(REF. 113-03)
Table of Contents
2......... Project Description
2.2 Revised
Recommended Outline Development Plan
2.3 Implementation
Programme and Phasing
2.4 Summary
of Concurrent Projects
2.5 Project
Implementation Schedule
3......... Project OrganiSation
4.4 Laboratory
Measurement / Analysis
4.9 Performance
Compliance Test
5.2 Monitoring
Parameters for Construction Noise
5.3 Monitoring
Equipment for Construction Noise
5.4 Monitoring
Locations for Construction Noise
5.5 Baseline
Monitoring for Construction Noise
5.6 Impact
Monitoring for Construction Noise
5.7 Event
and Action Plan for Construction Noise
5.8 Noise
Parameters for Operational Traffic Noise
5.9 Monitoring
Locations for Operational Traffic Noise
5.10 Monitoring
Requirement for Operational Traffic Noise
5.11 Event
and Action Plan for Traffic Noise
5.12 Commissioning
Test for Fixed Plant Noise
6......... Water Quality Impact
6.9 Laboratory
Measurement / Analysis
7......... Sewerage AND Sewage Treatment IMplications
7.2 Sewerage
and Sewage Treatment Implications during Construction Phase
7.4 Sewerage
and Sewage Treatment Implications during Operational Phase
8......... Waste Management Implications
9......... Land Contamination Impact
10.3 Monitoring
and Audit Requirement
12........ Landscape and Visual Impact.
13 Impact on
Cultural Heritage
14........ Site Environmental Audit
14.2 Compliance
with Legal and Contractual Requirements
15.2 Baseline
Monitoring Report
15.3 Monthly
Monitoring Reports
15.4 Final
EM&A Review Reports
15.6 Interim
Notifications of Environmental Quality Limit Exceedances
APPENDICES
Appendix 2.1 Implementation
Programme and Phasing
Appendix 2.2 Project
Implementation Schedule (PIS)
Appendix
3.1 Project Organisation
for Environmental Works
Appendix
4.1 Sample Data Record Sheet for TSP
Monitoring
Appendix
5.1 Sample Data Record Sheet for
Construction Noise Monitoring
Appendix
6.1 Sample Data Record Sheet for Water
Quality Monitoring
Appendix
15.1 Sample Template for Interim Notifications
of Environmental Quality Limits Exceedances
FIGURES
Figure 1.2 Location of Designated Projects
Figure 1.3 Location of Designated Projects Subject
to Environmental Permit Application
Figure 2.1 Revised Recommended Outline Development
Plan (RODP)
Figure 2.2 Development Phasing Plan
Figure 2.3 Locations of Concurrent Projects
Figure 4.1 Location of Construction Dust
Monitoring Stations
Figure 5.1 Locations of Construction Noise
Monitoring Stations (Sheet 1 of 2)
Figure 5.2 Locations of Construction Noise Monitoring
Stations (Sheet 2 of 2)
Figure 5.3 Locations of Traffic Noise Monitoring
Stations (Sheet 1 of 2)
Figure 5.4 Locations of Traffic Noise Monitoring
Stations (Sheet 2 of 2)
Figure 6.1 Water Quality Monitoring Stations
Designated Project
Reference No.
|
Schedule 2
Designated Project
|
Work Component /
Reference in Revised RODP
|
|
DP1 1
|
Part I, A.1
|
A road which is an
expressway, trunk road, primary distributor road or district distributor road
including new roads, and major extensions or improvements to existing road
|
Construction of new
primary distributor road (Road P1)
|
DP2 1
|
Part I, A.1
|
A road which is an
expressway, trunk road, primary distributor road or district distributor road
including new roads, and major extensions or improvements to existing road
|
Construction of
eight new distributor roads (Roads D1 to D8)
|
DP3 2
|
Part I, A.2
|
A railway and its
associated stations
|
Construction of new
West Rail Hung Shui Kiu Station (HSK Station) (Site
4-34)
|
DP4
(Potential DP) 2
|
Part I, A.3
|
A tramway and its
associated stations
|
Construction of
Environmentally Friendly Transport Services (EFTS) – subject to further
review
|
DP5 1
|
Part I, A.8
|
A road or railway
bridge more than 100 m in length between abutments
|
Construction of slip
roads between: Road D8 Junction and existing Castle Peak Road; Junction of
D8/P1 and Junction of D7/P1; and Kong Sham Western Highway (KSWH) connection
to Road D3
|
DP6 1
|
Part I, A.9
|
A road fully
enclosed by decking above and by structure on the sides for more than 100 m
|
Construction of
partly depressed and partly decked-over roads located at Road D2, Road D4,
and Road D6
|
DP7
(Potential DP) 2
|
Part I, B.5
|
A container back-up
area, container storage, container handling or container packing area
(including a container vehicle parking area) more than 5 ha in size and
within 300 m of an existing or planned receiver
|
Construction of a
new container back-up and storage area (Sites 3-1, 3-4, 3-5, 3-13 and 3-14) –
subject to further review
|
DP8 2
|
Part I, F.1
|
Sewage treatment
works with an installed capacity of more than 15,000 m3 per day
|
Construction
of new HSK Sewage Treatment Works (STW) (Site 3-26 and part of existing San
Wai STW)
|
DP9 1
|
Part I, F.3(b)
|
A sewage pumping
station –
(b)
with an installed capacity of more than 2,000 m3 per day and a
boundary of which is less than 150 m from an existing or planned receiver
|
Construction of four
new sewage pumping stations (SPS) (Sites 2-34, 3-41, 3-48 and 4-35)
|
DP10 2
|
Part I, F.4
|
An activity for the
reuse of treated sewage effluent from a treatment plant
|
Construction of
flushing water service reservoirs (FLWSR) for reuse of reclaimed water at Tan
Kwai Tsuen and Fung Kong Tsuen (Site 3-3 and Site 5-40)
|
DP11 2
|
Part I, G.2
|
A refuse transfer
station
|
Construction of one
refuse transfer station (RTS) (Site 3-12)
|
DP12 1
|
Part 1, Q.1
|
All projects
including new access roads, railways, sewers, sewage treatment facilities,
earthworks, dredging works and other building works partly or wholly in an
existing or gazetted proposed country park or
special area, a conservation area, an existing or gazetted
proposed marine park or marine reserve, a site of cultural heritage, and a
site of special scientific interest.
|
Construction of Road
P1 and a slip-road from KSWH to Road D3 partly located within the
"Conservation Area” of Yuen Tau Shan
|
Note:
DP 1 - Construction of New Primary Distributor Road (Road P1)
DP2 - Construction of Eight New Distributor Roads (Roads D1 to D8)
· Road D1: This road provides a partly dual three and partly dual two, west to east primary connection at the northern part of the Project area linking Tin Shui Wai (TSW) with the KSWH and providing links to District Distributors that provide the secondary links to the south of the Project area. The local road from a section of Road D1 near Lau Fau Shan to serve the residential sites and commercial sites in the northern part of the Project area will be restricted to private cars access only. A section of Road D1 from KSWH to road junction of Road D4/D3/D1 will be partly depressed and partly decked-over to allow crossing of the EFTS alignment. A section of Road D1 near the roundabout with Tin Wah Road will be a bridge structure (not greater than 30 m in length between abutments) to allow the local road to/from residential sites in the northern part of the Project area in parallel with Lau Fau Shan Road to the end of Site 2-1.
· Road D2: Comprises a north-south primary route that links to Ping Ha Road and Hung Tin Road. Road D2 is planned to dual 2 standards by widening of existing Ping Ha Road to enhance the magnitude of residential development and reduce the environmental adverse noise impact that is realisable in the north east of the Project area. The link will accommodate the traffic capacity currently carried along the Tin Ying Road and Ping Ha Road and also has the capacity to service existing and proposed development. Most of the Road D2 is constructed at-grade, except a section of approximately 450 m which is a depressed road in order to improve pedestrian connectivity between the residential Sites 1-5, 1-6 and 2-31.
· Road D3: Provides a link between Road D4/D1 and Road D5. A depressed road will be constructed near the roundabout of Road D4/D1 to avoid reduction on the traffic flow efficiency to and from Road D1. A section of Road D3 will be constructed in abutment for connection from slip road from KSWH to the at-grade section of Road D3.
· Road D4: Provides a link between Road D1/D3 to Road D2 to facilitate an eastward connection to TSW New Town and Castle Peak Road via Road D4. This route will serve to alleviate the pressure on other west to east links. A section of Road D4 of approximately 300 m length will be constructed as depressed road with partial pedestrian decking-over to facilitate access, and thus increasing connectivity between Sites 2-30 and 2-32.
· Road D5: Provides a link between the services areas (e.g. Special Industry (Logistics Facility)) and connects to Road P1 in the west and Tin Ha Road in the east. The whole section of Road D5 will be at-grade with a roundabout with Road D3.
· Road D6: Connects with Road D8 along its alignment. The route will play a major role in servicing the proposed HSK Station and related development as well as the proposed commercial sites and mixed commercial/residential development. To avoid conflict to pedestrian activity in the Regional Plaza near the proposed HSK Station, half of Road R6 will be constructed in depressed road of approximate 550 m length with partial decking-over in the Regional Plaza section.
·
Road D7: Road D7 provides access from
Road P1 to the commercial sites at Sites 4-12, 4-13 and 4-16.
· Road D8: Road D8 provides a connection between the proposed Road P1 and Castle Peak Road. The route will provide an important west to east link whilst also providing a major means of access to the proposed HSK Station, the civic node at Site 4-31, and the commercial and residential developments located east of the proposed HSK Station. The road will be constructed at-grade with a depressed EFTS crossing under Road D8.
DP3 - Construction of New West Rail Hung Shui Kiu Station (Site 4-34)
DP4 - Construction of Environmental Friendly Transport Services –Potential DP subject to further review
DP5 - Construction of Slip Roads between: Road D8 Junction and Existing Castle Peak Road; Junction of D8/P1 and Junction of D7/P1; and KSWH Connection to Road D3
DP6 - Construction of Partly Depressed and Partly Decked-over Roads Located at Road D2, D4 and D6
DP7 - Construction of a New Container Back-up and Storage Area – Potential DP subject to further review
DP8 - Construction of New HSK Sewage Treatment Works
DP9 - Construction of Four New Sewage Pumping Stations
1.3.19 Since all these SPSs are with an installed capacity of more than 2000 m3 per day and are located within 150 m from existing and/or planned residential area or educational institution, these SPSs are classified as DPs under Item F.3, Part 1, Schedule 2 of the EIAO.
DP10 - Construction of Flushing Water Service Reservoirs for Reuse of Reclaimed Water at Tan Kwai Tsuen and Fung Kong Tsuen
1.3.20 In order to achieve a sustainable development, reclaimed water from the sewage treatment plant will be reused for flushing water serving the Project. To facilitate the reuse of reclaimed water, service reservoirs at Tan Kwai Tsuen and Fung Kong Tsuen would be constructed (Site 3-3 and Site 5-40).
DP11 - Construction of a Refuse Transfer Station
1.3.21 In the northern part of the Project area along the KSWH, Site 3-12 has been proposed for the provision of a new “RTS” to support the existing NWNT “RTS” and cope with the new population waste generation. A Community Green Station is also co-located within the site to enhance environmental education and help collect different types of recyclables in the local community, which could provide synergistic effect to achieve better operational efficiency.
DP12 - Construction of Road P1 and a Slip Road from Kong Sham Western Highway to Road D3 Partly within the “Conservation Area” of Yuen Tau Shan
· Guide the set-up of an EM&A programme to ensure compliance with the EIA recommendations;
· Specify the requirements for monitoring equipment;
· Propose environmental monitoring points, monitoring frequency etc.;
· Propose Action and Limit Levels; and
· Propose Event and Action Plans.
· Responsibilities of the Contractor, the Engineer or Engineer’s Representative (ER), Environmental Team (ET), and the Independent Environmental Checker (IEC) under the context of EM&A;
· Project organisation for the EM&A works;
· The basis for, and description of the broad approach underlying the EM&A programme;
· Details of the methodologies to be adopted, including all laboratories and analytical procedures, and details on quality assurance and quality control programme;
· The rationale on which the environmental monitoring data will be evaluated and interpreted;
· Definition of Action and Limit Levels;
· Establishment of Event and Action Plans;
· Requirements for reviewing pollution sources and working procedures required in the event of non-compliance with the environmental criteria and complaints; and
· Requirements for presentation of environmental monitoring and audit data and appropriate reporting procedures.
· The provision of about 61,000 new residential units will house an estimated new population of about 176,000 persons. With the existing population and population from the planned/committed residential developments within the Project area, the overall population is projected to be around 218,000 persons upon full development.
