TABLE OF CONTENTs
5.......... Water Quality Impacts
5.2 Environmental Legislation, Policies, Plans,
Standards and Criteria
5.3 Water Sensitive Receivers for the Project
5.4 Water Sensitive Receivers for Sewage
Pumping Stations (DP9)
5.5 Baseline Conditions ¡V River Water Quality
in Deep Bay WCZ
5.6 Baseline Conditions ¡V River Water Quality
in North Western WCZ
5.7 Baseline Conditions ¡V Marine Water Quality
in Deep Bay WCZ
5.8 Baseline Conditions ¡V Marine Water Quality
in North Western Water
5.9 Assessment Approach and Methodology
5.10 Identification and Evaluation of
Environmental Impacts ¡V Construction Phase
5.11 Identification and Evaluation of
Environmental Impacts ¡V Operational Phase
5.12 Cumulative Impacts from Concurrent Projects
5.13 Mitigation Measures ¡V Construction Phase
5.14 Mitigation Measures ¡V Operational Phase
5.15 Evaluation of Residual Environmental
Impacts
5.17 Environmental
Acceptability of Schedule 2 Designated Projects
APPENDICES
Appendix 5.1 Key Assumptions for
Quantification of Construction Site Run-off
Appendix 5.4 Key Assumptions for Compiling
Non-Point Source Pollution from Surface Run-off
FIGURES
Figure 5.1 Key
Water Bodies Within Study Area and Water Quality Monitoring Stations
Figure 5.2 Locations
of Inland Water Bodies ¡V Key Plan
Figure 5.2.1 Locations of
Inland Water Bodies ¡V Sheet 1 of 14
Figure 5.2.2 Locations of
Inland Water Bodies ¡V Sheet 2 of 14
Figure 5.2.3 Locations of
Inland Water Bodies ¡V Sheet 3 of 14
Figure 5.2.4 Locations of
Inland Water Bodies ¡V Sheet 4 of 14
Figure 5.2.5 Locations of
Inland Water Bodies ¡V Sheet 5 of 14
Figure 5.2.6 Locations of
Inland Water Bodies ¡V Sheet 6 of 14
Figure 5.2.7 Locations of
Inland Water Bodies ¡V Sheet 7 of 14
Figure 5.2.8 Locations of
Inland Water Bodies ¡V Sheet 8 of 14
Figure 5.2.9 Locations of
Inland Water Bodies ¡V Sheet 9 of 14
Figure
5.2.10 Locations of
Inland Water Bodies ¡V Sheet 10 of 14
Figure
5.2.11 Locations of
Inland Water Bodies ¡V Sheet 11 of 14
Figure 5.2.12 Locations of Inland Water
Bodies ¡V Sheet 12 of 14
Figure
5.2.13 Locations of
Inland Water Bodies ¡V Sheet 13 of 14
Figure
5.2.14 Locations of
Inland Water Bodies ¡V Sheet 14 of 14
Figure 5.3 Proposed
Locations of Flood Retention Facilities
Figure 5.4 Indicative
Locations of Marine Water Sensitive Receivers and Observation Points
Figure 5.6 Locations
of Footbridges and Cycle Bridges
Figure 5.7 Locations
of Foundations for the Proposed Viaduct of DP12
¡P Construction of new primary distributor road (Road P1) (DP1)
¡P Construction of eight new distributor roads (Roads D1 to D8) (DP2)
¡P Construction of slip roads between: Road D8 Junction and existing Castle Peak Road; Junction of D8/P1 and Junction of D7/P1; and KSWH connection to Road D3 (DP5)
¡P Construction of partly depressed and partly decked-over roads located at Road D2, Road D4 and Road D6 (DP6)
¡P Construction of four new SPSs (Sites 2-34, 3-41, 3-48 and 4-35) (DP9)
¡P Construction of Road P1 and slip-road from KSWH to Road D3 partly located within the ¡§CA¡¨ of Yuen Tau Shan (DP12)
Environmental Impact Assessment Ordinance (EIAO)
¡P Annex 6 ¡V Criteria for Evaluating Water Pollution; and
¡P Annex 14 ¡V Guidelines for Assessment of Water Pollution.
Water Quality
Objectives
Table 5.1 Summary
of Water Quality Objectives for Deep Bay WCZ
Criteria |
Subzone |
|
Aesthetic appearance |
(a) Waste discharges shall cause no objectionable
odours or discolouration of the water. |
Whole Zone |
(b) Tarry residues, floating wood, articles made
of glass, plastic, rubber or of any other substances should be absent. |
Whole Zone |
|
(c) Mineral oil should not be visible on the
surface. Surfactants should not give rise to a lasting foam. |
Whole Zone |
|
(d) There should be no recognisable sewage-derived
debris. |
Whole Zone |
|
(e) Floating, submerged and semi-submerged
objects of a size likely to interfere with the free movement of vessels, or
cause damage to vessels, should be absent. |
Whole Zone |
|
(f) Waste discharges shall not cause the water to
contain substances which settle to form objectionable deposits. |
Whole Zone |
|
Bacteria |
(a) The level of Escherichia coli should not exceed 610 per 100 mL, calculated as
the geometric mean of all samples collected in one calendar year. |
Secondary Contact Recreation Subzone and
Mariculture Subzone (L.N. 455 of 1991) |
(b) The level of Escherichia coli should be zero per 100 ml, calculated as the
running median of the most recent 5 consecutive samples taken at intervals of
between 7 and 21 days. |
Yuen Long & Kam Tin (Upper) Subzone, Beas
Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones |
|
(c) The level of Escherichia coli should not exceed 1000 per 100 ml, calculated as
the running median of the most recent 5 consecutive samples taken at
intervals of between 7 and 21 days. |
Yuen Long & Kam Tin (Lower) Subzone and other
inland waters |
|
(d) The level of Escherichia coli should not exceed 180 per 100 mL, calculated as
the geometric mean of all samples collected from March to October inclusive
in one calendar year. Samples should be taken at least 3 times in a calendar
month at intervals of between 3 and 14 days. |
Yuen Long Bathing Beach Subzone (L.N. 455 of
1991) |
|
Colour |
(a) Waste discharges shall not cause the colour
of water to exceed 30 Hazen units. |
Yuen Long & Kam Tin (Upper) Subzone, Beas
Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones |
(b) Waste discharges shall not cause the colour
of water to exceed 50 Hazen units. |
Yuen Long & Kam Tin (Lower) Subzone and other
inland waters |
|
Dissolved
oxygen (DO) |
(a) Waste discharges shall not cause the level of
dissolved oxygen to fall below 4 milligrams per litre for 90% of the sampling
occasions during the year; values should be taken at 1 metre below surface. |
Inner Marine Subzone excepting Mariculture
Subzone |
(b) Waste discharges shall not cause the level of
dissolved oxygen to fall below 4 milligrams per litre for 90% of the sampling
occasions during the year; values should be calculated as water column
average (arithmetic mean of at least 2 measurements at 1 metre below surface
and 1 metre above seabed). In addition, the concentration of dissolved oxygen
should not be less than 2 milligrams per litre within 2 metres of the seabed
for 90% of the sampling occasions during the year. |
Outer Marine Subzone excepting Mariculture
Subzone |
|
(c) The dissolved oxygen level should not be less
than 5 milligrams per litre for 90% of the sampling occasions during the
year; values should be taken at 1 metre below surface. |
Mariculture Subzone |
|
(d) Waste discharges shall not cause the level of
dissolved oxygen to be less than 4 milligrams per litre. |
Yuen Long & Kam Tin (Upper and Lower)
Subzones, Beas Subzone, Indus Subzone, Ganges Subzone, Water Gathering Ground
Subzones and other inland waters of the Zone |
|
pH |
(a) The pH of the water should be within the
range of 6.5-8.5 units. In addition, waste discharges shall not cause the natural
pH range to be extended by more than 0.2 units. |
Marine waters excepting Yung Long Bathing Beach
Subzone |
(b) Waste discharges shall not cause the pH of
the water to exceed the range of 6.5-8.5 units. |
Yuen Long & Kam Tin (Upper and Lower)
Subzones, Beas Subzone, Indus Subzone, Ganges Subzone and Water Gathering
Ground Subzones |
|
(c) The pH
of the water should be within the range of 6.0-9.0 units. |
Other inland waters |
|
(d) The pH of the water should be within the
range of 6.0-9.0 units for 95% of samples. In addition, waste discharges
shall not cause the natural pH range to be extended by more than 0.5 units. |
Yung Long
Bathing Beach Subzone |
|
Temperature |
Waste discharges shall not cause the natural
daily temperature range to change by more than 2.0 degrees Celsius. |
Whole Zone |
Salinity |
Waste discharges shall not cause the natural
ambient salinity level to change by more than 10% |
Whole Zone |
Suspended
solids (SS) |
(a) Waste discharges shall neither cause the natural
ambient level to be raised by 30% nor give rise to accumulation of suspended
solids which may adversely affect aquatic communities. |
Marine waters |
(b) Waste discharges shall not cause the annual
median of suspended solids to exceed 20 milligrams per litre. |
Yuen Long & Kam Tin (Upper and Lower)
Subzones, Beas Subzone, Ganges Subzone, Indus Subzone, Water Gathering Ground
Subzones and other inland waters |
|
Ammonia |
The un-ionised ammoniacal nitrogen level should
not be more than 0.021 milligram per litre, calculated as the annual average
(arithmetic mean). |
Whole Zone |
Nutrients |
(a) Nutrients shall not be present in quantities
sufficient to cause excessive or nuisance growth of algae or other aquatic
plants. |
Inner and
Other Marine Subzone |
(b) Without limiting the generality of objective
(a) above, the level of inorganic nitrogen should not exceed 0.7 milligram
per litre, expressed as annual mean. |
Inner Marine Subzone |
|
(c) Without limiting the generality of objective (a)
above, the level of inorganic nitrogen should not exceed 0.5 milligram per
litre, expressed as annual water column average (arithmetic mean of at least
2 measurements at 1 metre below surface and 1 metre above seabed). |
Outer Marine Subzones |
|
5-day biochemical
oxygen demand (BOD) |
(a) Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 3 milligrams per litre. |
Yuen Long & Kam Tin (Upper) Subzone, Beas
Subzone, Indus Subzone, Ganges Subzone and Water Gathering Ground Subzones |
(b) Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 5 milligrams per litre. |
Yuen Long & Kam Tin (Lower) Subzone and other
inland waters |
|
Chemical
oxygen demand (COD) |
(a) Waste discharges shall not cause the chemical
oxygen demand to exceed 15 milligrams per litre. |
Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges
Subzone and Water Gathering Ground Subzones |
(b) Waste discharges shall not cause the chemical
oxygen demand to exceed 30 milligrams per litre. |
Yuen Long & Kam Tin (Lower) Subzone and other
inland waters |
|
Toxins |
(a) Waste discharges shall not cause the toxins
in water to attain such levels as to produce significant toxic carcinogenic,
mutagenic or teratogenic effects in humans, fish or any other aquatic
organisms, with due regard to biologically cumulative effects in food chains
and to toxicant interactions with each other. |
Whole Zone |
(b) Waste discharges shall not cause a risk to
any beneficial uses of the aquatic environment. |
Whole Zone |
|
Phenol |
Phenols shall not be present in such quantities
as to produce a specific odour, or in concentration greater than 0.05
milligrams per litre as C6H5OH. |
Yung Long Bathing Beach Subzone |
Turbidity |
Waste discharges shall not reduce light
transmission substantially from the normal level. |
Yung Long Bathing Beach Subzone |
Table 5.2 Summary
of Water Quality Objectives for North Western WCZ
Parameters |
Criteria |
Subzone |
Aesthetic appearance |
(a) Waste discharges shall cause no objectionable
odours or discolouration of the water. |
Whole Zone |
(b) Tarry residues, floating wood, articles made
of glass, plastic, rubber or of any other substances should be absent. |
Whole Zone |
|
(c) Mineral oil should not be visible on the
surface. Surfactants should not give rise to a lasting foam. |
Whole Zone |
|
(d) There should be no recognisable
sewage-derived debris. |
Whole Zone |
|
(e) Floating, submerged and semi-submerged objects
of a size likely to interfere with the free movement of vessels, or cause
damage to vessels, should be absent. |
Whole Zone |
|
(f) Waste discharges shall not cause the water to
contain substances which settle to form objectionable deposits. |
Whole Zone |
|
Bacteria |
(a) The level of Escherichia coli should not exceed 610 per 100 mL, calculated as
the geometric mean of all samples collected in one calendar year. |
Secondary Contact Recreation Subzones |
(b) The level of Escherichia coli should be less than 1 per 100 mL, calculated as
the running median of the most recent 5 consecutive samples taken at
intervals of between 7 and 21 days. |
Tuen Mun (A) and Tuen Mun (B) Subzones and Water
Gathering Ground Subzones |
|
(c) The level of Escherichia coli should not exceed 1000 per 100 mL, calculated as
the running median of the most recent 5 consecutive samples taken at
intervals of between 7 and 21 days. |
Tuen Mun (C) Subzone and other inland waters |
|
(d) The level of Escherichia coli should not exceed 180 per 100 mL, calculated as
the geometric mean of all samples collected from March to October inclusive.
