(REF. 113-03)

TABLE OF CONTENTS

 

14        Summary of Environmental Outcomes. 14-1

14.1     Overview.. 14-1

14.2     Environmental Benefits of the Project 14-1

14.3     Environmentally Friendly Options Considered and Incorporated in the Preferred Option  14-2

14.4     Environmental Design Recommended. 14-4

14.5     Key Environmental Problems Avoided and Environmentally Sensitive Areas Protected  14-7

14.6     Estimated Population Protected from Various Environmental Impacts. 14-9

14.7     Environmental Benefits of the Project and Environmental Protection Measures Recommended  14-10

14.8     Compensation Areas and Enhancements Included. 14-15

 


 

 


14                  Summary of Environmental Outcomes

14.1                 Overview

14.1.1            This chapter summarises the key environmental outcomes arising from the EIA Study. Chapter 2 outlines the alternatives considered during the optioneering process, which has taken account of public views and findings of various technical assessments.  Alternative options for land uses, designs and construction methodologies have been duly considered throughout the process in response to the public aspirations collated during the public engagement exercises. The technical assessments (Chapter 3 to 12) conducted have demonstrated that all the statutory requirements in EIA Study Brief (EIA SB No.: ESB-291/2015) and Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) have been compiled with (see also Appendix 1.1).

14.1.2            The following sections summarise the approaches that have been adopted to either avoid or minimise various environmental impacts throughout the design process, and the associated environmental enhancements and compensation measures.

 

14.2                 Environmental Benefits of the Project

14.2.1            The Project aspires to turn the existing vast extent of brownfield operations including container storage, port back-up, construction material/machinery storage, car repair workshops, recycling yards, and rural workshops, etc., which have created considerable environmental, traffic, visual, and other problems, to more optimal uses and better land utilisation for the future development of Hong Kong.  The development of the Project could result in the following local and strategic benefits:

·                The re-arrangement of the road network by replacement of Tin Ying Road and downgrading of Hung Tin Road will reduce the existing road traffic noise and minimise air pollutants generated from road traffic. The proposal for replacement of Tin Ying Road also provides an opportunity to integrate a leisure riverside promenade along the river channel and facilitate better connectivity between Tin Shui Wai (TSW) New Town and the Project area.

·                At present, the proliferation of brownfield operations in the Project area has created considerable environmental, traffic, visual, flooding and other problems. One of the objectives of developing the Project is to convert these brownfield sites to more optimal uses and improve the overall environment of the area.  Approximately 24 ha of land at the northern fringe of the Project area is reserved “Port Back-up, Storage and Workshop Uses” (“PBU+SWU”). This area may accommodate some of the existing brownfield operations through the possible development of multi-storey buildings or other land efficient means. The provision of this dedicated area will help to alleviate existing industrial/residential interface issues resulting from existing brownfield sites.  In addition, new roads will be provided to directly connect this area to Kong Sham Western Highway (KSWH) thereby eliminating the current movement of heavy goods vehicles through built-up areas including residential areas.

·                Within the proposed development area, most of the existing villages and brownfield sites, are currently not covered by or properly connected to the existing sewerage system. New public sewers are proposed under this Project to collect sewage in the proposed development area which will replace the existing unsewered areas.  This is likely to result in an improvement to the water quality of watercourses within the Project area.

·                A number of the cultural heritage are located within the Project area. The Project provides an opportunity to promote the cultural heritage resources within and surrounding the area though the provision of a cultural heritage trail. This trail is proposed to begin at the TSW Station and proposed Hung Shui Kiu Station along the existing West Rail Line (HSK Station) and permeates through the Project area, along the existing “Open Space” and “Amenity” zones to interlink the heritage features at Ha Tsuen. The trail provides a safe and efficient amenity for people to explore many of the culturally significant areas in the Project area and is also intended to help promote these features and draw people to the area.

·                The retention of the San Sang San Tsuen egretry in “Green Belt” (“GB”) that is buffered by “Local Open Space” (“LO”), is an improvement upon its current condition in a highly disturbed open storage area, as it increases protection of the egretry.  The “LO” also provides an eco-corridor, covering the ardeid flight paths, and providing connectivity to foraging habitats to the east.

·                The Project provides an opportunity to showcase a range of green initiatives adopted to create a green city. For sustainable development of the NDA, one of the key planning concepts is to minimise traffic generation through transit-oriented development. Major population, economic activities and community facilities will be concentrated within walking distance of railway and public transport nodes. Green mobility is promoted within the Project through the introduction of the Green Transit Corridor (GTC) and a comprehensive cycle track and pedestrian walkway network. To promote sustainable use of water, opportunities for using reclaimed water and harvested rainwater for non-potable purposes such as toilet flushing and irrigation within the Project area would be explored. Other green initiatives include the provision of Community Green Station for environmental education and collection of recyclables from the local community; and promotion of energy efficient buildings and installations.

