LIST OF Appendices
Key Assessment Assumptions and Limitation of
Assessment Methodologies |
|
Summary of Environmental Impacts |
, Air Quality Impact;
, Noise Impact;
, Water Quality Impact;
, Sewerage and Sewage Treatment Implications;
, Waste Management Implications;
, Land Contamination;
, Landscape and Visual Impacts; and
, Hazard to life.
Table
13.1 Summary of Key Environmental
Outcomes and Benefits
Environmental
/ Social Benefits of the Project |
, Optimise the land resources of an existing
30-ha railway depot site for property development which could create a
sustainable community in phases; , Enhance local environment in Siu Ho Wan
area through the confinement of future depot operation within a concrete
slab/ podium deck such that potential environmental impacts associated with
the industrial activities could be minimised; , Increase the flexibility for future land
use planning of the Siu Ho Wan area by isolating the industrial interface
within a concrete slab/podium deck; , Enhance the transportation network in Siu
Ho Wan area through the provision of SHO; and , Improve the local environment with the
provision of SHO which would in future alleviate the traffic burden on the
surrounding road network and the associated vehicular emissions and traffic
noise in Siu Ho Wan area |
Environmentally Friendly Design and Options |
, Avoidance of encroachment into recognized
sites of conservation importance; , Avoidance of marine transportation as far
as practicable; , Minimisation of environmental impacts to
SHD Topside Development; , Adoption of environmental friendly
construction method; , Avoidance of emergency discharge from sewage
pumping station (SPS); , Adoption of proactive measures to avoid
illegal dumping; , Provision of railway noise mitigation
measures; and , Implementation of environmental monitoring
and auditing system. |
Air
Quality Impact |
Construction Phase: , Major potential air quality impacts during
the construction works of the Project would be construction dust arising from
excavation, materials handling, spoil removal, pilling, backfilling works,
haul road and wind erosion of exposed area. With the implementation of
recommended dust suppression measures including watering once per hour on
active works areas, exposed areas and unpaved haul roads, and mitigation
measures specified in the Air Pollution Control (Construction Dust)
Regulation and EM&A programme, the predicted dust impact on the air
sensitive receivers would comply with the dust criteria as stipulated in
EIAO-TM and air quality objectives (AQO). Operation Phase: , Gaseous
and particulate emissions generated from exhaust emissions of equipment used
for maintenance operations are expected to be insignificant as the equipment
is operated on a routine but infrequent basis. With the operation activities at
Reprovisioned SHD same as those at existing SHD, it is anticipated that there
would be no additional and insignificant air quality impact arising from the
operation of Reprovisioned SHD. , No
air quality impact is expected from the operation of SHO with emission free
electric-powered rail system and thus the exhaust air from railway operations
would be insignificant. In
addition, exhausts for general ventilation and smoke extraction facilities
will be carefully positioned to avoid causing nuisance to the surrounding
environment. Thus, air quality
impact during operation phase of SHO is considered insignificant. , No adverse odour impact from the sewage
pumping stations (SPS) would be anticipated with the implementation of
deodouriser (at least 95% of odour removal efficiency) and maintaining a
slight negative pressure of the ventilation system within the facilities and
locating the exhaust outlet of the deodouriser away from the nearby ASRs, as
far as practicable. |
Noise
Impact |
Construction Phase: , Potential construction noise impact arising
from the operation of powered mechanical equipment (PME) would be
expected. With the implementation
of mitigation measures including use of quiet powered mechanical equipment
and use of movable noise barriers/enclosure for some construction activities,
the predicted construction noise levels at the representative noise sensitive
receivers would comply with the construction noise criteria stipulated in
TM-EIAO. Operation Phase (Fixed
Noise Sources): ,
Maximum
allowable sound power level emitted from planned fixed plant have been
predicted. The fixed plant noise
impacts predicted at the existing and planned NSRs would comply with the
respective noise criteria. Operation Phase (Railway
Noise): ,
The
potential rail noise impacts associated with the operation of existing SHD
and TCL/AEL will be alleviated by the provision of the mitigation measures
including self-protecting building design, cantilevered noise barrier and noise
canopies along the podium edge of SHD Topside Development for protecting the
affected NSRs to acceptable noise levels. Alternative approaches in noise
mitigation package could be further explored by the Project Proponent of SHD
Topside Development in the detailed design stage. Cumulative Operational
Noise Impact: ,
Based
on the findings of cumulative operational noise impact assessment, the
mitigated noise levels at all representative NSRs would comply with the noise
criteria as stipulated in the TM-IND.