Samples should be taken at least 3 times in one calendar month at intervals
of between 3 and 14 days. |
Bathing Beach Subzones |
|
Colour |
(a) Waste discharges shall not cause the colour
of water to exceed 30 Hazen units. |
Tuen Mun (A) and Tuen Mun (B) Subzones and Water
Gathering Ground Subzones |
(b) Waste discharges shall not cause the colour
of water to exceed 50 Hazen units. |
Tuen Mun (C) Subzone and other inland waters |
|
Dissolved
oxygen (DO) |
(a) Waste discharges shall not cause the level of
dissolved oxygen to fall below 4 mg per litre for 90% of the sampling
occasions during the whole year; values should be calculated as water column
average (arithmetic mean of at least 3 measurements at 1 m below surface,
mid-depth and 1 m above seabed). In addition, the concentration of dissolved
oxygen should not be less than 2 mg per litre within 2 m of the seabed for
90% of the sampling occasions during the whole year |
Marine waters |
(b) Waste
discharges shall not cause the level of dissolved oxygen to be less than 4
milligrams per litre. |
Tuen Mun
(A), Tuen Mun (B) and Tuen Mun (C) Subzones, Water Gathering Ground Subzones
and other inland waters |
|
pH |
(a) The pH of the water should be within the
range of 6.5-8.5 units. In addition, waste discharges shall not cause the
natural pH range to be extended by more than 0.2 units. |
Marine waters excepting Bathing Beach Subzones |
(b) Waste discharges shall not cause the pH of
the water to exceed the range of 6.5-8.5 units. |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones |
|
(c) The pH
of the water should be within the range of 6.0-9.0 units. |
Other inland waters |
|
(d) The pH of the water should be within the
range of 6.0-9.0 units for 95% of samples. In addition, waste discharges
shall not cause the natural pH range to be extended by more than 0.5 units. |
Bathing
Beach Subzones |
|
Temperature |
Waste discharges shall not cause the natural
daily temperature range to change by more than 2.0 degrees Celsius. |
Whole Zone |
Salinity |
Waste discharges shall not cause the natural
ambient salinity level to change by more than 10% |
Whole Zone |
Suspended solids
(SS) |
(a) Waste discharges shall neither cause the
natural ambient level to be raised by 30% nor give rise to accumulation of
suspended solids which may adversely affect aquatic communities. |
Marine waters¡¦ |
(b) Waste discharges shall not cause the annual
median of suspended solids to exceed 20 milligrams per litre. |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones |
|
(c) Waste discharges shall not cause the annual
median of suspended solids to exceed 25 mg per litre. |
Other inland waters |
|
Ammonia |
The un-ionised ammoniacal nitrogen level should
not be more than 0.021 milligram per litre, calculated as the annual average
(arithmetic mean). |
Whole Zone |
Nutrients |
(a) Nutrients shall not be present in quantities
sufficient to cause excessive or nuisance growth of algae or other aquatic
plants. |
Marine waters |
(b) Without limiting the generality of objective
(a) above, the level of inorganic nitrogen should not exceed 0.3 mg per
litre, expressed as annual water column average (arithmetic mean of at least
3 measurements at 1 m below surface, mid-depth and 1 m above seabed). |
Castle Peak Bay Subzone |
|
(c) Without limiting the generality of objective (a)
above, the level of inorganic nitrogen should not exceed 0.5 mg per litre,
expressed as annual water column average (arithmetic mean of at least 3
measurements at 1 m below surface, mid-depth and 1 m above seabed). |
Marine waters excepting Castle Peak Bay Subzone |
|
5-day
biochemical oxygen demand (BOD) |
(a) Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 3 milligrams per litre. |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones |
(b) Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 5 milligrams per litre. |
Other inland waters |
|
Chemical
oxygen demand (COD) |
(a) Waste discharges shall not cause the chemical
oxygen demand to exceed 15 milligrams per litre. |
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones |
(b) Waste discharges shall not cause the chemical
oxygen demand to exceed 30 milligrams per litre. |
Other inland waters |
|
Toxins |
(a) Waste discharges shall not cause the toxins
in water to attain such levels as to produce significant toxic, carcinogenic,
mutagenic or teratogenic effects in humans, fish or any other aquatic
organisms, with due regard to biologically cumulative effects in food chains
and to toxicant interactions with each other. |
Whole Zone |
(b) Waste discharges shall not cause a risk to
any beneficial uses of the aquatic environment. |
Whole Zone |
|
Phenol |
Phenols shall not be present in such quantities
as to produce a specific odour, or in concentration greater than 0.05
milligrams per litre as C6H5OH. |
Bathing Beach Subzones |
Turbidity |
Waste discharges shall not reduce light
transmission substantially from the normal level. |
Bathing Beach Subzones |
Technical Memorandum
Practice Note
Technical Circular
Existing Inland Watercourses
¡P Tin Shui Wai Main Channel and its tributaries (TSW);
¡P Hang Hau Tsuen Channel and its tributaries (HTT);
¡P Small watercourses along Deep Bay (DB);
¡P Upstream / tributaries of Shan Pui River (SPR); and
¡P Upstream / tributaries of Tuen Mun River (TMR).
Tin Shui Wai Main Channel and its Tributaries (TSW)
Hang Hau Tsuen Channel and its Tributaries (HTT)
Table 5.3 Summary
of Major Watercourses at or Near the Project Area
ID (See Figure 5.1) |
Existing Fresh Water System |
Description |
Water Sections to be Removed or
Realigned |
||||||
General |
Major Sub-sections of the Fresh
Water System |
Figure Reference (Fig. Ref.) |
Name |
Description |
Fig. Ref. |
||||
Name |
Description |
||||||||
Watercourses Discharging to Deep Bay WCZ |
|||||||||
TSW |
TSW Main Channel and its tributaries |
A large fresh water system, which spreads across the majority of the
Project area and generally runs from south to north and finally enters the
marine water of Deep Bay WCZ |
TSW Main Channel |
Core channel of the fresh water system, which generally runs along the
north-eastern boundary of the Project area from south to north and eventually
joins the marine water of Deep Bay WCZ in the north. |
Overview: Figure 5.1 Close up maps: Figure 5.2.6, Figure 5.2.7 (see upper right) and Figure 5.2.11 (see bottom left) |
N/A - The whole section of the Tin Shui Wan Main Channel will be
retained under the Project |
|||
Lo Uk Tsuen tributaries |
Upstream tributaries of the fresh water system, which generally run
across the middle portion of the Project area from west to east and
eventually enters the TSW Main Channel; Some small watercourses (originate
from the hill side in the west) also enter these Lo Uk Tsuen tributaries. |
Overview: Figure 5.1 Close up maps: Figure 5.2.7 (see bottom right) and Figure 5.2.8 (see upper part) |
TSW3 |
A small upstream section of Lo Uk Tsuen Tributaries to be removed
under the Project |
|||||
Hung Shiu Kiu (HSK) Main Street Channel |
An upstream tributary of the fresh water system, which originates from
a water channel near Wo Ping San Tsuen in the south and then runs towards the
north and eventually enters the TSW Main Channel |
Overview: Figure 5.1 Close up maps: Figure 5.2.8 (see bottom right) and Figure 5.2.9 (see right hand side) |
N/A -The whole section of HSK Main Street Channel will be retained
under the Project |
||||||
Tin Sam Channel tributaries |
Upstream tributaries of the fresh water system, which originates from
a watercourse in the south and then runs near Tin Sam towards the north and
eventually joins the HSK Main Street Channel. Some small watercourses (originate
from the hillside in the west) also run across the Project area towards the
east and then enter Tin Sam Channel |
Overview: Figure 5.1 Close up maps: Figure 5.2.4, Figure 5.2.8 (see bottom right) and Figure 5.2.9 (see left hand side) |
TSW1A, TSW1B, TSW1C, TSW1D |
4 minor sections that finally drain into Tin Sam Channel to be removed
under the Project |
|||||
TSW4 |
A section of Tin Sam Channel to be realigned under the Project |
||||||||
Others small tributaries |
Small watercourses near Tin Wah Road in the northern Project area,
which finally discharge to the TSW Main Channel |
Figure 5.2.7 (see upper right) |
TSW2, TSW2A, TSW2B |
Minor watercourses near Tin Wah Road to be removed under the Project |
Figure 5.2.7 (see upper right) |
||||
Small watercourse near Hung Uk Tsuen in the eastern portion of the
Project area, which finally discharges to the TSW Main Channel |
TSW5 |
A water section (west of Hung Uk Tsuen) to be removed under the
Project |
|||||||
HHT |
Hang Hau Tsuen Channel and its tributaries |
A relatively small stormwater system at the northern tip of the
Project area, which generally runs from south to north and finally discharges
to the marine water of Deep Bay WCZ. |
Overview: Figure 5.1 Close up maps: Figure 5.2.1 and Figure 5.2.7 (see upper middle) |
HHT1 |
A side branch of the Channel to be removed |
||||
HHT2 |
An upstream section of the Channel to be removed |
||||||||
DB |
Small water-courses along Deep Bay |
These small watercourses are located at the north-western boundary of
the Project area, generally running from south to north and finally enters
the marine water of Deep Bay WCZ. |
Overview: Figure 5.1 Close up map: Figure 5.2.2 |
N/A ¡V All of these minor watercourses will be retained under the
Project |
|||||
SBR |
Upstream tributaries of Shan Pui River |
These small watercourses are located around the proposed combined flushing
water service reservoir (FLWSR) and fresh water service reservoir (FWSR) in
the south, within the catchment of Shan Pui River, which would eventually
discharge to the marine water of Deep Bay WCZ. |