·
Commercial sites for office, retail and
hotel developments around the proposed HSK Station and existing TSW Station to
reinforce their respective roles as “Regional Economic and Civic Hub” and
“District Commercial Node”, as well as two commercial sites in the northern
edge of the Project area to complement local economic activities in the Lau Fau Shan and the northern part of TSW New Town area.
· Enterprise and Technology Park for accommodating a variety of innovation and technology uses, which may include research centre, testing & certification use, data centre, modern industries and other related businesses and non-polluting industrial uses.
· Logistics Facility to facilitate accommodation of modern logistics buildings.
· Multi-storey buildings on land reserved for Port Back-Up, Storage and Workshop Uses to accomodate some of the affected brownfield operations in a land-efficient manner.
· Industrial land for general industrial uses.
· A comprehensive Open Space network, including a continuous riverside promenade and a Regional Town Park in the centre of the Project area, that would optimise existing natural, cultural and landscape resources and provide recreational and leisure spaces.
· A variety of “G/IC” facilities such as social welfare facilities, education facilities, etc. to support the existing neighbourhood and future population.
· A New HSK Sewage Treatment Works (STW) with a tertiary and secondary plus treatment process and
· Four new Sewage Pumping Stations (SPSs) with a design capacity of 27,000 m3 (SPS1), 39,500 m3 (SPS2), 11,000m3 (SPS3), and 68,000m3 (SPS4).
· A Fresh Water Service Reservoir (FWSR) and FLWSRs
· A RTS to support the existing NWNT RTS and cope with the new population waste generation.
· District Cooling System (DCS) in the vicinity of the proposed HSK Station and the existing TSW Station – subject to further review.
· Primary Distributor Road (Dual 2 / Dual 3 Standard) – Road P1.
· Eight District Distributor Roads (Dual 2 / Dual 3 Standards).
· Green Transit Corridor (GTC) comprising EFTS, pedestrian walkways and cycle tracks, which would traverse the core of residential, commercial and other land reserves within the Project area – details subject to further review.
· Comprehensive Pedestrian Walkway and Cycle Track Network to promote walking and cycling within the Project area.
Table 2.1 Major Planning Parameters of the Revised RODP
Land Use |
|
Residential Residential
and Commercial / Residential |
80 (18%) 80 |
Economic Commercial
(office, hotel and retail) Logistics
Facilities Port
Back Up, Storage and Workshop Uses Enterprise
and Technology Park Industrial |
105 (24%) 22 37 24 9 13 |
Public Facilities Government,
Institution or Community (other than Education) Education
and Related Uses Public
Utilities (Petrol Filling Station, Bus Depot, Regional Plaza, Station, etc.) |
86(20%) 32 28 26 |
Open Space Regional
Open Space District
Open Space Local
Open Space |
66(15%) 16 27 23 |
New Roads and Amenity New
Roads Amenity |
104(23%) 86 18 |
Total |
|
Others Existing
Road and River Channel Green
Belt (Preserved Knolls & Hillslopes) Retained
Existing/ Committed Development (including villages) |
70 54 149 |
Grand
Total |
714 |
|
|
Advance Works
· Site formation works for “Residential” (“R”), “G/IC”, “Commercial” (“C”) and “Industrial” (“I”) sites.
· Two new SPSs (SPS1 and SPS2) (DP9) and associated rising mains.
· Primary Distributor Road P1 under KSWH and associated interchange/junction works connecting with KSWH, Castle Peak Road and other District Distributors (DP1).
· Slip Roads between Road D8 Junction and existing Castle Peak Road; Junction of D8/P1 and Junction of D7/P1 (DP5).
· Essential utilities for the future development of relevant sites in the Project, such as sewerage, watermains, power supply cables and electricity substation (ESS), etc.
Stage 1
· Site formation works for the three “OU(PBU+SWU)” sites and two “R” sites.
· A section of District Distributor Road D1 (DP2) connecting the “OU(PBU+SWU)” sites to KSWH.
· Utilities laying works for the future development of relevant sites in the Project, such as sewerage, watermains, power supply cables, etc. along the proposed Road P1.
Stage 2
· District Distributor Road D6, D7 and D8 (DP2 and DP6) and local roads, and associated pedestrian walkway and cycle tracks.
· District Distributor Road D1, a section of Road D3 (DP2) and local roads, and associated pedestrian walkway and cycle tracks.
· Site formation works for “R”, “C”, “G/IC” and open space sites in the southern Project area and associated section of the GTC.
· Site formation works for the remaining “OU(PBU+SWU)” sites and RTS in the northern Project area.
· Two new SPSs (SPS3 and SPS4) (DP9) and associated rising mains.
· New HSK STW Phase 1 (DP8).
· A FWSR and FLWSRs for reuse of reclaimed water (DP10) near Tan Kwai Tsuen and associated supply networks.
· DCS near proposed HSK Station (if implemented).
· Utilities for the future development of relevant sites in the Project, such as sewerage, watermains, power supply cables, ESS, etc.
Stage 3
· District Distributor Road D4 and Ping Ha Road (Road D2) widening (DP2 and DP6) and local roads, and associated pedestrian walkways and cycle tracks.
· District Distributor Road D3 and D5 (DP2), and associated pedestrian walkways and cycle tracks.
· Slip roads connecting KSWH and Road D3 (DP5 and DP12).
· Site formation works for “R”, “C” and “G/IC” sites in the eastern and northern parts of the project area and associated section of GTC.
· Site formation works for “OU(Logistics Facilities)” and “OU(Enterprise and Technology Park)” sites in the western Project area and associated section of GTC.
· New HSK STW Phase 2 (DP8).
· A FLWSR for reuse of reclaimed water near Fung Kong Tsuen (DP10) and associated supply networks.
· Extension of FWSR near Fung Kong Tsuen and associated supply networks.
· Revitalisation of existing Tin Sam Channel and HSK Main Channel.
· Flood retention facilities and open spaces.
· Utilities for the future development of relevant sites in the Project, such as sewerage, watermains, power supply cables, etc.
Stage 4
· Local roads serving development sites, and associated pedestrian walkways and cycle tracks.
· Site formation works for “R”, “G/IC”, “C”, open spaces and riverside promenade sites in the eastern and northern Project areas and associated section of GTC.
· Revitalisation of TSW Main Channel.
· Flood retention facilities.
· DCS near existing TSW Station (if implemented).
· Construction of EFTS (DP4) (if implemented), and associated pedestrian walkway and cycle tracks within the GTC.
· Utilities for the future development of relevant sites in the Project, such as sewerage, watermains, power supply cables, etc.
· Engineering Study Review for Site Formation and Infrastructure Works at San Hing Road, Tuen Mun - Investigation (and its Additional Services)
· Engineering Study for Site Formation and Infrastructural Works at Hong Po Road – Feasibility Study
· Site Formation and Infrastructural Works for the Development near Tan Kwai Tsuen, Yuen Long – Feasibility Study
· Preliminary Land Use Study for Lam Tei Quarry and the Adjoining Areas
· Yuen Long and Kam Tin Sewerage Disposal Stage 2 and Stage 3
· Tuen Mun Western Bypass
· Proposed Development Under the Study on the Enhancement of the Lau Fau Shan Rural Township and Surrounding Areas
· Planning and Engineering Study for Housing Sites in Yuen Long South – Investigation
· Water Supply to Hung Shui Kiu New Development Area
· Site Formation and Infrastructural Works for the Development at Long Bin, Yuen Long, Feasibility Study
The
Contractor
· Implement the EIA recommendations and requirements;
· Provide assistance to Environmental Team (ET) in carrying out monitoring and auditing;
· Submit proposals on mitigation measures in case of exceedances of Action and Limit Levels in accordance with the Event and Action Plans;
· Implement measures to reduce impact where Action and Limit Levels are exceeded; and
· Adhere to the agreed procedures for carrying out compliant investigation.
· Set up all the required environmental monitoring stations;
· Monitor various environmental parameters as required in the EM&A Manual;
· Analyse the environmental monitoring and audit data, review the success of EM&A programme, confirm the adequacy of mitigation measures implemented and the validity of the EIA predictions, and to identify any adverse environmental impacts arising;
· Carry out site inspection to investigate and audit the Contractors’ site practice, equipment and work methodologies with respect to pollution control and environmental mitigation measures, and take proactive actions to pre-empt problems;
· Audit and prepare audit reports on the environmental monitoring data and site environmental conditions;
· Report on the environmental monitoring and audit results to the Independent Environmental Checker (IEC), Contractor, the ER and EPD or its delegated representative;
· Recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit Levels in accordance with the Event and Action Plans;
· Undertake regular on-site audits / inspections and report to the Contractor and the ER of any potential non-compliance;
· Follow up and close out non-compliance actions; and
· Adhere to the procedures for carrying out environmental complaint investigation.
Engineer
or Engineer’s Representative
· Supervise the Contractor’s activities and ensure that the requirements in the EM&A Manual are fully complied with;
· Inform the Contractor when action is required to reduce impacts in accordance with the Event and Action Plans;
· Assist the Project Proponent in employing an IEC to audit the results of the EM&A works carried out by the ET;
· Comply with the agreed Event and Action Plans in the event of any exceedance; and
· Adhere to the procedures for carrying out complaint investigations.
Independent
Environmental Checker
· Review the EM&A works performed by the ET (at not less than monthly intervals);
· Audit the monitoring activities and results (at not less than monthly intervals);
· Validate and confirm the accuracy of monitoring results, monitoring equipment, monitoring locations, monitoring procedures and location of sensitive receivers;
· Report the audit results to the ER and EPD in parallel;
· Review the EM&A reports (monthly and quarterly summary reports) submitted by the ET;
· Review the proposal on mitigation measures submitted by the Contractor in accordance with the Event and Action Plans;
· Check the mitigation measures submitted by the Contractor in accordance with the Event and Action Plans;
· Check the mitigation measures that have been recommended in the EIA and this Manual, and ensure they are properly implemented in a timely manner, when necessary; and
· Report the findings of site inspections and other environmental performance reviews to ER and EPD.
· to identify the extent of construction dust impact on sensitive receivers;
· to determine the effectiveness of mitigation measures to control fugitive dust emission from activities during the construction phase;
· to audit the compliance of the Contractor with regard to dust control, contract conditions and the relevant dust impact criteria;
· to recommend further mitigation measures if found to be necessary; and
· to comply with Action and Limit (A/L) Levels for air quality as defined in this Manual.
· 1-hour TSP limit of 500 µg m-3
· 0.6 - 1.7 m3 per minute (20 - 60 standard cubic feet per minute) adjustable flow range;
· equipped with a timing / control device with ± 5 minutes accuracy for 24 hours operation;
· installed with elapsed-time meter with ± 2 minutes accuracy for 24 hours operation;
· capable of providing a minimum exposed area of 406 cm2;
· flow control accuracy: ± 2.5% deviation over 24-hour sampling period;
· equipped with a shelter to protect the filter and sampler;
· incorporated with an electronic mass flow rate controller or other equivalent devices;
· equipped with a flow recorder for continuous monitoring;
· provided with a peaked roof inlet;
· incorporated with a manometer;
· able to hold and seal the filter paper to the sampler housing at horizontal position;
· easy to change the filter; and
· capable of operating continuously for 24-hour period.
· The wind sensors shall be installed on masts at an elevated level 10 m above ground so that they are clear of obstructions or turbulence caused by the buildings;
· The wind data shall be captured by a data logger. The data recorded in the data logger shall be downloaded periodically for analysis at least once a month;
· The wind data monitoring equipment shall be re-calibrated at least once every six months; and
· Wind direction should be divided into 16 sectors of 22.5 degrees each.
