(REF.
113-03)
TABLE OF CONTENTS
APPENDICES
Appendix 15.1 Key Assessment Assumptions and Limitation of
Assessment Methodologies
Appendix 15.2 Summary of Environmental Impacts
15.1.1 This EIA Report has provided an assessment of the potential environmental impacts associated with the construction and operation of the Hung Shui Kiu New Development Area (HSK NDA) (herein referred to as the “Project”), based on the engineering design information available at this stage.
15.1.2 The assessment has been conducted, in accordance with the EIA Study Brief (No. ESB–291/2015) under the Environmental Impact Assessment Ordinance (EIAO) for the Project, covering the following environmental issues:
· Air Quality Impact
· Noise Impact
· Water Quality Impact
· Sewerage and Sewage Treatment Implications
· Waste Management Implications
· Land Contamination Impact
· Ecological Impact
· Fisheries Impact
· Landscape and Visual Impact
· Impact on Cultural Heritage
15.1.3 The findings of this EIA Study have determined the likely nature and extent of environmental impacts predicted to arise from the construction and operation of the Project. During the EIA process, environmental control measures have been identified and incorporated into the planning and design of the Project, to achieve compliance with environmental legislation and standards during both the construction and operation phases. The Project Implementation Schedule (PIS) listing the recommended mitigation measures is presented in Chapter 13.
15.1.4 Overall, the EIA Study has predicted that the Project, with the implementation of the mitigation measures, would be environmentally acceptable with no adverse residual impacts on the population and environmentally sensitive resources. Table 15.1 below summarises the environmental outcomes/benefits that have accrued from the environmental considerations and analysis during the EIA process and the implementation of environmental control measures of the Project. This has included specific assessment for the Schedule 2 Designated Projects (DP) subject to environmental permit application under this Study. The summary of environmental impacts and the summary of key assessment assumptions and limitations of methodologies are presented in Appendices 15.1 and 15.2, respectively.
15.1.5 Environmental monitoring and audit (EM&A) requirements have been recommended where necessary, to check on project compliance of environmental legislation and standards. These are presented in a separate, stand-alone EM&A Manual. The EM&A Manual includes a PIS, which summarises all of the mitigation measures, implementation locations, timeframe, agency, etc.
Table 15.1 Summary of Key Environmental Outcomes and Benefits
The Project Need |
·
The development at HSK will help to create new
developable land (approximately 714 hectares, which will include
approximately 61,000 new flats (about half for public housing)) thereby
contributing toward Hong Kong’s housing supply targets. In doing so it will help facilitate the
achievement of the Government’s multi-pronged strategy to increase much
needed land supply, particularly in the medium and long term. · To achieve the vision of building a sustainable, people-oriented and balanced living and working community for Hong Kong, the Project also aims to increase land supply for economic use by providing employment opportunities of 150,000. An NDA at Hung HSK provides an opportunity to shift some of the population from the dense urban areas to the New Territories, thereby a more balanced territorial development pattern and a less congested environment could be achieved, which is particularly needed in those urban areas characterised by extremely high development densities. · The strategic location of HSK, close to the Tuen Mun, Tin Shui Wai (TSW) and Yuen Long New Towns, Qianhai in Shenzhen, and connected by a number of existing and planned strategic transport links to other parts of the Territory, the Hong Kong International Airport and Shenzhen, is fundamental to its development as a regional centre and strategic employment hub. ·
Development of brownfield sites has also been highlighted
as an opportunity for increasing land supply in Hong Kong. HSK currently comprises a large area of
existing brownfield sites many of which are incompatible with the surrounding
environment. The feasibility of accommodating some of the affected brownfield
operations in multi-storey buildings will be explored. · Without the Project the present mix of non-compatible land uses (e.g. residential blocks located next to open storage or port backup areas) would remain. In addition, the current living environment would also remain unchanged, which includes traffic congestion, poor air quality, noisy environment and unpleasant landscape and streetscape. |
Environmental / Social Benefits of the Project |
·
Alleviate the current housing shortfall and achieve the
long-term housing needs of Hong Kong. The Project will provide about 61,000
new flats (about half for public housing). ·
Approximately 150,000 new job places would be generated
upon full development of the Project, through a mix of commercial, business,
industrial, community and government land uses. This would help to address
the over concentration of commercial activities and employment opportunities
in the main urban areas, boost the vibrancy of local communities, meet the
short fall of jobs in TSW New Town. ·
The “Logistics, Enterprise and Technology Quarter” at the
northwestern part of the Project provides another major employment cluster. ·
Being located close to the Tuen Mun, TSW and Yuen Long New
Towns, Qianhai in Shenzhen, and connected by a number of existing and planned
strategic transport links to other parts of the Territory, the Hong Kong
International Airport and Shenzhen, there is potential for the Project to be
developed as a regional centre and strategic employment hub. ·
The Project will provide a series of civic elements and a
wide range of “Government, Institution or Community” facilities including
hospital, clinics, magistracy, community halls, performance venue, wet
markets, youth centres, educational facilities, social welfare facilities,
sports and recreation facilities, etc. ·
The Project will be a place for leisure pursuits
integrated with natural, cultural and landscape resources, which is intended
to foster health, wellness and human-nature integration. |
Environmentally Friendly Design and Benefits |
·
The re-arrangement of the road network by replacement of
Tin Ying Road and downgrading of Hung Tin Road will reduce the existing road traffic
noise and minimise pollutants generated from existing road traffic. ·
The provision of a dedicated area for “Port Back-up,
Storage and Workshop Uses” (“PBU+SWU”) at the northern fringe of the Project
area, will help to alleviate existing industrial/residential interface issues
resulting from brownfield operations.
In addition, new roads will be provided to directly connect this area
to Kong Sham Western Highway (KSWH) thereby eliminating the current movement of
heavy good vehicles (HGV) through built-up areas including residential
areas. ·
All existing industrial sources with Specified Process
under Air Pollution Control Ordinance within the proposed development area
will be removed. Sites for industrial use are planned at the southwest of the
Project area. Since the annual winds
at the Project area are north-easterly and easterly direction, these
industrial emission sources would be at the downwind direction and its
emission impact to the air sensitive uses within Project would be minimised. ·
The planned logistics facilities buildings sited at the
west of the Project area would act as noise screening structures to screen
the fixed plant noise from “PBU+SWU”, on the existing village houses. ·
The proposed building height and development intensity
profile for the Project area gives due regard to the physical form and
setting of the existing and retained land uses. The proposed height and
intensity profile is configured to give emphasis to specific areas within the
Project area that are proposed as major development nodes and points of
congregation, and also ensures the development heights fall towards existing
villages to be retained and other low-rise developments, and towards areas of
open space. This will allow better
integration with the existing / retained areas and enhance the overall
quality of visual character. ·
Concerted efforts would be made to incorporate as many
greening opportunities as possible within the Project area. This would provide ecological benefits
through the use of native and wildlife-friendly plant species, to provide
habitats and connectivity across the Project area. It would also avoid/minimise visual impact
due to the new built development. The
Regional Town Park planned at the core of the Project is conveniently located
for the enjoyment of new and existing communities. It would also
avoid/minimise visual and landscape impact due to the new built development.
