use of turf management |
6.7 |
WQ31 |
Application of chemicals, if necessary, will be confined to the
approved list and the dosage as well as the frequency and intensity should be
well justified according to genuine operational needs. |
Area with Natural Turf |
Future operator |
|
|
P |
|
WPCO, EIAO-TM |
6.7 |
WQ32 |
The dosage of pesticides and fertilizers shall be controlled to limit
any residual dosage to less than 10%. |
Area with Natural Turf |
Future operator |
|
|
P |
|
WPCO, EIAO-TM |
6.7 |
WQ33 |
Provide two sequential storage tanks to contain surface water with
residual fertilizers and pesticides and third holding tank for incidental
rainstorm |
Area with Natural Turf |
Project Proponent,
Contractor, Future operator |
P |
P |
P |
|
WPCO, EIAO-TM |
6.7 |
WQ34 |
A Stormwater Re-use Management Plan is recommended for the operator
including: 1) Healthy use of fertilizers and pesticides, and safe operation
of the chemical disposal. 2) Operation and maintenance of water
storage/holding tanks. 3) Frequency of testing and sampling, and appropriate
testing parameters. 4) Alert levels and action limit levels. 5) Emergency
measures. |
Area with Natural Turf |
Future operator |
|
|
P |
|
WPCO, EIAO-TM |
6.7 |
WQ35 |
The storage and holding tanks shall be emptied prior to application of
fertilizers and pesticides. In
general, the intercepted surface water may be recycled by irrigation into the
football pitch. |
Area with Natural Turf |
Future operator |
|
|
P |
|
WPCO, EIAO-TM |
6.11 |
WQ36 |
Encourage recycling of stormwater for irrigation and flushing |
Sewerage and Stormwater
System |
Future operator |
|
|
P |
|
WPCO, EIAO-TM |
6.11 |
WQ37 |
Cleansing detergents shall not be used for washing the spectator
seats. |
Spectator Seats |
Future operator |
|
|
P |
|
WPCO, EIAO-TM |
Sewerage and Sewage Treatment
Implications |
|||||||||
7.2 |
SS1 |
Implementation of Sewer No. 1 and Sewer No.2 as proposed in Sections
7.2.2 - 7.2.3 of the EIA Report |
As per Figure 7-2-2 of EIA Report |
Contractor |
|
P |
|
|
EIAO-TM |
Waste Management |
|||||||||
8.5 |
WM1 |
Inert C&D materials (or public fills) will be used to form the
ramps and other filling area as far as civil engineering design permits. |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal Ordinance,
EIAO-TM |
8.5 |
WM2 |
Prepare a Construction and Demolition Material Management Plan
(C&DMMP) to encourage C&D material recycling and waste minimization
and submit the Plan to the Public Fill Committee for approval. |
Whole construction site |
Contractor |
P |
|
|
|
Waste Disposal Ordinance,
EIAO-TM |
8.5 |
WM3 |
The contractor should formulate waste management measures on waste
minimization, storage, handling and disposal in a Waste Management Plan as
part of Environmental Management Plan. |
Whole construction site |
Contractor |
|
P |
|
|
Environment, Transport
and Works Bureau Technical Circular (Works) No. 19/2005 |
8.5 |
WM4 |
Adopt good site practice as follows: |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal Ordinance,
EIAO-TM, Practice Note for Registered Contractors No. 17 |
- Provide training to workers on site cleanliness, waste management
(waste reduction, reuse and recycle) and chemical handling procedures |
|||||||||
- Provide sufficient waste collection points and regular removal |
|||||||||
- Cover waste materials with tarpaulin or in enclosure during
transportation |
|||||||||
- Maintain drainage systems, sumps and oil interceptors |
|||||||||
- Sort out chemical waste for proper handling and treatment onsite or
offsite |
|||||||||
8.5 |
WM5 |
Adopt waste reduction measures as follows: |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal Ordinance,
EIAO-TM, Practice Note for Registered Contractors No. 17 |
- Allocate area/containers for sorting, recovering and storing waste
for reuse, recycle or disposal (e.g. demolition debris and excavated
materials, general refuse like aluminium cans.) Remove waste from the Site
for sorting once generated if no suitable space can be identified. |
|||||||||
- Allocate area for proper storage of construction materials to
prevent contamination |
|||||||||
- Minimize wastage through careful planning and avoiding over-purchase
of construction materials |
|||||||||
8.5 |
WM6 |
Store waste materials properly as follows: |
Whole construction site |
Contractor |
|
P |
|
|
ProPECC PN 1/94, EIAO-TM,
Practice Note for Registered Contractors No. 17 |
- Avoid contamination by proper handling and storing waste |
|||||||||
- Prevent erosion by covering waste |
|||||||||
- Apply water spray on excavated materials |
|||||||||
- Maintain and clean storage area regularly |
|||||||||
- Sort and stockpile different materials at designated location to
enhance reuse |
|||||||||
8.5 |
WM7 |
Apply for relevant waste disposal permits in accordance with the Waste
Disposal Ordinance (Cap. 354), Waste Disposal (Charges for Disposal of
Construction Waste) Regulation (Cap. 345) and the Land (Miscellaneous
Provisions) Ordinance (Cap. 28), Dumping at Sea Ordinance (Cap. 466). |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal Ordinance
(Cap. 354), Waste Disposal (Charges for Disposal of Construction Waste)
Regulation (Cap. 345) and the Land (Miscellaneous Provisions) Ordinance (Cap.