Table 4.1 Proposed Construction Dust Monitoring Stations
Monitoring Station ID |
EIA ID |
Location |
Phases of the Project |
Monitoring Period(1) |
Existing
Air Sensitive Receivers |
||||
AM1 |
A204 |
Kam Cheong Garden |
Advance Works, Stage 1 Works and Stage 2 Works |
Year 2024 - 2031 |
AM2 |
A208 |
Oaklands Court |
Year 2024 - 2031 |
|
AM3 |
A209 |
Ling Liang Church Primary School |
Year 2024 - 2031 |
|
AM4 |
A310 |
Tin Ha Road Playground |
Year 2024 - 2031 |
|
AM5 |
A415 |
Tin Sum Tsuen |
Stage 2 Works and Stage 3 Works |
Year 2026 - 2035 |
AM6 |
A410 |
Galore Garden |
Year 2026 - 2035 |
|
AM7 |
A414 |
Shek Po Tusen |
Advance Works and Stage 3 Works |
Year 2024 - 2029 Year 2031 - 2035 |
AM8 |
A813 |
Block H, Tin Shing Court |
Advance Works, Stage 2 Works, Stage 3 Works and
Stage 4 Works |
Year 2024 - 2038 |
AM9 |
A702 |
San Uk Tsuen |
Stage 3 Works |
Year 2031 - 2035 |
AM10 |
A802 |
Kiu Tau Wai |
Stage 3 Works and Stage 4 Works |
Year 2031 - 2038 |
AM11 |
A703 |
Sha Chau Lei Tsuen |
Year 2031 - 2038 |
|
AM12 |
A704 |
Ha Tsuen Shi |
Year 2031 - 2038 |
|
AM13 |
A708 |
Sik Kong Wai |
Year 2031 - 2038 |
|
AM14 |
A601 |
Tseung Kong Wai |
Advance Works, Stage 2 Works, Stage 3 Works and
Stage 4 Works |
Year 2026 - 2038 |
AM15 |
A1101 |
Lo Uk Tsuen |
Stage 3 Works and Stage 4 Works |
Year 2031 - 2038 |
AM16 |
A1103 |
Block 8, Locwood Court |
Year 2031 - 2038 |
|
AM17 |
A1106 |
Shui Lung House, Tin Shui Estate |
Year 2031 - 2038 |
|
AM18 |
A1303 |
Sha Kong Wai Tsai |
Year 2031 - 2038 |
|
AM19 |
A1305 |
Ngau Hom Tsuen |
Year 2031 - 2038 |
|
AM20 |
A1302 |
Wing Jan School |
Year 2031 - 2038 |
|
AM21 |
A1002 |
Fung Kong Tsuen |
Advance Works, Stage 2 Works, Stage 3 Works and
Stage 4 Works |
Year 2026 - 2038 |
Planned
Development |
||||
AM22 |
P240 |
Planned Village Resite
at Site 4-20 |
Advance Works and Stage 2 Works |
Occupied date – Year 2031 |
AM23 |
P1032 |
Planned
Port Back-up, Storage and Workshop at
Site 3-6 |
Advance Works and Stage 2 Works |
Occupied date – Year 2031 |
AM24 |
P1501 |
Planned
Port Back-up, Storage and Workshop at Site 3-8 |
Advance Works and Stage 2 Works |
Occupied date – Year 2031 |
AM25 |
P606 |
Planned
Port Back-up, Storage and Workshop at Site 3-14 |
Stage 3 Works |
Occupied date – Year 2035 |
Note: (1) The
monitoring period is subject to the construction programme
of the relevant contracts in the Construction Stage.
i.
at the site boundary or such locations close to
the major dust emission source;
ii.
close to the air sensitive receivers as defined
in the EIAO-TM;
iii.
proper position/sitting and orientation of the
monitoring equipment; and
iv.
take into
account the prevailing meteorological conditions.
i.
a horizontal platform with appropriate support
to secure the samplers against gusty wind shall be provided;
ii.
two samplers shall be placed less than 2 m
apart;
iii.
the distance between the sampler and an
obstacle, such as buildings, must be at least twice the height that the
obstacle protrudes above the sampler;
iv.
a minimum of 2 m of separation from walls, parapets
and penthouses is required for rooftop samplers;
v.
a minimum of 2 m of separation from any
supporting structure, measured horizontally is required;
vi.
no furnace or incinerator flue is nearby;
vii.
airflow around the sampler is unrestricted;
viii.
the sampler is more than 20 m from the
dripline;
ix.
any wire fence and gate, to protect the
sampler, shall not cause any obstruction during monitoring;
x.
permission must be obtained to set up the
samplers and to obtain access to the monitoring stations; and
xi.
a secured
supply of electricity is needed to operate the samplers.
Table 4.2 Summary of Construction Dust Monitoring Programme
Monitoring
Period |
Duration |
Sampling
Parameter |
Frequency |
Baseline Monitoring |
Consecutive days of at least 2 weeks before
commencement of major construction works |
1-hour TSP |
3 times per day |
Impact Monitoring |
Throughout the construction phase |
1-hour TSP |
3 times in every 6 days
when documented and valid complaint was received |
Table 4.3 Action and Limit Levels for Air Quality (Dust)
Parameter |
Action Level (1) |
Limit Level |
TSP (1 hour average) |
BL <= 384 µgm-3, AL = (BL * 1.3 + LL)/2 BL > 384 µgm-3, AL = LL |
500 µgm-3 |
Note: (1) BL = Baseline level, AL = Action level,
LL = Limit level.
Table 4.4 Event and Action Plan for Air Quality (Dust)
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action level being exceeded by one sampling |
1. Identify
source, investigate the causes of complaint and propose remedial measures; 2. Inform
Contractor, IEC and ER; 3. Repeat
measurement to confirm finding; and 4. Increase
monitoring frequency to daily. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method; and 3. Review
and advise the ET and ER on the effectiveness of the proposed remedial
measures. |
1. Notify
Contractor. |
1. Identify
source(s), investigate the causes of exceedance and propose remedial
measures; 2. Implement
remedial measures; and 3. Amend
working methods agreed with the ER as appropriate. |
Action level being exceeded by two or more
consecutive sampling |
1. Identify
source; 2. Inform
Contractor, IEC and ER; 3. Advise
the Contractor and ER on the effectiveness of the proposed remedial measures; 4. Repeat
measurements to confirm findings; 5. Increase
monitoring frequency to daily; 6. Discuss
with IEC and Contractor on remedial actions required; 7. If
exceedance continues, arrange meeting with Contractor, IEC and ER; and 8. If
exceedance stops, cease additional monitoring. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method; 3. Discuss
with ET, ER and Contractor on possible remedial measures; 4. Advise
the ET and ER on the effectiveness of the proposed remedial measures; and 5. Supervise
Implementation of remedial measures. |
1. Confirm
receipt of notification of exceedance in writing; 2. Notify
Contractor; 3. Ensure
remedial measures properly implemented by the Contractor; and 4. If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated. |
1. Identify
source and investigate the causes of exceedance; 2. Submit
proposals for remedial measures to the ER with a copy to ET and IEC within
three working days of notification; 3. Implement
the agreed proposals; and 4. Amend
proposal as appropriate. |
Limit level being exceeded by one sampling |
1. Identify
source, investigate the causes of exceedance and propose remedial measures; 2. Inform
Contractor, IEC, ER, and EPD; 3. Repeat
measurement to confirm finding; 4. Increase
monitoring frequency to daily; and 5. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results. |
1. Check
monitoring data submitted by ET; 2. Check
Contractor’s working method; 3. Discuss
with ET and Contractor on possible remedial measures; 4. Advise
the ER on the effectiveness of the proposed remedial measures; and 5. Supervise
implementation of remedial measures. |
1. Confirm
receipt of notification of exceedance in writing; 2. Notify
Contractor; 3. Ensure
remedial measures properly implemented. |
1. Identify
source(s) and investigate the causes of exceedance; 2. Take
immediate action to avoid further exceedance; 3. Submit
proposals for remedial measures to ER with a copy to ET and IEC within three
working days of notification; 4. Implement
the agreed proposals; and 5. Amend
proposal if appropriate. |
Limit level being exceeded by two or more
consecutive sampling |
1. Notify
IEC, ER, Contractor and EPD; 2. Identify
source; 3. Repeat
measurement to confirm findings; 4. Increase
monitoring frequency to daily; 5. Carry
out analysis of Contractor’s working procedures to determine possible
mitigation to be implemented; 6. Arrange
meeting with IEC and ER to discuss the remedial actions to be taken; 7. Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results; and 8. If
exceedance stops, cease additional monitoring. |
1. Check
monitoring data submitted by the ET; 2. Discuss
amongst ER, ET, and Contractor on the potential remedial actions; 3. Review
Contractor’s remedial actions whenever necessary to assure their effectiveness
and advise the ER accordingly; and 4. Supervise
the implementation of remedial measures. |
1. Confirm
receipt of notification of exceedance in writing; 2. In
consultation with the ET and IEC, agree with the Contractor on the remedial
measures to be implemented; 3. Supervise
the implementation of remedial measures; and 4. If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated. |
1. Identify
source(s) and investigate the causes of exceedance; 2. Take
immediate action to avoid further exceedance; 3. Submit
proposals for remedial measures to the ER with a copy to the IEC and ET
within three working days of notification; 4. Implement
the agreed proposals; 5. Revise
and resubmit proposals if problem still not under control; and 6. Stop
the relevant portion of works as determined by the ER until the exceedance is
abated. |
· Watering once time per hour on active works areas and exposed areas so as to achieve a dust removal efficiency of 91.7%.
· When there are open excavation and spoil handling works, hoarding of 3 m high should be provided along the construction site boundary adjacent to the non-construction areas such as residential, educational institutes or recreation area in use so as to minimise the dust impact.
· Use of frequent watering for particularly dusty construction areas and areas close to ASRs.
· Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions. Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines.
· Open stockpiles shall be avoided or covered. Where possible, prevent placing dusty material storage piles near ASRs.
· Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations.
· Establishment and use of vehicle wheel and body washing facilities at the exit points of the site.
· Provision of wind shield and dust extraction units or similar dust mitigation measures at the loading area, and use of water sprinklers at the loading area where dust generation is likely during the loading process of loose material, particularly in dry seasons/ periods.
· Provision of not less than 2.4 m high hoarding from ground level along site boundary where adjoins roads, streets or other accessible to the public except for a site entrance or exit. Good site practice shall also be adopted by the Contractor to ensure the conditions of the hoardings are properly maintained throughout the construction period.
· Imposition of speed controls for vehicles on site haul roads.
· Where possible, routing of vehicles and positioning of construction plant should be at the maximum possible distance from ASRs.
· Every stock of more than 20 bags of cement or dry pulverised fuel ash (PFA) should be covered entirely by impervious sheeting or placed in an area sheltered on the top and the 3 sides.
Table 5.1 Proposed Noise Monitoring Stations during Construction Phase
Monitoring Station ID |
EIA ID |
Location |
Impact Monitoring Period (1) |
CM1 |
ETCW02 |
No. 739, Oaklands Court |
Q2 2023 – Q3 2031 |
CM2 |
ESFW01 |
No. 332, Chung Uk Tsuen |
Q2 2024 – Q3 2031 |
CM3 |
ESFW02 |
Village house, Nai Wai |
Q2 2023 – Q3 2031 |
CM4 |
ECUT01 |
No. 16, Chung Uk Tsuen |
Q2 2024 – Q3 2031 |
CM5 |
ELFS02 |
No. 3H, San Hing Tsuen |
Q1 2031 – Q4 2035 |
CM6 |
ELFS03 |
No. 310, Sha Kong Wai |
Q1 2031 – Q2 2037 |
CM7 |
ELFS04 |
Wing Jan School/Wing Jan Lutheran Church |
Q1 2031 – Q2 2032 |
CM8 |
ETSW05 |
Shui Fung House, Tin Shui Estate |
Q1 2031 – Q4 2038 |
CM9 |
ETSW08 |
VTC Youth College (Tin Shui
Wai) |
Q1 2031 – Q4 3028 |
CM10 |
ETSW11 |
YLPMSAA Tang Siu Tong Secondary School |
Q4 2031 – Q3 2037 |
CM11 |
E53902 |
No. 125, Lee Fong Yuen |
Q2 2024 – Q3 2031 |
CM12 |
ETST05b |
No. 143, Tin Sum, (West Façade) |
Q1 2026 – Q3 2031 |
CM13 |
ESLUT01 |
No. 46A, San Lee Uk
Tsuen |
Q1 2019 – Q3 2028 |
CM14 |
ESLUT03 |
No. 62, San Lee Uk
Tsuen |
Q1 2019 – Q3 2035 |
CM15 |
ESLUT04 |
No. 254, San Lee Uk
Tsuen |
Q1 2019 – Q3 2035 |
CM16 |
E52505 |
Hung Yan House, Hung Fuk
Estate |
Q1 2019 – Q4 2029 |
CM17 |
EHUT04 |
No. 85A, Kiu Tau Wai |
Q1 2032 – Q4 2033 |
CM18 |
ESPT06 |
No. 201, Shek Po Tsuen |
Q1 2032 – Q3 2035 |
CM19 |
ESST07 |
No, 60, San Sang Tsuen |
Q3 3027 – Q3 2035 |
CM20 |
ESCL03 |
No. 45, Sha Chau Lei Tsuen |
Q2 2031 – Q3 2035 |
CM21 |
EHTS01 |
No. 1B, San Uk Tsuen |
Q1 2031 – Q3 2035 |
CM22 |
ELUT01 |
Block 11, Yan Wu Garden |
Q1 2031 – Q1 2034 |
CM23 |
ESKT02 |
No. 151, Sik Kong Wai |
Q4 2031 – Q3 2033 |
CM24 |
ETKW01 |
No.108C, Tseung Kong Wai |
Q3 2028 – Q3 2035 |
CM25 |
ETTT01 |
Block A Luxor Garden, Tung Tau Tsuen |
Q1 2031 – Q4 2038 |
CM26 |
EFKT01 |
No.61, Fung Kong Tsuen |
Q3 2022 – Q2 2034 |
CM27 |
40305 |
Planned Residential Development in Site 4-3 |
Q2 2033 – Q3 2034 |
CM28 |
42001 |
Planned Residential Development in Site 4-20 |
Q1 2026 – Q3 2031 |
CM29 |
42251 |
Planned Residential Development in Site 4-22 |
Q2 2024 – Q3 2031 |
CM30 |
21801 |
Planned Residential Development in Site 2-18 |
Q1 2031 – Q4 2036 |
CM31 |
52408 |
Planned Residential Development in Site 5-24 |
Q2 2024 – Q3 2035 |
CM32 |
52151 |
Planned School in Site 5-21 |
Q1 2031 – Q4 2035 |
Note: (1) The
monitoring period is subject to the construction programme
of the relevant contracts in the Construction Stage.
i.
at locations close to the major site activities
which are likely to have noise impacts;
ii.
close to the NSRs; and
iii.
for monitoring
locations located in the vicinity of the sensitive receivers, care shall be
taken to cause minimal disturbance to the occupants during monitoring.
