TABLE OF CONTENTS

 

 

2       PROJECT DESCRIPTION.. 2-1

2.1       Site Location and History. 2-1

2.2       Purpose and Objective of the Project 2-1

2.3       Consideration of Alternatives/Options. 2-2

2.4       Details of the Project 2-8

2.5       Concurrent Projects. 2-11

 

 

 

LIST OF FIGURES

NEX1062/S/SHD/ACM/Z10/101

Scope of Project

NEX1062/S/SHD/ACM/Z10/102

Layout of Reprovisioned Siu Ho Wan Depot

NEX1062/S/SHD/ACM/Z10/103

Major Concurrent Projects in the Vicinity of the Project

NEX1062/S/SHD/ACM/Z10/105

Tentative Works Area

                             

 

 

LIST OF Appendices

Appendix 2.1

Railway Area Plan

Appendix 2.2A

Depot Replanning Options

Appendix 2.2B

Station Options

Appendix 2.3

Depot Replanning Scheme

Appendix 2.4

Tentative Works Programme and Location of Works Front

Appendix 2.5

Construction Interface between the Project and the SHD Topside Development

Appendix 2.6

Tentative Population Intake Year of Planned Comprehensive Residential and Commercial Development Atop SHD

 

                                                                                          

 


2                  PROJECT DESCRIPTION

2.1              Site Location and History

2.1.1          The existing SHD, with an area of about 30 hectares, is sited on reclaimed land in Northshore Lantau and is located approximately 5km east of Tung Chung New Town.  It is bounded by an existing seawall maintenance access road to its north, and the TCL/AEL, North Lantau Highway (NLH) and Tuen Mun ¨C Chek Lap Kok Link slip road (under construction) to its south (Figure No. NEX1062/S/SHD/ACM/Z10/101 refers).

2.1.2          The existing SHD is delineated as ¡°railway area¡± under the Railway Area Plan (RAP) (refer to Appendix 2.1) which also covers AEL and TCL.  The RAP was deposited in the Land Registry on 25 March 1994 under section 3 of the Mass Transit Railway (Land Resumption and Related Provisions) Ordinance (Cap 276).  The SHD has operated since 1998 for supporting the operation of the existing TCL, AEL and DRL.  The existing SHD comprises stabling sidings and main depot building located in the centre of the site, permanent way facilities at the north eastern side, test track at the southern area, and other supporting facilities including maintenance workshops, utilities and drainage, ancillary buildings and facilities, traction substation and sewage pumping station, etc.

2.2              Purpose and Objective of the Project

2.2.1          Under the comprehensive strategic study, ¡°Hong Kong 2030+: Towards a Planning Vision and Strategy Transcending 2030¡± (Hong Kong 2030+), the territorial development strategy and a spatial planning framework is being established to guide the future planning, land and infrastructure development and the shaping of the built environment of Hong Kong.  Under key strategic direction of ¡°Underscoring Compact Development¡± and ¡°Optimising Land Uses¡± as indicated in the public engagement document (October 2016) of Hong Kong 2030+, it is proposed to underscore transit-oriented, compact development with railway as the backbone of the public transport system and to explore more topside development respectively.

2.2.2          The Project, which includes railway replanning works at the existing SHD to allow for topside development and provides a new railway station at Siu Ho Wan, supports this strategic planning objective of building a sustainable community served by environmentally friendly rail transport.     

Benefit of the Project

2.2.3          The existing SHD is located at a developed area for railway operation with no natural habitats of flora and fauna nor sensitive receivers nearby, and thus any potential impacts from the Project on-site to the existing environment would be significantly reduced.  

2.2.4          The Project will optimize utilization of an existing 30-ha railway depot site for creation of land resources suitable for property development to create a sustainable community in phases, without causing disruption to the normal operation of the depot, TCL, AEL and DRL.  The Topside Development has been planned and designed to take account of the constraints and opportunities of the SHD Replanning Works, allowing self-contained development packages in the implementation stage to provide as much housing as practicable to address issues on housing supply in phases, complying with environmental legislations and regulations.

2.2.5          The future depot operation will also be confined within a concrete slab/podium deck, leading to an improvement to the surrounding local environment in the Siu Ho Wan area through enclosing the industrial activities of the depot.  In addition, isolating this industrial interface would allow flexibility for future land use planning of the Siu Ho Wan area. 

2.2.6          The existing TCL is an electrically-powered rail which is a more sustainable form of transport than road transport. The provision of SHO along the existing TCL serving the local community in Siu Ho Wan is in line with the transport policy of having more environmentally friendly railway as the backbone of transport network. 