28), Dumping at Sea Ordinance (Cap. 466), EIAO-TM |
8.5 |
WM8 |
Hire licensed waste disposal contractors for waste collection and
removal. Dispose waste at licensed waste disposal facilities |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal Ordinance,
EIAO-TM |
8.5 |
WM9 |
Implement trip-ticket system for recording the amount of waste
generated, recycled and disposed, including chemical wastes |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation, Waste Disposal Ordinance, EIAO-TM |
8.5 |
WM10 |
Reduce water content in wet spoil generated from piling work by mixing
with dry materials. Only dispose treated spoil with less than 25% dry density
to Public Fill Reception Facilities |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal Ordinance,
EIAO-TM |
8.5 |
WM11 |
Dispose dry waste or waste with less than 70% water content by weight
to landfill |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal Ordinance,
EIAO-TM |
8.5 |
WM12 |
Follow the Code of Practice on the Packaging, Labelling and Storage
of Chemical Waste as follows: |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation, EIAO-TM |
- Store chemical wastes with suitable containers. Seal and maintain
the container to avoid leakage or spillage during storage, handling and
transport |
|||||||||
- Label chemical waste containers in both English and Chinese with
instructions in accordance to Schedule 2 of the Waste Disposal (Chemical
Waste) (General) Regulation |
|||||||||
- The container capacity should be smaller than 450 litres unless
agreed by the EPD |
|||||||||
8.5 |
WM13 |
Comply with the requirement of the chemical storage area: |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation, EIAO-TM |
- Store only chemical waste and label clearly the chemical characters
of the waste |
|||||||||
- Have at least 3 sides enclosed and protected from rainfall with
cover |
|||||||||
- Provide sufficient ventilation |
|||||||||
- Have impermeable floor and has bunds to contain 110% of the capacity
of the largest container or 20% of the total volume of the stored waste in
the area, whichever is larger |
|||||||||
- Adequately spaced incompatible materials |
|||||||||
8.5 |
WM14 |
Transfer used lubricants, waste oils and other chemicals to oil
recycling companies, if possible, and empty oil drums for reuse or refill. No
direct or indirect discharge is permitted |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation, EIAO-TM |
8.5 |
WM15 |
Hire licensed chemical waste disposal contractors for waste collection
and removal. Dispose chemical waste at the approved Chemical Waste Treatment
Centre at Tsing Yi or other licensed facility |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation, EIAO-TM |
8.5 |
WM16 |
Hire reputable waste collector to separately collect and dispose
general refuse from other wastes. Cover the waste to prevent being blown away |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal (Chemical
Waste) (General) Regulation, EIAO-TM |
8.5 |
WM17 |
The hauling of C&D materials shall follow established environmental
mitigation measures as stated in Practice Note for Registered Contractors No.