The Regional Plaza next to the proposed HSK Station is another important
”breathing and leisure” space within the high density built-up area of the
Regional Economic and Civic Hub. It
would provide not just a beautifully landscaped public space connecting the
station with the surrounding commercial complexes and public transport interchange
(PTI) but also provides leisure and food and beverage uses itself. The provision of strategically located
green/open spaces also serves as a visual corridor / breezeway and promotes
air ventilation within the built areas. ·
For sustainable development of the Project, one of the
key planning concepts is to minimise traffic generation. Major population,
economic activities and community facilities will be concentrated within
walking distance of mass transit and public transport nodes. To help reduce
vehicular emissions and traffic noise, green mobility is promoted within the
Project area through the introduction of the Green Transit Corridor (GTC) and
a comprehensive pedestrian walkways and cycle tracks network. ·
To promote sustainable use of water, reusing reclaimed
water from treated sewage and harvested rainwater for non-potable purposes
such as toilet flushing and irrigation within the Project would be
explored. The reduced amount of
effluent discharge from the new HSK sewage treatment works (STW) (Phase 1 and
2) via Urmston Road Submarine Outfall would reduce the pollution loading to
the North Western Water Control Zone (WCZ). ·
Sustainable drainage systems or facilities have also been
identified (e.g. rainwater harvesting, roadside bioretention swales,
blue-green infrastructure, flood retention facilities). The implementation of these measures would
reduce and attenuate stormwater flows, avoid/reduce flooding, improve water
quality of channels, and improve ecological value of channels and the downstream
Deep Bay waters. ·
Other green initiatives include the provision of
community green station for environmental education and collection of
recyclables from the local community; and promotion of energy efficient
buildings and installations. ·
With reuse of reclaimed water, part of the treated sewage
would be reused and the effluent discharge to North Western WCZ will be
minimised. ·
The majority of Sites of Conservation Importance
(“Coastal Protection Area” (“CPA”), most of the “Conservation Area” (“CA”))
have been avoided during the development of the Revised RODP. Where there is a slight encroachment into
the “CA” the preferred option has avoided impacts to semi natural/natural
habitats and graves. ·
The retention of the San Sang San Tsuen egretry in “Green
Belt” (“GB”) that is buffered by “Local Open Space” (“LO”), is an improvement
upon its current condition in a highly disturbed open storage area, as it
increases protection of the egretry. The “LO” also provides an eco-corridor,
covering the ardeid flight paths, and providing connectivity to foraging
habitats to the east. ·
Impacts to Declared Monuments and Graded Historic
Buildings have been avoided. To
promote the cultural heritage resources within and surrounding the Project
area, a cultural heritage trail is proposed. The trail provides a safe and
efficient amenity for people to explore many of the culturally significant
areas in the Project area and is also intended to help promote these features
and draw people to the area. |
Air Quality Impact |
Construction Phase: ·
Potential air quality impacts from the construction works
of the Project would be mainly due to construction dust from excavation,
materials handling, spoil removal and wind erosion. With the implementation
of recommended dust suppression measures including watering once per hour on
active works areas, exposed areas and unpaved haul roads, other site
management areas, and mitigation measures specified in the Air Pollution
Control (Construction Dust) Regulation and EM&A programme, the predicted
dust impact on the air sensitive receivers would comply with the dust
criteria as stipulated in EIAO-TM and air quality objectives (AQO). Operation Phase: ·
Cumulative air quality impact arising from the vehicular
emissions from the open roads, portal emission and emission from ventilation
building of the planned Tuen Mun Western Bypass and chimney emissions within
the assessment area has been assessed at the worst case years scenarios, Year
2024-2030 scenario and Year 2031-2039 scenario. The assessment results conclude that the
predicted cumulative 1-hour average and annual average Nitrogen Dioxide,
daily average and annual average Respirable Suspended Particulates / Fine
Suspended Particulates, and 10-minutes average and daily average Sulphur
Dioxide concentrations at representative air sensitive receivers (ASRs) would
comply with the AQO. · Exceedance of 5 odour units would be predicted at portion of Site 3-1 (“Other Use” (“OU(PBU+SWU)”)) due to the nearby existing chicken farm. It is proposed that air sensitive uses at Site 3-1 should not be located at these exceedance zone or the fresh air intake of the building located at least 6m above ground. ·
With the implementation of the proposed mitigation
measures, the cumulative odour impact due to operation of planned refuse transfer
station (RTS), new HSK STW and upgraded and expanded San Wai STW at the
representative ASRs would comply with the odour criterion of EIAO-TM. ·
No adverse odour impact from the four planned sewage
pumping stations (SPS) would be anticipated with the implementation of
deodouriser (at least 90% of odour removal efficiency) and maintaining a
slight negative pressure of the ventilation system within the facilities and
locating the exhaust outlet of the deodouriser away from the nearby ASRs, as
far as practicable). |
Noise Impact |
Construction Phase: ·
Potential construction noise impact arising from the
operation of powered mechanical equipment (PME) would be expected. With the implementation of mitigation
measures including use of quiet powered mechanical equipment, use of movable
noise barriers, proper workfront management, proper grouping of PMEs for some
construction activities at the critical works area and provision of minimum
separations between the schools and the critical works areas during the examination
period, the predicted construction noise levels at the representative noise
sensitive receivers would comply with the construction noise criteria
stipulated in EIAO-TM. ·
The Contractor should liaise with the school
representative(s) to obtain the examination schedule so as to avoid noisy
construction activities during school examination period. ·
As the construction of the Project may involve different
parties, it is proposed to set up a liaison group among relevant government
departments, contractors of the works contracts, etc. during construction
phase of the Project to ensure proper implementation of the proposed noise
mitigation measures. Operation Phase (Road Traffic Noise): ·
The potential road traffic noise impact has been assessed
based on the worst-case traffic flows in Year 2048. Without any noise mitigation measures in
place, the predicted noise levels at the existing NSRs outside and inside
Project would range from 56 – 79 dB(A) and 54 – 77 dB(A), respectively. For the planned NSRs within Project area,