Scenario ¡°With¡± the Project

2.2.7          Upon completion of each stage of the SHD Replanning Works and respective phase of the SHD Topside Development, the existing land use of the Project site which is solely for industrial operation will be changed to diverse development with a mix of industrial activities, major trade or commercial activities and residential premises. 

2.2.8          The project site would be served by road network with its western access connected to the Tai Ho Interchange linking with the NLH and the planned Road P1 (Tung Chung to Tai Ho Section).  The provision of SHO on TCL would in future alleviate the traffic burden on the surrounding road network and the associated vehicular emissions and traffic noise in Siu Ho Wan area. 

Scenario ¡°Without¡± the Project

2.2.9          Without the Project, the existing SHD remains an open air design with maintenance workshops and facilities, e.g. paint shop and traction substation etc., housed within isolated buildings. Most of the stabling tracks and train washing facilities are located outdoor without cover.  The operation of the depot is considered as an industrial activity with potential indirect impacts to the local environment, even though there are currently no sensitive receivers in the vicinity of existing SHD.  

2.2.10       Without the SHD Replanning Works, the provision of housing supply through the utilization of the railway depot site could not be achieved.   The Siu Ho Wan area would remain as a low-rise industrial area with an open air depot on site, constraining the flexibility of future development planning of land uses in the Siu Ho Wan area that are sensitive to industrial land use.

2.3              Consideration of Alternatives/Options

SHD Replanning Works

Development Siting

2.3.1          As discussed in Section 2.2.3, the existing location of SHD is currently being occupied for depot operation without any natural habitats of flora and fauna on site. The nearest village is at Pak Mong located some 1.2km away.  During the planning and conceptual design stage, recognised sites of conservation importance in the vicinity of the SHD have been identified and avoided, for any permanent works for the western access and local access road or temporary works such as vehicle parking, equipment storage and accesses.  As such, there would be no impact to recognised sites of conservation importance in the vicinity of the works area (Figure No. NEX1062/S/SHD/ACM/Z10/103 refers).

2.3.2          The SHO, and SHD Replanning Works and the SHD Topside Development is considered to be a sustainable development.  The SHD site is therefore justifiable from land use suitability and technical sustainability perspectives to optimize utilization of railway land for comprehensive development purpose.

2.3.3          There are certainly environmental benefits of having the construction works on a developed area which is currently used as a railway depot, avoiding potential impacts on ecological and landscape resources. Given the locality of the site, there are no existing air and noise sensitive receivers in the immediate proximity of the SHD. The site is also bounded by the Lautau Airport Railway (LAR), North Lantau Highway (NLH) and Tuen Mun ¨C Chek Lap Kok Link slip road (under construction) to its south/southeast, separated with a significant buffer area to any ecological sensitive area such as the Tai Ho Priority Site.  As such, potential environmental impacts on existing sensitive receivers are minimal and no environmental dis-benefit is anticipated with respect to the development siting.

Depot Replanning Sequences

2.3.4          During the development of a feasible depot replanning sequences, engineering and environmental factors as listed in Table 2.1 have been considered.  Among all considerations, maintaining a safe depot operation condition without any disturbance to the operating railway is an overriding consideration. 

Table 2.1     Considerations and Constraints for Depot Replanning Sequences

Considerations

Description

Engineering Factors

Construction /Operational Safety, Flexibility and Maintenance Requirements

¡¤     Safety, flexibility and maintenance requirements in the design and track works of each stage of reprovisioned facilities; 

¡¤     Operational safety to existing depot facilities;

¡¤     Avoidance/minimisation on construction risks on existing facilities and interface projects;

¡¤     Minimization of all interface risks associated with existing SHD and mainline operations; and

¡¤     Provision of firefighting and emergency evacuation throughout all stages.

Constructability

¡¤     Practicality in constructing the depot structures/facilities in the vicinity of operating tracks; and

¡¤     Maximisation of concrete slab area for phased construction of SHD Topside Development.

Depot Operation Requirements

¡¤     Achievement of projected fleet size (i.e. trains to be stabled) in each stage; and

¡¤     Availability of reprovisioned facilities before existing one to be decommissioned by replanning works.

Construction Programme

Minimisation of construction period. Shorter construction period is preferable in order to minimise the disturbance to the depot operation and community.

Environmental Factors

Noise

Minimisation of noise impact from existing SHD operation to SHD Topside Development.

Construction Dust

Minimisation of construction dust impact during SHD Replanning Works. 

Other Factors

Community Disruption

Safe and normal operation of existing SHD to be maintained throughout the SHD Replanning Works.

