TABLE OF CONTENTS

 

 

6       Sewerage and sewage treatment implications.. 6-1

6.1       Introduction. 6-1

6.2       Legislation, Standards and Guidelines. 6-1

6.3       Existing and Planned Conditions. 6-1

6.4       Assessment Methodology and Design Criteria. 6-2

6.5       Sewage Flow Estimation. 6-3

6.6       Cumulative Impacts and Proposed Sewerage Network. 6-4

6.7       Design, Construction and Maintenance Arrangements. 6-6

6.8       Conclusions. 6-6

 

LIST OF FIGURES

NEX1062/S/SHD/ACM/Z10/180        Existing Sewerage Layout Plan         

NEX1062/S/SHD/ACM/Z10/181        Proposed Sewerage Layout Plan

 

LIST OF APPENDICES

Appendix 6.1         Estimated Sewage Generated from the Existing SHD

Appendix 6.2         Estimated Sewage Generated from the SHO and Reprovisioned SHD

Appendix 6.3         Schematic Plan of Proposed Sewerage System within SHO and Reprovisioned SHD

Appendix 6.4         Proposed Sewage Rising Main Scaled Alignment Plan and Cross Sections

Appendix 6.5          Estimation of Sewage Retention Time in Pumping System and Rising Mains

Appendix 6.6         Proposed Diameter of Rising Mains for SHO and Reprovisioned SHD

Appendix 6.7         Assessment on the Public Sewerage System Downstream of FMH7022270

Appendix 6.8         Proposed Construction, Operation and Maintenance Matrix



6                  Sewerage and sewage treatment implications

6.1              Introduction

6.1.1          The potential sewerage impacts associated with construction and operation of the Project are presented in this section. The main objectives of this sewerage assessment include the followings:

¡¤         Review the existing sewerage condition of the Site based on available information;

¡¤         Assess the sewage generated from the Project;

¡¤         Outline the methodology adopted in this assessment;

¡¤         Assess any potential impact on the existing or planned sewerage facilities nearby due to the Project; and

¡¤         Propose mitigation measures and/or improvement works, if required, to minimize any potential sewerage impact from the Project.

 

6.2              Legislation, Standards and Guidelines

6.2.1          The standards and guidelines for assessing the existing sewerage and design of the proposed sewerage are listed in Table 6.1.

Table 6.1     List of Design Standards for Sewerage Design

Design Standards

Hong Kong Buildings Ordinance and Building Regulations

Sewerage Manual Part 1 and Part 2, Drainage Services Department (DSD¡¯s Sewerage Manual)

Guidelines for Estimating Sewage Flows for Sewage Infrastructure Planning Version 1.0 (Report No. EPD/TP 1/05) (GESF), Environmental Protection Department

 

6.3              Existing and Planned Conditions

Existing Sewage Treatment Works

6.3.1          The Siu Ho Wan Sewage Treatment Works (SHWSTW), situated at about 420 meters from the eastern boundary of SHD, is a chemically enhanced primary treatment works (CEPT) with an ultimate design capacity of 180,000 m3/day[1] and a design peak flow of 3,750 L/s. The catchment of SHWSTW covers areas in North Lantau including Tung Chung, Tai Ho, Sunny Bay and the Hong Kong International Airport (HKIA). The current mean daily average flow towards SHWSTW is approximately 52,000 m3/day.

Existing and Planned Sewerage Networks

6.3.2          The sewage inside the existing SHD is collected by gravity sewers and rising mains. The sewage is then conveyed to an existing pumping station within the SHD and ultimately pumped to existing manhole FMH7022270 via an existing DN200 rising main crossing the North Lantau Highway and Lantau Airport Railway along Shum Shui Kok Drive. The existing manhole conveyed sewage from SHD, a DN150 rising sewer and a 300mm dia. gravity sewer to existing DSD pumping station and the sewage is then pumped to SHWSTW. Total sewerage discharge (ADWF) from the existing SHD is about 8.63 L/s (746 m3/day). Estimating of the existing sewage is shown in Appendix 6.1, while the existing sewerage system is shown in Figure No. NEX1062/S/SHD/ACM/Z10/180.