·                Sustainable drainage systems or facilities have also been identified (e.g. rainwater harvesting, roadside bioretention swales, blue-green infrastructure, flood retention facilities). The implementation of these measures would reduce and attenuate stormwater flows, avoid/reduce flooding, improve water quality of river channels.

 

14.3                 Environmentally Friendly Options Considered and Incorporated in the Preferred Option

14.3.1            Avoidance of environmental impacts has been one of the key considerations throughout the entire EIA Study. For those impacts that could not be avoided, due consideration has been given to minimise those impacts as much as practicable so that all the residual impacts would comply with statutory requirements.  Given the views and opinions collated from community engagement exercises, much emphasis have been given to address the natural resources such as San Sang San Tsuen egretry, natural habitats, built heritage, etc.  All these approaches to avoid environmental impacts have been suitably incorporated into the Revised Recommended Outline Development Plan (RODP).  A summary of these approaches is given below: 

·                Avoidance of impacts to “Conservation Area” (“CA”);

·                Avoidance of impacts to San Sang San Tsuen Egretry;

·                Avoidance of direct impacts to Deep Bay Link (DBL) project mitigation ponds (wetland compensation area);

·                Avoidance of direct impact to natural watercourse;

·                Preservation of habitats with ecological value;

·                Avoidance of emergency discharge for sewage pumping stations (SPS);

·                Avoidance of impacts arising from the provision of Fresh Water Service Reservoir (FWSR); and

·                Avoidance of encroachment on built heritage.

Avoidance of Impacts to “Conservation Area” and Deep Bay Link Project Mitigation Ponds

14.3.2            As discussed in Section 2.6, during the evolution of the Revised RODP, the western Project boundary was extended to include the KSWH to facilitate the construction of a new primary distributor (Road P1).  Given the presence of ecologically sensitive wetlands (e.g. DBL project mitigation ponds) to the east and west of the KSWH and “CA” to the west of KSWH, options for the alignment of Road P1 and the subsequent Project boundary were investigated.

14.3.3            The preferred option included only two proposed slip roads which will connect from the existing KSWH to the Road D3 at the northwestern part of the Project area. These slip roads will be located at the east and west of the KSWH. As a result, only one slip road and at-grade road will encroach into the “CA” of Yuen Tau Shan, west of KSWH.  The area that would be encroached is located in existing reinforced concrete flood storage ponds and associated maintenance access road (i.e. resulting in no loss of semi natural/natural habitats).  In addition, Road P1 will go around the eastern ponds rather than overhanging the ponds as per the other option.  Therefore, the preferred option avoids impacts to the semi-natural/natural habitats and graves of the “CA”, as well as avoiding the direct loss of wetland habitats associated with the four mitigation ponds. 

Avoidance of Impacts to San Sang San Tsuen Egretry

14.3.4            The San Sang San Tsuen egretry is currently located in an open storage site within the Project area at the western edge of San Sang Tsuen, next to KSWH. Alternatives to avoid or minimise impacts to the egretry by adjusting the land use zonings in its vicinity were explored (see Section 2.10).  In the preferred option, the egretry is retained in “GB”. Further protection from disturbance is provided through the provision of “LO”, which provides a buffer to the south of the “GB”. The “LO” also provides an eco-corridor, covering the ardeid flight paths, and joining the “GB” supporting the egretry to “GB” and foraging habitats to the east.        

Preservation of Habitats with Ecological Value

14.3.5            Most of the sites of conservation importance as well as habitats with high ecological value have been excluded from the Project area in order to avoid any direct impacts.  Moreover, under the Revised RODP, the majority of “GB” would be retained during the development to avoid the loss of natural habitats.

14.3.6            To avoid direct impacts to a species of conservation importance, Incense Tree, it is recommended to preserve the tree in situ together with the woodland habitat in which it occurs, in Tung Tau Tsuen.

Avoidance of Direct Impact to Natural Watercourse

14.3.7            A natural watercourse is located in the “Industry” (“I”) zone in the west of the Project area.  To avoid direct loss of this watercourse, the Revised RODP has zoned the watercourse and the area south of it as “GB” thereby protecting it from development. 