the predicted unmitigated traffic noise levels would be in range of 43 – 80
dB(A). Practicable traffic noise
mitigation measures are therefore formulated for achieving compliance with
the EIAO-TM traffic noise criteria. ·
With the proposed noise barriers and low noise road
surfacing in place on the Project roads, the predicted overall noise traffic
levels at some of the existing and planned residential NSRs would still
exceed the relevant noise criterion. For
the planned NSRs, alternative development layout and special building design
such as facades designed as blank façade, provision of acoustic
windows/acoustic balcony can mitigate the traffic noise impact to within the
respective noise criteria. . Regarding the adverse noise impact from the
existing road sections, low noise road surfacing would be considered to be
implemented under the policy endorsed by the Executive Council to address the
existing noise impacts from existing roads or by the Project if significant
noise impact from the existing roads is due to the Project. Environmental review will be conducted at
the later design stage to review and ascertain the proposed provisional noise
mitigation measures taking into account the latest design standard at that
time for the suitability and application of the low noise road surfacing
materials. ·
For the affected planned educational NSRs, with the
implementation of additional mitigation measures including boundary wall,
noise insulated windows and provision of air conditioning, no exceedance of
the overall traffic noise criterion is predicted. Hence, no adverse residual road traffic
noise is anticipated. Operation Phase (Fixed Noise Sources): ·
Maximum allowable sound power level emitted from fixed
plant have been predicted. The fixed plant
noise impacts predicted at the existing and planned NSRs would comply with
the respective noise criteria. Operation Phase (Railway Noise): ·
The potential rail noise impacts from West Rail Line and
Light Rail Transit have been assessed.
Under unmitigated scenario, noise impacts at planned NSRs would exceed
the stipulated noise criteria not more than 3 dB(A). Mitigation measures
including architectural fins, non-sensitive use or fixed glazing, and
building layout set back proposed for the affected NSRs are considered
effective to reduce the noise impact. Operation Phase (Helicopter Noise): ·
Helicopter noise impact from existing helipad near Kong
Sham Western Highway has been assessed.
The predicted helicopter noise levels at the existing and planned NSRs
would comply with the noise criteria as stated in the EIAO-TM. |
Water Quality Impact |
Construction Phase:
·
Water quality impacts from land-based construction would
be controlled by implementing the recommended mitigation measures and good
site practices. Inland water quality monitoring and regular site inspections
would be carried out routinely to minimise water quality impacts upon the
nearby inland waters. An Emergency Response
Plan is recommended to minimise the potential water quality impact from
construction site discharges under failure of treatment facilities during
emergency situations or inclement weather. Operation Phase:
·
All sewage generated from the Project will be discharged to
the public sewerage system for proper treatment and disposal at the North
Western WCZ. No increase in the pollution loading to the Deep Bay waters
would be induced by the Project. New public sewers are proposed under this
Project to collect sewage from the existing unsewered development within the
proposed development areas. The sewage loading currently discharged from this
unsewered development to Deep Bay would be diverted to sewage treatment works
and disposed to the North Western WCZ under this Project. Hence, this Project
would actually have beneficial effect by reducing the pollution loading to
Deep bay. Various precautionary measures are proposed to be incorporated in
the design of new SPSs and rising mains to avoid emergency bypass and leakage
of sewage to the maximum practicable extent.
A
Contingency Plan is recommended to minimise impacts associated with the
remote occurrence of emergency discharge from SPS. Stormwater control
measures such as adequate storm drainage system with suitable pollutant
removal devices, blue-green infrastructure and best stormwater management
practices are also recommended for the Project to minimise the non-point
source pollution arising from surface run-off. Hence, it is anticipated that
the water quality impacts associated with the non-point source discharge from
the road surfaces and development areas would be minimised. |
Sewerage and Sewage Treatment Implications |
·
Upon the review on the sewage flow generated from this
Project, proposed HSK STW (Phase 1) with a capacity of 70,000 m3
per day and proposed expansion to HSK STW (Phase 2) to an overall capacity of
85,500 m3 per day will be required to serve the Project. ·
The use of reclaimed water from the new HSK STW is proposed
to be further polished and supplied to the Project for toilet flushing. The
total projected demand of reclaimed water for the Project is in order of
39,800 m3 per day. The water quality of the reclaimed water is
proposed to meet the stringent standard as to minimise the potential health
impact. The implementation of reclaimed water use scheme is to be liaised
with WSD, EPD and DSD. ·
Based upon the assessment, it can be concluded that the
proposed Project is sustainable from sewerage collection, treatment, reuse
and disposal perspective. Use of reclaimed water is proposed for irrigation
and toilet flushing in the Project which is generated by the tertiary
treatment and polishing at the new HSK STW. |
Waste Management Implications |
·
The main waste types to be generated during the
construction phase of the Project will include construction and demolition
(C&D) materials, chemical waste, general refuse, excavated sediment and
contaminated soil. Reduction measures have been recommended to minimise the amount
of materials generated by the Project by reusing C&D materials as far as
practicable before offsite disposal. Provided that the waste is handled,
transported and disposed of using approved methods, adverse environmental
impacts would not be expected. ·
The main waste types to be generated during the operation
phase of the Project will include municipal solid waste (MSW), chemical
waste, screenings, grits and sewage sludge. Three new refuse collection
points (RCPs) and a new RTS have been included in the Revised RODP in
preparation for the increased quantity of waste in the district. A Community
Green Station is proposed to be co-located with the new RTS for environmental
education purposes, convenient collection of recyclables from the local
community, and to provide synergy to achieve better operational efficiency
and environmental sustainability. Provided that the waste is handled,
transported and disposed of using approved methods, adverse environmental
impacts would not be expected. |
Land Contamination Impact |
·
Based on the findings from land contamination assessment,
total of 480 potentially contaminated sites were identified, of which 253
potentially contaminated sites are currently used as open area storage,
container storage and warehouse sites.