Overview: Figure 5.1 Close up map: Figure 5.2.14 |
N/A ¡V All these minor watercourses will be retained under the Project |
|||||
Watercourses discharging to North Western WCZ |
|||||||||
TMR |
Upstream tributaries of Tuen Mun River |
These watercourses are the upstream tributaries of Tuen Mun River
found at the southern tip of the Project area. They are running generally from north
to south and eventually enters the marine water of North Western WCZ |
Overview: Figure 5.1 Close up map: Figure 5.2.5 |
TMR1 |
An upstream section of this tributary to be removed under the Project |
||||
Small Watercourses Along Deep Bay (DB)
Upstream Tributaries of Shan Pui River (SMR)
Upstream Tributaries of Tuen Mun River (TMR)
Planned Inland Watercourses
Existing Ponds and Wet Agricultural Areas
Table 5.4 Ponds
and Agricultural Wet Areas within Assessment Area
ID |
Description |
Location |
Within Project Area? (Yes/No) |
Figure Reference |
Remarks |
P1A |
Inactive fish pond |
North of Project Area to the south of Hang Hau Tsuen Channel |
No |
|
|
P1B |
Inactive fish pond |
North of Project Area to the south of Hang Hau Tsuen Channel |
No |
|
|
P1C |
Inactive fish pond |
North of Project Area to the south of Hang Hau Tsuen Channel |
No |
|
|
P3A |
Active fish pond |
North of Project area along the coastline of Deep Bay |
No |
|
|
P3B |
Active fish pond |
North of Project area along the coastline of Deep Bay |
No |
|
|
P3C |
Inactive fish pond |
North of Project area along the coastline of Deep Bay |
No |
|
|
P3D |
Active fish pond |
North of Project area along the coastline of Deep Bay |
No |
|
|
P6A |
Inactive fish pond |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
P6B |
Inactive fish pond |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
P6C |
Inactive fish pond |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
P6D |
Inactive fish pond |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
P7 |
Inactive fish pond |
North of Project Area to the west of TSW Main Channel |
No |
|
|
P7A |
Recreational pond |
North of Project Area to the west of TSW Main Channel |
No |
|
|
P8A |
Flood protection pond |
At the ¡§Village Type Development¡¨ (¡§V¡¨) near Sik Kong Tsuen |
Yes |
|
|
P8B |
Inactive fish pond |
At the northern part of Project area near San
Wai |
Yes |
P8B will be removed under the Project |
|
P8C |
Inactive fish pond |
At the northern part of Project area near San
Wai |
Yes |
P8C will be removed under the Project |
|
P9A |
Flood protection pond |
At the ¡§V¡¨ in middle portion of the Project area |
Yes |
|
|
P9B |
Flood protection pond |
At the ¡§V¡¨ in middle portion of the Project area |
Yes |
|
|
P9C |
Flood protection pond |
At the ¡§V¡¨ in middle portion of the Project area |
Yes |
|
|
P9D |
Wetland mitigation pond |
Near the western boundary of Project area underneath KSWH |
Yes |
|
|
P9E |
Wetland mitigation pond |
Near the western boundary of Project area underneath KSWH |
Yes |
|
|
P9F |
Wetland mitigation pond |
West of Project area underneath KSWH |
Yes |
|
|
P9G |
Wetland mitigation pond |
West of Project area underneath KSWH |
Yes |
|
|
P9H |
Inactive fish pond |
West of Project area and to the west of KSWH |
No |
|
|
P9I |
Inactive fish pond |
West of Project area and to the west of KSWH |
No |
|
|
P9J |
Inactive fish pond |
West of Project area and to the west of KSWH |
No |
|
|
P10 |
Inactive fish pond |
At the southern portion of Project area near
San Sang San Tsuen |
Yes |
P10 will be removed under the Project |
|
P10A |
Recreational pond |
At ¡§V¡¨ east of Project area |
No |
|
|
P10B |
Recreational pond |
At ¡§V¡¨ east of Project area |
No |
|
|
P10C |
Flood protection pond |
At the ¡§V¡¨ in the eastern portion of the Project area |
Yes |
|
|
P11A |
Inactive fish pond |
North of Yuen Long Highway and to the south of Project area |
No |
|
|
P11B |
Inactive fish pond |
North of Yuen Long Highway and to the south of Project area |
No |
|
|
P12 |
Reinforced concrete flood storage pond |
To the immediate west of KSWH |
Yes |
|
|
A1 |
Wet agricultural area |
West of Project area and to the west of KSWH |
No |
|
|
A2A |
Wet agricultural area |
At the ¡§V¡¨ in middle portion of the Project area |
Yes |
|
|
A2B |
Wet agricultural area |
At the border of ¡§V¡¨ area in middle portion of the Project area |
Yes |
Part of A2B, A3C, A3D (located outside the ¡§V¡¨ area) will be removed |
|
A2C |
Wet agricultural area |
At the border of ¡§V¡¨ area in middle portion of the Project area |
Yes |
||
A2D |
Wet agricultural area |
At the border of ¡§V¡¨ area in middle portion of the Project area |
Yes |
||
A3 |
Wet agricultural area |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
A3A |
Wet agricultural area |
At the southern part of the Project area near the upstream tributaries
of Tuen Mun River |
Yes |
A3A will be removed under the Project |
|
A3C |
Wet agricultural area |
South of Project area near the upstream tributaries of Tuen Mun River |
No |
|
|
A4A |
Wet agricultural area |
North of Yuen Long Highway and to the south of Project area |
No |
|
|
A4B |
Wet agricultural area |
North of Yuen Long Highway and to the south of Project area |
No |
|
|
A4C |
Wet agricultural area |
North of Yuen Long Highway and to the south of Project area |
No |
|
Shaded cell: Ponds
/ wet agricultural areas to be completed or partially removed under the Project
Planned Ponds and Agricultural Wet Areas
Planned Flood Retention Facilities
Marine Water Sensitive Receivers
¡P Existing and planned cooling water intakes along the coastlines of outer Deep Bay, Tuen Mun District and North Lantau;
¡P Existing and planned flushing water intakes along the coastlines of Tuen Mun District and North Lantau;
¡P Existing bathing beaches in Tuen Mun District;
¡P Existing Tuen Mun typhoon shelter;
¡P Existing Gold Coast marina;
¡P Planned marina at Tung Chung East;
¡P Existing Tai O estuary;
¡P Existing Sha Chau and Lung Kwu Chau Marine Park;
¡P Planned The Brothers Marine Park;
¡P Existing Mai Po Inner Deep Bay Ramsar Site;
¡P Existing oyster culture area at inner Deep Bay;
¡P Existing fish spawning ground north of Lantau;
¡P Existing artificial reefs near airport and Sha Chau;
¡P Other existing ecological resources along the coastlines of Deep Bay, Sha Chau, Lung Kwu Chau, The Brothers and north Lantau including coral habitats, horseshoe crab habitats, seagrass habitats, mangrove habitats and Sites of Special Scientific Interest (SSSIs).
Table 5.5 Tentative Discharge
Points of Emergency Overflow from SPS and Downstream Receiving Water
SPS (see Figure 5.5) |
Discharge Point of Emergency Overflow and Downstream Receiving Water (refer to Table 5.3 for detailed description of Receiving Water) |
SPS No. 1 |
Tin Sam Channel, which would then discharge
to the TSW Main Channel and finally to the marine water of Deep Bay WCZ. |
SPS No. 2 |
A side branch of Tin Sam Channel,
which would firstly drain into Tin Sam Channel and then discharge to the TSW
Main Channel and finally to the marine water of Deep Bay WCZ. |
SPS No. 3 |
Tin Sam Channel, which would then
discharge to the TSW Main Channel and finally to the marine water of Deep Bay
WCZ. |
SPS No. 4 |
Lo Uk Tsuen Tributaries, which
would then enter the TSW Main Channel and finally to the marine water of Deep
bay WCZ. |
Tin Shui Wai Main Channel and Its Tributaries (TSW)
Table 5.6 Summary Statistics of River Water
Quality Data at Tin Shui Wai Catchment Collected by EPD in 2014
Parameters |
EPD Stations (Figure 5.1) |
WPCO
WQO |
|
TSR1 |
TSR2 |
||
Dissolved
oxygen (DO) (mg/L) |
5.8 |
9.4 |
Waste discharges shall not cause the level of
dissolved oxygen to be less than 4 mg/L |
(3.1 ¡V 9.3) |
(8.2 ¡V 12.0) |
||
pH |
7.6 |
8.2 |
The pH of the water should be within the
range of 6.0-9.0 |
(7.2 ¡V 8.0) |
(7.4 ¡V 8.7) |
||
Suspended
solids (mg/L) |
5 |
5 |
Waste discharges shall not cause the annual median
of suspended solids to exceed 20mg/L |
(2 - 23) |
(2 -8) |
||
5-day
Biochemical Oxygen Demand (BOD) (mg/L) |
6 |
2 |
Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 5mg/L |
(4 - 40) |
(<1 - 7) |
||
Chemical
Oxygen Demand (COD) (mg/L) |
15 |
6 |
Waste discharges shall not cause the chemical
oxygen demand to exceed 30mg/L |
(6 - 48) |
(<2 - 12) |
||
Oil
& grease (mg/L) |
<0.5 |
<0.5 |
Not available |
(<0.5 ¡V 2.8) |
(<0.5 - <0.5) |
||
Faecal
coliforms (cfu/100mL) |
650,000 |
47,000 |
Not available |
(75,000 - 7,000,000) |
(5,300 - 200,000) |
||
E. coli (cfu/100mL) |
210,000 |
20,000 |
Not exceed 1000 per 100 ml,
calculated as the running median of the most recent 5 consecutive samples
taken at intervals of between 7 and 21 days |
(15,000 ¡V 2,500,000) |
(2,800 - 88,000) |
||
Ammonia-nitrogen
(mg/L) |
2.20 |
0.34 |
Not available |
(0.40 ¡V 4.30) |
(0.10 ¡V 1.50) |
||
Nitrate-nitrogen
(mg/L) |
0.51 |
0.77 |
Not available |
(<0.01 - 1.00) |
(0.54 - 0.96) |
||
Total
Kjeldahl nitrogen (mg/L) |
3.85 |
0.69 |
Not available |
(0.83 - 7.20) |
(0.19 ¡V 2.20) |
||
Ortho-phosphate
(mg/L) |
0.17 |
0.05 |
Not available |
(0.06 - 0.38) |
(<0.01 - 0.19) |
||
Total
phosphorus (mg/L) |
0.34 |
0.08 |
Not available |
(0.10 - 0.69) |
(0.03 ¡V 0.30) |
||
Total
sulphide (mg/L) |
<0.02 |
<0.02 |
Not available |
(<0.02 - 0.02) |
(<0.02 - <0.02) |
||
Aluminium
(µg/L) |
121 |
133 |
Not available |
(67 - 393) |
(87 - 191) |
||
Cadmium
(µg/L) |
<0.1 |
<0.1 |
Not available |
(<0.1 - 0.1) |
(<0.1 - <0.1) |
||
Chromium
(µg/L) |
1 |
<1 |
Not available |
(<1 - 2) |
(<1 - 1) |
||
Copper
(µg/L) |
3 |
1 |
Not available |
(2 - 10) |
(<1 - 9) |
||
Lead
(µg/L) |
1 |
1 |
Not available |
(<1 - 6) |
(<1 - 5) |
||
Zinc
(µg/L) |
26 |
17 |
Not available |
(18 - 97) |
(<10 - 65) |
||
Flow
(L/s) |
Not Measured |
46 |
Not available |
(13 ¡V 210) |
Note:
(1)
Data source: River Water Quality in Hong Kong in 2014 (EPD).