Avoidance of Emergency Discharge for Sewage Pumping Stations

14.3.8            Emergency discharge of sewage from SPS could result if the electrical power supply was interrupted or the pump units failed. In order to minimise the chance of emergency sewage discharge, a standby pump would be provided to cater for emergency breakdown or maintenance of the duty pump. Backup power supply in the form of dual / ring circuit power supply or generator would be provided to secure electrical power supply.  An emergency storage tank / spare volume of wet well would be provided for the proposed SPSs to cater for breakdown and maintenance of duty pump. Twin rising mains system would be provided to facilitate maintenance works and to avoid emergency discharge of sewage. With incorporation of the recommended preventive measures, the chance of emergency sewage bypass would be extremely remote. 

Avoidance of Impacts Arising from the Provision of Fresh Water Service Reservoir

14.3.9            The new FWSR should have a hydraulic head of approximately 60 m to compensate the head loss during water supply and to maintain the minimum residual head in the system.  Due to this, (hydraulically) suitable locations for the potential FWSR were considered.  The preferred option provides the greatest engineering and environmental benefits.  Under the Revised RODP, the proposed FWSR is located in the southeast of the project area near Tan Kwai Tsuen, between the Project development area and Au Tau Water Treatment Works. Compared to the other options explored, this option avoids direct impacts on sites of conservation importance (“CA”) and potential impacts to species of conservation importance.

Avoidance of Encroachment on Built Heritage

14.3.10          All Declared Monuments and Graded Historic Buildings would be preserved in the Revised RODP.

14.4                 Environmental Design Recommended

14.4.1            Other than initiatives to avoid environmental impacts as summarised in Section 14.2, efforts have been exercised to minimise impacts. The need for any environmental designs required to mitigate the associated impacts have also be identified and will be implemented, as appropriate. A summary of these approaches is given below. 

·                Providing a sustainable drainage system;

·                Reuse of reclaimed water;

·                Adopting stepped building heights;

·                Providing greening;

·                Provision of GTC;

·                Providing direct noise mitigation measures;

·                Careful location of the “I” zone;

·                Location of fixed plant in “PBU+SWU” sites;

·                Implementation of Environmental Monitoring and Auditing System; and

·                Noise barriers and bird collision.

Providing a Sustainable Drainage System

14.4.2            Sustainable drainage system or facilities identified will be further reviewed for their potential implementation. A summary of these approaches is given below:

·                “harvested rainwater” will be adopted to store and treat the collected rainwater for irrigation or non-portable uses;

·                “roadside bioretention swales” is proposed to attenuate any surface run-off to the downstream throughout the infiltration process with filtration media as well as reducing water logging and ponding issues of roads and footpaths;

·                Blue-green infrastructure and revitalisation of existing drainage channels will be adopted with a green and ecologically friendly approach for integration within the overall land use planning;

·                Flood retention facilities (e.g. an underground stormwater storage tank installed in “LO”) will be provided to avoid increasing the flooding susceptibility of areas downstream and low-lying villages; and

·                a flood pond in the form of a flood retention lake will be provided within the Regional Town Park to serve as a flood mitigation measure and recreation feature to optimise land use.Reuse of Reclaimed Water

14.4.3            A new HSK Sewage Treatment Works (STW) is proposed to handle the additional sewage from the proposed development. In order to achieve a sustainable development, part of the treated sewage effluent will be reused as reclaimed water for toilet flushing in the Project, while the rest of the treated sewage effluent will be discharged via Urmston Road Outfall for proper disposal at the North Western WCZ.  Hence, no increase in the pollution load to the Deep Bay waters would be induced by the Project.

Adoption of Stepped Heights for Building

14.4.4            The proposed building height and development intensity profile for the Project area gives due regard to the physical form and setting of the existing and retained land uses. The proposed height and intensity profile is configured to give emphasis to specific areas within the Project that are proposed as major development nodes and points of congregation. The overall intensity and height profile steps down towards the Lau Fau Shan and Deep Bay area to ensure a better integration with the area and enhance variety in height and massing of new developments. Exemplifying the concept of rail-based planning, a gradation approach is adopted with developments of higher intensity and building height planned around the proposed railway stations to minimise the need for road transportation.  The intensity and building height descend towards the northern periphery by designating some low-rise, low-density developments along Lau Fau Shan Road to allow visual relief between the Project and the existing low-rise, low density Lau Fau Shan area.