Warehouse sites may not be contaminated if they are used to store
general household goods (e.g. furniture and toys). Container storage and open
area storage, on the other hand, typically comprise a large portion of area
for goods / container storage with possibly smaller portion for potentially
contaminating activities such as vehicle / equipment maintenance area and the
associated chemical handling/storage. The contamination (if any) is therefore
expected to be localised if the main types of goods stored on-site are not
potential sources of contamination. In
addition, the land uses of the remaining identified potentially contaminated
sites are not large scale polluting installations / facilities, which further
support the contamination (if any) would be localised rather that
widespread.. ·
The chemicals of concern (COCs) identified with the
potential to be present at the potentially contaminated sites include metals,
VOCs, SVOCs, PCRs and PCBs. These COCs
are readily treatable using proven physical, chemical and biological
remediation techniques; as demonstrated by the successful remediation of soil
contaminated with the abovementioned COCs in other Hong Kong projects. By implementing the recommended further
works, the actual contaminated site(s) within the assessment area would be
located and any contaminated soil and groundwater would be identified and
treated. ·
Given the above, land contamination impacts are therefore
considered not insurmountable. · As the identified potentially contaminated sites are still in operation and the development will only commence in stages from 2019 to 2037/38, and there may be change in land use prior to development within both the potentially contaminated and non-contaminated sites, it is recommended to conduct further works. This would include site re-appraisal, SI works as well as submission of supplementary Contamination Assessment Plan(s), Contamination Assessment Report(s) and Remediation Action Plan(s) (RAP(s)) for the Environmental Protection Department’s (EPD) approval after the sites are handed over to project proponent for development. If contaminated soil and/or groundwater were identified, remediation should be carried out according to EPD’s approved RAP(s) and Remediation Report(s) (RR(s)) should be submitted to EPD for agreement after completion of the remediation works. No development works shall be commenced prior to EPD’s agreement of the RR(s). ·
The implementation of the recommended further works under
this Project would clean up any contaminated site(s) identified within the
assessment area. The recommended
further works would not only minimise the health risks to future occupants
arising from the exposure of the contaminated soil and/or groundwater, it
would also provide the opportunity to treat the contaminated soil /
groundwater using proven remediation techniques for reuse as useful materials
(such as backfilling materials); thereby minimising the amount of waste
disposing into the already depleting landfills in Hong Kong and achieving a
more sustainable development. ·
Furthermore, the Project would allow the conversion of
any contaminated site(s) into land that is safe for more optimal
development. This would assist in addressing Hong Kong’s long-term
housing demand and other land use needs. |
Ecological Impact |
·
Thirteen habitats were identified within the Project area
including developed area/wasteland, village/orchard, agricultural area (dry),
agricultural area (wet), plantation, woodland, shrubland, grassland, marsh,
fishponds and mitigation ponds, stormwater drain/recreational pond, natural
watercourse, and modified watercourse. ·
Approaches for avoidance and minimisation of potential
ecological impact arising from the proposed new development have been
considered. The Project area has been
generated to cover mainly developed or highly disturbed areas which are of
limited ecological value. Under the
Revised RODP, areas within “GB” zoning would be retained to avoid loss of
habitats. Apart from a small developed
area within the “CA” at the northwest of San Sang San Tsuen, other
ecologically important areas (i.e. “CPA”, Ngau Hom Shek egretry, Shenzhen Bay
Bridge egretry and San Sang San Tsuen egretry) and ecologically sensitive
habitats (i.e. hillside woodland) would not be directly impacted. ·
San Sang San Tsuen egretry would be retained under the
Revised RODP and its surrounding areas are proposed as “LO” to further reduce
the potential disturbance impacts to the nesting ardeids. In addition, construction works in the vicinity
of the egretry would not be undertaken during the breeding season of
ardeids. Provision of hoarding would
be provided to reduce the construction disturbance such as noise, glare and
dust to the egretry. Flight paths
between the egretry and TSW Main Channel would be retained under the “LO”
zone. ·
While the slip road would unavoidably be hanged over a
small area (0.1 ha) at the fringe of the “CA” zone at northwest of San Sang
San Tsuen. Given the affected area was
small, developed (i.e. roads and reinforced concrete flood) and without
any species of conservation value recorded, the impact was negligible. ·
A mature individual of Incense Tree recorded within Tung
Tau Tsuen woodland would be impacted directly under the development. To avoid
this impact, this affected woodland would be preserved in situ with the Incense Tree. ·
Crested Serpent Eagle habitat within the “GB” zone (Site
3-2) would be indirectly impacted by disturbance from construction works in
the nearby “OU” sites. Hoarding would
be erected along the boundary of Site 3-2 to mitigate such impacts. Screening planting would be provided to
minimise operational phase disturbance from developed areas. ·
Construction works proposed in watercourses, including
TSW Main Channel and its tributary, and streams that involve in the covered
drainage network, would be carefully designed during the detailed design
phase. To minimise the potential water
quality impacts, it is recommended works to be undertaken when the channel is
in dry condition and dry season, when the water flow is low. ·
A section of Tin Sam Channel would be realigned under the
proposed development. Opportunities for ecological enhancement (e.g.
bioengineering, creating meanders) would be considered to improve to the
ecological value. Provision of natural
substrates that would encourage colonisation of flora and freshwater fauna in
the bottom and banks of the revitalised watercourses is recommended. ·
Enhancement planting area with native species would be
considered at the suitable area of the proposed Fung Kong Tsuen flushing
water service reservoir site. |
Fisheries Impact |
·
Existing fisheries resources within the assessment area
include active fishponds (outside the Project area) and capture fisheries
resources of North Western and Deep Bay WCZ. The value of capture fisheries in
the North Western WCZ is low to moderate while low in Deep Bay WCZ. An important nursery and spawning ground
for commercial fisheries species has been identified within the North Western
WCZ; however this is outside the Project area. No oyster culturing and intertidal fishing
were recorded within the coastal area from Ngau Hom Sha to Lau Fau Shan. ·
Potential fisheries impacts arising from the Project have
been assessed. No active fishponds are
located within the Project area and therefore would not be lost due to
Project. Three inactive fishponds
would be lost due to the Project therefore the impact to pond fish culture is
considered negligible to low when taking into account the potential
conversion of inactive fishponds back to active fishpond. ·
No unacceptable water quality impacts to the Deep Bay WCZ
and North Western WCZ are anticipated from the Project with proper
implementation of mitigation measures as recommended in Section 5.13 and 5.14.