(2)
Data presented are annual arithmetic means of depth-averaged results
except for E. coli and faecal
coliforms that are annual geometric means.
(3) Data in brackets indicate the ranges.
Table 5.7 Summary
Statistics of River Water Quality at Tin Shui Wai Catchment Collected under
this EIA in 2014
Parameters |
Sampling Stations (Figure 5.1) |
WPCO
WQO (in
inland waters) |
||
TSR3 |
HT |
HSK |
||
Dissolved
oxygen (DO) (mg/L) |
5.7 |
5.6 |
5.7 |
Waste discharges shall not cause the level of
dissolved oxygen to be less than 4 mg/L |
(4.2 ¡V 7.2) |
(2.0 - 8.7) |
(2.1 - 10.1) |
||
pH |
8 |
8.3 |
8.6 |
The pH of the water should be within the
range of 6.0-9.0 |
(7.9 ¡V 8.3) |
(8.1 - 8.4) |
(7.8 ¡V 9.8) |
||
Suspended
solids (SS) (mg/L) |
45 |
16 |
11 |
Waste discharges shall not cause the annual
median of suspended solids to exceed 20mg/L |
(18 - 74) |
(7 ¡V 30) |
(8 ¡V 14) |
||
5-day
Biochemical Oxygen Demand (BOD) (mg/L) |
4.9 |
15.0 |
14.1 |
Waste discharges shall not cause the 5-day biochemical
oxygen demand to exceed 5mg/L |
(3.6 ¡V 6.1) |
(2.3 ¡V 36) |
(3.5 ¡V 27) |
||
Chemical
Oxygen Demand (COD) (mg/L) |
26 |
38 |
32 |
Waste discharges shall not cause the chemical
oxygen demand to exceed 30mg/L |
(4 - 39) |
(12 ¡V 68) |
(11 - 54) |
||
Faecal
coliforms (cfu/100mL) |
7,000 |
34,000 |
95,000 |
Not available |
(1,800 - 50,000) |
(1,200 ¡V 420,000) |
(7,200 ¡V 410,000) |
||
E. coli (cfu/100mL) |
4,300 |
20,500 |
72,000 |
Not exceed 1000 per 100 ml,
calculated as the running median of the most recent 5 consecutive samples taken
at intervals of between 7 and 21 days |
(800 ¡V 50,000) |
(1,200 ¡V 280,000) |
(6,900 ¡V 350,000) |
||
Ammonia-nitrogen
(mg/L) |
4 |
3 |
7 |
Not available |
(3 ¡V 6) |
(<0.01 ¡V 6) |
(1 ¡V 13) |
||
Nitrate-nitrogen
(mg/L) |
0.32 |
0.72 |
0.75 |
Not available |
(0.14 ¡V 0.61) |
(0.09 ¡V 1.5) |
(0.24 ¡V 1.30) |
||
Total
Kjeldahl nitrogen (mg/L) |
4.7 |
4.5 |
7.6 |
Not available |
(4 - 6) |
(<0.1 ¡V 9.9) |
(1 ¡V 14) |
||
Ortho-phosphate
(mg/L) |
0.26 |
0.27 |
0.47 |
Not available |
(0.14 - 0.41) |
(0.07 ¡V 0.51) |
(0.07 ¡V
1.1) |
||
Total
phosphorus (mg/L) |
0.42 |
0.5 |
0.72 |
Not available |
(0.3 ¡V 0.65) |
(0.09 ¡V 0.97) |
(0.13 ¡V
1.4) |
||
Total
sulphide (mg/L) |
<0.1 |
<0.1 |
<0.1 |
Not available |
(<0.1 - <0.1) |
(<0.1 - <0.1) |
(<0.1 - <0.1) |
||
Aluminium
(µg/L) |
627 |
74 |
63 |
Not available |
(140 ¡V 1,300) |
(31 ¡V 190) |
(45 ¡V 81) |
||
Cadmium
(µg/L) |
0.14 |
0.10 |
<0.1 |
Not available |
(<0.1 ¡V 0.25) |
(<0.1 ¡V 0.12) |
(<0.1 - <0.1) |
||
Chromium
(µg/L) |
1.8 |
<1 |
1.2 |
Not available |
(<1 ¡V 3.7) |
(<1 - <1) |
(<1 ¡V 1.9) |
||
Copper
(µg/L) |
2.9 |
2.0 |
2.9 |
Not available |
(<1 ¡V 7.2) |
(<1 ¡V 3.6) |
(<1 ¡V 9.5) |
||
Lead
(µg/L) |
2.1 |
1.1 |
1.2 |
Not available |
(<1 - 5) |
(<1 ¡V 1.4) |
(<1 ¡V 2.3) |
||
Zinc
(µg/L) |
31 |
17 |
15 |
Not available |
(21 - 45) |
(<10 ¡V 27) |
(<10 ¡V 19) |
||
Velocity
(L/s) |
0.2 |
0.2 |
2.7 |
Not available |
(0.1 ¡V 0.2) |
(0.2 ¡V 0.2) |
(2.1 ¡V 3.3) |
Note:
(1)
Data source: River Water Sampling conducted on six days in 2014 (on
28 & 30 April, 2 May, 8, 10 & 12 Dec) under this Study.
(2)
Data presented are annual arithmetic means of depth-averaged results
except for E. coli and faecal coliforms
that are annual geometric means.
(3)
Data in brackets indicate the ranges.
Hang Hau Tsuen Channel (HHT)
Table 5.8 Summary
Statistics of River Water Quality at Hang Hau Tsuen Channel Collected under
this EIA in 2014
Parameters |
Additional Stations (Figure
5.1) |
WPCO WQO (in inland waters) |
LFS |
||
Dissolved oxygen (DO) (mg/L) |
5 |
Waste
discharges shall not cause the level of dissolved oxygen to be less than 4
mg/L |
3 ¡V 7.8 |
||
pH |
7.9 |
The pH of the water should be within the
range of 6.0-9.0 |
7.8 ¡V 8.0 |
||
Suspended
solids (SS) (mg/L) |
26 |
Waste discharges shall not cause the annual
median of suspended solids to exceed 20mg/L |
(9 ¡V 53) |
||
5-day
Biochemical Oxygen Demand (BOD) (mg/L) |
11.6 |
Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 5mg/L |
(2.8 ¡V 34) |
||
Chemical
Oxygen Demand (COD) (mg/L) |
38 |
Waste discharges shall not cause the chemical
oxygen demand to exceed 30mg/L |
(22 ¡V 54) |
||
Faecal
coliforms (cfu/100mL) |
24,000 |
Not available |
(10,000 ¡V 340,000) |
||
E. coli (cfu/100mL) |
13,000 |
Not exceed 1000 per 100 ml,
calculated as the running median of the most recent 5 consecutive samples
taken at intervals of between 7 and 21 days |
(3,000 - 100,000) |
||
Ammonia-nitrogen
(mg/L) |
4 |
Not available |
(<0.01 ¡V 5) |
||
Nitrate-nitrogen
(mg/L) |
0.53 |
Not available |
(0.18 ¡V 0.81) |
||
Total
Kjeldahl nitrogen (mg/L) |
4.8 |
Not available |
(<0.1 ¡V 5.5) |
||
Ortho-phosphate
(mg/L) |
0.28 |
Not available |
(0.08 ¡V 0.53) |
||
Total
phosphorus (mg/L) |
0.48 |
Not available |
(0.32 ¡V 0.37) |
||
Total
sulphide (mg/L) |
<0.1 |
Not available |
(<0.1 - <0.1) |
||
Aluminium
(µg/L) |
50 |
Not available |
(40 ¡V 58) |
||
Cadmium
(µg/L) |
0.12 |
Not available |
(<0.1 ¡V 0.21) |
||
Chromium
(µg/L) |
<1 |
Not available |
(<1 - <1) |
||
Copper
(µg/L) |
2.1 |
Not available |
(<1 ¡V 5.4) |
||
Lead
(µg/L) |
1.7 |
Not available |
(<1 ¡V 2.8) |
||
Zinc
(µg/L) |
27 |
Not available |
(<10 ¡V 41) |
||
Velocity
(L/s) |
0.2 |
Not available |
(0.2 ¡V 0.2) |
Note:
(1)
Data source: River Water Sampling conducted on six days in 2014 (on
28 & 30 April, 2 May, 8, 10 &12 Dec) under this Study.
(2)
Data presented are annual arithmetic means of depth-averaged results
except for E. coli and faecal
coliforms that are annual geometric means.
(3)
Data in brackets indicate the ranges.