 

2.3.5          During the development of depot replanning options, it was identified that certain facilities including the traction substation, wash control facility and train wash facility at the western and eastern of SHD must be retained to avoid any disturbance to the operating railway.   The existing SHD facilities shall also be maintained on site at all-time to maintain depot operation for continuous and safe operation of existing TCL, AEL and DRL.  Relocating some of the depot facilities off-site temporarily to create more space for SHD redevelopment at early stages is therefore not feasible.  The existing spare space located at the southern part of the depot site (planned to be used for future stabling area expansion when the train fleet size increases to meet additional passenger demand) allows the first stage of replanning works without causing disruption to the existing depot operation and operating railway.  It would also be necessary to sequence the works such that prolonged decommissioning and reprovisioning of depot facilities could be avoided in each stage in order to achieve the short term goal for housing supply and more importantly, the planning vision in Hong Kong 2030+.  Having regard to these constraints and considerations, options available for the depot replanning works would be limited. 

2.3.6          A 6-stage replanning option as shown in Appendix 2.2A was considered in the feasibility study.  For this option, the arrangement of reprovisioned facilities would be restricted by each staging area which is relatively small for practical construction planning as well as achieving operation requirements due to inadequate number of stabling berths and supporting facilities in certain stages.  An enhanced replanning option, i.e. 4-stage replanning option (Appendix 2.2A refers), was then developed to resolve and deal with the issues as identified in the 6-stage option.  With the possibility of minimising the number of topside tower blocks that may be exposed to the potential industrial/residential interface between stages of replanning works, preference is given to the 4-stage replanning option as this option can be well respond to the constraints presented in construction planning and address the overriding needs of the depot operation. 

Siu Ho Wan Station (SHO)

Station Options

2.3.7          Options and alternatives of project design, as well as construction methods were reviewed and considered during selection of the preferred option of SHO along TCL, taking account of engineering feasibility, operational safety, site constraints, programme and environmental aspects as presented in Table 2.2.

Table 2.2     Considerations for Selection of Station Location and Construction Method

Considerations

Description

Engineering Factors

Interface with Existing/Committed  Infrastructures

Interface with existing/committed infrastructure include:

¡¤     Proximity to the existing North Lantau Highway

¡¤     Close proximity to slip road LE01 from the committed Tuen Mun-Chek Lap Kok Link; and

¡¤     Existing AEL and TCL.

Construction /Operational Safety, Flexibility and Maintenance Requirements

¡¤     Safety, flexibility and maintenance requirements in the design and track works at existing TCL; 

¡¤     Operational safety to existing train services, limitation of working hours for works above or in close vicinity to existing rail tracks; and

¡¤     Avoidance/minimisation on construction risks on existing facilities and interface projects.

Constructability

¡¤     Practical construction at or close to existing facilities and interface projects; and

¡¤     Practical station option for railway track with up to 140kph design speed.

Land Acquisition

This issue is considered in order to minimise area of land that may need to be acquired so as to minimise disruption to the local community.

Construction Programme

Minimisation of construction period. Shorter construction period is preferable in order to minimise the disturbance to the community.

Environmental Factors

Ecology

Direct impact on significant ecological resources should be avoided.   

Air Quality, Noise and water quality

Potential air quality, noise and water quality impacts should be minimised.

Other Environmental Considerations

Other environmental factors considered include:

¡¤     avoidance or minimisation of landscape and visual impacts associated with the above-ground structure(s);

¡¤     preservation of mature trees;

¡¤     minimisation of C&D / Waste generation (e.g. contaminated soil/sediment); and

¡¤     minimisation of cumulative impacts from interface projects.

Other Factors

Community Disruption

Safe and normal operation of existing TCL and AEL shall be maintained during the construction of SHO.

 

Avoidance/
Minimisation of Issues/Constraints

Minimisation of project areas encroaching into developed area, and interface issues with other projects currently being planned or constructed.

 

2.3.8          During the preliminary design stage, two station options, namely Central Station and Western Station, were developed and studied for selection of the preferred station option.  Locations of the two station options are provided in Appendix 2.2B.  

2.3.9          The two station location options have been compared and detailed discussion on the selection of station option is presented in Appendix 2.2B, with summary of findings presented in Table 2.3.

Table 2.3     Comparison of Station Options

Considerations

Central Station Option

Western Station Option

Engineering Factors

¡¤      Interface with existing / committed infrastructure include:

-   North Lantau Highway

-   Tuen Mun-Chek Lap Kok Link; and

-   Existing AEL and TCL.