Therefore, monitoring of fisheries resources during the construction
and operation phase would not be necessary. |
Landscape and Visual Impact |
·
Landscape and visual mitigation works in relation to the
Project during the construction stage rely heavily on the minimisation of the
footprint of the works area, avoidance of significant topographical changes
together with the retention, protection and compensatory planting of trees /
vegetation. These measures if deployed have the capacity to reduce, in most
cases, the level of residual impact experienced by the visually sensitive
receivers (VSRs), landscape resources (LRs) and landscape character areas
(LCAs) at the construction stage. ·
It is not possible to fully mitigate all impacts due to
the large scale nature of the Project.
It is also no possible to fully mitigate all impacts in relation to
loss of mature woodland or tree planting, including the visual amenity/
screening they provide in the construction period and early operational
stages, mainly as long periods of time are required to sufficiently
compensate for the associated impacts. Providing compensatory measures are
applied, in combination with transplantation of existing trees (which can
help to accelerate the compensation period), the impacts to VSRs and LRs
affected by the Project can be reduced. Building and road greening measures
such as use of climbing plants and vertical planting help to break up the
uniformity of new road formation and structures, when used in combination
with wider screening measures they will help to reduce the visual impacts in
the early operational stages until tree screens and the Open Space Framework
have established and matured. ·
On review of the likely LR and LCA residual impacts, the
majority of LRs would be subject to Insubstantial to Slight Impacts, while a
few remaining would continue to be subject to Moderate impacts by operational
Year 10. ·
On review of the likely visual residual impacts, the
majority of VSRs would be subject to Moderate to Substantial Impacts, while
the remaining would be subject to None, Insubstantial, and Slight impacts by
operational Year 10. This is due to
the fact there is no way to mitigate the overall change in visual character
going from a rural, low-rise area to dense, high-rise development. |
Impact on Cultural Heritage |
·
Apart from the few nil grade built heritage located at
Yick Yuen Tsuen, Tin Sam San Tsuen and South of Tin Sam, the two Declared
Monuments, and seven Graded Historic Buildings would be preserved. ·
Twelve nil grade built heritage in Yick Yuen Tsuen, Tin
Sam San Tsuen and south of Tin Sam are to be directly impacted during the
construction phase by landfill. In the
light of their removal is unavoidable, preservation by record (including
cartographic and photographic record) prior to any construction works would
be required for the directly impacted built heritage. ·
As these nil grade built heritage contained no cultural
heritage significance, the impact to cultural heritage caused by the proposed
development to them is unavoidable yet acceptable with mitigation measures. ·
Based on desktop review and through archaeological survey
conducted between January and March 2015, a total of six Sites of
Archaeological Interest (SAIs) and four Archaeological Potential Areas (APAs)
are identified within the assessment area.
The six SAIs contained high archaeological significance. Tseung Kong Wai SAI (F1) and Tung Tau Tsuen
SAI (F2) might be partially impacted by construction works, but there is no
insurmountable impact. ·
For the Tseung Kong Wai SAI and Tung Tau Tsuen SAI, the
archaeological impact arising from the construction works should be assessed
when the detailed design of the works is available. Preservation in situ is the top priority to
safeguard the archaeological remains in the impacted area by amending the
layout plans of the construction works.
However, if the works cannot avoid disturbance to the archaeological
deposit, depending on degree of direct impact, the following mitigation
measures should be considered, such as archaeological surveys, archaeological
watching brief, preservation by records and relocation of archaeological
remains. The scope and programme of
the archaeological fieldwork would be agreed with AMO. ·
The four APAs contained uncertain archaeological
potential. Further archaeological survey
is required to be conducted at the two APAs (APA1 and APA2) to ascertain the
extent of any archaeological remains within the APAs if any construction
works will be carried out. Based on
the findings of the survey, mitigation measures could be proposed, such as
preservation in situ, preservation by records, or relocation of
archaeological remains, in prior agreement with the AMO before the
commencement of any construction works.
Direct impact arising from the proposed development within APA3 should
be avoided as far as possible. |
Environmental
Acceptability of Schedule 2 Designated Projects (DP) Subject to EP
Application* |
|
DP1 – Construction of new primary distributor road (P1) |
Air Quality Impact: ·
No unacceptable adverse air quality impacts to the ASRs
in the vicinity are anticipated. |
Noise Impact: ·
With the implementation of recommend mitigation measures
for construction noise and operational traffic noise impact arising from the
DP1, no unacceptable noise impact would be anticipated. |
|
Water Quality Impact: ·
With proper implementation of the recommended mitigation
measures and Best Management Practices (BMPs) for construction activities, as
well as the recommended stormwater control measures and BMPs to reduce
pollution arising from surface run-off during the operational phase, no
unacceptable water quality impact would be resulted. |
|
Sewerage and Sewage Treatment Implications: ·
No unacceptable adverse sewerage and sewage impacts are
anticipated. |
|
Waste Management Implications: ·
Provided that the waste is handled, transported and
disposed of using approved methods, adverse environmental impacts would not
be expected. |
|
Land Contamination Impact: ·
Prior to the commencement of construction of DP1, the recommended
further works under this EIA Study (including site re-appraisal, SI works and
if required, remediation works (refer to Section
8.9 for details)) will be carried out for the concerned sites listed in Appendix 8.2. Any soil / groundwater contamination would
be identified and properly treated prior to the development of the concerned
sites. No residual land contamination
impacts are anticipated, it is considered environmentally acceptable if the
recommended further works were followed. |
|
Ecological Impact: · With implementation of the recommended mitigation / precautionary measures, no significant adverse ecological impacts are anticipated. |
|
Fisheries Impact: ·
No unacceptable adverse fisheries impacts to the
fisheries resources are anticipated. |
|
Landscape and Visual Impact: ·
The residual landscape impacts during the Operational
Phase consist largely of loss of vegetation and fragmentation of some
LRs. This loss of vegetation, however,
will only be temporary as it will be replaced by new and/or compensatory
planting, specifically in the roadside planting areas required for Primary
Distributor roads. The implementation
of mitigation measures during the Construction and Operation Phases help to
reduce the impacts imposed on the LRs and LCAs, enough to reduce the impact
significance on these LRs and LCAs. ·
The residual ‘mitigation’ will be via the creation of new
LRs, specifically, high-quality roadside vegetation as the result of new
roads and their greening requirements.
Furthermore, areas of amenity plantings and new high quality trees and
roadside greening at Road P1 will introduce additional new landscape and
LRs. The new road and related
infrastructure will bring forth both impacts and new amenities that seek to
balance new development with ample greening and well-designed roads and
spaces. ·
The reinstated vegetation is recommended to consist
largely of native or naturalised species so as to enhance the ecological
integrity and biodiversity of the Project.