6.3.3          As the existing 1200mm dia. rising main along North Lantau Highway as shown in Figure No. NEX1062/S/SHD/ACM/Z10/180 is the only means of conveying sewage from Tung Chung to SHWSTW, construction of an additional 1200mm dia. rising main had commenced and rehabilitation of the existing mains would be undertaken by Agreement No. CE 6/2012 (DS) ¡°Construction of Additional Sewage Rising Mains and Rehabilitation of the Existing Sewage Rising Main between Tung Chung and Siu Ho Wan ¨C Investigation, Design and Construction¡±.

6.3.4         According to the approved Environmental Impact Assessment of the Tung Chung New Town Extension (TCNTE EIA) (Register No.: AEIAR-196/2016), a twin 600mm dia. rising mains was proposed to transfer sewage from the planned Tung Chung East (East) Sewage Pumping Station to SHWSTW.   Its alignment would follow the future Road P1 (Tung Chung ¨C Tai Ho Section) and then along the footpath at the rear of the existing seawall outside the SHD.  The rising mains would then cross below the Tung Chung Line (TCL) tunnel and Airport Express Line (AEL) and North Lantau Highway, then along the existing eastern drainage reserve and maintenance access road with discharge to SHWSTW.  The existing/planned/proposed sewerage network in vicinity of the project site are included in Figure No. NEX1062/S/SHD/ACM/Z10/181.

6.4              Assessment Methodology and Design Criteria

Assessment Methodology

6.4.1          The impact assessment has been carried out in accordance with the guidelines set out in GESF for Sewerage Infrastructure Planning Version 1.0 (Report No. EPD/TP1/05) and DSD¡¯s Sewerage Manual.

Development Parameters

6.4.2          For the purpose of this study, assumptions on the operation of SHO and Reprovisioned SHD have been made and summarised in Table 6.2, which are subjected to adjustment where necessary in detailed design stage.

Table 6.2     Development Schedule

Employee/ Job Type

Project Element

Reprovisioned SHD

(Floor Area: 49,386 m2)

SHO

(Floor Area: 13,465 m2)

J2 - Electricity, Gas & Water

1,260

-

J3 - Transport, Storage & Communication

1,933

864

J4 - Wholesale & Retail

-

26

J10 - Restaurants & Hotels

100

3

Contributing Population from

Public toilet

-

419

Total Population

3,293

1,312

 

 

Unit Flow Factors ¨C Commercial Flows

6.4.3          Commercial flows comprise flows from the employee and commercial activities which contain 11 job types as classified in GESF.  The unit flow factors of commercial flows are shown in Table 6.3.

Table 6.3     Unit Flow Factors for Commercial Flows

Employee/ Job Type(1)

Unit Flow Factor (m3/head/day)

Commercial Employee

0.080

Commercial activities:

J2 Electricity, Gas & Water

0.250

J3 Transport, Storage & Communication

0.100

J4 Wholesale & Retail

0.200

J10 Restaurants & Hotels

1.500

Note:

(1) Appendix V of Guidelines for Estimating Sewage Flows for Sewage Infrastructure Planning Version 1.0 (Report No. EPD/TP 1/05) refers.

 

Peaking Factors

6.4.4          The Peaking Factor (P) is used to determine peak flows which are flows resulting from a combination of factors including diurnal and seasonal flow variations of flow components and characteristic response of inflow and base flows to storm events. Peak flows could be determined from peaking factors and adequate safety margins could be provided during the planning of sewerage facilities.

Table 6.4     Peaking Factors

Population Range

Peaking Factor (including stormwater allowance) for facility with existing upstream sewerage

Peaking Factor (excluding stormwater allowance) for facility with new upstream sewerage

a)     For sewers

<1,000

8

6

1,000 - 5,000

6

5

5,000 - 10,000

5

4

10,000 - 50,000

4

3

> 50,000

b)    Sewage Treatment Works, Preliminary Treatment Works and Pumping Station

<10,000

4

3

10,000 - 25,000

3.5

2.5

25,000 - 50,000

3

2

> 50,000

 

6.5              Sewage Flow Estimation

6.5.1          Sewage (ADWF) generated from the operation of SHO and Reprovisioned SHD are estimated to be about 3.25 L/s (281 m3/day) and 10.97 L/s (948 m3/day) respectively based on GESF. Details of the sewage estimation is shown in Appendix 6.2. The current sewage generated from the existing SHD is about 8.63 L/s (746 m3/day). The operation of SHO and Reprovisioned SHD will generate an additional sewerage flow of 5.59 L/s (i.e. 483 m3/day).