Small Watercourses along Deep Bay (DB)
Upstream Tributaries of Shan Pui River (SPR)
Tuen Mun River
Table
5.9 Summary
Statistics of River Water Quality at Tuen Mun River Collected by EPD in 2014
Parameters |
Tuen Mun River |
WPCO WQO (in inland waters) |
|||||
TN1 |
TN2 |
TN3 |
TN4 |
TN5 |
TN6 |
||
Dissolved Oxygen (DO) (mg/L) |
4.8 |
8.5 |
6.1 |
6.5 |
5.8 |
6.1 |
Waste discharges shall not
cause the level of dissolved oxygen to be less than 4 mg/L. |
(3.1 ¡V 9.9) |
(6.1 - 11.7) |
(4.2 ¡V 8.7) |
(5.1 ¡V 9.3) |
(4.8 - 7.7) |
(4.1 ¡V 7.3) |
||
pH |
7.7 |
7.6 |
7.7 |
7.7 |
7.6 |
7.6 |
The pH of the water should be
within the range of 6.5-8.5 (for TN2) and 6.0-9.0 (for remaining stations). |
(7.5 ¡V 9.2) |
(7.2 - 8.3) |
(7.3 ¡V 8.2) |
(7.5 ¡V 8.3) |
(7.4 ¡V 8.1) |
(7.0 ¡V 8.1) |
||
Suspended Solids (SS) (mg/L) |
10 |
4 |
3 |
3 |
3 |
3 |
Waste discharges shall not cause the annual median of
suspended solids to exceed 20 mg/L (for TN2) and 25 mg/L (for remaining
stations). |
(5 - 120) |
(<1 - 64) |
(1 - 29) |
(2 - 12) |
(2 - 15) |
(2 - 9) |
||
5-day Biochemical Oxygen
Demand (BOD) (mg/L) |
24 |
3 |
2 |
2 |
2 |
2 |
Waste discharges shall not
cause the 5-day biochemical oxygen demand to exceed 3 mg/L (for TN2) and 5 mg/L (for remaining
stations). |
(10 - 38) |
(<1 - 9) |
(<1 - 6) |
(<1 - 7) |
(<1 - 6) |
(<1 - 4) |
||
Chemical Oxygen Demand (COD)
(mg/L) |
35 |
6 |
7 |
9 |
10 |
6 |
Waste discharges shall not
cause the chemical oxygen demand to exceed 15 mg/L (for TN2) and 30 mg/L (for
remaining stations). |
(18 - 45) |
(4 - 31) |
(4 - 14) |
(5 - 17) |
(6 - 16) |
(2 - 12) |
||
Oil & grease (mg/L) |
0.8 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
<0.5 |
Not available |
(<0.5 ¡V 1.3) |
(<0.5 - 0.6) |
(<0.5 ¡V <0.5) |
(<0.5 - <0.5) |
(<0.5 - <0.5) |
(<0.5 - <0.5) |
||
Faecal coliforms (cfu/100mL) |
540,000 |
65,000 |
48,000 |
59,000 |
51,000 |
21,000 |
Not available |
(94,000 ¡V 2,600,000) |
(29,000 - 350,000) |
(650 - 450,000) |
(7,700 - 300,000) |
(8,900 - 260,000) |
(190 - 500,000) |
||
E. coli (cfu/100mL) |
120,000 |
29,000 |
4,500 |
7,600 |
6,500 |
2,400 |
Not exceed 1000
per 100 ml, calculated as the running median of the most recent 5 consecutive
samples taken at intervals of between 7 and 21 days |
(62,000 - 320,000) |
(11,000 - 61,000) |
(160 - 31,000) |
(1,600 - 50,000) |
(900 - 49,000) |
(10 - 51,000) |
||
Ammonia-nitrogen (mg/L) |
6.55 |
1.45 |
0.36 |
0.33 |
0.35 |
0.41 |
Not available |
(0.35 ¡V 9.30) |
(0.29 - 7.00) |
(0.25 ¡V 0.69) |
(0.15 ¡V 1.20) |
(0.27 ¡V 0.78) |
(0.26 - 0.76) |
||
Nitrate-nitrogen (mg/L) |
0.49 |
2.00 |
0.42 |
0.45 |
0.47 |
0.35 |
Not available |
(<0.01 - 1.60) |
(1.30 - 3.00) |
(0.24 - 0.94) |
(0.23 ¡V.0.96) |
(0.21 ¡V 0.95) |
(0.14 ¡V 1.20) |
||
Total Kjeldahl nitrogen
(mg/L) |
8.85 |
1.85 |
0.68 |
0.65 |
0.66 |
0.62 |
Not available |
(2.70 ¡V 11.00) |
(0.51 ¡V 8.90) |
(0.52 ¡V 1.10) |
(0.28 - 1.60) |
(0.47 ¡V 1.20) |
(0.43 ¡V 1.20) |
||
Ortho-phosphate (mg/L) |
0.58 |
0.22 |
0.04 |
0.03 |
0.03 |
0.04 |
Not available |
(0.16 - 0.91) |
(0.04 - 1.00) |
(<0.01 - 0.06) |
(0.02 - 0.06) |
(0.01 - 0.06) |
(0.01 - 0.06) |
||
Total phosphorus (mg/L) |
0.93 |
0.25 |
0.07 |
0.06 |
0.06 |
0.06 |
Not available |
(0.30 - 1.40) |
(0.05 ¡V 1.20) |
(0.05 - 0.10) |
(0.04 - 0.10) |
(0.05 - 0.10) |
(0.05 - 0.14) |
||
Total sulphide (mg/L) |
0.04 |
<0.02 |
<0.02 |
<0.02 |
<0.02 |
<0.02 |
Not available |
(<0.02 - 0.14) |
(<0.02 - <0.02) |
(<0.02 - <0.02) |
(<0.02 - <0.02) |
(<0.02 - 0.02) |
(<0.02 - <0.02) |
||
Aluminium (µg/L) |
96 |
174 |
144 |
162 |
146 |
80 |
Not available |
(68 ¡V 1,142) |
(92 - 524) |
(<50 - 316) |
(<50 - 279) |
(<50 - 302) |
(<50 - 175) |
||
Cadmium (µg/L) |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
Not available |
(<0.1 - 0.2) |
(<0.1 - 0.1) |
(<0.1 - 0.2) |
(<0.1 - 0.2) |
(<0.1 - 0.1) |
(<0.1 - 0.2) |
||
Chromium (µg/L) |
<1 |
1 |
3 |
3 |
3 |
3 |
Not available |
(<1 - 4) |
(<1 - 4) |
(1 ¡V 5) |
(2 - 5) |
(2 - 5) |
(1 - 6) |
||
Copper (µg/L) |
5 |
2 |
7 |
5 |
5 |
6 |
Not available |
(3 - 69) |
(<1 - 10) |
(4 - 10) |
(2 - 10) |
(2 - 11) |
(3 - 18) |
||
Lead (µg/L) |
1 |
2 |
<1 |
<1 |
1 |
<1 |
Not available |
(<1 - 14) |
(<1 - 12) |
(<1 - 3) |
(<1 - 4) |
(<1 - 3) |
(<1 - 3) |
||
Zinc (µg/L) |
36 |
21 |
23 |
19 |
18 |
22 |
Not available |
(20 - 133) |
(<10 - 93) |
(12 - 62) |
(14 - 45) |
(11 - 42) |
(<10 - 60) |
||
Flow (L/s) |
137 |
14 |
Not Measured |
Not Measured |
Not Measured |
Not Measured |
Not available |
(23 - 270) |
(3 - 102) |
Note:
(1)
Data
source: River Water Quality in Hong Kong in 2014 (EPD).
(2)
Data presented
are in annual medians of monthly samples, except those for faecal coliforms and
E.coli which are in annual geometric
means.
(3)
Figures in
brackets are annual ranges.
Table 5.10 Summary
Statistics of Marine Water Quality of Deep Bay WCZ Collected by EPD in 2014
Parameter |
Inner Deep Bay |
Outer Deep Bay |
WPCO WQOs (in marine
waters) |
||||
DM1 |
DM2 |
DM3 |
DM4 |
DM5 |
|||
Temperature (oC) |
24.2 (14.3 ¡V 32.1) |
24.4 (14.5 - 31.9) |
24.4 (15.1 - 32.0) |
24.2 (15.4 - 30.7) |
24.1 (16.3 - 30.7) |
Not more than 2oC in daily temperature range |
|
Salinity |
15.5 (3.5 - 24.4) |
17.5 (5.6 ¡V 25.8) |
21.2 (10.7 - 29.4) |
22.7 (14.8 - 30.5) |
25.7 (15.3 - 33.0) |
Not to cause more than 10% change |
|
Dissolved Oxygen (DO) (mg/L) |
Depth average |
3.7 (1.3 - 6.1) |
4.6 (2.6 ¡V 6.8) |
5.5 (4.1 ¡V 7.3) |
5.5 (3.8 ¡V 7.4) |
5.8 (4.1 ¡V 7.3) |
Not less than 4 mg/L for 90% of the samples |
Bottom |
Not measured |
Not measured |
Not measured |
5.6 (3.6 ¡V 7.4) |
5.7 (3.6 - 7.2) |
Not less than 2 mg/L for 90% of the samples |
|
Dissolved Oxygen (DO) (% Saturation) |
Depth average |
48 (18 - 73) |
60 (36 - 81) |
73 (60 - 88) |
75 (55 - 89) |
79 (62 - 94) |
- |
Bottom |
Not measured |
Not measured |
Not measured |
75 (53 - 91) |
78 (53 - 97) |
- |
|
pH |
7.4 (7.1 - 7.7) |
7.5 (7.3 ¡V 7.9) |
7.7 (7.5 ¡V 7.9) |
7.8 (7.5 - 8.0) |
7.9 (7.7 - 8.1) |
6.5 - 8.5 (¡Ó 0.2 from natural range) |
|
Suspended Solids (mg/L) |
46.2 (15.0 - 95.0) |
23.0 (13.0 - 41.0) |
15.5 (4.9 - 53.0) |
12.8 (2.9 - 47.5) |
6.3 (2.4 - 10.6) |
Not more than 30% increase |
|
Ammonia Nitrogen (NH3-N) (mg/L) |
2.080 (0.930 - 4.500) |
1.410 (0.330 - 2.800) |
0.536 (0.069 - 1.700) |
0.282 (0.019 - 0.850) |
0.194 (0.024 - 0.657) |
- |
|
Unionised Ammonia (UIA) (mg/L) |
0.026 (0.006 - 0.077) |
0.025 (0.005 - 0.076) |
0.014 (0.001 - 0.045) |
0.006 (<0.001 - 0.011) |
0.005 (<0.001 - 0.011) |
Not more than 0.021 mg/L |
|
Nitrite Nitrogen (NO2-N) (mg/L) |
0.367 (0.170 - 0.560) |
0.291 (0.100 - 0.570) |
0.184 (0.055 - 0.350) |
0.155 (0.036 - 0.360) |
0.124 (0.016 - 0.283) |
- |
|
Nitrate Nitrogen (NO3-N) (mg/L) |
1.030 (0.380 - 2.500) |
0.918 (0.460 - 1.800) |
0.759 (0.410 - 1.100) |
0.730 (0.245 - 1.100) |
0.561 (0.104 - 1.030) |
- |
|
Total Inorganic Nitrogen (TIN) (mg/L) |
3.48 (2.36 ¡V 5.74) |
2.61 (1.56 ¡V 3.75) |
1.48 (0.84 - 3.07) |
1.17 (0.56 - 2.24) |
0.88 (0.24 - 1.82) |
Not more than 0.7 mg/L (for Inner Deep Bay and not more than
0.5mg/L (for Outer Deep Bay) |
|
Total Nitrogen (TN) (mg/L) |
4.17 (2.43 - 6.80) |
3.15 (2.02 ¡V 4.85) |
1.79 (1.12 ¡V 3.77) |
1.39 (0.78 ¡V 2.59) |
1.08 (0.40 ¡V 2.11) |
- |
|
Orthophosphate Phosphorus (Ortho P) (mg/L) |
0.213 (0.110 - 0.320) |
0.183 (0.110 - 0.260) |
0.093 (0.045 - 0.180) |
0.047 (0.032 - 0.070) |
0.033 (0.015 - 0.050) |
- |
|
Total Phosphorus (TP) (mg/L) |
0.31 (0.18 - 0.50) |
0.27 (0.17 - 0.41) |
0.13 (0.08 - 0.24) |
0.07 (0.05 - 0.10) |
0.05 (0.03 - 0.07) |
- |
|
Chlorophyll-a (µg/L) |
6.4 (1.7 - 17.0) |
7.6 (1.8 - 31.0) |
4.7 (0.4 - 18.0) |
1.7 (<0.2 - 5.9) |
2.6 (0.4 ¡V 15.7) |
- |
|
E. coli (cfu/100 mL) |
1300 (72 - 140000) |
380 (36 - 7800) |
37 (<1 - 840) |
90 (19 - 600) |
170 (23 - 450) |
- |
Note:
(1) Data source: Marine Water Quality in Hong Kong in 2014 (EPD).
(2) Except as specified, data presented are depth-averaged values calculated by taking the means of three depths: surface, mid-depth and bottom.
(3) Data presented are annual arithmetic means of depth-averaged results except for E.coli and faecal coliforms that are annual geometric means.
(4) Data in brackets indicate the ranges.