Table 5.2 Action and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700 – 1900 hours |
When one documented complaint is
received |
75 dB(A)* |
Notes:
·
If
works are to be carried out during restricted hours, the conditions stipulated
in the Construction Noise Permit (CNP) issued by the Noise Control Authority
have to be followed.
·
* 70 dB(A) and 65 dB(A) for schools during normal teaching
periods and school examination periods, respectively.
Table 5.3 Event and Action Plan for Construction Noise
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action Level |
1.
Notify IEC and Contractor; 2.
Carry out investigation; 3.
Report the results of investigation to the IEC,
ER and Contractor; 4.
Discuss with the Contractor and formulate
remedial measures; and 5.
Increase monitoring frequency to check mitigation
effectiveness. |
1.
Review the analysed
results submitted by the ET; 2.
Review the proposed remedial measures by the
Contractor and advise the ER accordingly; and 3.
Supervise the implementation of remedial
measures. |
1.
Confirm receipt of notification of failure in
writing; 2.
Notify Contractor; 3.
Require Contractor to propose remedial measures
for the analysed noise problem; and 4.
Ensure remedial measures are properly
implemented. |
1.
Submit noise mitigation proposals to IEC; and 2.
Implement noise mitigation proposals. |
Limit
Level |
1.
Identify source; 2.
Inform IEC, ER, EPD and Contractor; 3.
Repeat measurements to confirm findings; 4.
Increase monitoring frequency; 5.
Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented; 6.
Inform IEC, ER and EPD the causes and actions taken for the
exceedances; 7.
Assess effectiveness of Contractor’s remedial
actions and keep IEC, EPD and ER informed of the results; and 8.
If exceedance stops, cease additional monitoring. |
1.
Discuss amongst ER, ET, and Contractor on the
potential remedial actions; 2.
Review Contractors remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly; and 3.
Supervise the implementation of remedial
measures. |
1.
Confirm receipt of
notification of failure in writing; 2.
Notify Contractor; 3.
Require Contractor to
propose remedial measures for the analysed noise
problem; 4.
Ensure remedial
measures properly implemented; and 5.
If exceedance
continues, consider what portion of the work is responsible and instruct the
Contractor to stop that portion of work until the exceedance is abated. |
1.
Take immediate action to avoid further
exceedance; 2.
Submit proposals for remedial actions to IEC within 3
working days of notification; 3.
Implement the agreed proposals; 4.
Resubmit proposals if problem still not under
control; and 5.
Stop the relevant portion of works as determined
by the ER until the exceedance is abated. |
Table 5.4 Traffic Noise Monitoring Locations
Monitoring Station ID |
EIA ID |
Location |
Noise Barrier Location |
OM1 |
E2-OC_R01 |
Sha Kong Wai |
VB2, Tin Wah Road / Lau Fau
Shan Road |
OM2 |
E2-IA_R01 |
Fung Kong Tsuen |
VB5, Proposed Road D1 |
OM3 |
E1-IA_R01 |
Tseung Kong Wai |
VB7, VB8 & VB9, Proposed Road D3 |
OM4 |
E1-IF_R02 |
Ha Tsuen Shi |
VB26, Proposed Road L1 |
OM5 |
E1-OB_21 |
Lions Clubs International Ho Tak
Sum Primary School |
VB21 & VB24, Proposed Road D2/ Ping Ha Road |
OM6 |
E4-OA_R01 |
Tsing Cheun Wai |
VB39 & VB40, Proposed Road P1 |
·
At
locations close to the major site activities which are likely to have noise
impacts;
·
Close to
the NSRs; and
·
For
monitoring locations located in the vicinity of the sensitive receivers, care
should be taken to cause minimal disturbance to the occupants during
monitoring.
·
One set of
measurements at the morning traffic peak hour on normal weekdays;
·
One set of
measurements at the evening traffic peak hour on normal weekdays;
·
A
concurrent census of traffic flow and percentage heavy vehicle shall be
conducted for the Project roads and the existing road network in the vicinity
of each measuring point;
·
Average
vehicle speed estimated for Project road and the existing road network in the
vicinity of each measuring points; and
·
The two
sets of monitoring data should be obtained within the first year of operation.
·
Only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction program.
·
Silencers
or mufflers on construction equipment should be utilised and should be properly
maintained during the construction program.
·
Mobile
plant, if any, should be sited as far away from NSRs as possible.
·
Machines
and plant (such as trucks) that may be in intermittent use should be shut down
between works periods or should be throttled down to a minimum.
·
Plant
known to emit noise strongly in one direction should, wherever possible, be
orientated so that the noise is directed away from the nearby NSRs.
·
Material
stockpiles and other structures should be effectively utilised, wherever
practicable, in screening noise from on-site construction activities.
·
Wing Jan
School/Wing Jan Lutheran Church
·
VTC Youth
College (Tin Shui Wai)
·
YLPMSAA
Tang Siu Tong Secondary School
·
No. 62,
San Lee Uk Tsuen
·
No. 60,
San Sang Tsuen
·
No. 1B,
San Uk Tsuen
·
Planned
School in Site 1-3
·
Planned
School in Site 1-15
·
Planned
Residential Development in Site 4-20
·
Planned
Residential Development in Site 4-22
·
Planned
School in Site 5-21
·
Wing Jan
School/Wing Jan Lutheran Church
·
VTC Youth
College (Tin Shui Wai)
·
YLPMSAA
Tang Siu Tong Secondary School
·
Planned
School in Site 1-3
·
Planned
School in Site 5-21
·
Wing Jan
School/Wing Jan Lutheran Church
·
VTC Youth
College (Tin Shui Wai)
·
YLPMSAA
Tang Siu Tong Secondary School
·
Planned
School in Site 1-3
·
Planned
School in Site 1-15
·
Planned
School in Site 5-21
Table 5.5 List of Proposed Noise Mitigation Measures (Low-Noise Road Surfacing)
ID |
Road |
Length, m |
LNS1 |
Not used |
- |
LNS2 |
Tin Wah Road |
350 |
LNS3 |
Proposed Roundabout at Junction J2 |
210 |
LNS4 |
Proposed Road D1 |
500 |
LNS5 |
Proposed Road near Site2-26 |
280 |
LNS6 |
Proposed Road D1 |
400 |
LNS7 |
Proposed Road D1 |
640 |
LNS8 |
Proposed Road D1 (Depressed
Section) |
120 |
LNS9 |
Proposed Road L1 |
670 |
LNS10 |
Proposed Road P1 |
560 |
LNS11 |
Proposed Road L5 |
440 |
LNS12 |
Proposed Road D2 |
280 |
LNS13 |
Proposed Road D2 (Depressed
Section) |
180 |
LNS14 |
Proposed Road D2 |
1260 |
LNS15 |
Proposed Road L3 |
390 |
LNS16 |
Proposed Road D2 |
370 |
LNS17 |
Proposed Roundabout at Junction J8 |
190 |
LNS18 |
Ping Ha Road |
110 |
LNS19 |
Not used |
- |
LNS20 |
Kiu Fat Street |
280 |
LNS22 |
Proposed Road near Site 5-13 |
730 |
LNS23 |
Hung Chi Road / Proposed Road L5 |
340 |
LNS24 |
Not used |
- |
LNS25 |
Not used |
- |
LNS26 |
Not used |
- |
LNS27 |
Proposed Road near Site 4-24 |
140 |
LNS28 |
Not used |
- |
LNS29 |
Proposed Road L2 |
670 |
LNS30 |
Proposed Road near Site 4-29 |
270 |
LNS31 |
Not used |
- |
LNS32 |
Proposed Road P1 |
790 |
LNS33 |
Proposed Road P1 |
380 |
LNS34 |
Proposed Road P1 |
610 |
LNS35 |
Proposed Road D8 |
480 |
LNS36 |
Proposed Road near Site 4-33 |
210 |
- |
Hung Chi Road |
350 |
- |
Hung Shui
Kiu Tin Sum Road (East Section and South of San Lee Uk
Tsuen) |
480 |
Table 5.6 List of Proposed Noise Mitigation Measures (Barriers and Enclosure)
Noise Barrier ID |
Location |
Barrier Type |
Height, mAG |
Length, m |
CB1 |
Proposed Road D2 |
Cantilever |
6+4.2 m at 45 degree |
50 |
CB2 |
Not used |
- |
- |
- |
CB3a |
Proposed Road P1 |
Cantilever |
5.5+2.5 m at 45 degree |
80 |
CB3b |
Proposed Road P1 |
Cantilever |
5.5+2.5 m at 45 degree |
130 |
CB4 |
Not used |
- |
- |
- |
CB5 |
Proposed Road D2, near Site 1-22 |
Cantilever |
6+4.2 m at 45 degree |
130 |
VB2 |
Tin Wah Road / Lau Fau
Shan Road |
Vertical |
5 |
140 |
VB3 |
Proposed Road D1 |
Vertical |
3 |
120 |
VB4 |
Proposed Road D2 |
Vertical |
5 |
140 |
VB5 |
Proposed Road D1 |
Vertical |
5 |
90 |
VB6 |
Proposed Road D1 |
Vertical |
5 |
150 |
VB7 |
Proposed Road D3 |
Vertical |
4 |
60 |
VB8 |
Proposed Road D3 |
Vertical |
4 |
50 |
VB9 |
Proposed Road D3 |
Vertical |
4 |
50 |
VB10 |
Proposed Road D2 |
Vertical |
4 |
180 |
VB11 |
Not used |
- |
- |
- |
VB12 |
Proposed Road D2 |
Vertical |
6 |
110 |
VB13 |
Not used |
- |
- |
- |
VB14 |
Not used |
- |
- |
- |
VB15 |
Proposed Road D2 |
Vertical |
5 |
30 |
VB16 |
Proposed Road D2 |
Vertical |
5 |
60 |
VB17 |
Proposed Road D2 |
Vertical |
5 |
20 |
VB18 |
Proposed Road D2 |
Vertical |
4 |
60 |
VB19 |
Not used |
- |
- |
- |
VB20 |
Proposed Road L3 |
Vertical |
7 |
110 |
VB21 |
Proposed Road D2/ Ping Ha Road |
Vertical |
7 |
50 |
VB22 |
Not used |
- |
- |
- |
VB23 |
Proposed Road D2/ Ping Ha Road |
Vertical |
7 |
130 |
VB24 |
Ping Ha Road |
Vertical |
7 |
160 |
VB25 |
Not used |
- |
- |
- |
VB26 |
Proposed Road L1 |
Vertical |
5 |
70 |
VB27 |
Not used |
- |
- |
- |
VB28 |
Hung Tin Road |
Vertical |
5 |
90 |
VB29 |
Hung Tin Road |
Vertical |
7 |
80 |
VB30 |
Not used |
- |
- |
- |
VB31 |
Hung Tin Road |
Vertical |
7 |
60 |
VB32 |
Not used |
- |
- |
- |
VB33 |
Not used |
- |
- |
- |
VB34 |
Not used |
- |
- |
- |
VB35 |
Proposed Road D5 |
Vertical |
5 |
80 |
VB36 |
Proposed Road D5 |
Vertical |
5 |
70 |
VB37 |
Proposed Road D5 |
Vertical |
3 |
70 |
VB38 |
Proposed Road D5 |
Vertical |
3 |
80 |
VB39 |
Proposed Road P1 |
Vertical |
3 |
100 |
VB40 |
Proposed Road P1 |
Vertical |
3 |
130 |
VB41 |
Proposed Road D2 |
Vertical |
5 |
130 |
VB42 |
Not used |
- |
- |
- |
Table 5.7 Details of Proposed Boundary Wall for Planned Education Institutes
Boundary Wall ID |
Location |
Barrier Type |
Height, mAG |
Length, m |
VB1 |
Boundary Wall at Site 2-9 |
Vertical |
3 |
65 |
VB43 |
Boundary wall at Site 4-36 |
Vertical |
3 |
60 |
VB44 |
Boundary wall at Site 4-36 |
Vertical |
3 |
120 |
VB45 |
Boundary wall at Site 4-33 |
Vertical |
3 |
200 |
VB46 |
Boundary wall at Site 5-34 |
Vertical |
3 |
150 |
VB47 |
Boundary wall at Site 5-34 |
Vertical |
3 |
160 |
Table 5.8 Proposed Additional Mitigation Measures at Planned Sites
Site Ref. No. |
Use |
Proposed Additional Mitigation Measures |
Applied to |
Figure Reference |
1-2 |
Residential |
Acoustic Windows |
1
- 17/F |
Figure
4.7.19 |
1-15 |
Educational |
Blank Façade |
1
edge of 1 building |
Figure
4.7.21 |
1-22 |
Educational |
Noise Insulated Windows and Air Conditioning |
1
school |
Figure
4.7.21 |
2-26 |
Educational |
Blank Façade |
1
edge of 1 building |
Figure
4.7.20 |
4-1 |
Staff Quarters |
Acoustic Windows |
1
- 25/F |
Figure
4.7.25 |
Blank Façade |
1
edge of 2 buildings |
|||
4-5 |
Residential |
Acoustic Windows |
20
- 42/F |
Figure
4.7.25 |
4-24 |
Residential |