14.4.5            A majority of residential developments are proposed within the eastern part of the Project area, along the TSW Main Channel. Maximum development heights generally range from a maximum of 95 mPD to a maximum of 135 mPD, creating a curvilinear building height profile from north to south along the Channel. The proposed building height restrictions have provided flexibility in design such that stepped height profile within each site can be realised to create visual porosity and visual interest. This building height strategy also ensures the development heights will fall towards existing villages to be retained and other low-rise developments, and towards areas of open space.the new HSK STW will be equipped with secondary treatment plus disinfection and nitrogen removal to further minimise the pollution loading to the North Western WCZ.

Providing Greening

14.4.6            Concerted efforts would be made to incorporate as many greening opportunities as possible within the Project area.  Making reference to the principles and guidelines on greening as provided in the Hong Kong Planning Standards and Guidance, and other Government studies on green roof application and sustainable living space, greening ratios of 30% to 60%, 30% to 60% and 30% to 85% are recommended for “Regional Open Space” (“RO”), “District Open Space” (“DO”) and “LO”, respectively.  For government facilities / school / residential development areas, the greening ratio of 20% to 30% is recommended.  More greenery, especially at-grade tree planting are encouraged to provide in the development sites.

14.4.7            The open space network is structured along the river channels.  The high quality riverside promenades provide the vertebrae of the open space framework from which a series of ancillary open spaces are developed.  The riverside promenade along the TSW Main Channel would be activated by the introduction of shopping street along it and would become a major focal point of the Project area.  A “LO” is planned in the northern end of the shopping street as a destination and will service as an important recreational area for residents living in adjacent residential developments and the general public.

14.4.8            The Regional Town Park planned at the core of the Project area is conveniently located for the enjoyment of new and existing communities.  It will be easily accessible by the general public and local residents as it will be linked with the north-south running open space spines and riverside promenades.  An Eco-Trail is also proposed to link the Regional Town Park with the hiking trails in Yuen Tau Shan through the “GB” and “LO” the Enterprise and Technology Park (“E+TP”).

14.4.9            The Regional Plaza accommodating the proposed HSK Station is another important ”breathing and leisure” space within the high density built-up area of the Regional Economic and Civic Hub.  It would provide not just a beautifully landscaped public space connecting the station with the surrounding commercial complexes and public transport interchange (PTI) but also provides leisure and food and beverage uses itself.

Provision of Green Transit Corridor

14.4.10          Although the proposed HSK Station and existing TSW Station will serve as the public transport backbone of the Project area, by considering the proposed large number of population and employment as envisaged in the Revised RODP, and that the Logistics, Enterprise and Technology Quarter which are key employment generating uses are located outside the railway station catchment, provision of a highly efficient and environmental-friendly feeder system would cater for internal movement and reduce the adverse road traffic and environmental impact.  As such, a designated area has been reserved on the Revised RODP for a GTC and possible provision of an environmentally friendly transport services (EFTS) in the Project. The EFTS corridor would be abutted by cycling tracks and pedestrian walkways.  This will allow the public to cycle within vehicle free routes.  The quality of the reserve will be enhanced through the application of high and low profile landscape treatments.

Providing Direct Noise Mitigation Measures

14.4.11          Exceedances of the noise criteria at some Noise Sensitive Receivers (NSR) are still predicted even with implementation of the environmentally friendly designs in the Revised RODP such as deletion of Tin Ying Road, provision of depressed road, alternative land use arrangement/alternative siting of noise sensitive use away from the roads, arrangement of non-noise sensitive building as screening structure, the noise barriers on KSWH (according to the associated approved EIA Report, and low noise road surfacing on road section of Castle Peak Road in the vicinity of NDA (between KSWH and Hung Tin Road).  Therefore, noise mitigation measures in terms of noise barriers and low noise road surfacing on Project roads within the Project area are proposed.

Careful Location of “Industry” Zone

14.4.12          All existing industrial sources with Specified Process under Air Pollution Control Ordinance within the assessment area will be removed. Sites for industrial uses are planned to the southwest of the Project area.  Since the annual winds at the Project area are north-east and east direction, these industrial emission sources would be at the downwind direction and its emission impact to the air sensitive uses within Project would be minimised.

Location of Fixed Plant in “PBU+SWU” Sites

14.4.13          The planned logistics facility buildings sited at the west of the Project would act as noise screening structures to screen the fixed plant noise from “PBU+SWU”, on the existing village houses.

Implementation of Environmental Monitoring and Auditing System during Construction Phase

14.4.14          In addition to the mitigation measures as described above (see more details in the Project Implementation Schedule given in the Environmental Monitoring and Audit Manual), a comprehensive environmental monitoring and auditing programme would be implemented to cover various aspects of concern. An independent environmental checker would also be employed to ensure that all the necessary mitigation measures are implemented in a timely and orderly manner.