It is therefore concluded that, with implementation of the recommended
noise mitigation measures for fixed plant, mainline operation and train
operation within SHD, there would be no adverse cumulative operational noise
impacts to the NSRs. |
Water
Quality Impact |
Construction
Phase:
, Water quality
impacts from land-based construction would be controlled by implementing the
recommended mitigation measures and good site practices. Regular site
inspections would be carried out to minimise water quality impacts.
Operation
Phase:
, Various
precautionary measures are proposed to be incorporated in the design of the
SPS to avoid consequences of pump and/or power failure to the maximum
practicable extent. With the
incorporation of the precautionary measures, no emergency sewage discharge
during the operation of SHO and Reprovisioned SHD is anticipated and the
potential water quality impact in the unlikely event that discharge does
occur would be minimised. , Storm water
control measures including adequate storm drainage system with suitable
pollutant removal devices and best storm water management practices will be
adopted for the Project to minimise the potential water quality impact. |
Sewerage
and Sewage Treatment Implications |
,
Upon
the review on the sewage flow generated from this Project, the SHWSTW should have sufficient capacity to cater for
the projected sewage arising from the Project and SHD Topside Development. No adverse impact due to the
cumulative sewerage generation from the Project and the SHD Topside
Development on the existing sewerage system is anticipated. ,
With
the implementation of mitigation measures including the provision of twin
rising mains, dual feed power supply, spare pumps, emergency storage and
control system etc, no emergency sewage discharge during the operation of SHO and
Reprovisioned SHD is anticipated. ,
Based
upon the assessment, it can be concluded that the proposed Project is
sustainable from sewerage collection, treatment and disposal perspective. |
Waste
Management Implications |
, The main waste types to be generated during
the construction phase of the Project will include construction and
demolition (C&D) materials, chemical waste, general refuse and excavated
sediment. Reduction measures have been recommended to minimise the amount of
materials generated by the Project by reusing C&D materials and excavated
sediment as far as practicable before offsite disposal. Provided that the
waste is handled, transported and disposed of using approved methods, adverse
environmental impacts would not be expected. , The main waste types to be generated during
the operation phase of the Project will include chemical waste and municipal solid
waste. Provided that the waste is handled, transported and disposed of using
approved methods, adverse environmental impacts would not be expected. |
Land
Contamination |
,
Based on the findings from desktop review and
site reconnaissance, 9 facilities / areas within the existing SHD have been
identified as potentially contaminated. ,
As the
concerned areas are still in operation and undertaking the SI works at this
stage is not feasible due to significant impact to the existing SHD
operations and the need for maintaining the depot function to support
existing operating railway lines, the SI works and any necessary remediation
action are recommended to be carried out after decommissioning of the
facilities but prior to construction works at the concerned areas. The recommended further works, including
the submission of Supplementary
CAP(s), CAR(s) / RAP(s) and RR(s), would need to follow EPD¨s Guidance
Manual, Guidance Note and Practice Guide. ,
The
chemicals of concern (COCs) identified with the potential to be present at
the potentially contaminated areas include metals, VOCs, SVOCs, PCRs and PCBs. Remediation methods that have
demonstrated to effectively treat the aforementioned soil and groundwater
contaminants include biological treatment and physical / chemical treatment; as demonstrated by the successful
remediation of soil contaminated with the abovementioned COCs in other Hong
Kong projects. By implementing
the recommended further works, the actual contaminated site(s) within the
assessment area would be located and any contaminated soil and groundwater
would be identified and treated. ,
Given
the above, land contamination impacts are therefore considered not
insurmountable. |
Landscape
and Visual |
,
On
review of the likely LR and LCA residual impacts arising from construction
and operation of the Project, the majority of LRs would be subject to
Insubstantial impact, while only
one LR would continue to be subject to Moderate impact by operational Year
10. Besides, All LCAs would be reduced to Insubstantial impact by operational
Year 10. Review of the likely
visual residual impacts also indicates all VSRs would be subject to Insubstantial
to Slight impact by operational Year 10.
The residual
landscape and visual impact is considered acceptable with mitigation measures
implemented during construction and operation phases. |
Hazard
to Life |
,
With
careful planning and design of the Project, the proposed scheme has
completely avoided locating additional population within the CZ of SHWWTW to
minimise potential risk. ,
The
criterion of Annex 4 of the TM-EIAO for Individual Risk met with regards to
the hazards to life posed by SHWWTW.
The societal risk for the cumulative impact from SHWWTW in the
construction and operational phases also falls within the ALARP region of
stipulated criteria under TM-EIAO.
A cost-benefit analysis has been undertaken considering a range of
mitigation measures but no mitigation measures are cost effective. Nevertheless, precautionary
measures for chlorine released from SHWWTW such as provision of emergency
plan for efficient evacuation including good practice (i.e. adequate training
and drills for construction workers) during construction phase shall be
implemented to further reduce the risk level. |