Where feasible, roadside street trees should be restored back to
native tree species in order to compensate for the loss of native vegetation
and other LRs. The provision of
roadside “Amenity” (“A”) zones provides additional room for this type of
planting. ·
A very small proportion of Residential VSRs, Recreational
VSRs, and Travelling VSRs will experience Slight visual impacts from the DP
after implementation of mitigation measures. This is largely due to the scale
and visibility of the proposed road within the Project and proximity of the
VSRs to the sources of impact, with viewers located either close by or within
the Project. As a result of the road being constructed at-grade, the
visibility is very limited, thus rendering their impact significance to be
small. ·
Mitigation measures are expected to adequately compensate
for the change in visual outlook for these VSRs. The overall change that is to occur as a
result of development of this DP will ultimately bring about positive
change. The transformation of existing
roads with unplanned, poor-quality trees and roadside vegetation into new
roads with proper planter width, soil depth, and carefully selected street
trees will greatly improve the visual outlook as well as provide
beautification and greening to the Project. |
|
Impact on Cultural Heritage: ·
No unacceptable adverse impacts to the cultural heritage
resources are anticipated. |
|
DP2 – Construction of eight new distributor roads (Roads
D1 to D8) |
Air Quality Impact: ·
No unacceptable adverse air quality impacts to the ASRs
in the vicinity are anticipated. |
Noise Impact: ·
With the implementation of recommend mitigation measures
for construction noise and operational traffic noise impact arising from the
DP2, no unacceptable noise impact would be anticipated. |
|
Water Quality Impact: ·
With proper implementation of the recommended mitigation
measures and Best Management Practices (BMPs) for construction activities, as
well as the recommended stormwater control measures and BMPs to reduce
pollution arising from surface run-off during the operational phase, no
unacceptable water quality impact would be resulted. |
|
Sewerage and Sewage Treatment Implications: ·
No unacceptable adverse sewerage and sewage impacts are
anticipated. |
|
Waste Management Implications: ·
Provided that the waste is handled, transported and
disposed of using approved methods, adverse environmental impacts would not
be expected. |
|
Land Contamination Impact: ·
Prior to the commencement of construction of DP2, the recommended
further works under this EIA Study (including site re-appraisal, SI works and
if required, remediation works (refer to Section 8.9 for details)) will be
carried out for the concerned sites listed in Appendix 8.2. Any soil /
groundwater contamination would be identified and properly treated prior to
the development of the concerned sites.
No residual land contamination impacts are anticipated, it is
considered environmentally acceptable if the recommended further works were
followed. |
|
Ecological Impact: ·
With implementation of the recommended mitigation /
precautionary measures, no significant adverse ecological impacts are
anticipated. |
|
Fisheries Impact: ·
No unacceptable adverse fisheries impacts to the
fisheries resources are anticipated. |
|
Landscape and Visual Impact: ·
The residual landscape impacts during the Operational
Phase consist largely of loss of vegetation and fragmentation of some
LRs. This loss of vegetation, however,
will only be temporary as it will be replaced by new and/or compensatory
planting, specifically in the roadside planting areas required for all
District Distributor roads. The
implementation of mitigation measures during the Construction and Operation
Phases help to reduce the impacts imposed on the LRs and LCAs, enough to
reduce the impact significance on these LRs and LCAs. ·
The residual ‘mitigation’ will be via the creation of new
LRs, specifically, high-quality roadside vegetation as the result of new
roads and their greening requirements.
Furthermore, areas of amenity plantings and new high quality trees and
roadside greening at Roads D1-D8 will introduce additional new landscape and
LRs, as well as vertical greening in the vicinity of vertical noise barrier
locations. Collectively the new roads
and related infrastructure will bring forth both impacts and new amenities
that seek to balance new development with ample greening and well-designed
roads and spaces. ·
The reinstated vegetation is recommended to consist
largely of native or naturalised species so as to enhance the ecological
integrity and biodiversity of the Project.
Where feasible, roadside street trees should be restored back to
native tree species in order to compensate for the loss of native vegetation
and other LRs. The provision of
roadside “A” zones provides additional room for this type of planting. ·
A very small proportion of Residential VSRs, Recreational
VSRs, and Travelling VSRs will experience Slight visual impacts from the Project
after implementation of mitigation measures. This is largely due to the scale
and visibility of proposed roads within the Project and proximity of the VSRs
to the sources of impact, with viewers located either close by or within the
Project. As a result of roads being constructed at-grade, their visibility is
very limited, thus rendering their impact significance to be small. ·
Mitigation measures are expected to adequately compensate
for the change in visual outlook for these VSRs. The overall change that is to occur as a
result of development of road DPs will ultimately bring about positive
change. The transformation of existing
roads with unplanned, poor-quality trees and roadside vegetation into new
roads with proper planter width, soil depth, and carefully selected street
trees will greatly improve the visual outlook as well as provide
beautification and greening to the Project.