Acoustic Windows |
1
- 20/F |
Figure
4.7.26 |
4-26 |
Residential |
Acoustic Windows |
3
- 11/F |
Figure
4.7.26 |
4-28 |
Residential |
Acoustic Windows |
1
- 2/F |
Figure
4.7.26 |
4-33 |
Educational |
Noise Insulated Windows and Air Conditioning |
1
school |
Figure
4.7.27 |
5-7b |
Residential/ Commercial |
Acoustic Windows |
1
- 9/F |
Figure
4.7.22 |
5-14 |
Educational |
Noise Insulated Windows and Air Conditioning |
2
schools |
Figure
4.7.23 |
5-16 |
Residential |
Acoustic Windows |
3
- 22/F |
Figure
4.7.21 |
5-17 |
Residential |
Acoustic Windows |
4
- 29/F |
Figure
4.7.22 |
5-21 |
Educational |
Noise Insulated Windows and Air Conditioning |
1
school |
Figure
4.7.23 |
5-22 |
Residential |
Acoustic Balcony |
1
- 21/F |
Figure
4.7.24 |
5-28 |
Residential Home for the Elderly |
Noise Insulated Windows and Air Conditioning |
1
Residential Home for the Elderly |
Figure
4.7.24 |
5-32 |
Residential/ Commercial |
Acoustic Windows |
1
- 28/F |
Figure
4.7.24 |
Acoustic Balcony |
1
- 9/F |
|||
5-34 |
Educational |
Blank Façade |
1
edge of 1 building |
Figure
4.7.24 |
Noise Insulated Windows and Air Conditioning |
1
school |
|||
5-37 |
Educational |
Noise Insulated Windows and Air Conditioning |
1
school |
Figure
4.7.24 |
Note: For Site 5-28, the need of additional measures would
be subject to whether the LNRS can apply on Hung Shui
Kiu Tin Sam Road (East Section).
· All the pumps and noisy plants should be enclosed inside a building structure;
· Proper selection of quiet plant aiming to reduce the tonality at NSRs;
· Installation of silencer/acoustic enclosure/acoustic louvre for the exhaust of ventilation system; and
· Openings of ventilation systems should be located away from NSRs as far as practicable.
Table 6.1 Proposed Water Quality Monitoring Stations
Fresh Water
System |
Station |
Description |
Easting |
Northing |
TSW Main Channel and its
tributaries |
U1 |
Upstream Stations |
815936 |
834150 |
U2 |
816240 |
834009 |
||
U3 |
816137 |
832945 |
||
U4 |
816092 |
832459 |
||
U5 |
816067 |
832292 |
||
U6 |
817701 |
832513 |
||
TS1 |
Gradient Stations |
816815 |
832297 |
|
TS2 |
817277 |
833356 |
||
TSR1 |
817687 |
833812 |
||
ST |
816938 |
833266 |
||
SW |
816304 |
834321 |
||
HT |
816866 |
834314 |
||
LUT |
817595 |
834737 |
||
D2 |
Impact Station |
817533 |
836078 |
|
Hang Hau Tsuen Channel |
LFS |
Gradient Station |
816504 |
835862 |
D1 |
Impact Station |
816187 |
836064 |
|
Tuen Mun River |
D3 |
Impact Station |
816437 |
831500 |
Small Watercourses along Deep Bay |
DB |
Gradient Station |
816091 |
834976 |
D4 |
Impact Station |
815874 |
835223 |
|
Upstream / Tributaries of Shan Pui River |
U7 |
Upstream Station |
818712 |
831733 |
D5 |
Impact Station |
818857 |
832139 |
|
D6 |
Impact Station |
818889 |
832005 |
6.3.8
When
alternative monitoring locations are proposed, they shall be chosen based on
the following criteria:
a) at locations close to and preferably at the boundary of the mixing zone
of the major site activities as indicated in the EIA Report, which are likely
to have water quality impacts;
b) close to the sensitive receptors which are directly or likely to be
affected;
c) for monitoring locations located in the vicinity of the sensitive
receptors, care shall be taken to cause minimal disturbance during monitoring;
d) two or more
control stations which shall be at locations representative of the project site
in its undisturbed condition. Control stations shall be located, as far as is
practicable, both upstream and downstream of the works area.
·
investigate
the problems and the causes;
·
issue
action notes to the Contractor who is responsible for the works;
·
implement
remedial and corrective actions immediately;
·
re-inspect
the site conditions upon completion of the remedial and corrective actions; and
·
record the event and
discuss with the Contractor for preventive actions.
Dissolved Oxygen and Temperature
Measuring Equipment
· a DO level in the range of 0 – 20 mg/L and 0 – 200% saturation; and
· a temperature of 0 – 45 degree Celsius.
Turbidity
Measurement Instrument
Calibration
of In-Situ Instruments
Table 6.2 Analytical Methods to be Applied to Water Quality Samples
Parameters |
Analytical Method |
Detection Limit |
Suspended
Solids |
APHA
2540D * |
1
mg/L |
* APHA American Public Health Association
Standard Methods for the Examination of Water and Wastewater.
Table 6.3 Action and Limit Levels for Water Quality Impact Stations (D1,
D2 and D3)
Parameters |
Action
Level |
Limit
Level |
DO in mg/L |
Surface, middle,
bottom DO £ 5 %-ile of baseline data |
Surface, middle DO £ 4 mg/L and 1%-ile of baseline data for
surface and middle layer Bottom DO £ 2 mg/L and 1%-ile of baseline data for
bottom layer |
SS in mg/L |
Depth-average SS ≥ 95 %-ile of baseline data |
Depth-average SS ≥ 99 %-ile of baseline |
Turbidity in NTU |
Depth-average SS ≥ 95 %-ile of baseline data |
Depth-average SS ≥ 99 %-ile of baseline |
pH |
Beyond the range 6.6 to 8.4 |
Beyond the range of 6.5 to 8.5 |
Notes:
(1) For DO, non-compliance
of the water quality limits occurs when monitoring result is lower than the
limits.
(2) For SS and turbidity,
non-compliance of the water quality limits occurs when monitoring result is
higher than the limits.
Table 6.4 Event and Action Plan for Water Quality
Event |
ET Leader |
IEC |
ER |
Contractor |
Action level being exceeded by one sampling
day |
·
Repeat in-situ measurement to confirm findings; ·
Identify source(s) of impact; ·
Inform IEC and Contractor; ·
Check monitoring data, all plant, equipment and Contractor's working
methods; ·
Discuss mitigation measures with IEC and Contractor; ·
Repeat measurement on next day of exceedance. |
·
Discuss with ET and Contractor on the mitigation measures; ·
Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; ·
Assess the effectiveness of the implemented mitigation measures. |
·
Discuss with IEC on the proposed mitigation measures; ·
Make agreement on the mitigation measures to be implemented; |
·
Inform the ER and confirm notification of the non-compliance in
writing; ·
Rectify unacceptable practice; ·
Check all plant and equipment; ·
Consider changes of working methods; ·
Discuss with ET and IEC and propose mitigation measures to IEC and
ER; ·
Implement the agreed mitigation measures. |
Action level being exceeded by more than
one consecutive sampling days |
·
Repeat in-situ measurement to confirm findings; ·
Identify source(s) of impact; ·
Inform IEC and Contractor; ·
Check monitoring data, all plant, equipment and Contractor's working
methods; ·
Discuss mitigation measures with IEC and Contractor; ·
Ensure mitigation measures are implemented; ·
Prepare to increase the monitoring frequency to daily; ·
Repeat measurement on next day of exceedance. |
·
Discuss with ET and Contractor on the mitigation measures; ·
Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; ·
Assess the effectiveness of the implemented mitigation measures. |
·
Discuss with IEC on the proposed mitigation measures; ·
Make agreement on the mitigation measures to be implemented; ·
Assess the effectiveness of the implemented mitigation measures. |
·
Inform the Engineer and confirm notification of the non-compliance in
writing; ·
Rectify unacceptable practice; ·
Check all plant and equipment; ·
Consider changes of working methods; ·
Discuss with ET and IEC and propose mitigation measures to IEC and ER
within 3 working days; ·
Implement the agreed mitigation measures. |
Limit level being exceeded by one sampling
day |
·
Repeat in-situ measurement to confirm findings; ·
Identify source(s) of impact; ·
Inform IEC, contractor and EPD; ·
Check monitoring data, all plant, equipment and Contractor's working
methods; ·
Discuss mitigation measures with IEC, ER and Contractor; ·
Ensure mitigation measures are implemented; ·
Increase the monitoring frequency to daily until no exceedance of
Limit level. |
·
Discuss with ET and Contractor on the mitigation measures; ·
Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; ·
Assess the effectiveness of the implemented mitigation measures. |
·
Discuss with IEC, ET and Contractor on the proposed mitigation
measures; ·
Request Contractor to critically review the working methods; ·
Make agreement on the mitigation measures to be implemented; ·
Assess the effectiveness of the implemented mitigation measures. |
·
Inform the Engineer and confirm notification of the non-compliance in
writing; ·
Rectify unacceptable practice; ·
Check all plant and equipment; ·
Consider changes of working methods; ·
Discuss with ET , IEC and ER and propose mitigation measures to IEC
and ER within 3 working days; ·
Implement the agreed mitigation measures. |
Limit level being exceeded by more than one
consecutive sampling days |
·
Repeat in-situ measurement to confirm findings; ·
Identify source(s) of impact; ·
Inform IEC, contractor and EPD; ·
Check monitoring data, all plant, equipment and Contractor's working
methods; ·
Discuss mitigation measures with IEC, ER and Contractor; ·
Ensure mitigation measures are implemented; ·
Increase the monitoring frequency to daily until no exceedance of
Limit level for two consecutive days. |
·
Discuss with ET and Contractor on the mitigation measures; ·
Review proposals on mitigation measures submitted by Contractor and
advise the ER accordingly; ·
Assess the effectiveness of the implemented mitigation measures. |
·
Discuss with IEC, ET and Contractor on the proposed mitigation
measures; ·
Request Contractor to critically review the working methods; ·
Make agreement on the mitigation measures to be implemented; ·
Assess the effectiveness of the implemented mitigation measures; ·
Consider and instruct, if necessary, the Contractor to slow down or
to stop all or part of the marine work until no exceedance of Limit level. |
·
Inform the ER and confirm notification of the non-compliance in
writing; ·
Rectify unacceptable practice; ·
Check all plant and equipment; ·
Consider changes of working methods; ·
Discuss with ET , IEC and ER and propose mitigation measures to IEC
and ER within 3 working days; ·
Implement the agreed mitigation measures; ·
As directed by the Engineer, to slow down or to stop all or part of
the marine work or construction activities. |
This Page Left Blank Intentionally
·
To ensure
the waste arising from the works are handled, stored, collected, transferred
and disposed of in an environmentally acceptable manner; and
·
To
encourage the reuse and recycling of material.