Table 5.11 Summary
Statistics of Marine Water Quality of North Western Water WCZ Collected by EPD
in 2014
Parameter |
Lantau
Island (North) |
Pearl
Island |
Pillar
Point |
Urmston Road |
Chek Lap Kok |
WPCO WQO (in marine waters) |
||
NM1 |
NM2 |
NM3 |
NM5 |
NM6 |
NM8 |
|||
Temperature
(oC) |
23.4 (17.2 -
28.9) |
23.9 |
23.9 (17.3 -
28.9) |
24.0 |
24.3 |
23.8 |
Not
more than 2oC in daily temperature range |
|
Salinity |
30.2 (25.2 -
32.3) |
28.3 |
28.0 |
27.1 (20.4 -
32.2) |
25.3 (10.1 -
32.5) |
28.5 |
Not to cause more than 10%
change |
|
Dissolved Oxygen
(DO) (mg/l) |
Depth average |
5.6 (3.2 - 8.5) |
5.8 |
5.8 |
5.7 |
6.3 |
6.2 |
Not less than 4 mg/l for
90% of the samples |
Bottom |
5.4 (1.9 - 9.5) |
5.7 (3.2 - 9.5) |
5.7 |
5.6 |
6.3 (4.2 - 9.2) |
5.8 |
Not less than 2 mg/l for
90% of the samples |
|
Dissolved Oxygen (DO) (%
Saturation) |
Depth average |
77 (46 - 108) |
80 |
80 |
77 |
86 |
85 |
- |
Bottom |
75 (27 - 121) |
79 |
79 |
77 |
86 |
80 |
- |
|
pH |
7.9 (7.6 - 8.0) |
7.9 |
7.9 |
7.8 |
7.9 |
8.0 |
6.5 - 8.5 (¡Ó 0.2 from natural range) |
|
Suspended Solids (SS) (mg/l) |
6.6 |
4.3 (1.5 - 12.3)
|
7.6(2.0 - 30.0) |
6.8 |
8.6 (2.6 - 44.0) |
9.0 |
Not more than 30% increase |
|
Ammonia Nitrogen (NH3-N) (mg/L) |
0.093 |
0.107 (0.014 -
0.260) |
0.108 (0.006 -
0.277) |
0.122 |
0.091 (<0.005
- 0.243) |
0.041 (0.006 - 0.094) |
- |
|
Unionised Ammonia (UIA)
(mg/L) |
0.003 |
0.003 |
0.003 |
0.004 (<0.001
- 0.008) |
0.003 |
0.002 |
Not more than 0.021 mg/l for annual mean |
|
Nitrite Nitrogen (NO2-N) (mg/L) |
0.058 (0.023 -
0.115) |
0.081 |
0.091 |
0.108 (0.022 -
0.323) |
0.108 |
0.067 |
- |
|
Nitrate Nitrogen (NO3-N) (mg/L) |
0.268 (0.067 -
0.603) |
0.394 |
0.426 |
0.480 (0.047 -
1.010) |
0.544 |
0.364 |
- |
|
Total Inorganic Nitrogen
(TIN) (mg/L) |
0.42 |
0.58 |
0.63 |
0.71 |
0.74 (0.10 -
1.51) |
0.47 |
Not more than 0.5 mg/l for annual mean |
|
Total Nitrogen (TN) (mg/L) |
0.59 |
0.78 |
0.81 |
0.89 |
0.93 |
0.63 |
- |
|
Orthophosphate Phosphorus (PO4) (mg/L) |
0.021 |
0.023 |
0.025 |
0.028 |
0.022 |
0.015 |
- |
|
Total Phosphorus (TP) (mg/L) |
0.04 |
0.04 |
0.04 |
0.05 |
0.04 (<0.02 -
0.07) |
0.03 (<0.02 - 0.06) |
- |
|
Chlorophyll-a (µg/L) |
2.0 |
2.3 |
2.7 (0.3 - 11.0) |
3.3 |
3.8 |
3.8 |
- |
|
E. coli (cfu/100 mL) |
300 (36 - 2200) |
71 |
110 |
190 |
22 |
3 |
- |
Note:
(1) Data source: Marine Water Quality in Hong Kong in 2014 (EPD).
(2) Data presented are annual arithmetic means of
depth-averaged results except for E.coli
and faecal coliforms that are annual geometric means.
(3) Data in brackets indicate the ranges.
¡P EPD River Water Quality in Hong Kong in 2014;
¡P EPD Marine Water Quality in Hong Kong in 2014;
¡P Government aerial photos;
¡P GeoInfo Map from Lands Department;
¡P Approved EIA Report for Deep Bay Link;
¡P Approved EIA Report for Shenzhen Western Corridor;
¡P Approved EIA Report for Upgrading and Expansion of San Wai Sewage Treatment Works (SW STW) and Expansion of Ha Tsuen Sewage Pumping Station;
¡P Approved EIA for Hang Hau Tsuen Channel at Lau Fau Shan; and
¡P Approved EIA for Expansion of Hong Kong International Airport into a Three-Runway System.
¡P Site formation and demolition of existing buildings;
¡P Construction of new infrastructure including: footbridges, cycle bridges, new buildings, Flushing Water Service Reservoirs (FLWSR), Fresh Water Service Reservoirs (FWSR), sewerage / drainage / road / street networks, SPS, new HSK STW, eco trail, cultural heritage trail, cycle track / cycle way, parks, Environmentally Friendly Transport Services (EFTS), EFTS depot, proposed West Rail HSK Station (HSK Station), Public Transport Interchange (PTI), petrol / Liquefied Petroleum Gas (LPG) filling stations, Refuse Transfer Station (RTS), District Cooling System (DCS), electricity substations, channel revitalisation and greening works and flood retention facilities (involving flood retention lakes), etc.;
¡P General construction activities;
¡P Construction site run-off;
¡P Construction works near watercourses;
¡P Construction works in watercourses / reinforced concrete flood storage pond;
¡P Removal or diversion of watercourses;
¡P Removal or filling of ponds and wet areas;
¡P Accidental spillage;
¡P Sewage from construction workforce;
¡P Groundwater from contaminated areas, contaminated site run-off and wastewater from land decontamination; and
¡P Sewerage diversion works.
General Construction Activities
Construction Site Run-off
Table 5.12 Averaged Daily
Construction Site Run-off for the Project by Stages
Phase (refer to Figure
2.18) |
Approximate Area
(km2) |
Approximate Daily
Volume of Construction Site Run-off (m3/day) |
ASEP Phase 1 (see Note 1) |
0.002 |
1 |
ASEP Phase 2 (see Note 1) |
0.038 |
22 |
ASEP Phase 3 (See Note 1) |
0.470 |
268 |
Stage 1 |
0.024 |
14 |
Stage 2 |
1.365 |
777 |
Stage 3 |
2.008 |
1,144 |
Stage 4 |
0.619 |
353 |
Note 1: ASEP ¡V Advance Site
Formation and Engineering Infrastructure Project
Table 5.13 Averaged Daily
Construction Site Run-off for DP1, DP2, DP5, DP6, DP9 and DP 12
DP (refer to Section 5.1.2) |
Approximate Area
(km2) |
Approximate Daily
Volume of Construction Site Run-off (m3/day) |
DP1 |
0.108 |
62 |
DP2 |
0.307 |
175 |
DP5 |
0.009 |
5 |
DP6 |
0.005 |
3 |
DP9 |
0.009 |
5 |
DP12 |
0.004 |
2 |
¡P Run-off and erosion of exposed bare soil and earth, drainage channel, earth working area and stockpiles;
¡P Release of any bentonite slurries, concrete washings and other grouting materials with construction run-off or stormwater;
¡P Wash water from dust suppression sprays and wheel washing facilities; and
¡P Fuel, oil and lubricants from maintenance of construction vehicles and equipment.
Construction Works near Watercourses
Construction Works in Watercourses / Concrete Flood Storage Pond
Removal / Diversion of Watercourses
Table 5.14 Minor
Sections of Watercourses to be Removed or Diverted
Name of Water Section to be
Removed or Diverted |
Description |
Remarks |
Figure Reference |
Water Sections belong to the
tributaries of Tin Shui Wai Main Channel (TSW): |
|||
TSW3 |
A
small upstream water section of Lo Uk Tsuen Tributaries (in the middle west
portion of the Project area) |
To be
removed under the Project |
Figure
5.2.8 (see middle left) |
TSW1A |
A
minor water section (in the southern Project area) that finally drain into
Tin Sam Channel |
To be
removed under the Project |
Figure
5.2.9 (see left hand side) |
TSW1B |
A
minor water section (in the southern Project area) that finally drain into
Tin Sam Channel |
To be
removed under the Project |
Figure
5.2.9 (see left hand side) |
TSW1C |
A
minor water section (in the southern Project area) that finally drain into
Tin Sam Channel |
To be
removed under the Project |
Figure
5.2.9 (see left hand side) |
TSW1D |
A
minor water section (in the southern Project area) that finally drain into
Tin Sam Channel |
To be
removed under the Project |
Figure
5.2.9 (see left hand side) |
TSW4 |
A
section of Tin Sam Channel (in the southern Project area) |
To be
realigned under the Project |
Figure
5.2.9 (see left hand side) |
TSW2 |
A
minor water section (in the northern Project area) that finally drain into
the TSW Main Channel |
To be
removed under the Project |
Figure
5.2.7 (see upper right) |
TSW2A |
A
minor water section (in the northern Project area) that finally drain into
the TSW Main Channel |
To be
removed under the Project |
Figure
5.2.7 (see upper right) |
TSW2B |
A
minor water section (in the northern Project area) that finally drain into
the TSW Main Channel |
To be
removed under the Project |
Figure
5.2.7 (see upper right) |
TSW5 |
A
minor water section (in the eastern tip of Project area) that finally drain
into the TSW Main Channel |
To be
removed under the Project |
Figures
5.2.12 (see lower left), Figure
5.2.13 (see upper left corner) |
Water Sections belong to the
tributaries of Hang Hau Tsuen (HHT): |
|
||
HHT1 |
A
side branch Hang Hau Tsuen Channel in the northern Project area |
To be
removed under the Project |
Figure
5.2.1 |
HHT2 |
An
upstream section of Hang Hau Tsuen Channel in the northern Project area |
To be
removed under the Project |
Figure
5.2.7 (see upper middle) |
Water Section belongs to the
tributaries of Tuen Mun River (TMR): |
|
||
TMR1 |
An
upstream section of the Tuen Mun River in the southern tip of Project area |
To be
removed under the Project |
Figure
5.2.5 (see upper right) |
Removal / Filling of Ponds and Wet Areas
Table
5.15 Ponds and Wet Areas to be
Completely or Partially Removed
ID |
Description |
Location |
Within Project Area? (Yes /No) |
Figure Reference |
Remarks |
P8B |
Inactive
fish pond |
At the
northern part of Project area to the south of Fung Kong Tsuen |
Yes |
Figure
5.2.7 |
P8B will
be removed under the Project |
P8C |
Inactive
fish pond |
At the
northern part of Project area to the south of Fung Kong Tsuen |
Yes |
Figure
5.2.7 |
P8C will
be removed under the Project |
P10 |
Inactive
fish pond |
At the southern
portion of Project area to the west of San Lee Uk Tsuen |
Yes |
Figure
5.2.9 |
P10 will
be removed under the Project |
A2B |
Wet
agricultural area |
At the
border of ¡§V¡¨ area in middle portion of the Project area |
Yes |
Figure
5.2.8 |
Part of
A2B, A3C, A3D located outside the ¡§V¡¨ will be removed under the Project |
A2C |
Wet
agricultural area |
At the
border of ¡§V¡¨ area in middle portion of the Project area |
Yes |
Figure
5.2.8 |
|
A2D |
Wet
agricultural area |
At the
border of ¡§V¡¨ area in middle portion of the Project area |
Yes |
Figure
5.2.8 |
|
A3A |
Wet
agricultural area |
At the
southern part of the Project area near the upstream tributaries of Tuen Mun
River |
Yes |
Figure
5.2.5 |
A3A will
be removed under the Project |
Accidental Spillage
Sewage from Construction Workforce
Groundwater from Contaminated Areas, Contaminated Site Run-off and Wastewater from Land Decontamination
Sewage Disposal Strategy for the New Developments
Pollution Loading to North Western WCZ
Table 5.16 Existing and Likely Future Point
Source Loading to North Western WCZ from Urmston Road Outfall
Parameter |
Unit |
Existing Condition,
see Note 1 |
Likely Future
Condition Assumed in Approved EIA for SW STW (without this Project), see
Note 1 |
Likely Future
Condition Assumed under
this EIA (with this
Project) see Notes 1 & 2 |
||
SW STW Phase 1 only (2026) |
plus HSK STW
Phase 1 (2031) |
plus HSK STW
Phase 2 (2037/38) |
||||
TSE Discharge |
m3
/day |
164,000 (see Note 4) |
246,000 (see Note 5) |
200,000 (see Note 6) |
231,051 (see Note 7) |
245,696 (see Note 8) |
Biochemical Oxygen Demand (BOD) |
kg/day |
37,064 |
24,600 |
20,000 |
20,621
|
20,914 |
Suspended Solids (SS) |
kg/day |
33,784 |
13,530 |
11,000 |
11,932
|
12,371
|
Ammonia Nitrogen (NH3-N) |
kg/day |
3,570 |
6,150 |
5,000 |
5,062 |
5,091 |
Organic
Nitrogen (Org-N) |
kg/day |
2,952 |
2,165 |
1,760 |
1,822
|
1,851
|
Total
Inorganic Nitrogen (TIN), see Note 3 |
kg/day |
3,928 |
6,150 |
5,000 |
5,248
|
5,366 |
Total Nitrogen (TN) |
kg/day |
6,880 |
8,315 |
6,760 |
7,071
|
7,217
|
Total Phosphorus (TP) |
kg/day |
940 |
556 |
452 |
522
|
555 |
E. coli |
no./day |
2.89E+16 |
4.92E+08 |
4.00E+08 |
4.03E+08 |
4.05E+08 |
Note:
(1)
The effluent
concentrations / standards used for compiling the pollution loading are
detailed in Appendix
5.2. The existing and upgraded SW STW would adopt preliminary treatment and
CEPT with disinfection respectively.