Noise Barriers and Bird Collision

14.4.15          In order to minimise the potential impact of bird collision, only solid noise barrier will be used during construction phase.  Transparent noise barrier will be avoided as far as possible. Use of tinted materials and superimposing dark patterns or strips on the barrier, as per Environmental Protection Department (EPD)/Highways Department requirements would be employed to minimise bird mortality from collision.

 

14.5                 Key Environmental Problems Avoided and Environmentally Sensitive Areas Protected

14.5.1            Sections 14.3 and 14.4 have summarised the key approaches adopted in the current proposal to avoid, minimise and mitigate environmental impacts. Some of these approaches have contributed to avoid a number of environmental problems and to protect a number of environmentally sensitive areas. Table 14.1 presents the key environmental problems that have been avoided and any sensitive areas protected by these approaches.

Table 14.1    Summary of Key Environmental Problems Avoided and Sensitive Areas Protected

Design Approach

Environmental Problems Avoided and Sensitive Areas Protected

Avoidance of Impact on Sites of Conservation Importance (Section 14.3.2 – 14.3.3)

·         The majority of Sites of Conservation Importance (“Coastal Protection Area” (“CPA”), most of the “CA”) have been avoided.

·         Where there is a slight encroachment into the “CA” the preferred option has avoided impacts to semi-natural/natural habitats and graves. 

Avoidance of impacts to San Sang San Tsuen Egretry (Section 14.3.4)

·         Egretry is retained and protected in “GB”.

·         Protection from disturbance is provided through the provision of “LO”, which provides a buffer to the south of the “GB”. 

·         The “LO” also provides an eco-corridor, covering the ardeid flight paths, and joining the “GB” supporting the egretry to “GB” and foraging habitats to the east.        

Avoidance impacts to DBL project mitigation ponds (Section 14.3.2 – 14.3.3)

·         The preferred option avoids direct loss of the four mitigation ponds.

Preservation of habitats with ecological value (Section 14.3.5)

·         Most of the sites of conservation importance as well as habitats with high ecological value have been excluded from the Project area in order to avoid any direct impacts. 

·         The majority of “GB” is retained during the development to avoid the loss of natural habitats.

·         Avoidance of direct impacts to species of conservation importance.

Avoidance of direct impacts on natural watercourse (Section 14.3.7)

·         The Revised RODP retains the natural watercourse, south of the “I” zone, in “GB” zone.

Avoidance of emergency discharge for SPS (Section 14.3.8)

·         The recommended preventive and design measures would protect the inland watercourses and Deep Bay waters downstream of the SPS.

Avoidance of encroachment on built heritage (Section 14.3.10)

·         All Declared Monuments and Graded Historic Buildings would be preserved in the Revised RODP.

Providing sustainable drainage system (Section 14.4.2)

·         Reduce and attenuate stormwater flows, avoid/reduce flooding, improve water quality of channels.

Reuse of Reclaimed Water (Section 14.4.3)

·         Reduce the amount of effluent discharge from the new HSK STW via Urmston Road Submarine Outfall and thus minimise pollution loading to the North Western WCZ.

Adopting stepped building heights (Section 14.4.4 – 14.4.5)

·         Allow better integration with the existing / retained areas and enhance the overall quality of visual character.

Providing greening (Section 14.4.6 – 14.4.9)

·         Create greening and landscape resources that would improve the overall quality of landscape character.

Provision of GTC (Section 14.4.10)

·         Help reduce vehicular emissions and traffic noise.

Providing direct noise mitigation measures (Section 14.4.11)

·         NSRs are protected to achieve the statutory traffic noise requirement.

Careful Location of “Industry” Zone (Section 14.4.12)

·         Locating new industrial sources to planned industrial zones at the downwind direction, minimises the emission impact to the air sensitive uses within Project.

Location of Fixed Plant in “PBU+SWU” Sites (Section 14.4.13)

·         The planned logistic facility buildings screen the fixed plant noise from “PBU+SWU”, on the existing village houses.

Implementation of Environmental Monitoring and Auditing System (Section 14.4.14)

·         Ensure that all the recommended measures are in place.

Design of Noise Barriers (Section 14.4.15)

·         Minimise the potential impact of bird collision.

 

14.6                 Estimated Population Protected from Various Environmental Impacts

14.6.1            Blue-green infrastructure would be incorporated so that high flows due to Project will be directed into adequate stormwater attenuation facilities within the proposed development area during storm events, and the polder schemes could serve as a flood mitigation measures to protect the existing villages to avoid flooding (i.e. eight existing villages within Revised RODP with a total population of approximately 5,000).