¡¤      Realignment of North Lantau Highway and Tuen Mun-Chek Lap Kok Link would be required

¡¤      Natural terrain improvement works will affect the operation of North Lantau Highway

¡¤      Additional road gazette required as a results of realignment of  North Lantau Highway and Tuen Mun-Chek Lap Kok Link

¡¤      Extensive rock excavation is required for station construction

¡¤      Same construction period but advance preparation works including realignment of North Lantau Highway and Tuen Mun-Chek Lap Kok Link would be required

¡¤      Interface with existing / committed infrastructure include:

-   Existing AEL and TCL.

¡¤      Realignment of North Lantau Highway and Tuen Mun-Chek Lap Kok Link would not be required

¡¤      Works within Tuen Mun-Chek Lap Kok Link gazette boundary

¡¤      Fewer interface issues with existing / committed infrastructures

 

 

Environmental Factors

¡¤     Direct impact on surrounding ecological habitats, Tai Ho Priority Site and landscape resources (e.g. channelized watercourse, plantation, hillside shrubland and grassland) due to natural terrain improvement works to the south of SHD

¡¤     Relative higher construction dust, noise and water quality impacts anticipated due to road realignment works and rock excavation

¡¤     Larger area of landscape resources and characters affected

¡¤     Higher C&D / Waste generation due to more construction works required

¡¤     No direct impact on recognized sites of conservation importance in the Project Area and its vicinity

¡¤     Relative lower construction dust, noise and water quality impacts anticipated

¡¤     Relative fewer environmental issues anticipated

Other Factors

¡¤     Normal operation of North Lantau Highway and Tuen Mun-Chek Lap Kok Link will be affected

¡¤      North Lantau Highway and Tuen Mun-Chek Lap Kok Link will not be affected

 

Preferred Station Option

2.3.10       Based on the comparison results as presented in Table 2.3 above, it is considered that the Western Station would have minimal impacts on the environment and public.  The Western Station is therefore selected as the preferred station option.

Associated Track Alignment

2.3.11       The location of SHO dictates the extent and location of associated track works required for realigning the existing AEL/TCL, as well as the associated track alignment.  As such, based on the preferred station option ¨C Western Station, the track alignment has been proposed to suit the location of SHO and to allow for safe operation of the operating railway during construction. 

Construction Method, Sequences and Programme

Construction Method

2.3.12       Similar to the development of the depot replanning schemes, maintaining a safe depot operation condition without any disturbance to the operating railway is an overriding consideration factor in the determination and selection of construction sequences and methods.  Relevant railway safety regulations must be followed throughout the construction period.

2.3.13       The piling works for the foundation of the podium deck are considered to be relatively extensive amongst the major construction works of the Project.  Percussive piling and bored piling are the commonly adopted piling methods for construction of residential buildings in Hong Kong.  For minimization of potential impacts to the environment, the quieter construction method, i.e. bored piling method, will be adopted for the foundation of the SHD Topside Development.

2.3.14       Marine transportation for construction materials and spoil during the construction phase of the Project would be avoided as far as possible to minimize marine traffic and associated potential impacts on marine environment.    

Construction Sequences and Programme

2.3.15       Construction of the concrete slab would be completed as soon as possible in respective staging area, such that the remaining replanning works including architectural builder's work and finishes (ABWF), electrical and mechanical (E&M) provision and track works would be conducted under the concrete slab to minimize construction noise impacts from the replanning works.  It is expected that there would be insignificant noise contribution from these remaining works as these works would be conducted under the concrete slab.

2.3.16       Under the SHD Replanning Works, the tracks and facilities within the existing SHD would be suitably rearranged to facilitate the property enabling works for supporting the construction of the SHD Topside Development.  In order to maintain the existing depot¡¯s daily operation and minimize disturbance to the existing depot, the SHD Replanning Works should be executed in stages with limited construction access and works area. Each stage of replanning works includes depot structure and foundation construction, temporary/ permanent relocation and re-provision of depot facilities and tracks that subsequently require considerable time for testing and commissioning (T&C), etc.  In addition to replanning a site with a total area of about 30 hectares, the 4-stage replanning works would be completed in about 18 years. 

2.3.17       As discussed in Section 2.2, the SHD Topside Development has been planned and designed to take advantage of the staging of the SHD Replanning Works, providing as much housing as practicable to relieve housing supply issues in phases, minimizing environmental interface issues between the normal SHD operation and Topside Development with environmental compliance (details refer to construction interface and population intake phasing information in Appendices 2.5 and 2.6 respectively).