6.5.2          Based on the sewerage and sewage treatment implication study of Proposed Comprehensive Residential and Commercial Development atop SHD (SHD Topside Development), the estimated sewage flow (ADWF) generated from SHD Topside Development in Year 2038, the year of last population intake, will be 12,068 m3/day.

6.6              Cumulative Impacts and Proposed Sewerage Network

6.6.1          For the SHO and Reprovisioned SHD, internal gravitational and pumping sewerage system shall be proposed to collect all wastewater from various buildings, SHO, as well as from tracks.  A schematic plan showing the internal sewerage system within SHO and Reprovisioned SHD is presented in Appendix 6.3.  The design and alignment will be subject to detailed design.  All the sewage collected within the internal sewerage system will ultimately be conveyed to the proposed ultimate pumping station and discharged via twin rising mains of 200mm dia. to public sewerage system. The twin rising mains will be provided parallel to the Sewage Outfall Culvert beyond the Drainage Reserve and finally connected to public sewerage system via designated discharge manhole which is the existing manhole FMH7022270. The alignment plan and sections of the proposed sewage rising main is provided in Appendix 6.4.

6.6.2          The sewage generated from the SHD Topside Development will be conveyed to SHWSTW using a separate pumping system which will be constructed under SHD Topside Development. Separate sewerage systems for the Project and SHD Topside Development are deemed to be necessary for clear demarcation on the operation, management and maintenance responsibilities between railway facilities and SHD Topside Development.

6.6.3          The foul water sump size will be designed to contain one hour ADWF of emergency storage with provision of three pumps (two for duty and one for standby in operation).  With respect to flow capacity, each of the duty pumps and the standby pump solely would be able to handle the peak flow from SHO and Reprovisioned SHD. The design capacity in ADWF and peak flow of the proposed ultimate sewage pumping station will be 1,229m3/day and 58L/s respectively. Dual-feed power supply will also be provided to the pumping station.

6.6.4          Either ductile iron (DI) pipes or high-density polyethylene pipe (HDPE) and fittings with sufficient strength to resist the pumping pressure and external load would be adopted as the rising sewer. Thrust blocks, supports or relevant fittings would be provided to avoid pipe failure such as pipe bursting and leakage.

6.6.5          Main Control System would provide the human-machine interface for monitoring and control of the pumping system through the integrated workstations. Under normal operation, the pumps will operate autonomously according to the levels of the respective wet wells. However, when the automatic control fails and any condition occurs where the pumps are unable to cope with the amount of sewage, the operator will be alerted to operate the pumps remotely from the integrated workstation and handle the emergency situation. Regular maintenance and checking of plant equipment will also be undertaken by qualified personnel to prevent equipment failure.  On-site staff for 24-7 emergency repair service would be provided to handle emergence situations. The pumping system is therefore able to resume operation generally within 1 hour after emergency repair in the event of any incident. Tank away, if necessary, would be conducted as a last resort for proper disposal at public sewage treatment works. Operation and Maintenance (O&M) Manual will also be prepared to standardize operation and maintenance procedures.

6.6.6          With the implementation of precautionary measures recommended in Sections 6.6.3 to 6.6.5, no emergency discharge of sewage during the operation of SHO and Reprovisioned SHD is anticipated.

6.6.7          Retention time of sewage in the pumping system and rising mains were estimated according to the schematic plan shown in Appendix 6.3, and the calculation is shown in Appendix 6.5 with results summarized in Table 6.5.  Results indicated that the accumulating retention time of the sewage is slightly more than 2 hours.   Variation of flow pattern may also result in longer detention time in particular during night time period.  Based on the findings in Appendix 6.5, effective septicity control measures including active on-line monitoring of sewage septicity and active septicity treatment or dosage system will be provided by the SHO and Reprovisioned SHD to mitigate septicity problem that may arise in the downstream public sewerage system.

Table 6.5     Estimated Sewage Retention Time for Each Internal Pumping System and Ultimate Pumping Station

Pumping
System(1)

ADWF

(m3/day)

Approximate Length of R.M. (m)

Sewage Retention Time (hours)

Accumulating Sewage Retention Time(2) (hours)

1

1,022

853

0.97

1.44(3)

2

166

204

0.58

0.58(4)

3

624

176

0.47

0.47(4)

4

91

418

0.97

0.97(4)

5

25

655

0.19

0.19(4)

Ultimate Pumping Station

1,229

1249

1.11

2.55(5)

Note:

(1)    Schematic plan showing the internal sewerage system network within SHO and Reprovisioned SHD adopted for estimation is provided in Appendix 6.3.