14.6.2            With the implementation of proposed noise mitigation measures, all the total planned population assigned within Project area (approximately 218,000) would be protected from road traffic noise.

14.7                 Environmental Benefits of the Project and Environmental Protection Measures Recommended

14.7.1            Mitigation measures have been recommended to further reduce the environmental impacts due to construction and operation of the Project. Key recommended mitigation measures and any associated benefits are summarised in Table 14.2 below.

 

Table 14.2  Key Recommended Mitigation Measures

Environmental Aspect

Mitigation Measure and any Associated Benefit

Air Quality Impact

·         Implementing relevant control measures as required in the Air Pollution Control (Construction Dust) Regulation to minimise dust generation.

·         Watering once per hour on exposed worksites and haul roads during the construction phase to minimise dust impact.

·         For open excavation and spoil handling works, provision of 3m high hoarding along the construction site boundary adjacent to the non-construction areas such as residential, educational institutes or recreation area in use to minimize the dust impact.

·         Limitation of size of active work area of the work contract closest to some affected ASRs to one third of monthly average work area of the work contract during the construction phase to minimise dust impact

·         Provision of deodourising units on the four planned SPSs to alleviate the odour impact.

·         Enclosed the potential odour emission sources of the planned new STW and the vented air to be treated in the deodourising unit to alleviate the odour impact.

·         Provision of deodourising units on the planned Refuse Transfer Station to alleviate the odour impact.

Noise Impact

·         Adoption of quiet powered mechanical equipment (PME), movable noise barriers, proper workfront management, proper grouping of PME for some construction activities at critical work areas and provision of minimum separations between the affected schools and the critical works areas during examination period to minimise the construction noise impact.

·         Liaison with the school representative(s) to obtain the examination schedule so as to avoid noisy construction activities during school examination period. 

·         Set up a liaison group among relevant government departments, contractors of the Works contracts, etc. during construction phase of the Project to ensure proper implementation of mitigation measures.

·         Provision of noise mitigation measures including low noise road surfacing and noise barriers on the Project roads to reduce road traffic noise impacts on nearby NSRs.  If exceedance is still predicted at the planned NSRs, special building designs (such as blank facades, provision of acoustic windows/acoustic balcony) for affected planned residential NSRs, and provision of boundary wall, air conditioning and noise insulated windows for affected planned educational institutes  are also proposed to further minimise the traffic noise impact.

·         Provision of silencers for the ventilation fans of the four planned SPSs to alleviate the fixed plant noise impact.

·         Provision of acoustic fins, non-sensitive use or fixed glazing and layout set back at the NSR to alleviate the railway noise impact.

Water Quality Impact

·         The mitigation measures as detailed in the ProPECCPN 1/94 “Construction Site Drainage” and the ETWB TC (Works) No. 5/2005 “Protection of natural streams/rivers from adverse impacts arising from construction works” as well as other good site practices are recommended to minimise the potential water quality impacts from the construction activities.

·         An Emergency Response Plan (ERP) is recommended to minimise the potential water quality impact from construction site discharges under failure of treatment facilities during emergency situations or inclement weather.

·         Water quality monitoring at all major watercourses identified within the Project area is recommended to be carried out before, during and after the construction phase.

·         It is also recommended that regular site inspections during the construction phase should be undertaken to inspect the construction activities and works areas in order to ensure the recommended mitigation measures are properly implemented.

·         Various precautionary measures are proposed to be incorporated in the design of the SPS and rising mains to avoid emergency bypass and leakage of sewage to the maximum practicable extent.

·         A Contingency Plan (CP) is recommended to minimise impacts associated with the remote occurrence of emergency discharge from SPS. The CP should include locations of water bodies or water sensitive receivers in the vicinity of the emergency discharges, a list of relevant government departments to be informed and to provide assistance in the event of emergency discharge, reporting procedures required in the event of emergency discharges and procedures listing the most effective means in rectifying the breakdown of the SPS.

·         Stormwater control measures such as adequate storm drainage system with suitable pollutant removal devices, blue-green infrastructure and best storm water management practices are recommended to minimise the non-point source pollution due to surface run-off arising from the Project operation.

·         Provision of perimeter drainage with suitable interceptors or stop-logs and appropriate treatment facilities are recommended in the open areas of the industrial (“I”) zone and “PBU+SWU” of the Project to prevent the contaminated wash-off or accidental spillage from entering the nearby water environment. An ERP is also recommended for the “I” zone and “PBU+SWU” to deal with accidental spillage.