2.3.18       It is not practical and feasible to construct the SHD concrete slab in one go because it is necessary to vacate the depot area stage by stage in order to facilitate the SHD Replanning Works, while at the same time maintaining the daily depot operation to support daily services of the existing railway lines.  In connection with this, all the depot facilities would need to be re-provided in the newly vacated area before decommissioning of existing depot facilities.  The option of completing the whole concrete slab within the SHD boundary (i.e. Year 2034) before population intake at the SHD Topside Development is therefore considered to contradict with the prime objective of the SHD Topside Development to provide as much housing as practicable for addressing the need of housing supply.     

2.3.19       The main environmental dis-benefit of expediting housing supply atop SHD in phases would be potential impacts on earlier phases of the SHD Topside Development due to construction noise from remaining stages of the SHD Replanning Works and operational noise impacts from the existing SHD.  This is a key issue in the EIA studies and comprehensive mitigation measure packages have been adopted to control the noise impacts to meet established noise standards.

2.3.20       For construction noise, as addressed in Section 4 in details, mitigation measures such as temporary noise barriers, enclosure and quality powered mechanical equipment (QPME) with lower sound power levels will be adopted.  Details of the construction noise mitigation and mitigated noise levels are provided in Section 4.5.

2.3.21       For the noise impact from the existing SHD operation, provision of mitigation measures at the existing SHD has been explored.  Temporary mitigation measures including noise barriers of about 12m high and canopies at the podium edge have been proposed to mitigate the noise impact from the existing SHD operation at Stage 3 and 4 areas during the interim interfacing period of about 30 months.  Details of the noise impact assessment and proposed mitigation measures are provided in Section 4.6.  The existing built and operating areas at SHD are highly constrained by tracks, main depot building and maintenance facilities with minimal spacing.  In addition, there are limited spaces at the existing operating areas next to stabling tracks. Therefore it is impractical to have temporary noise mitigation structures constructed along the stabling tracks for mitigation of potential noise impacts from the operating SHD to the earlier phases of the SHD Topside Development.   

Public Concern

2.3.22       During the course of the EIA study, the public has indicated the Project should avoid direct impact on ecological resources, such as the Tai Ho Priority Site and the Brothers Marine Park, in relation to encroachment of works area or illegal dumping at these sensitive areas.  This concern has been taken into account during the selection of works area(s) such that neither temporary works area nor elements of the Project will encroach into any recognised sites of conservation importance.  The Project Proponent will also take the initiative to adopt global positioning system (GPS) or equivalent system for tracking and monitoring of dump trucks engaged for the Project in order to prohibit illegal dumping and landfilling of excavated materials generated from the Project (details refer to Section 7.5.6).   

2.4              Details of the Project

SHD Replanning Works

Depot Replanning Sequences

2.4.1          The proposed depot replanning sequences will be carried out in stages to allow continuous and safe operation of existing TCL, AEL, DRL as well as the existing SHD.  Details of the tentative depot replanning scheme is presented in Appendix 2.3 with a summary of sequences described below.    

2.4.2          The decking area over the tracks in operation has been maximized to reduce the potential railway noise impacts to earlier phases of the SHD Topside Development.  Reprovisioning of stabling tracks is therefore proposed to be conducted in the first stage of the Replanning Works.  The existing spare space is relatively long and is enough to accommodate 3 berths of train in a linear track at this area, allowing increase of stabling tracks as well as catering for the fleet expansion to meet the increasing passenger upon completion of Stage 1 Replanning Works.  However, the width of the existing spare space is not enough to accommodate the reprovisioned main depot building which is located at the centre of existing SHD site.  Upon operation of Stage 1 Reprovisioned SHD, more trains movement could be contained under the concrete slab, and the potential railway and fixed plant noise impact to the topside development could be minimized. 

2.4.3          Adopting the same approach, Stage 2 Replanning Works is proposed to be conducted at the north-western area of SHD site which currently contains stabling area and plantrooms which will all be reprovisioned at Stage 1 Reprovisioned SHD.  As the site of Stage 2 Replanning Works is of the same width and in similar size of the adjoining area which contains the main depot building and sidings, it is suitable for reprovisioning of similar facilities. 

2.4.4          Upon operation of Stage 2 Reprovisioned SHD, Stage 3 Replanning Works will commence to allow all the remaining facilities to be reprovided before start of Stage 4 SHD Replanning Works.  After operation of Stage 3 Reprovisioned SHD, the remaining facilities at Stage 4 SHD Replanning Works will be decommissioned and demolished. Depot facilities will be provided to cater for future needs in Stage 4 Reprovisioned SHD.  The ultimate Reprovisioned SHD will be underneath the landscaped deck below the SHD Topside Development. 

2.4.5          The proposed layout of the Reprovisioned SHD under concrete slab is presented in Figure No. NEX1062/S/SHD/ACM/Z10/102.  The function and area of the Reprovisioned SHD will be the same as the existing SHD.