17 “Control of Environmental Nuisance from Construction Sites” issued by the
Buildings Department |
Whole construction site |
Contractor |
|
P |
|
|
Practice Note for Registered
Contractors No. 17 “Control of Environmental Nuisance from Construction
Sites”, BD |
8.5 |
WM18 |
Provide recycling bins for sorting out recyclables for collection by
recycling companies. Non-recyclables should be removed to designated
landfills every day by licensed collectors to prevent environmental and
health nuisance. |
Whole construction site |
Contractor |
|
P |
|
|
Waste Disposal Ordinance,
EIAO-TM |
8.5 |
WM19 |
Organize training and reminders to site staff on waste minimization through
avoidance and reduction, reusing and recycling |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM |
8.5 |
WM20 |
Bentonite slurry which will not be reused shall be disposed of from
the Site as soon as possible. Residual
used dewatered bentonite slurry should be disposed to a public filling area
and liquid bentonite slurry if mixed with inert fill material should be
disposed to a public filling area. |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM |
8.5 |
WM21 |
If chemical wastes were to be produced at the construction site, the
Contractor would be required to register with the EPD as a Chemical Waste
Producer, and to follow the guidelines stated in the Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes. |
Whole construction site |
Contractor |
|
P |
|
|
Code of Practice on the
Packaging, Labelling and Storage of Chemical Wastes, Waste Disposal (Chemical
Waste) (General) Regulation |
Good quality containers compatible with the chemical wastes should be
used, and incompatible chemicals should be stored separately. |
|||||||||
Appropriate labels should be securely attached on each chemical waste
container indicating the corresponding chemical characteristics of the waste such
as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc. |
|||||||||
The Contractor shall use a licensed collector to transport the
chemical wastes. |
|||||||||
The licensed collector shall deliver the waste to the Chemical Waste Treatment
Centre at Tsing Yi, or other licensed facility, in accordance with the Waste
Disposal (Chemical Waste) (General) Regulation |
|||||||||
8.5 |
WM22 |
Carry out weekly site inspection to check the implementation status of
the recommended waste management measures. |
Whole Construction site |
Contractor |
|
P |
|
|
Waste Disposal Ordinance,
EIAO-TM |
8.5 |
WM23 |
Minimize unnecessary waste generation by means of promotion materials,
such as wider use of information technology and announcements |
Whole Project Site |
Future operator |
|
|
P |
|
Waste Disposal Ordinance,
EIAO-TM |
8.5 |
WM24 |
Encourage spectators to bring along personal containers for food and
drinks |
Whole Project Site |
Future operator |
|
|
P |
|
Waste Disposal Ordinance,
EIAO-TM |
8.5 |
WM25 |
Sufficient recycling containers will be provided at suitable locations
to encourage recycling of such waste aluminium cans, plastics and waste
paper. |
Whole Project Site |
Future operator |
|
|
P |
|
Waste Disposal Ordinance,
EIAO-TM |
8.5 |
WM26 |
Adequate solid waste storage facilities shall be provided |
Whole Project Site |
Future operator |
|
|
P |
|
Waste Disposal Ordinance,
EIAO-TM, PNAP No.98 |
Land Contamination |
|||||||||
No mitigation measure is required |
|||||||||
Ecology |
|||||||||
10.11 |
E1 |
Erection of hoarding, fencing or provision of clear demarcation of
work zone |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM |
10.11 |
E2 |
Designate areas for placement of equipment, building materials and
wastes away from drainage channels |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM |
10.11 |
E3 |
Carry out weekly site inspection to check the implementation status
and the effectiveness of the proposed mitigation measures |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM |
Landscape and Visual |
|||||||||
Table 11-22 |
LV1 |
Construction Lighting Control |
Whole construction site |
Contractor |
|
P |
|
|
BS EN 12464-2:2007 |
Table 11-22 |
LV2 |
Temporary Landscape Treatments |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM |
Table 11-22 |
LV3 |
Decoration of Hoarding |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM |
11.9.47 |
LV4 |
All security floodlights for construction sites shall be equipped with
adjustable shield, frosted diffusers and reflective covers, and be carefully
controlled to minimize light pollution and night-time glare to nearby
receivers |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM |
11.4.3 |
LV5 |
Site inspection should be undertaken once every two weeks. |
Whole construction site |
Contractor |
|
P |
|
|
EIAO-TM |