The HSK STW (Phase 1 and Phase 2) is assumed to employ secondary
treatment plus disinfection and 75% N removal subject to further detailed EIA
studies. The effluent standards of the HSK STW is subject to further studies
during the EIA stage of this STW.
(2)
TSE discharge from
YLS STW is assumed to be disposed locally in Deep Bay WCZ under this EIA study.
(3)
Total inorganic nitrogen
(TIN) is equal to the sum of ammonia nitrogen (NH3-N), nitrate nitrogen (NO3-N)
and nitrite nitrogen (NO2-N)
(4)
Design flow of
existing SW STW (with preliminary treatment)
(5)
Design flow of
upgraded SW STW assumed in the approved EIA for SW STW
(6)
Design flow of
upgraded SW STW (Phase 1). The flow
due to the new development of HSK NDA in year 2026 (14,538 m3/day as mentioned
in Table 6.9) is assumed to be treated by SW STW (see Section 6.6.3).
(7)
noCombined TSE flow
of upgraded SW STW and new HSK STW (Phase 1) assumed in this EIA, with
consideration of the flow reduction due to the proposed water reclamation
facilities. According to Section 5.11.5 and Table 6.9, about 31,051 m3/day will be treated by secondary plus
treatment (with UV disinfection and 75% nitrogen removal) and discharged to
Urmston Road Outfall during HSK STW , while the rest (45,137 m3/day - 31,051
m3/day = 14,086 m3/day) will be treated by tertiary treatment for reclaimed
water reused in the Project.
(8)
Combined TSE flow
of upgraded SW STW and new HSK STW (Phase 1 and 2) assumed in this EIA, with
consideration of the flow reduction due to the proposed water reclamation
facilities. According to Section 5.11.5 and Table 6.10, about 45,696 m3/day will be treated by secondary plus
treatment (with UV disinfection and 75% nitrogen removal) and discharged to
Urmston Road Outfall from HSK STW , while the rest (85,500 m3/day - 45,696
m3/day = 39,804 m3/day) will be treated by tertiary treatment for reclaimed
water reused in the Project.
Pollution Loading to
Deep Bay WCZ
Table 5.17 Existing
and Likely Future Sewage Loading to Deep Bay WCZ (Without this Project)
Parameter |
Unit |
Existing
Condition (without this Project), see Notes 1 and 2 |
Likely Future Condition (without this Project), see Notes 1
and 2 |
Sewage flow |
m3
/day |
1,616 |
1,895 |
BOD |
kg/day |
182 |
213 |
SS |
kg/day |
89 |
104 |
NH3-N |
kg/day |
46 (see Note 3) |
54
(see Note 3) |
Org-N |
kg/day |
see Note 3 |
see Note 3 |
TN |
kg/day |
46 |
54 |
TP |
kg/day |
9 |
11 |
E. coli |
no./day |
2.95 x1011 |
3.46E+11 |
Note:
(1)
Only areas to be
redeveloped under this Project are considered in the loading estimation. Project areas that will not be developed
under this Project (e.g. ¡§GB¡¨ and existing ¡§V¡¨ areas) are excluded in the
estimation.
(2)
All sewage
generated from the unsewered areas would be discharged to septic tanks and
soakaway system. The loading given in this table represents the residual
loading after treatment by septic tanks. Further load reduction due to the
soakaway system is excluded in this estimation, which is a conservative
approach. With consideration of the
soakaway facilities, the actual loading to Deep Bay would be smaller than that
shown in this table.
(3)
With reference to
the approved EIA Report for ¡§Liantang / Heung Yuen Wai Boundary Control Point
and Associated Works¡¨, the amount of NH3-N in the effluent of septic
tank would be increased (due to the conversion of Org-N to NH3-N)
after the
biological reactions within the septic tank but it will not exceed the amount
of TN in the effluent, Thus, the Org-N loading is assumed to be negligible.
Sewage Overflow or Emergency Bypass due to Capacity Constraints, Aging or Damage of the Sewerage Network
Sewage Pumping Stations (DP9)
Table 5.18 Design
Capacities of Sewage Pumping Stations (DP9)
SPS |
Estimated Sewage Flow (m3/day) (1) |
Design Capacities (m3/day) |
SPS No. 1 |
26,641 |
27,000 |
SPS No. 2 |
39,130 |
39,500 |
SPS No. 3 |
10,957 |
11,000 |
SPS No. 4 |
67,943 |
68,000 |
Note:
(1) Estimated sewage flow of pumping stations SPS1, SPS2, SPS3 and SPS4 in
year 2037/38 as mentioned in Table 6.14.
Table 5.19 Tentative
Discharge Points of Emergency Overflow from SPS and Downstream Receiving Water
SPS (see Figure 5.5) |
Discharge Point of Emergency Overflow and
Downstream Receiving Water (refer to Table 5.3 for detailed description
of Receiving Water) |
SPS No.
1 |
Tin Sam
Channel, which would then discharge to the TSW Main Channel and finally to
the marine water of Deep Bay WCZ. |
SPS No.
2 |
A side branch
of Tin Sam Channel, which would firstly drain into Tin Sam Channel and then
discharge to the TSW Main Channel and finally to the marine water of Deep Bay
WCZ. |
SPS No.
3 |
Tin Sam
Channel, which would then discharge to the TSW Main Channel and finally to
the marine water of Deep Bay WCZ. |
SPS No.
4 |
Lo Uk
Tsuen Tributaries, which would then enter the TSW Main Channel and finally to
the marine water of Deep Bay WCZ. |
Emergency Discharge from the New HSK STW
Table 5.20 Emergency
Discharge Scenarios for the New HSK STW
Scenario |
Discharge Route |
Receiving Water Body |
(A) New HSK STW not
functioning and no treatment of the incoming sewage |
Raw sewage ® NWNT Tunnel ® Urmston Road Outfall |
North
Western waters |
(B) NWNT Tunnel / Urmston Road Outfall not in
operation |
Treated effluent ® TSW Main Channel ® Deep Bay |
Deep Bay
waters |
(C) New
HSK STW and NWNT Tunnel / Urmston Road Outfall not in operation or breakdown
of SPS |
Raw sewage ® TSW Main Channel ® Deep Bay |
Deep
Bay waters |
Surface Run-off from New Developments
Areas to be Developed under this Project
Existing / Future Paved Area (Without this Project)
Future Paved Area (With this Project)
Non-Point Source Pollution from Surface Run-off
Table 5.21 Non-Point Source Pollution
from Area to be Developed under the Project
Parameters |
Approximate Loading under
Existing Condition and Likely Future Condition (without this Project) |
Approximate Loading
(kg/day) under Likely Future Condition (with this Project) |
SS (kg/day) |
612 |
542 |
BOD (kg/day) |
318 |
282 |
NH3-N (kg/day) |
3 |
3 |
Org-N (kg/day) |
17 |
15 |
TIN (kg/day), See Note 1 |
8 |
8 |
TN (kg/day) |
25 |
23 |
TP (kg/day) |
3 |
3 |
Surface Run-off from Major Roads (DP1, DP2, DP5, DP6 and DP12)
Table 5.22 Average Daily Run-off from Major
Roads
DP |
Area (km2) |
Surface Run-off (m3/day) |
DP1 |
0.108 |
369 |
DP2 |
0.307 |
1,049 |
DP5 |
0.009 |
31 |
DP6 (See Note 1) |
0.005 |
See
Note 1 |
DP9 |
0.009 |
31 |
DP12 |
0.004 |
14 |
Total |
0.442 |
1,494 |
Note 1: DP6 is enclosed by decking and
therefore the generation of rainwater run-off from DP6 is assumed to be
negligible.