·
Waste
Collection Licence and Waste Disposal Licence under the Waste Disposal
Ordinance (Cap. 354);
·
Application
for Registration under Section 7(5) of the Waste Disposal (Chemical Waste)
(General) Regulation (Cap. 354C);
·
Public
Dumping Licence under the Land (Miscellaneous Provisions) Ordinance (Cap. 28);
·
Effluent
Discharge Licence under the Water Pollution Control Ordinance (Cap. 358); and
·
Approval
of Construction & Demolition Material Management Plan (C&DMMP).
This Page Left Blank Intentionally
This Page Left Blank Intentionally
This Page Left Blank Intentionally
12.2.1 The proposed mitigation measures for the landscape and visual impacts are summarised below as well as in the PIS in Appendix 2.2. The landscape and visual mitigation measures proposed should be incorporated in the detailed landscape and engineering design. The construction phase mitigation measures should be implemented as early as possible during construction and should be in place throughout the entire construction period. Mitigation measures for the operational phase should be implemented during the detailed design and be built as part of the construction works so that they are in place on commissioning of the Project (Table 12.1).
Table 12.1 Proposed
Landscape and Visual Mitigation Measures
ID No. |
Landscape
and Visual Mitigation Measures |
Mitigate
Landscape Impacts |
Mitigate
Visual Impacts |
Construction Phase |
|||
CM1 |
Minimised construction area and contractor’s temporary
works areas The
construction area and contractor’s temporary works areas should be minimised. General
Good Practice Measures - For areas unavoidably disturbed by the Project on a
short term basis e.g. works areas, the general principle to try and restore
these to their former state to suit future land use, should be adhered to. |
X |
X |
CM2 |
Stripping
and storing of topsoil Topsoil,
where identified, should be stripped and stored for re-use in the
construction of the soft landscape works, where practical. The Contract Specification shall include
storage and reuse of topsoil as appropriate. On potentially contaminated sites (as per Chapter 8) where
investigation results indicate soil contamination is present, the use of
contaminated soils for planting is to be avoided where appropriate. |
X |
|
CM3 |
Protection
of existing trees Tree
Protection & Preservation – Exiting trees to be retained within the
Project Site should be carefully protected during construction. Detailed Tree
Protection Specification shall be provided in the Contract Specification.
Under this specification, the Contractor shall be required to submit, for
approval, a detailed working method statement for the protection of trees
prior to undertaking any works adjacent to all retained trees, including
trees in Contractor’s works areas. A
detailed tree survey will be carried out for the Tree Removal Application
(TRA) process which will be carried out at the later detailed design stage of
the Project. The detailed tree survey will propose which trees should be
retained, transplanted or felled and will include details of tree protection
measures for those trees to be retained. |
X |
X |
CM4 |
Transplantation
of existing trees where practical Trees
unavoidably affected by the Project works should be transplanted where practical.
Trees should be transplanted straight to their final receptor site and not
held in a temporary nursery as far as possible. A detailed Tree Transplanting
Specification shall be provided in the Contract Specification, where
applicable. Sufficient time for necessary tree root and crown preparation
periods shall be allowed in the project programme. A
detailed transplanting proposal will be submitted to relevant government
departments for approval in accordance with DEVB TCW 06/2015
and 07/2015 and final locations of transplanted trees
should be agreed prior to commencement of the work. For
trees associated with highways e.g. roadside planting along highways, that
are unavoidably affected and should be transplanted, HyD
HQ/GN/13 ‘Interim Guidelines for Tree Transplanting Works under Highways
Department's Vegetation Maintenance Ambit’ should be referred to. |
X |
X |
CM5 |
Control of night-time lighting Control of night-time lighting and glare by hooding
all lights. Construction day and night time lighting should be
controlled to minimise glare impact to adjacent VSRs during the Construction
phase. |
|
X |
CM6 |
Construction of decorative hoarding around
construction works Erection of decorative mesh screens or construction
hoardings around works areas in visually unobtrusive colours. Screen hoarding shall be erected along areas of the
construction works site boundary where the works site borders publically
accessible routes and/or is close to visually sensitive receivers (VSRs). It
is proposed that the screening be compatible with the surrounding environment
and where possible, non-reflective, recessive colours be used. |
|
X |
CM7 |
Reduction of construction period to practical
minimum Options to reduce the construction period to
practical minimum to be provided. |
|
X |
CM8 |
Prevention of run-off Limitation of / Ensuring no run-off into surrounding
landscape and prohibit run-off from entering adjacent water bodies and
waterways. |
X |
|
CM9 |
Phasing of construction stage Phasing of the construction stage to reduce visual
impacts. |
|
X |
CM10 |
Advance screen planting Advance screen planting of fast growing tree and
shrub species to noise barriers and hoardings. Trees shall be capable of
reaching a height >10m within 10 years. |
X |
X |
CM11 |
Minimise disturbance footprints To minimise landscape and visual impacts, the
footprint and elevation of such elements should be optimised to reduce
topographical/ landform changes, as well as reduce land take and interference
with natural terrain. Where there is a need to significantly cut into the
existing landform, retaining walls should be considered as well as cut
slopes, to minimise landform changes and land resumption, while also
considering visual amenity. Earthworks and engineered slopes should be
designed to be a visually interesting landform, compatible with the
surrounding landscape and to mimic the natural contouring and terrain e.g.
introduction and continuation of natural features such as spurs and ridges
where appropriate, to support assimilation with the hillside setting. |
X |
|
CM12 |
Protection of existing watercourses For all the natural rivers and streams inside the
development area, consideration of protection measures should be made to
minimise any impacts from the construction works. Avoid affecting Watercourses – In the detailed
design, consideration should be made of watercourses, to minimise any impacts
e.g. at new bridge crossings, viaducts, road alignment etc. Guidelines stated
should be followed. Bridges and box culverts should also be used to
minimise the necessity of watercourse modification and protect the
watercourses where necessary. |
X |
|
CM13 |
Hydroseeding on modified slopes Hydroseeding of modified slopes should be done as soon as
grading works are completed to prevent erosion and subsequent loss of
landscape resources and character. Woodland tree seedlings and/ or shrubs
should be planted where slope gradient and site
conditions allow. In addition, landscape planting should be provided
for the retaining structures associated with modified slopes where conditions
allow. All slope landscaping works should comply with GEO
Publication No. 1/2011-Technical Guidelines on Landscape Treatment for
Slopes. |
X |
X |
CM14 |
Integrate Open Space Network with existing nullah conditions For watercourses affected during construction,
measures should be sought to minimise the impact with respect to the existing
nullah conditions, existing shrubs and trees along
the banks. Where natural streams are unavoidably affected along
some of their length, they can be diverted to avoid the proposed new
developments and retain the integrity of the whole stream. Detailed design of
any stream diversion should follow the Guidelines in ETWB Technical Circular
(Works) No. 5/2005 (Protection of natural streams/rivers from adverse impacts
arising from construction works) and appropriate construction methods should
be used. |
X |
X |
Operation Phase |
|||
OM1 |
Compensatory tree planting where practical Compensatory Planting – Compensatory tree
planting for felled trees shall be provided to the satisfaction of relevant
Government departments. Required numbers and locations of compensatory trees
shall be determined and agreed separately with Government during the Tree
Removal Application process under ETWBTC 7/2015. Compensatory planting is proposed at the
potential open areas such as open spaces, amenity areas, open areas of the
streetscapes, as well as the open areas within development lots. |
X |
X |
OM2 |
Sensitive design of above-ground structures All above-ground structures, including SPS,
Electrical Sub-Stations, EFLS Stations, Emergency and Firemens’
Accesses, etc. shall be sensitively designed in a manner that responds to the
existing and planned urban context. The footprint and massing of development components
and the works area should also be kept to a practical minimum and the
detailed design of development components for Construction phase should
follow the Sustainable Building Design Guidelines. The form, textures,
finishes and colours of the proposed development components should aim to be
compatible with the existing surroundings. To improve visual amenity designs
should be aesthetically pleasing and treatment of structures also improve
visual amenity. |
X |
X |
OM3 |
Sensitive design of hardscape
elements along roadsides Streetscape elements along new and existing roads
(e.g. paving, signage, street furniture, lighting etc.) shall be sensitively
designed in a manner that responds to the existing and planned urban context. |
X |
X |
OM4 |
Reinstatement of streetscape
elements All streetscape areas and hard and soft landscape
areas disturbed during construction shall be reinstated to equal or better
quality, to the satisfaction of the relevant Government departments. |
X |
X |
OM5 |
Visual softening via soft
landscape elements Attractive soft landscape in areas adjoining SPS,
Electrical Sub-Stations, EFTS Stations, Emergency and Firemen’s’ Accesses,
etc. (taking into account the necessary setbacks) so as to provide a visual
softening and greening effect (e.g. provision of tree / shrub / climber
planting). |
|
X |
OM6 |
Quality greening along roadside
amenity strips Shade trees, ornamental tree / shrub /
climber planting should be provided along roadside amenity strips to enhance
the townscape quality. Provision of utility free planting strips for
quality planting shall be adopted according to DEVB TCW 2/2012. |
X |
X |
OM7 |
Design of street lighting Appropriate design of street lighting to avoid
glare and light pollution to surrounding areas. |
|
X |
OM8 |
Sensitive and chromatic treatment
of architectural facades Elegant architectural and engineering design, sensitive architectural and chromatic treatment for building facades. The form, textures, finishes and colours of the
proposed development components should aim to be compatible with the existing
surroundings. To improve visual amenity designs should be aesthetically
pleasing and treatment of structures also improve visual amenity. For
example, natural building materials such as stone and timber, should be
considered for architectural features, and light earthy tone colours such as
shades of green, shades of grey, shades of brown and off-white should also be
considered to reduce the visibility of the development components. |
|
X |
OM9 |
Sensitive design of vertical
landscape areas Elegant, sensitive design and
generous planting of the associated landscape areas. Open Space Provision - the principles adopted in the RODP planning ensure that public open space systems are incorporated. All requirements for open space areas stipulated
in the planning documents for the formulation of the Preliminary Layout Plan
should be adhered to. |
X |
X |
OM10 |
Sensitive design of noise barriers
and enclosures The visual impact of noise barriers &
enclosures will be mitigated by appropriate detailed design, including
suitable combination of transparent and sound absorbent materials,
appropriate colour selection of panels and supporting structures, or
provision of at-grade planting of trees, shrubs and/or climbers camouflage to
the barriers, as well as design of supporting structures to incorporate a
high level of quality and aesthetics. A combination of transparent panels at
top and solid panels at bottom would lighten the visual impact, and at the
same time maintain the attractiveness by using colourful panels. |
|
X |
OM11 |
Tree planting at site boundaries Tree planting screens along appropriate site
boundaries |
X |
X |
OM12 |
Night time lighting Control of lighting glare. A balance between
lighting for safety, and avoiding excessive lighting can be achieved through
consideration of the following: the type of lamp (light source) used; use of
directional lighting to avoid light spill into sensitive areas; height of the
lighting column can affect the amount/extent of glare; and control/timing of
lighting periods of some facilities, particularly those close to sites of
conservation importance. |
|
X |
OM13 |
Green roofs and vertical greening Green roofs and vertical greening provision of green
roofs and vertical greening where feasible and appropriate to mitigate visual
impacts of buildings and structures |
X |
X |
OM14 |
Greening of viaduct structures and
noise barriers Aesthetic improvement of viaduct
structures and noise barriers through greening of structure where feasible
and appropriate to mitigate visual impact of viaduct and noise barrier form |
X |
X |
·
The extent
of the agreed works areas should be regularly checked during the construction
phase. Any trespass by the contractor outside the limit of the works, including
any damage to existing trees and woodland shall be noted and reported to the
ER.
·
The
progress of the engineering works should be regularly reviewed on site to
identify the earliest practical opportunities for the landscape works to be undertaken.
·
The tree
and shrub transplanting and planting operations.
·
Topsoil
protection and storage operations.
·
All
existing trees and vegetation within the study area which are not directly
affected by the works are retained and protected.
·
The
methods of protecting existing vegetation proposed by the Contractor are
acceptable and enforced.
·
All
landscaping works are carried out in accordance with the specifications, with
particular attention to approved use of herbicides or pesticides.
·
The
species and mix of new plant species to be planted are in accordance with
contract specification.