Sewerage and Sewage Treatment  Implications

·         Providing new sewage network in the project which will replace the existing unsewered areas within the development area, will reduce the pollution loading to Deep Bay.

·         Various preventive and design measures are recommended for the proposed SPS to prevent emergency discharge and thus protect the downstream water quality.

Waste Management Implications

·         Implementation of good site practices and waste reduction measures (e.g. reuse of construction and demolition (C&D) materials before off-site disposal or develop a materials recovery and recycling programme during construction and operation).

·         Preparation of an Environmental Management Plan (EMP), which includes the Waste Management Plan (WMP) in accordance with the ETWB TC(W) No. 19/2005.

·         Implement a trip-ticket system for each works contract in accordance with DEVB TC(W) No. 6/2010 to ensure that the disposal of C&D materials are properly documented and verified.

·         Handling and disposal of asbestos containing materials should be carried out in accordance with the ProPECC PN 2/97 and the Code of Practice on the Handling, Transportation and Disposal of Asbestos Waste.

·         Handling of chemical waste in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, and disposal of chemical waste at licensed chemical waste recycling / treatment facilities.

·         Options for adoption of automatic refuse collection system and organic waste treatment facilities within the residential and commercial complexes will be considered.

·         A Community Green Station is proposed to be co-located with the new RTS for environmental education purpose and convenient collection of recyclables from the local community to provide synergy to achieve better operational efficiency and environmental sustainability.

Land Contamination Impact

·         Further works, including site re-appraisal, site investigation as well as submission of supplementary Contamination Assessment Plan(s), Contamination Assessment Report(s) and Remediation Action Plan(s) (RAP(s)) for EPD approval are recommended to be carried out after the sites are handed over to Project Proponent for development.

·         If contaminated soil and/or groundwater were identified, suitable remediation measures according to the results from future SI works will be proposed in the RAP(s) and submitted to EPD for approval. Remediation should be carried out according to EPD approved RAP(s) and Remediation Report(s) (RR(s)) should be submitted to EPD for agreement after completion of the remediation works. Regular site audit during construction phase is required to ensure the proposed mitigation measures as recommended in the future RAP(s) are implemented effectively. No development works shall be commenced prior to EPD agreement of the RR.

·         By implementing the recommended further works under this Project, the actual contaminated site(s) within the assessment area would be located and any contaminated soil and groundwater would be identified and treated. The recommended further works would not only minimise the human health risks arising from the exposure of the contaminated soil and/or groundwater, it would also provide the opportunity to treat the contaminated ‘waste’ using proven remediation techniques into useful products (such as backfilling materials); thereby minimising the amount of waste disposing into the already depleting landfills in Hong Kong and achieving a more sustainable development.

·         Furthermore, the Project would allow the conversion of the contaminated site(s) into land that are safe for more optimal development (e.g. residential development).  The more optimal development would assist in addressing Hong Kong’s long-term housing demand and other land use needs.

Ecological Impact

·         Preservation of Tung Tau Tsuen woodland in situ and plant species of conservation importance (Incense Tree).

·         Phasing the construction works outside the breeding season of ardeids (i.e. March to August).

·         Implementation of hoarding / screening during the construction phase.

·         Retention of vegetation/habitats where possible and provision of buffer planting.

·         Minimise or incorporate wildlife-friendly lighting along the river channel or vegetated areas.

·         Develop appropriate mitigation strategies to avoid potential injury to roosting bats if found in any buildings or trees that would be removed during construction phase.

·         Incorporation screening measures (e.g. include amenity strip and additional tree planting, vertical greening walls, green roof, noise barriers) to minimise the disturbance impact to mitigation ponds.

·         Use of tinted materials and superimposing dark patterns or strips on the barrier, to minimise bird mortality from collision.

Fisheries Impact

·         Implementation of water quality mitigation measures to minimise the potential water quality impacts to ponds.