Provision of Sewerage System

2.4.6          Due to the SHD Replanning Works, the existing sewerage system serving the SHD is required to be upgraded and reprovided for the future Reprovisioned SHD and SHO.  Sewage generated from the existing SHD is currently conveyed by an existing sewerage system to the nearby Siu Ho Wan Sewage Treatment Works (SHWSTW) for treatment and disposal.  Based on the findings of the Sewerage Impact Assessment (Section 6 refers), upgrading and reprovision of the sewerage network including installation of new sewage pumping station and provision of additional rising mains (change from rising main to twin rising mains) would be required to cater for the sewage generated by the Project.  Twin rising mains would be adopted for the reprovisioned sewerage network without encroachment on any sites of conservation importance in order to minimize impacts on the environment.   The location of the rising mains is shown in Figure Nos. NEX1062/S/SHD/ACM/Z10/180 and NEX1062/S/SHD/ACM/Z10/181. 

2.4.7          The installation of new rising mains outside the existing SHD boundary would only involve small scale and localized construction works such as open trench excavation method.  The proposed additional rising mains will be at the same location of the existing rising main located in developed area.  Provision of the additional rising mains will be conducted during Stage 1 SHD Replanning Works.   

Western access and Local Accesses

2.4.8          A western access road bridge connecting to the proposed Tai Ho Interchange bridge link would be required to serve SHO, Reprovisioned SHD and SHD Topside Development as local access and emergency vehicular access.  The western end of this proposed bridge would likely be supported on the proposed Tai Ho Interchange bridge link, the design of which is yet to be commenced during the preparation of this EIA Report. 

2.4.9          Apart from the western access road bridge, local accesses including vehicular access ramp and staircase as mean of escape (MoE) would be required to enhance the connectivity to SHO and SHD Topside Development.  

Construction Works Areas

Major Works Areas

2.4.10       Major works areas during the construction phase of the Project include the areas of SHD Replanning Works, SHO and associated trackworks, as well as provision of sewerage system, western access and local accesses outside the existing SHD boundary.  Locations of major works areas are indicated in Figure No. NEX1062/S/SHD/ACM/Z10/105.   

Temporary Works Area

2.4.11       Temporary works area within the Scheme Boundary may be required for the provision of site office, temporary storage of construction materials, utility or temporary access to support the construction of the Project.  There may be minor activities / works to be conducted within temporary works area for supporting the construction of the Project based on the latest information at the time of writing.  Subject to actual site conditions and constraints, temporary works as mentioned above would also be required to be conducted in and around the Scheme Boundary.  The locations of works area would be selected with considerations of their accessibility and suitability for supporting construction works, as well as avoiding significant environmental impacts associated with the provision of temporary works area(s).  Therefore only short-term minor environmental impacts are anticipated, and implementation of appropriate standard control measures and good site practices would minimize any environmental disturbance.  Locations of temporary works area are indicated in Figure No. NEX1062/S/SHD/ACM/Z10/105.

Construction Works and Method

2.4.12       Details of a tentative works programme and location of works front of the Project are presented in Appendix 2.4.  Major construction works of the Project would include the following activities:

¡¤               Demolition of existing depot facilities;

¡¤               Pipe jacking works for installation of underground utilities and associated excavation and lateral support (ELS) works;

¡¤               Piling works, pile cap construction and ELS works related to the construction of planned SHD Topside Development;

¡¤               Pad footing foundation works;

¡¤               Construction of SHO and track works at existing AEL/TCL tracks; as well as local access roads and emergency vehicular access (EVA);

¡¤               Construction of concrete slab; and

¡¤               Reprovision of SHD facilities including sewerage system within SHD boundary by stages (under the concrete slab). 

2.4.13       The construction works in each stage of replanning works will generally follow the sequence as listed below:

¡¤               Mobilization and installation of fencing and hoarding;

¡¤               Site clearance, building demolition of existing railway facilities and ground investigation works ;

¡¤               Utility and underground railway facilities system diversion;

¡¤               Installation of mini-piles, pre-bored socket H piles and bored piles;

¡¤               Excavation and lateral support (ELS) works;

¡¤               Excavation to foundation level;

¡¤               Pile cap and tie beam construction;

¡¤               Construction of Means of access (MOA);

¡¤               Column casting and roof slab construction;

¡¤               Architectural builder's work and finishes (ABWF);

¡¤               Building services;

¡¤               Trackworks; and

¡¤               Systems installation and Testing and commissioning.