·
The newly
planted trees, shrubs and grassed areas are maintained throughout the
establishment period, particularly in respect of the following:
Table
12.2 Monitoring Programme for Landscape
and Visual
Stage |
Monitoring
Task |
Monitoring
Report |
Form
of Approval |
Frequency |
Design |
Monitoring of design works against the recommendations
of the landscape and visual impact assessments within the EIA should be
undertaken by the Engineer and Landscape Architect, to ensure that they
fulfil the intentions of the mitigation measures. Any changes to the design,
including design changes on site should also be checked. |
Report by Engineer confirming that the design conforms to requirements
of EP |
Approval by Project Proponent |
At completion of design stage |
Construction |
Monitoring of the contractor’s operations
during the construction period. |
Report on Contractor's compliance by ET |
Countersignature of report by IEC |
Monthly |
Establishment Works |
Monitoring of the planting works during the
12-months Establishment Period after completion of the construction
works. Auditing period for transplanted
Important Trees may lengthen. |
Report on Contractor's compliance by ET |
Countersignature of report by IEC |
Bi-monthly |
|
Monitoring of important trees during the 24-month Establishment Period
after completion of the construction works. |
Report on Contractor's compliance by ET |
Counter signature of report by IEC |
Monthly |
ET
– Environmental Team, IEC – Independent Environmental Consultant, EP –
Environmental Permit
Table 12.3 Event/Action
Plan for Landscape and Visual
Event |
Action |
|||
|
ET |
IEC |
ER |
Contractor |
Design Check |
1. Check final design conforms to the requirements
of EP and prepare report. |
1. Check report. 2. Recommend remedial design if
necessary. |
1. Undertake remedial design if
necessary. |
- |
Nonconformity on one occasion |
1. Inform the IEC, ER and the Contractor 2. Discuss remedial actions with IEC, ER and Contractor 3. Monitor remedial actions until rectification has been completed |
1. Check
inspection report. 2. Check Contractor’s working method 3. Discuss with ET, ER and Contractor on possible
remedial measures. 4. Advise ER on effective of proposed remedial
measures. 5. Check implementation of remedial measures |
1. Confirm receipt of notification of nonconformity
in writing 2. Review and agree on the remedial measures
proposed by the Contractor 3. Ensure remedial measures are properly implemented |
1. Identify source and investigate the nonconformity 2. Amend working methods agreed with ER as appropriate 3. Rectify damage and undertake any necessary replacement |
Repeated Nonconformity |
1. Identify sources 2. Inform the Contractor, IEC and ER 3. Discuss inspection frequency 4. Discuss remedial actions with IEC, ER and Contractor 5. Monitor remedial actions until rectification has been completed 6. If nonconformity stops, cease additional monitoring |
1. Check inspection report 2. Check Contractor’s working method 3. Discuss with ET, ER and Contractor on possible
remedial measures 4. Advise ER on effectiveness of proposed remedial measures |
1. Notify the Contractor 2. In consultation with the ET and IEC, agree with the Contractor on the remedial measures to be implemented 3. Supervise implementation of remedial measures |
1. Identify source and investigate the nonconformity 2. Amend working methods agreed with ER as appropriate 3. Rectify damage and undertake any necessary
replacement. Stop relevant portion of
works as determined by ER until the nonconformity is abated. |
ET
– Environmental Team, IEC – Independent Environmental Consultant, EP –
Environmental Permit
This Page Left Blank Intentionally
Table 13.1 Mitigation Measures for Archaeological Resources
Archaeological Resource |
Site / Areas |
Previous Key Archaeological Findings |
Preservation and Significance |
Potential Impact by the Project (Revised RODP) |
Mitigation Measures |
Site of
Archaeological Interest (SAI)/ Archaeological Potential Area (APA)/
Traditional Villages with Archaeological Potential Site of
Archaeological Interest (SAI)/ Archaeological Potential Area (APA)/
Traditional Villages with Archaeological Potential Site of Archaeological
Interest (SAI)/ Archaeological Potential Area (APA)/ Traditional Villages
with Archaeological Potential |
F1 – Tseung Kong Wai SAI |
Remains
from Neolithic, Ming and Qing |
No apparent
removal of the original deposits. High
significance as archaeological deposit is known from previous surveys. |
The
scheduled land uses of the area include roads (Road D5 of Designated Project
No. 2), “LO” (3-22), “OU(LF)” (3-20) and “GB”
(3-23). There might
be some destruction to the archaeological deposits by the road, “LO” and “OU”
land use development. |
No works
that involve excavation or soil transportation is carried out in “GB”, hence
no mitigation measure is required. For the
rest of the site falls within the road, “LO” and “OU” land use development,
the archaeological impact arising from the proposed development should be
assessed when the detailed design of the development is available. Preservation in
situ is the top priority to safeguard the archaeological remains in the
impacted area by amending the layout plans of the construction works. However, if the works cannot avoid
disturbance to the archaeological deposit, depending on the degree of direct
impact, the following mitigation measures should be considered, such as
archaeological survey, archaeological watching brief, preservation by records and relocation of archaeological
remains. The scope and programme of the archaeological fieldwork would be agreed
with AMO. |
F2 – Tung
Tau Tsuen SAI |
Stone adze
(Neolithic) Stone pavement
and brick wall remains with celadon wares (Song) at Tung Tau Tsuen Celadon
from Song to Ming |
No apparent
removal of the original deposits. High
significance as archaeological deposit is known from previous surveys. |
North half
of the site falls within “DO” (2-32) and south half of the site falls within
“V”. |
As long as
no development is carried out in “V” area, no mitigation measure is
required. For the
northern half of the site falls within the “DO”, the archaeological impact
arising from the proposed development should be assessed when the detailed
design of the development is available. Preservation in situ is the top priority to
safeguard the archaeological remains in the impacted area by amending the
layout plans of the construction works.
However, if the works cannot avoid disturbance to the archaeological
deposit, depending on the degree of direct impact, the following mitigation
measures should be considered, such as archaeological survey, archaeological
watching brief, preservation by records and relocation of archaeological
remains. The scope and programme of the archaeological fieldwork would be agreed
with AMO. |
|
F3 – Hang Hau Tsuen SAI |
Geometric
patterned pottery (Bronze Age) Celadon
(Song) Blue and
White porcelain (Ming) |
Some apparent
modification to the local soil. High
significance as archaeological deposit is known from previous surveys. |
The
scheduled land uses of the area include “LO” (2-5) and “E” (2-16). Refer to the AFS (Appendix
12.2 refers), no archaeological impact is anticipated on Hang Hau Tsuen SAI within the Revised RODP. |
No archaeological
impact is anticipated and no mitigation measure is required. |
|
F4 – Sha
Kong Miu (North) SAI |
Hard
geometric pattern pottery and coarse pottery (Bronze Age) |
No apparent
removal to the original deposits. High
significance as archaeological deposit is known from previous surveys. |
The
scheduled land uses of the area include “G” (2-20). Refer to the AFS (Appendix
12.2 refers), no archaeological impact is anticipated on Sha Kong Miu (North) SAI within the Revised RODP. |
No
archaeological impact is anticipated and no mitigation measure is required. |
|
F5 – Ngau Hom Shek
SAI |
Double-F
pottery (Bronze Age) Celadon
(Song) Remains
from Ming |
The beach
site has been mostly destroyed. High
significance as archaeological deposit is known from previous surveys. |
The
scheduled land uses of the area include “GB” (3-2). Refer to the AFS (Appendix
12.2 refers), no archaeological impact is anticipated on Ngau Hom Shek
SAI within the Revised RODP. |
No impact
is anticipated as no development is proposed according to the Revised RODP. |
|
F6 – Fu Tei Au SAI |
Stone tools
and ceramics, postholes, house floors, ditches and burials of Late Neolithic
and Bronze Age |
High
significance as archaeological deposit is known from previous surveys. |
The SAI is
located within the assessment area but excluded in the Revised RODP. |
No impact is
anticipated as no development is proposed according to the Revised RODP. |
|
F7 – Tsing
Chuen Wai SAI |
Tile
sherds, celadon and white-glazed stoneware of Song dynasty |
High
significance as archaeological deposit is known from previous surveys. |
The SAI is
located outside the assessment area and is excluded in the Revised RODP |
No impact
is anticipated as no development is proposed according to the Revised RODP. |
|
APA 1 – Lau
Fau Shan |
Unknown |
Uncertain
Significance |
The
scheduled land uses of the area include “C” (2-1), “R3” (2-2 and 2-3), “OU”
(2-35) and the local road from a section of the proposed road D1. There might
be some destruction to the archaeological deposits by the “C”, “OU” and “R”
land use development. |
If
construction works are carried out inside the APA, various mitigation
measures would be proposed to verify the archaeological significance when
land access is assumed, including but not limited to: ·
Conduct an archaeological
survey to find out the extent and condition of archaeological deposits (if any),
and amend the layout plans to avoid further disturbance to significant
archaeological materials; ·
preservation by records
if the works cannot avoid the removal of the archaeological deposits after
survey; or ·
relocation of archaeological remains. Scope of the
Archaeological Survey would be agreed with the AMO. |
|
APA 2 – Kiu
Tau Wai |
Unknown |
Uncertain
Significance |
The
scheduled land uses of the area includes “GB” (5-10), “OU” (5-8) and “LO”
(5-11). There might
be some destruction to the archaeological deposits by the “OU” and “LO” land
use development. |
As long as
no works that involves excavation or soil transportation is carried out in
“GB”, no mitigation measure is required. If
construction works are carried out inside the APA, various mitigation measures
would be proposed to verify the archaeological significance when land access
is assumed, including but not limited to: ·
Conduct an archaeological
survey to find out the extent and condition of archaeological deposits (if
any), and amend the layout plans to avoid further disturbance to significant
archaeological materials; ·
preservation by records
if the works cannot avoid the removal of the archaeological deposits after
survey; or ·
relocation of archaeological remains. Scope
of the Archaeological Survey would be agreed with the AMO. |
|
APA 3 –
Hung Uk Tsuen (North) |
Unknown |
Uncertain
Significance |
The
scheduled land uses of the area includes “GB” (5-12) and “A”. |
Direct
impact arising from the proposed development to the small portion of the APA3
should be avoided as far as possible.
If direct impact is unavoidable, AMO’s comment on the proposed
development works should be sought at the detailed design stage. |
|
APA 4 –
Hung Uk Tsuen (South) |
Unknown |
Uncertain
Significance |
The
scheduled land uses of the area includes “GB” (5-15) and “V”. |
As long as
no works that involves excavation or soil transportation is carried out in
“GB”, no mitigation measure is required. Also, as no
development is proposed in the “V” zones, no impact is anticipated and hence no
mitigation measure is required. |
|
Site of
Archaeological Interest (SAI)/ Archaeological Potential Area (APA)/
Traditional Villages with Archaeological Potential |
21
Traditional Villages |
Unknown |
Uncertain
Significance |
No
development is proposed in the “V” zone. |
As no
development is proposed in the “V” zones, no impact is anticipated a hence no
mitigation measure is required. |
Table 13.2 Mitigation Measures for Built Heritage Resources
Areas |
Figure
Number |
Existing
Built Heritage |
Proposed Land Use on Revised RODP |
Mitigation
Measures |
|
Sun Fung Wai |
Figure 12.V1 |
12 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
Chung Uk Tsuen |
Figure 12.V2 |
25 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
Kau Lee Uk Tsuen |
Figure 12.V3 |
2 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
San Sang Tsuen |
Figure 12.V4 |
27 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
San Lee Uk Tsuen |
Figure 12.V5 |
3 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
Tin Sam |
Figure 12.V6.1 Figure 12.V6.2 |
1 Grade 3 Historic Building (C4 – Shrine (Tin Sam Tsuen)); 15 Nil Grade Built Heritage |
”V”, “R” |
No direct impact is anticipated at this stage on the graded historic
building and built heritage in “Village Type Development” area. Potential adverse impacts (e.g. removal) on structure of 4 heritage
resources with no grade located around Hung Leong Road. |
If direct impact to the historic buildings with no grade is not
avoidable, photographic and cartographic records of them must be kept before
demolition. |
Yick Yuen Tsuen |
Figure 12.V7 |
3 Nil Grade Built Heritage |
“E” “Government” “R” |
Potential adverse impacts (e.g. removal) on structure of 3 heritage
resources within the works area. |
If direct impact to the historic buildings with no grade is not avoidable,
photographic and cartographic records of them must be kept before demolition. |
Tin Sam San Tsuen |
Figure 12.V8 |
5 Nil Grade Built Heritage |
“E” “R” “DO” “LO” “Other
Specified Uses” (“OU”) |
Potential adverse impacts (e.g. removal) on structure of 6 heritage
resources within the works area. |
If direct impact to the historic buildings with no grade is not
avoidable, photographic and cartographic records of them must be kept before
demolition. |
Ha Tsuen Shi |
Figure 12.V9 |
1 Declared Monument (A1 – Tang Ancestral Hall (Ha Tsuen)); 2 Grade 2 Historic Building (C1 – Gate Tower (Ha Tsuen Shi) and C2 –
Kwan Tai Temple (Ha Tsuen Shi)); 18 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
Hong Mei Tsuen |
Figure 12.V10 |
4 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive development.