(2)    Accumulating sewage retention time is the summation of sewage retention time for the pumping system and its upstream pumping system.

(3)    Sewage from Pumping System 3 will be pumped to Ultimate Pumping Station via Pumping System 1 and thus accumulating sewage retention time of Pumping System 1 is the summation of 0.97 and 0.47 hours.

(4)    For Pumping System 2, 3, 4 and 5, there are no upstream pumping system and thus the accumulating sewage retention time at the pumping system is equal to the sewage retention time of the individual pumping system.

(5)    Total accumulating sewage retention time at ultimate pumping station is taken as the summation of maximum accumulating sewage retention time of its upstream pumping system and sewage retention time of the pumping station (i.e. 1.44 +1.11 = 2.55 hours).

6.6.8          The proposed sewerage layout plan for the Project is shown in Figure No. NEX1062/S/SHD/ACM/Z10/181. Calculation of the rising main for the SHO and Reprovisioned SHD is shown in Appendix 6.6.

6.6.9         Assessment on the public sewerage system downstream of FMH7022270 has been carried out. It is found that the existing sewer from FMH7022270 to FMH7022273 is under surcharged condition. In order to cater for the discharge of the sewage from SHO and Reprovisioned SHD to the sewage treatment works, modification works to upgrade the existing 300 mm dia. sewer to 375mm dia. are proposed and will be implemented by the Project Proponent to the satisfaction of EPD.  Temporary sewerage diversion works will be required before the modification works to maintain the sewage flow. It is considered that, with implementation of the proposed modification works, there will be no adverse impact on the public sewerage system. The calculation is provided in Appendix 6.7.

6.6.10      The tentative last population intake year of SHD Topside Development is 2038. The Government has identified available capacity of about 13,400m3/day to accept the total sewage arising from SHD Topside Development, SHO and Reprovisioned SHD for treatment at SHWSTW. Detailed breakdown is provided in Table 6.6.  Based on the findings of Table 6.6 above, there should be sufficient capacity at the SHWSTW to cater for the sewage generated from future SHO and Reprovisioned SHD.

Table 6.6     Estimation of Cumulative Sewage Flow in 2038 (with developments)

Source of Sewage

Approx. Estimated ADWF, m3/day

SHD Topside Development(1)

12,100

SHO and Reprovisioned SHD

1,229

Total

13,329

Available capacity in SHWSTW

13,400

Note: 

(1)    Reference was made on Table 6.5a of SHD Topside Development EIA Report (July 2017).

 

6.7              Design, Construction and Maintenance Arrangements

6.7.1          Reprovisioned sewerage system for supporting the operation of SHO and Repovisioned SHD will be designed and constructed by MTR.  All sewerage works shall meet the requirement of DSD and EPD in the aspects of design, construction, operation and maintenance. The proposed construction, operation and maintenance matrix of the reprovisioned sewerage system is shown in Appendix 6.8.

6.8              Conclusions

6.8.1          The future SHO and Reprovisioned SHD will generate a sewage flow of 281 m3/day and 948 m3/day (ADWF) respectively, an additional sewerage flow of 483 m3/day (5.59 L/s) comparing with the sewage generation from the existing SHD.

6.8.2          With consideration of cumulative sewage generation from the SHD Topside Development, one pumping station with provision of three pumps (two for duty and one for standby in operation) and twin DN200 rising mains are proposed to cater for the sewage generated from SHO and Reprovisioned SHD, while a separate sewerage system would be proposed for the SHD Topside Development.

6.8.3          An estimation of cumulative flow from SHD has been assessed, the results indicate that the SHWSTW should have sufficient capacity to cater for the sewage arising from the Project and the SHD Topside Development.  No adverse impact due to the cumulative sewerage generation from the Project and the SHD Topside Development on the existing sewerage system is anticipated.

6.8.4          With the implementation of mitigation measures including the provision of twin rising mains, dual feed power supply, spare pumps, emergency storage and control system etc, no emergency sewage discharge during the operation of SHO and Reprovisioned SHD is anticipated.


 



[1] According to Section 6.7.6.1 of Tung Chung New Town Extension (TCNTE EIA) (Register No.: AEIAR-196/2016), EPD has arranged with DSD to fit out the remainder of the treatment units at SHWSTW to its designed maximum handling capacity by 2024.