Added to this, numerous breezeways and view corridors planned along
roadways, riverine corridors and fung shui lanes enshrined in the urban
design framework will add visual interest to the development and provide it a
contextual setting and connection to the broader HSK and TSW area. These concepts, when combined with
mitigation, will greatly improve the overall visual outlook with regards to
construction of roads and road-related DPs. |
|
|
Impact on Cultural Heritage: ·
The construction of distributor road D5 might directly
impact on Tseung Kong Wai Site of Archaeological Interest. The archaeological
impact arising from the construction works should be assessed when the
detailed design of the works is available. Based on the findings of the
assessment, appropriate mitigation measures would be proposed in prior
agreement with the AMO. |
DP5 – Construction of slip roads (between: Road D8
Junction and existing Castle Peak Road; Junction of D8/P1 and Junction of
D7/P1; and KSWH connection to Road D3) |
Air Quality Impact: ·
No unacceptable adverse air quality impacts to the ASRs
in the vicinity are anticipated. |
Noise Impact: ·
With the implementation of recommend mitigation measures
for construction noise impact arising from the DP5, no unacceptable noise
impact would be anticipated. |
|
Water Quality Impact: ·
With proper implementation of the recommended mitigation
measures and Best Management Practices (BMPs) for construction activities, as
well as the recommended stormwater control measures and BMPs to reduce
pollution arising from surface run-off during the operational phase, no
unacceptable water quality impact would be resulted. |
|
Sewerage and Sewage Treatment Implications: ·
No unacceptable adverse sewerage and sewage impacts are
anticipated. |
|
Waste Management Implications: ·
Provided that the waste is handled, transported and
disposed of using approved methods, adverse environmental impacts would not
be expected. |
|
Land Contamination Impact: ·
Prior to the commencement of construction of DP5, the
recommended further works under this EIA Study (including site re-appraisal,
SI works and if required, remediation works (refer to Section 8.9 for details)) will be carried out for the concerned
sites listed in Appendix 8.2. Any soil / groundwater contamination would
be identified and properly treated prior to the development of the concerned
sites. No residual land contamination
impacts are anticipated, it is considered environmentally acceptable if the
recommended further works were followed. |
|
Ecological Impact: ·
With implementation of the recommended mitigation /
precautionary measures, no significant adverse ecological impacts are
anticipated. |
|
Fisheries Impact: ·
No unacceptable adverse fisheries impacts to the
fisheries resources are anticipated. |
|
Landscape and Visual Impact: ·
The residual landscape impacts during the Operational
Phase consist largely of loss of vegetation and fragmentation of some
LRs. This loss of vegetation, however,
will only be temporary as it will be replaced by new and/or compensatory
planting, specifically in the planting areas required for bridges and slip
roads. The implementation of
mitigation measures during the Construction and Operation Phases help to
reduce the impacts imposed on the LRs and LCAs, enough to reduce the impact
significance on these LRs and LCAs. ·
The residual ‘mitigation’ will be via the creation of new
LRs specifically, high-quality roadside vegetation. Furthermore, areas of amenity plantings,
new high quality trees, as well as vertical greening in the vicinity of the
flyovers and vertical noise barrier locations will introduce additional new
landscape and LRs. Collectively the new
roads and related infrastructure will bring forth both impacts and new
amenities that seek to balance new development with ample greening and
well-designed roads and spaces. ·
The reinstated vegetation is recommended to consist
largely of native or naturalised species so as to enhance the ecological
integrity and biodiversity of the Project.
Where feasible, roadside street trees should be restored back to
native tree species in order to compensate for the loss of native vegetation
and other LRs. The provision of
roadside “A” zones provides additional room for this type of planting. ·
A very small proportion of Residential VSRs, Recreational
VSRs, and Travelling VSRs will experience Slight visual impacts from the Project
after implementation of mitigation measures. This is largely due to the scale
and visibility of proposed roads within the Project and proximity of the VSRs
to the sources of impact, with viewers located either close by or within the
Project. Mitigation measures are
expected to adequately compensate for the change in visual outlook for these
VSRs. |
|
Impact on Cultural Heritage: ·
No unacceptable adverse impacts to the cultural heritage
resources are anticipated. |
|
DP6 – Construction of partly depressed and partly
decked-over roads located at Road D2; Road D4; and Road D6 |
Air Quality Impact: ·
No unacceptable adverse air quality impacts to the ASRs
in the vicinity are anticipated. |
Noise Impact: ·
With the implementation of recommend mitigation measures for
construction noise impact arising from the DP6, no unacceptable noise impact
would be anticipated. |
|
Water Quality Impact: ·
With proper implementation of the recommended mitigation measures
and Best Management Practices (BMPs) for construction activities, as well as
the recommended stormwater control measures and BMPs to reduce pollution
arising from surface run-off during the operational phase, no unacceptable
water quality impact would be resulted. |
|
Sewerage and Sewage Treatment Implications: ·
No unacceptable adverse sewerage and sewage impacts are
anticipated. |
|
Waste Management Implications: ·
Provided that the waste is handled, transported and
disposed of using approved methods, adverse environmental impacts would not
be expected. |
|
Land Contamination Impact: ·
Prior to the commencement of construction of DP6, the
recommended further works under this EIA Study (including site re-appraisal,
SI works and if required, remediation works (refer to Section 8.9 for details)) will be carried out for the concerned
sites listed in Appendix 8.2. Any soil / groundwater contamination would
be identified and properly treated prior to the development of the concerned
sites. No residual land contamination
impacts are anticipated, it is considered environmentally acceptable if the
recommended further works were followed. |
|
Ecological Impact: ·
With implementation of the recommended mitigation / precautionary
measures, no significant adverse ecological impacts are anticipated. |
|
Fisheries Impact: ·
No unacceptable adverse fisheries impacts to the
fisheries resources are anticipated. |
|
Landscape and Visual Impact: ·
The residual landscape impacts during the Operational
Phase consist largely of loss of vegetation and fragmentation of some
LRs. This loss of vegetation, however,
will only be temporary as it will be replaced by new and/or compensatory
planting, specifically on the roadside planting areas and landscaped spaces
on top of the decked-over roads. The
implementation of mitigation measures during the Construction and Operation
Phases help to reduce the impacts imposed on the LRs and LCAs, enough to
reduce the impact significance on these LRs and LCAs. ·
The residual ‘mitigation’ will be via the creation of new
LRs, specifically, high-quality roadside vegetation, new park/amenity spaces
on top of the decking, and areas of amenity plantings and new high quality
trees. Collectively the new decked-over
roads will bring forth both impacts and new amenities that seek to balance
new development with ample greening and well-designed roads and spaces. ·
The reinstated vegetation is recommended to consist
largely of native or naturalised species so as to enhance the ecological
integrity and biodiversity of the Project.
Where feasible, roadside street trees should be restored back to
native tree species in order to compensate for the loss of native vegetation
and other LRs. The provision of
roadside “A” zones provides additional room for this type of planting. ·
A very small proportion of Residential VSRs, Recreational
VSRs, and Travelling VSRs will experience Slight visual impacts from the DP
after implementation of mitigation measures during the construction phase.