2.4.14       For the construction works to be conducted in proximity to the operating depot tracks or the operating AEL and TCL tracks, the boundaries of these works areas should be erected with protective barriers and hoarding such that labour, plant and materials would not have uncontrolled access to any part of the operating tracks. 

2.4.15       The construction works will be generally conducted during daytime and evening time (i.e. 0700 ¨C 1900 hours), but the track works at existing AEL/TCL tracks and the works that would be conducted in proximity to the live tracks should be conducted during night-time period (i.e. between 1900 and 0700 hours) in order to avoid disruption or interruption to the normal operation of existing AEL and TCL.

2.4.16       As an indicative reference for this Environmental Impact Assessment, the tentative construction programme of the Project and SHD Topside Development, as well as the population intake of SHD Topside Development, is summarised in Table 2.4.  The construction interface between the Project and SHD Topside Development is provided in Appendix 2.5. 

Table 2.4     Tentative Construction Programme

 

SHD Replanning Works

SHO and Associated Trackworks

Planned SHD Topside Development (1)

Stage

Works Programme(1)

Completion of works & Operation

Works programme

Phase

Commencement  of Superstructure Works

Population Intake(4)

Start

Slab Completion(2)

1

2019

2023

2024

2019 ¨C 2026(3)

1

2023

2026-2027

2

2024

2026

2028

-

2

2027

2030

3

2028

2030

2032

-

3

2031

2034

4

2032

2034

2036

-

4

2032 for Phase 4a(5)

2035 for Phase 4b & 4c

2035 - 2038

Notes:

(1)    The foundation of SHD Topside Development including piling and excavation works will be conducted in parallel with replanning works in respective phasing.

(2)    Upon completion of concrete slab in respective phasing area, the contractor(s) of SHD Topside Development would be on board to commence the superstructure works.

(3)    Civil construction works for SHO will be completed in 2023 while building services (BS) and electrical and mechanical (E&M) works will be conducted in 2024-2026. Operation of SHO would commence in 2026.

(4)    Population intake year of different phases of SHD Topside Development is shown in Appendix 2.6. 

(5)    Phase 4a SHD Topside Development is located above Stage 3 SHD Replanning Works. 

 

2.5              Concurrent Projects

2.5.1          Major committed and planned projects that are located in the vicinity of the Project and may interface with the construction and operation of the Project include: 

¡¤         Comprehensive Residential and Commercial Development atop SHD (planned)

¡¤         Tung Chung New Town Extension (TCNTE) (planned)

¡¤         Construction of additional sewage rising main and rehabilitation of the existing sewage rising main between Tung Chung and Siu Ho Wan (planned)

¡¤         Tuen Mun ¨C Chek Lap Kok Link (committed project under construction)

¡¤         Organic Waste Treatment Facilities (OWTF) Phase I (committed project under construction)

¡¤         Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (committed project under construction)

¡¤         Topside Development at Hong Kong Boundary Crossing Facilities (HKBCF) Island of the Hong Kong-Zhuhai-Macao Bridge (HZMB) (planned)

¡¤         Hong Kong-Zhuhai-Macao Bridge (HZMB) Hong Kong Link Road (HKLR)

¡¤         North Commercial District (NCD) at the Hong Kong International Airport (HKIA)

¡¤         Hong Kong International Airport (HKIA) Three-Runway System (3RS)

2.5.2          The locations of the identified concurrent projects are shown in Figure No. NEX1062/S/SHD/ACM/Z10/103.  The potential cumulative environmental impacts of the identified concurrent projects during the construction and operation of the Project are summarised in Table 2.5.

Table 2.5     List of Concurrent Projects and Potential Cumulative Impacts

Concurrent Project(1)(2)

Programme

Potential Cumulative Impact

Start

Complete

Construction Phase

Operation Phase

The Project

SHD Replanning Works

2019

2036

¡¤    dust;

¡¤    noise;

¡¤    water quality;

¡¤    waste management;

¡¤    landscape and visual; and

¡¤    hazard to life 

¡¤    railway noise;

¡¤    fixed plant noise;

¡¤    sewage impact;

¡¤    landscape and visual; and

¡¤    hazard to life

SHO and associated track works at AEL/TCL

2019

2026(3)

¡¤    dust;

¡¤    noise;

¡¤    water quality;

¡¤    waste management;

¡¤    landscape and visual

¡¤    railway noise;

¡¤    fixed plant noise;

¡¤    sewage impact; and

¡¤    landscape and visual

Concurrent Project

Proposed Comprehensive Residential and Commercial Development atop SHD

2023

2038

¡¤    dust;

¡¤    noise;

¡¤    water quality;

¡¤    landscape and visual; and

¡¤    hazard to life 

¡¤    railway noise;