Table 11-23 |
LV6 |
Greening of Walkways, Ramps and Decks |
Landscape deck and
connections to surrounding footpath network |
Project Proponent/ Future
operator |
P |
|
P |
|
Greening Guidelines,
GLTMS of DEVB |
Table 11-23 |
LV7 |
Green Roofs and Vertical Greening |
External walls and roofs
of built structures |
Project Proponent/ Future
operator |
P |
|
P |
|
DEVB TC No.3/2012 – Site
Coverage of Greenery for Government Building Projects |
Table 11-23 |
LV8 |
Compensatory Tree Planting - A new parkland area is created in the
project development to be used for the implementation of compensatory tree
planting to offset the net loss of key landscape resources. It is recommended
that 340 trees be planted in this regard and a compensatory tree planting
proposal outlining the locations of tree compensation will be submitted
separately in seeking relevant government department’s approval in accordance
with DEVB TC No.7/2015. |
Designated planting areas |
Project Proponent/
Contractor |
P |
P |
|
|
DEVB TC No.7/2015 |
Table 11-23 |
LV9 |
Responsive Building Design |
All structures |
Project Proponent |
P |
|
|
|
EIAO-TM |
Table 11-23 |
LV10 |
Integration of Development Boundaries |
Project boundaries |
Project Proponent/ Future
operator |
P |
|
P |
|
EIAO-TM |
Table 11-23 |
LV11 |
Integration with Dining Cove and Waterfront Promenade |
Promenade interface and
Hotel |
Project Proponent/ Future
operator |
P |
|
P |
|
EIAO-TM |
Table 11-23 |
LV12 |
Light Penetration Under Deck - The landscape deck shall be cut back
and light wells incorporated to maximise natural light penetration to
at-grade covered areas under the deck, to allow for enhanced visual amenity,
improved utilisation of ground space and significant incorporation of both
horizontal and vertical greening at ground level. |
Landscape deck |
Project Proponent |
P |
|
|
|
EIAO-TM |
Table 11-23 |
LV13 |
Urban Park |
Designated area |
Project Proponent/ Future
operator |
P |
|
P |
|
Greening Guidelines,
GLTMS of DEVB |
Table 11-23 |
LV14 |
Bespoke Amenity Area Lighting |
Site wide |
Project Proponent/ Future
operator |
P |
|
P |
|
EIAO-TM |
11.9.42 |
LV15 |
Responsive Lighting Design and Disposition - Carry out the external
landscape lighting design with reference to (1) Lighting Guide 4: Sports
Lighting, Chartered Institution of Building Services Engineers; (2) BS EN
12193:2007 Light and Lighting-Sports Lighting, British Standards Institution
and (3) Guidance Notes for the Reduction of Obtrusive Light, The Institution
of Lighting Professionals as recommended in the Building Services Branch
Circular No. 10 of 2011 by Architectural Services Department - Design Considerations for Outdoor Sports
Venues Lighting and other applicable relevant international standards. - Select luminaries and fittings type to
minimise direct view of the light source (from the sides) and restrict side
dispersion. - Adopt a strategy to use
lamp posts of lower height and with less interval spacing to reduce the
lighting output from each lamp while maintaining the minimum luminance
requirement for the open space. -
Lowering of the lighting output (i.e. luminous flux) - All proposed hard structures should be
sensitively designed in a manner that responds to the existing and planned
landscape context, and minimizes potential adverse glare impacts. - The structural design should seek to
reduce the apparent visual mass through the use of natural materials such as
wooden frame and semi-transparent panels.
- subdued tones should be considered for the colour palette with
non-reflective finishes - Reduce the
direct sight of the luminaries from the observers, e.g. through planting of
trees within the MPSC. |
Site wide |
Project Proponent/ Future
operator |
P |
|
P |
|
EIAO-TM |
Table 11-23 |
LV16 |
Submit detailed landscape proposals and details of architectural
design, chromatic treatment and lighting, for all above ground structures,
including pedestrian links, stadium connections and ancillary buildings to
Planning Department for review to demonstrate that they would be sensibly
designed in a manner that responds to the existing urban context and minimize
any residual landscape and visual impact. |
Site wide |
Project Proponent/ Future
operator |
P |
|
P |
|
EIAO-TM |
11.11.5 |
LV17 |
Site inspection should be undertaken once every two months during the
12 month establishment period. |
Site wide |
Project Proponent/ Future
operator |
|
|
P |
|
EIAO-TM |
Cultural Heritage |
|||||||||
No mitigation measure is required |
* All
recommendations and requirements resulted during the course of EIA Process,
including ACE and/or accepted public comment to the proposed project.
** Des=Design;
C=Construction; O=Operation; Dec=Decommissioning