No direct impact is identified at this stage. |
Mitigation measure is not required. |
Lo Uk Tsuen |
Figure 12.V11 |
21 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive development.
No direct impact is identified at this stage. |
Mitigation measure is not required. |
San Uk Tsuen |
Figure 12.V12 |
10 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
San Wai |
Figure 12.V13 |
1 Grade 3 Historic Building (C3 – Shi Wang Study Hall (San Wai)); 79 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
Shek Po Tsuen |
Figure 12.V14 |
1 Grade 3 Historic Building (C5 – Entrance Gate of Shek
Po Wai (Shek Po Wai)); 30 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
Sik Kong Wai |
Figure 12.V15 |
25 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
Sik Kong Tsuen |
Figure 12.V16 |
27 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
Tseung Kong Wai |
Figure 12.V17 |
7 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive development.
No direct impact is identified at this stage. |
Mitigation measure is not required. |
Tung Tau Tsuen |
Figure 12.V18 |
1 Declared Monument (A2 – Yeung Hau Temple
(Ha Tsuen)); 1 Grade 3 Historic Building (C6 – Old Village School (Tung Tau Tsuen)) 12 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
Hung Uk Tsuen |
Figure 12.V19 |
1 Grade 3 Historic Building (C7 – Nos 76-77 Hung Uk
Tsuen (demolished)) 2 Nil Grade Built Heritage |
”V” |
The built heritage have been demolished. No direct impact is
identified at this stage. |
Mitigation measure is not required. |
San Hing Tsuen |
Figure 12.V20 |
2 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
Fung Kong Tsuen |
Figure 12.V21 |
10 Nil Grade Built Heritage |
”V” |
The built heritage are of considerable distance from the intrusive
development. No direct impact is identified at this stage. |
Mitigation measure is not required. |
Historic / clan graves or burial urns |
--- |
--- |
“GB” |
No built heritage is identified. |
Mitigation measure is not required. |
· Regular site inspections should be carried out and led by the ER and attended by the Contractor and ET at least once per week during the construction phase. The areas of inspection should not be limited to the environmental conditions and the pollution control and mitigation measures within the works area, it should also review the environmental conditions of locations that are beyond the boundary of the works area but are likely to be affected directly or indirectly by the construction site activities of the Project. During the inspection, the following information should be referred to:
· The EIA Report and EM&A recommendations on environmental protection and pollution control mitigation measures;
· Ongoing results of the EM&A programme;
· Works progress and programme;
· Individual works methodology proposals (which should include the proposal on associated pollution control measures);
· Contract specifications on environmental protection and pollution prevention control;
· Relevant environmental protection and pollution control legislations; and
· Previous site inspection results undertaken by the ET and others.
This Page Left Blank Intentionally
· Up to half a page of executive summary;
· Brief description of project background information;
· Drawings showing locations of the baseline monitoring stations;
· Monitoring results (in both hard and diskette copies) together with the following information:
o
Monitoring methodology
o
Name of the laboratory
and types of equipment used and calibration details
o
Parameters monitored
o
Monitoring locations
(and depth)
o
Monitoring date, time,
frequency and duration
o
QA/QC results and
detection limits
· Details of influencing factors, including:
o
Major activities, if
any, being carried out in the Project site during the period
o
Weather conditions
during the period
o
Other factors which
might affect the monitoring results
· Determination of the Action and Limit Levels (AL levels) for each monitoring parameter and statistical analysis of the baseline data;
· Revisions for inclusion in the EM&A Manual; and
· Comments and conclusions.
i) Executive summary (1-2 pages):
o
breaches of Action and
Limit levels;
o
compliant log
o
notifications of any
summons and successful prosecutions;
o
reporting changes; and
o
future key issues.
ii) Basic project information:
o
project organisation
including key personnel contact names and telephone numbers;
o
programme;
o
management structure;
and
o
works undertaken during the month.
iii) Environmental status:
o
advice on the status of
statutory environmental compliance such as the status of compliance with the EP
conditions under the EIAO, submission status under the EP and implementation
status of mitigation measures;
o
works undertaken during
the month with illustrations (such as location of works, daily excavation rate,
etc.); and
o
drawings showing the Project area, any environmental sensitive receivers and the
locations of the monitoring and control stations (with co-ordinates of the
monitoring locations).
iv) A brief summary of EM&A requirements including:
o
all monitoring
parameters;
o
environmental quality
performance limits (Action and Limit levels);
o
Event-Action Plans;
o
environmental
mitigation measures, as recommended in the EIA Report; and
o
environmental requirements in contract documents.
v) Implementation status
o
advice on the implementation status of environmental protection and pollution
control / mitigation measures, as recommended in the project EIA Report.
vi) Monitoring results (in both hard and diskette copies) together with the following information:
o
monitoring methodology;
o
name of laboratory and
types of equipment used and calibration details;
o
monitoring parameters;
o
monitoring locations;
o
monitoring date, time,
frequency, and duration;
o
weather conditions
during the period;
o
any other factors which
might affect the monitoring results; and
o
QA / QC results and
detection limits.
vii) Report on non-compliance, complaints, and notifications of summons and successful prosecutions:
o
record of all
non-compliance (exceedances) of the environmental quality performance limits
(Action and Limit levels);
o
record of all
complaints received (written or verbal) for each media, including locations and
nature of complaints investigation, liaison and consultation undertaken, actions
and follow-up procedures taken, results and summary;
o
record of all
notification of summons and successful prosecutions for breaches of current
environmental protection / pollution control legislation, including locations
and nature of the breaches, investigation, follow-up actions taken, results and
summary;
o
review of the reasons
for and the implications of non-compliances, complaints, summons and
prosecutions including review of pollution sources and working procedures; and
o
description of the actions taken in the event of non-compliance and deficiency
reporting and any follow-up procedures related to earlier non-compliance.
viii) Others
o
an account of the
future key issues as reviewed from the works programme and work method
statements;
o
advice on the solid and
liquid waste management status;
o
record of any project
changes from the originally proposed as described in the EIA Report (e.g.
construction methods, mitigation proposals, design changes, etc.); and
o
comments (for example, effectiveness and efficiency of the mitigation measures),
recommendations (for examples, any improvement in the EM&A programme) and
conclusions.
Subsequent Monthly
EM&A Reports
i) Executive summary (1-2 pages):
o
breaches of Action and
Limit levels;
o
compliant log;
o
notifications of any
summons and successful prosecutions;
o
reporting changes; and
o
future key issues.
ii) Basic project information:
o
project organisation
including key personnel contact names and telephone numbers;
o
programme;
o
management structure;
and
o
works undertaken during
the month; and
o
any updates as needed to the scope of works and construction methodologies.
iii) Environmental status:
o
advice on the status of
statutory environmental compliance such as the status of compliance with the EP
conditions under the EIAO, submission status under the EP and implementation
status of mitigation measures;
o
works undertaken during
the month with illustrations (such as location of works, daily excavation rate,
etc.); and
o
drawings showing the project are, any environmental sensitive receivers and the
locations of the monitoring and control stations.
iv) Implementation status
o
advice on the implementation status of environmental protection and pollution
control / mitigation measures, as recommended in the project EIA Report.
v) Monitoring results (in both hard and diskette copies) together with the following information:
o
monitoring methodology;
o
name of laboratory and
types of equipment used and calibration details;
o
monitoring parameters;
o
monitoring locations;
o
monitoring date, time,
frequency, and duration;
o
weather conditions
during the period;
o
any other factors which
might affect the monitoring results; and
o
QA / QC results and
detection limits.
vi) Report on non-compliance, complaints, and notifications of summons and successful prosecutions:
o
record of all
non-compliance (exceedances) of the environmental quality performance limits
(Action and Limit levels);
o
record of all
complaints received (written or verbal) for each media, including locations and
nature of complaints investigation, liaison and consultation undertaken,
actions and follow-up procedures taken, results and summary;
o
record of all
notification of summons and successful prosecutions for breaches of current
environmental protection / pollution control legislation, including locations
and nature of the breaches, investigation, follow-up actions taken, results and
summary;
o
review of the reasons
for and the implications of non-compliances, complaints, summons and
prosecutions including review of pollution sources and working procedures; and
o
description of the actions taken in the event of non-compliance and deficiency
reporting and any follow-up procedures related to earlier non-compliance.
vii) Others
o
an account of the
future key issues as reviewed from the works programme and work method
statements;
o
advice on the solid and
liquid waste management status;
o
record of any project
changes from the originally proposed as described in the EIA (e.g. construction
methods, mitigation proposals, design changes, etc.); and
o
comments (for examples, effectiveness and efficiency of the mitigation
measures), recommendations (for examples, any improvement in the EM&A
programme) and conclusions.
viii) Appendices
o
Action and Limit
levels;
o
graphical plots of
trends of the monitoring parameters at key stations over the past four
reporting periods for representative monitoring stations annotated against the
following:
a) major
activities being carried out on site during the period;
b) weather
conditions during the period; and
c) any other factors that might affect the monitoring results.
o
monitoring schedule for
the present and next reporting period;
o
cumulative statistics on
complaints, notifications of summons and successful prosecutions; and
o
outstanding issues and deficiencies.
i) Executive summary (1-2 pages):
ii) Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;
iii) Basic project information including a synopsis of the project organisation, contacts of key management, and a synopsis of work undertaken during the course of the project or past twelve months;
iv) A brief summary of EM&A requirements including:
o
environmental
mitigation measures for construction stage, as recommended in the project EIA
Report;
o
environmental impact
hypotheses tested;
o
environmental quality
performance limits (Action and Limit levels);
o
all monitoring
parameters;
o
Event and Action Plans;
i) A summary of the implementation status of environmental protection and pollution control / mitigation measures for construction stage, as recommended in the project EIA Report and summarised in the updated implementation schedule;
ii) Graphical plots and the statistical analysis of the trends of monitoring parameters over the course of the project, including:
o
the major activities
being carried out on site during the period;
o
weather conditions
during the period; and
o
any other factors which
might affect the monitoring results;
i) A summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
ii) A review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures as appropriate;
iii) A description of the actions taken in the event of non-compliance;
iv) A summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up actions taken and results;
v) A review of the validity of EIA predictions for construction stage and identification of shortcomings in EIA recommendations;
vi) Comments (for example, a review of the effectiveness and efficiency of the mitigation measures, the performance of the environmental management system, and the overall EM&A programme for construction stage); and
vii) Recommendations and conclusions (for example, a review of success of the overall EM&A programme for construction stage to cost-effectively identify deterioration and to initiate prompt effective mitigatory action when necessary).
Final
EM&A Review Report for Operation Stage
i) Executive summary (1-2 pages):
ii) Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;
iii) Basic project information including a synopsis of the project organisation, contacts of key management, and a synopsis of work undertaken during the course of the project or past twelve months;
iv) A brief summary of EM&A requirements including:
o
environmental
mitigation measures for operation stage, as recommended in the project EIA
Report;
o
environmental impact
hypotheses tested;
o
environmental quality
performance limits (Action and Limit levels);
o
all monitoring
parameters;
o
Event and Action Plans;
i) A summary of the implementation status of environmental protection and pollution control / mitigation measures for operation stage, as recommended in the project EIA Report and summarised in the updated implementation schedule;
ii) Graphical plots and the statistical analysis of the trends of monitoring parameters over the course of the project, including:
o
the major activities
being carried out on site during the period;
o
weather conditions
during the period; and
o
any other factors which
might affect the monitoring results;
i) A summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
ii) A review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures as appropriate;
iii) A description of the actions taken in the event of non-compliance;
iv) A summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up actions taken and results;
v) A review of the validity of EIA predictions for operation stage and identification of shortcomings in EIA recommendations;
vi) Comments (for example, a review of the effectiveness and efficiency of the mitigation measures, the performance of the environmental management system, and the overall EM&A programme for operation stage); and
vii) Recommendations and conclusions (for example, a review of success of the overall EM&A programme for operational stage to cost-effectively identify deterioration and to initiate prompt effective mitigatory action when necessary).