¡¤    fixed plant noise; and

¡¤    sewage impact; and

¡¤    landscape and visual

Tung Chung New Town Extension (TCNTE) (4)(9)

2017

2030

¡¤    noise; and

¡¤    water quality
 

 

¡¤    Landscape and visual

 

Construction of additional sewage rising main and rehabilitation of the existing sewage rising main between Tung Chung and Siu Ho Wan (5)

Q3 2016

Mid 2023 for new rising main & end 2025 for rehabili-tation of existing rising main

¡¤    noise; and

¡¤    water quality

 

Not Anticipated

Tuen Mun ¨C Chek Lap Kok Link(9)

2011

Northern connection: 2020 at the earliest

 

Southern connection: 1st half of 2019 at the earliest

Not Anticipated

¡¤    Landscape and visual

Organic Waste Treatment Facilities (OWTF)
Phase I (6)
(9)

2014

2016

¡¤    dust

Not anticipated

Hong Kong Boundary Crossing Facilities (HKBCF) Island of the Hong Kong-Zhuhai-Macao Bridge (HZMB) (8)(9)

2011

2017

Not anticipated

Not anticipated

Topside Development at Hong Kong Boundary Crossing Facilities (HKBCF) Island of the Hong Kong-Zhuhai-Macao Bridge (HZMB) (8)(9)

Under Planning stage

Under Planning stage

Not anticipated

Not anticipated

Hong Kong-Zhuhai-Macao Bridge (HZMB) Hong Kong Link Road (HKLR) (8)(9)

2012

2017

Not anticipated

Not anticipated

North Commercial District (NCD) at the Hong Kong International Airport (HKIA) (7)(8)(9)

-

(7)

Not anticipated

Not anticipated

Hong Kong International Airport (HKIA) Three-Runway System (3RS) (8)(9)

2017

2023

Not anticipated

Not anticipated

Notes:

(1)  As advised by CEDD, Siu Ho Wan (SHW) Reclamation and Road P1 (SHW Section) are in feasibility stage and has no implementation programme, thus are not considered as concurrent projects. These future projects, if proceed, will observe requirements in EIAO and take the SHD Replanning Works, SHO and associated track works at AEL/TCL as a committed project for the purpose of assessing cumulative impacts as appropriate.

(2)  Development at Siu Ho Wan and Associated Transport Infrastructures, Sediment Disposal Facility in South of Brothers, and the remaining identified Potential Near Shore Reclamation Sites in Western Waters of Hong Kong under Increasing Land Supply by Reclamation and Rock Cavern Development cum Public Engagement (i.e. Sunny Bay and Lung Kwu Tan) are also some concurrent projects in the North Lantau Waters but they would not contribute to any potential cumulative environmental impacts as the Project does not consist of any marine based works.

(3)  Civil construction works for SHO will be completed in 2023 while building services (BS) and electrical and mechanical (E&M) works will be conducted in 2024-2026. Operation of SHO would commence in 2026.

(4)  TCNTE will comprise of approximately 130ha of reclaimed land and 120ha existing land for the development of Tung Chung East and Tung Chung West developments respectively. The Road P1 (Tung Chung - Tai Ho Section) would also be built under the TCNTE. The construction period of the TCNTE would be between 2017 and 2030.  TCNTE is located at more than 1km from the Project but the associated Road P1 will be situated next to the Project, subject to the detailed design stage.  Cumulative impact is anticipated during the construction and operation of Road P1.  Also, cumulative construction noise and water quality impact from the proposed construction of sewerage networks under TCNTE is anticipated.

(5)  Information is made reference from http://www.legco.gov.hk/yr15-16/english/fc/pwsc/papers/p15-59e.pdf and TCNTW EIA report (Register No. AEIAR-196/2016).  The scope of this sewerage works comprises construction of an additional sewage rising main of about 6.5km from Tung Chung sewage pumping station to Siu Ho Wan sewage treatment works and rehabilitation of the existing sewage rising main.  Cumulative impact is anticipated during the construction of rising mains.

(6)  OWTF-Phase 1 is a biological treatment facility with a capacity of about 200 tonnes per day for converting organic waste into reusable compost and biogas. It is anticipated that the OWTF-Phase 1 would be commissioned in 2017.  Air emission from OWTF-Phase 1 is considered as secondary contribution to the construction dust during the construction phase of the Project.

(7)  First phase of NCD is targeted for completion in 2021.

(8)  Concurrent projects are located outside 500m study assessment area of the Project.

(9)  Vehicular emission from the traffic induced by the concurrent projects as secondary contribution has been considered in the dust assessment.