Changes of Hydrology and Potential Flooding Risk
Potential Flooding Risk Resulting from Hydrological Changes
Change of Existing Drainage Regime and Water Quality in Tin Shui Wai Main Channel and Inner Deep Bay
Change of Flow Regime and Hydrology
Change of Ground Water Levels
Revitalisation and Greening of Drainage Channel Banks
Discharge from the Potential District Cooling System (DCS)
Water Reclamation Facility
Table 5.23 Water
Quality Standards
for Reclaimed Water
Parameter |
Unit |
Reclaimed Water Quality |
E. coli |
cfu/100ml |
Non detectable |
Total Residual Chlorine |
mg/L |
≥1 (out of
treatment system) ≥ 0.2 (at point-of-use) |
Dissolved Oxygen |
mg/L |
≥2 |
TSS |
mg/L |
≤5 |
Colour |
Hazen Unit |
≤20 |
Turbidity |
NTU |
≤5 |
pH |
- |
6 to 9 |
Odour |
Threshold odor no. |
≤100 |
BOD5 |
mg/L |
≤10 |
Ammonia Nitrogen |
mg/L as N |
≤1 |
Synthetic Detergents |
mg/L |
≤5 |
Proposed HSK Station
Environmentally Friendly Transport Services and EFTS Depot
Public Transport Interchange and Petrol Filling Stations
¡§Industrial¡¨ and ¡§Port Back-up, Storage and Workshop Uses¡¨ Sites
Concrete Batching
Plants in ¡§Industry¡¨ Zone
¡§Industry¡¨ Zone and ¡§Port Back-up,
Storage and Workshop Uses¡¨ Areas
Surface Discharge
from the Open Areas of ¡§I¡¨ Zone and ¡§PBU + SWU¡¨ Areas
Refuse Transfer Stations and Refuse Collection Points
Maintenance of Drainage System
Fresh Water Service Reservoir (FWSR)
Flushing Water Service Reservoirs (FLWSR) for Use of Reclaimed Water
¡P Yuen Long and Kam Tin sewerage treatment upgrade - Upgrading of San Wai Sewage Treatment Works - Investigation, Design and Construction
Construction Site Run-off and General Construction Activities
¡P prevent or minimise the likelihood of pollutants (generated from construction activities) being in contact with rainfall or run-off; and
¡P abate pollutants in the stormwater surface run-off prior to the discharge of surface run-off to the nearby water bodies.
Construction Site Run-off
Boring and Drilling Water
Wheel Washing Water
Acid Cleaning, Etching and Pickling Wastewater
Effluent Discharge
Construction Works near Watercourses
¡P Impermeable sheet piles and cofferdams should be used as required to divert water flow from the construction works area so that all the construction works would be undertaken within a dry zone and physically separated from the watercourses.
¡P The proposed works should preferably be carried out within the dry season where the flow in the stormwater culvert / water channel / stream is low.
¡P The use of less or smaller construction plants may be specified in works areas close to the inland water bodies.
¡P Temporary storage of materials (e.g. equipment, filling materials, chemicals and fuel) and temporary stockpile of construction materials should be located well away from any watercourses during carrying out of the construction works.
¡P Stockpiling of construction materials and dusty materials should be covered and located away from any watercourses.
¡P Construction debris and spoil should be covered up and/or disposed of as soon as possible to avoid being washed into the nearby water receivers.
¡P Construction activities, which generate large amount of wastewater, should be carried out in a distance away from the watercourses, where practicable.
¡P Mitigation measures to control site run-off from entering the nearby water environment should be implemented to minimise water quality impacts. Surface channels should be provided along the edge of the waterfront within the work sites to intercept the run-off.
¡P Construction effluent, site run-off and sewage should be properly collected and/or treated.
¡P Any temporary works site inside the stormwater watercourses should be temporarily isolated, such as by placing of sandbags or silt curtains with lead edge at bottom and properly supported props to prevent adverse impact on the stormwater quality.
¡P Proper shoring may need to be erected in order to prevent soil / mud from slipping into the inland water bodies.
Revitalisation and Greening of Drainage Channel Banks
¡P Impermeable sheet piles and cofferdams should be used as required to divert water flow from the construction works area so that all the construction works would be undertaken within a dry zone and physically separated from the revitalised drainage channel water.
¡P The proposed works should preferably be carried out within the dry season where the flow in the revitalised drainage channel is low.
¡P The use of less or smaller construction plants may be specified in works areas close to the revitalised drainage channel.
¡P Temporary storage of materials (e.g. equipment, filling materials, chemicals and fuel) and temporary stockpile of construction materials should be located well away from the revitalised drainage channel during carrying out of the construction works.
¡P Stockpiling of construction materials and dusty materials should be covered and located away from the revitalised drainage channel water.
¡P Construction debris and spoil should be covered up and/or disposed of as soon as possible to avoid being washed into the nearby revitalised drainage channel.
¡P Construction activities, which generate large amount of wastewater, should be carried out a distance away from the revitalised drainage channel, where practicable.
¡P Mitigation measures to control site run-off from entering the nearby revitalised drainage channel should be implemented to minimise water quality impacts. Surface channels should be provided along the edge of the revitalised drainage channel within the work sites to intercept the run-off.
¡P Construction effluent, site run-off and sewage should be properly collected and/or treated.
¡P Any temporary works site inside the revitalised drainage channel should be temporarily isolated, such as by placing of sandbags or silt curtains with lead edge at bottom and properly supported props to prevent adverse impact on the revitalised drainage channel water.
¡P Proper shoring may need to be erected in order to prevent soil / mud from slipping into the revitalised drainage channel.
Construction Works in Watercourses / Concrete Flood Storage Pond
Removal / Diversion of Watercourses
Removal / Filling of Ponds and Wet Areas
Accidental Spillage
¡P Suitable containers should be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport.
¡P Chemical waste containers should be suitably labelled, to notify and warn the personnel who are handling the wastes, to avoid accidents.
¡P Storage area should be selected at a safe location on site and adequate space should be allocated to the storage area.
Sewage Effluent from Construction Workforce
Groundwater from Contaminated Areas, Contaminated Site Run-off and Wastewater from Land Decontamination
Emergency Response Plan for Construction Site Discharges
¡P Provide spare or standby treatment facilities of suitable capacities for emergency replacement in case damage or defect or malfunctioning of the duty treatment facilities is observed.
¡P Conduct daily integrity checking of the construction site drainage and treatment facilities to inspect malfunctions, in particular before, during and after a storm event.
¡P Carry out regular maintenance or desilting works to maintain effectiveness of the construction site drainage and treatment facilities in particular before, during and after a storm event.
Sewerage Diversion
Disposal of Sediment
DP1, DP2, DP5, DP6, DP9 and DP12
TSE Discharge and Sewerage Network
¡P Regular inspection, checking and maintenance of the sewerage system;
¡P Provisions of twin rising mains as backup and to facilitate maintenance and repairing purposes;
¡P Provisions of leakage collection systems linking to the nearest chamber at its downstream to the rising main for collection of sewage leakage from the damaged rising main;
¡P Use tankers to store emergency discharge and transport to the STW for disposal in case of both twin rising mains failure; and
¡P Provisions of spare / standby parts of sewage pipeworks to facilitate maintenance and repairing of equipment.
Sewage Pumping Stations
¡P A standby pump and screen should be provided to cater for breakdown and maintenance of the duty pump in order to avoid emergency discharge.
¡P Backup power supply in the form of dual / ring circuit power supply or generator should be provided to secure electricity supply.
¡P An alarm should be installed to signal emergency high water level in the wet well.
¡P An emergency storage tank / spare volume of wet well should be provided for the proposed SPS to cater for breakdown and maintenance of duty pump.
¡P Regular maintenance and checking of plant equipment should be undertaken to prevent equipment failure.
¡P Twin rising mains system should be provided to facilitate maintenance works and to avoid emergency discharge of sewage.
¡P A telemetry system to the nearest manned station / plant should be provided so that swift action can be undertaken in case of malfunction of the unmanned facilities.
¡P A bar screen (with clear spacing of approximately 25 mm) should be provided to cover the lower half of the opening of any emergency sewage bypass which can prevent the discharge of floating solids into receiving waters as far as practicable while ensuring flooding at the facilities would not occur event if the screen is blocked.
¡P Locations of water bodies or WSRs in the vicinity of the emergency discharges.
¡P A list of relevant government departments to be informed and to provide assistance in the event of emergency discharge, including key contact persons and telephone numbers.
¡P Reporting procedures required in the event of emergency discharges.
¡P Procedures listing the most effective means in rectifying the breakdown of the SPS in order to minimise the discharge duration.
Best Stormwater Management Practices and Stormwter Pollution Control Plan
Design Measures to Control Erosion and Run-off Quantity
Devices and Facilities to Control Sedimentation, Run-off Quality, Prevent ¡§First Flush¡¨ Pollution, Eliminate Pollutants in Point Source Discharge from Drainage Outfalls and Eliminate Pollutant Discharges into the Poor Flushing Water of Deep Bay WCZ
Administrative Measures to Control Sedimentation, Run-off Quality, Prevent ¡§First Flush¡¨ Pollution, Eliminate Pollutants in Point Source Discharge from Drainage Outfalls and Eliminate Pollutant Discharges into the Poor Flushing Water of Deep Bay WCZ
Blue-green Infrastructure to Control Sedimentation and Run-off Quantity
¡P Provision of bioswales, where practicable at roadside, to convey stormwater and provide removal of coarse and medium sediments. As the water is transported along the bioswales, it is treated to remove pollutants and the cleaned water can then be discharged into the receiving water bodies or retained for non-potable reuse, e.g. irrigation.
¡P Rainwater harvesting should be implemented within the development site, where possible, to collect rainwater from building roofs, podiums, walkway canopies and other built structures for reuse as an alternative water source e.g. irrigation. The system should meet the prevailing WSD guidelines.
¡P Porous paving material should be used, where practical to increase stormwater infiltration and improve groundwater recharge and reducing flooding from surface run-off.
Stormwater Pollution Control Plan
¡§Industrial¡¨ and ¡§Port Back-up, Storage and Workshop Uses¡¨ Sites
Concrete Batching Plants in ¡§Industry¡¨ Zone
Multi-storey Industrial Buildings in ¡§Industry¡¨ Zone and ¡§Port Back-up, Storage and Workshop¡¨ Areas
¡P Contact personnel and the means to contact.
¡P Procedures to initiate emergency repairs.
¡P Procedures to temporarily divert the incoming effluent to any designated temporary holding facility.
¡P
Procedures to partially / fully treat effluents
at an alternative treatment facility.
Surface Discharge from the Open Areas of ¡§Industry¡¨ Zone and ¡§Port Back-up, Storage and Workshop¡¨ Areas
¡P Contact personnel and the means to contact.
¡P Procedures to contain contaminants and prevent their escape and/or dispersion, e.g., through closing the stop-logs to isolate in the lot¡¦s perimeter drainage system from the surrounding stormwater drainage system.
¡P Procedures to divert / transport the contaminated materials to a designated temporary storage area or appropriate treatment facility.
¡P Procedures to clear up the lot and/or perimeter drainage system prior to opening the stop-logs.
Control of Operational Site Effluents
Maintenance of Drainage System
DP1, DP2, DP5, DP6, DP9 and DP12
Sewage Pumping Station (DP9)
New Roads (DP1, DP2, DP5, DP6 and DP12)
Other DPs
¡P DP3 - Construction of new West Rail HSK Station (Site 4-34)
¡P DP4 - Construction of EFTS ¡V subject to further review
¡P DP7 - Construction of a new container back-up and storage area (Site 3-1, 3-4, 3-5, 3-13 and 3-14) - subject to further review
¡P DP8 - Construction of new HSK STW (Site 3-26 and part of existing SW STW)
¡P DP10 - Construction of Flushing Water Service Reservoirs for reuse of reclaimed water at Tan Kwai Tsuen and Fung Kong Tsuen (Sites 3-3 and 5-40)
¡P DP11 - Construction of one RTS (Site 3-12)
Construction Phase
Operation Phase
([1])
Source: Base Map Data from Lands Department in 2016 (GeoInfo Map: http://www1.map.gov.hk/gih3/view/index.jsp).
([2]) The polder schemes include perimeter bunds to
prevent the ingress of flood water into the low-lying villages and pumping stations
to discharge the flood water within the bund to the nearby drainage
system. P8A, P9A, P9B and P10C are
part of the polder schemes to retain run-off from flowing into the low-lying
village areas.