Landscape and Visual Impact

·         CM1 - Minimised construction area and contractor’s temporary works areas

·         CM2 – Stripping and storing of top soil

·         CM3 – Protection of existing trees

·         CM4 – Transplantation of existing trees where practical

·         CM5 – Control of night time lighting

·         CM6 - Construction of decorative hoarding around construction works

·         CM7 – Reduction of construction period to a practical minimum

·         CM8 – Prevention of run-off

·         CM9 – Phasing of construction stage

·         CM10 – Advanced  screen planting

·         CM11 – Minimise disturbance footprints

·         CM12 – Protection of existing water courses

·         CM13 – Hydroseeding on appropriate slopes

·         CM14 – Integrate Open Space Framework with existing nullah conditions

·         OM1 – Compensatory tree planting where practical

·         OM2 – All above ground structures shall be sensitively designed

·         OM3 – Streetscape elements shall be sensitively designed

·         OM4 – Reinstatement of streetscape areas to equal or better quality

·         OM5 – Implementation of attractive soft landscape areas around above ground structures

·         OM6 – Provision of planting along roadside amenity strips

·         OM7 – Appropriate design of street lighting

·         OM8 – Sensitive and chromatic treatment of architectural facades

·         OM9 – Sensitive design of landscape area

·         OM10 – Sensitive design of noise barriers and enclosures

·         OM11 – Tree planting screens along site boundaries

·         OM12 – Control of night time lighting

·         OM13 – Provision of green roofs and vertical greening where possible

·         OM14 – Aesthetic improvement planting of viaduct structures

Impact on Cultural Heritage

·         Avoidance of Declared Monuments and graded buildings.

·         Preservation of 12 nil grade built heritages by cartographic and photographic record.

·         Further archaeological survey is required to be conducted at 2 Archaeological Potential Areas (APAs), APA1 and APA2 to ascertain the extent of any archaeological remains within the APAs if any construction works will be carried out.  Based on the findings of the survey, mitigation measures could be proposed and not limited to preservation in situ, preservation by records, or relocation of archaeological remains. Direct impact arising from the proposed development within APA3 should be avoided as far as possible.

·         2 Sites of Archaeological Interest (SAIs) might be partially impacted by construction works. The archaeological impact arising from the construction works should be assessed when the detailed design of the works is available. However, if the works cannot avoid disturbance to the archaeological deposit, depending on degree of direct impact, the following mitigation measures should be considered, such as archaeological surveys, archaeological watching brief, preservation by records and relocation of archaeological remains.  The scope and programme of the archaeological fieldwork would be agreed with AMO.

 

14.8                 Compensation Areas and Enhancements Included

Tree Compensation

14.8.1            The open space network is structured along the riverside channels. These provide the vertebrae of the open space framework from which a series of ancillary open spaces extend. The edge of the riverside corridors provide space for tree compensation, as do the numerous “LO” and “DO” sites scattered throughout the Project area.  The Regional Town Park will also provide space for tree compensation.  In total, 71 ha of land is set aside for tree compensation.  Spaces such as roadside amenity areas will be heavily wooded and provide space for tree compensation, whereas park areas and the riverside channels will have more a formal, structured tree spaces.

Enhancing Ecological Connectivity across the Revised RODP

14.8.2            Enhancement could be achieved by incorporating habitat creation through the landscaping plan (e.g. at “LO” and “DO” zoning), particularly at where areas connected to “GB” (i.e. natural habitats).  Introduction of native plant species as buffer planting could be adopted within the developed areas, to provide connectivity between any isolated “GB” zones within the Project area.  This can help to improve the current habitat quality of the “GB” zones as the majority of them were of low ecological value plantation.

Enhancement for San Sang San Tsuen Egretry

14.8.3            The retention of the San Sang San Tsuen egretry in “GB” that is buffered by “LO”, is an improvement upon its current condition in a highly disturbed open storage area, as it increases protection of the egretry.  In addition, the provision of landscape planting in the “LO” zone adjacent to the egretry with suitable trees and bamboo, such as Chinese Hackberry (Celtis sinensis) and Da Ngan Bamboo (Bambusa eutuldoides) that are potentially utilised by ardeids for nesting, to enhance nesting resources for breeding ardeids.  To maximise the planting’s potential for use by breeding ardeids, this should be located in an area with limited human disturbance.

Wetland Enhancement

14.8.4            Ecological enhancement could be provided though the inclusion of suitable planting within the flood retention lake at Site 1-27 to provide foraging habitat for wetland dependent species (e.g. ardeids). This could include appropriate planting of suitable trees and bamboo on the proposed island to potentially provide additional nesting resources for breeding ardeids.  The island embankments (e.g. slope surface, vegetation planting, etc.) should be appropriately designed to provide suitable foraging opportunities for ardeids.  For example, shallow water with gentle slope surfaces covered with marshy species may provide foraging ground for breeding ardeids.  

14.8.5            During detailed design for the realignment of the Tin Sam Channel, opportunities for ecological enhancement (e.g. bioengineering, creating meanders) would be considered to improve to the ecological value.  Provision of natural substrates that would encourage colonisation of flora and freshwater fauna in the bottom and banks of the revitalised watercourses is recommended.