However, during the operation phase, it is predicted to be no additional
visual impact. ·
The urban design framework sets forth the implementation
of several decked-over sections of roads to allow visual and physical
connections to areas of open space from residential and commercial nodes,
including the Regional Plaza. These
concepts, when combined with mitigation, will greatly improve the overall
visual outlook with regards to construction of roads and road-related DPs. |
|
Impact on Cultural Heritage: ·
No unacceptable adverse impacts to the cultural heritage
resources are anticipated. |
|
DP9 – Construction of four new sewage pumping stations
(Sites 2-34; 3-41; 3-48; and 4-35) |
Air Quality Impact: · No unacceptable adverse air quality impacts to the ASRs in the vicinity are anticipated with implementation of recommended dust suppression measures during construction phase, and installation of deodourising units and maintaining a slight negative pressure within the facilities and locating the exhaust outlet of the deodouriser away from the nearby ASRs, as far as practicable, during operation phase. |
Noise Impact: ·
With the implementation of recommend mitigation measures
for construction noise and operational fixed plant noise impact arising from
the DP9, no unacceptable noise impact would be anticipated. |
|
Water Quality Impact: ·
With proper implementation of the recommended mitigation measures
and Best Management Practices (BMPs) for construction activities, as well as
the recommended precautionary design measures to avoid emergency sewage
bypass during the operational phase, no unacceptable water quality impact
would be resulted. |
|
Sewerage and Sewage Treatment Implications: ·
No unacceptable adverse sewerage and sewage impacts are
anticipated. |
|
Waste Management Implications: ·
Provided that the waste is handled, transported and
disposed of using approved methods, adverse environmental impacts would not
be expected. |
|
Land Contamination Impact: ·
Prior to the commencement of construction of DP9, the
recommended further works under this EIA Study (including site re-appraisal,
SI works and if required, remediation works (refer to Section 8.9 for details)) will be carried out for the concerned
sites listed in Appendix 8.2. Any soil / groundwater contamination would
be identified and properly treated prior to the development of the concerned
sites. No residual land contamination
impacts are anticipated, it is considered environmentally acceptable if the
recommended further works were followed. |
|
Ecological Impact: ·
With implementation of the recommended mitigation /
precautionary measures, no significant adverse ecological impacts are
anticipated. |
|
Fisheries Impact: ·
No unacceptable adverse fisheries impacts to the
fisheries resources are anticipated. |
|
Landscape
and Visual Impact: · The residual landscape impacts during the Operational Phase are very minor and deemed acceptable assuming full implementation of mitigation measures. The implementation of mitigation measures during the Construction and Operation Phases help to reduce the impacts imposed on the LRs and LCAs, not enough to reduce the impact significance on the landscape. The residual ‘mitigation’ will be via the creation of new LRs as the result of new SPS and their site greening and amenity plantings. · Only one VSR, RES47, would be subject to adverse impacts as a result of the construction of four numbers of SPS. This is largely due to the scale, building height, and visibility of the proposed SPS, and proximity of the VSRs to the sources of impact, with viewers located either close by or within the Project area. As a result of the SPS buildings being constructed at-grade, their visibility is very limited, thus rendering their impact significance to be small. ·
Mitigation measures are expected to adequately compensate
for the change in visual outlook for these VSRs. The overall change that is to occur as a
result of development of DP5 will ultimately bring about positive
change. The implementation of
Operation Phase mitigation measures such as chromatic treatment on building
facades, vertical greening and green roofs, coupled with tree screens and quality
site landscaping will ensure that these buildings are unobtrusive and blend
in with the surrounding landscape.
These concepts, when combined with mitigation, will greatly improve
the overall visual outlook with regards to construction of SPS DPs. |
|
Impact on Cultural Heritage: ·
No unacceptable adverse impacts to the cultural heritage
resources are anticipated. |
|
DP12 – Construction of Road P1 and slip-road from KSWH to
Road D3 partly located within “CA” of Yuen Tau Shan |
Air Quality Impact: ·
No unacceptable adverse air quality impacts to the ASRs
in the vicinity are anticipated. |
Noise Impact: ·
With the implementation of recommend mitigation measures
for construction noise and operational traffic noise impact arising from the
DP12, no unacceptable noise impact would be anticipated. |
|
Water Quality Impact: ·
With proper implementation of the recommended mitigation
measures and Best Management Practices (BMPs) for construction activities, as
well as the recommended stormwater control measures and BMPs to reduce
pollution arising from surface run-off during the operational phase, no
unacceptable water quality impact would be resulted. |
|
Sewerage and Sewage Treatment Implications: ·
No unacceptable adverse sewerage and sewage impacts are
anticipated. |
|
Waste Management Implications: ·
Provided that the waste is handled, transported and
disposed of using approved methods, adverse environmental impacts would not
be expected. |
|
Land Contamination Impact: ·
Prior to the commencement of construction of DP12, the
recommended further works under this EIA Study (including site re-appraisal,
SI works and if required, remediation works (refer to Section 8.9 for details)) will be carried out for the concerned
sites listed in Appendix 8.2. Any soil / groundwater contamination would
be identified and properly treated prior to the development of the concerned
sites. No residual land contamination
impacts are anticipated, it is considered environmentally acceptable if the
recommended further works were followed. |
|
Ecological Impact: ·
Given the small size and low ecological value of the affected area i.e. concrete flood
storage ponds and associated maintenance access, the impact was
negligible
with
implementation of the recommended mitigation / precautionary measures, no significant
adverse ecological impacts are anticipated. |
|
Fisheries Impact: ·
No unacceptable adverse fisheries impacts to the
fisheries resources are anticipated. |
|
Landscape and Visual Impact: ·
The residual landscape impacts during the Operational Phase
consist largely of loss of vegetation and fragmentation of some LRs. This loss of vegetation, however, will only
be temporary as it will be replaced by new and/or compensatory planting,
specifically in the ground-level spaces underneath the elevated road
structure. The implementation of
mitigation measures during the Construction and Operation Phases help to
reduce the impacts imposed on the LRs and LCAs, enough to reduce the impact
significance on these LRs and LCAs. ·
The residual ‘mitigation’ will be via the creation of new
LRs, specifically, high-quality amenity vegetation. Collectively the new elevated road and
related infrastructure will bring forth both impacts and new amenities that
seek to balance new development with ample greening and well-designed roads
and spaces. ·
The reinstated vegetation is recommended to consist
largely of native or naturalised species so as to enhance the ecological
integrity and biodiversity of the Project area. Where feasible, roadside street trees should
be restored back to native tree species in order to compensate for the loss
of native vegetation and other LRs.
The provision of roadside “A” zones provides additional room for this
type of planting. ·
A very small proportion of Residential VSRs, Recreational
VSRs, and Travelling VSRs will experience Slight visual impacts from the DP
after implementation of mitigation measures. This is largely due to the scale
and visibility of proposed road within the Project area and proximity of the
VSRs to the sources of impact, with viewers located close by the DP. |
|
Impact on Cultural Heritage: ·
No unacceptable adverse impacts to the cultural heritage
resources are anticipated. |
Note:
* Location of DPs is presented in Figure 1.2 and Figure 1.3