This Section presents the
findings of the Hazard to Life Quantitative Risk Assessment (QRA) undertaken
for the Project. The assessment
includes an evaluation of the risks associated with storage, transfer, handling
and use of LNG and natural gas and other dangerous goods, marine transport and
activities of LNG carriers and FSRU Vessel and natural gas subsea pipelines
within Hong Kong waters in normal and adverse weather or tidal situations, and
accidental spillage or leakage of LNG or natural gas. The risks during the construction and
operations phases of the Project are also assessed in consideration of other
potential contributors to risk in the vicinity of the Project¡¦s facilities.
The
key legislation and guidelines which are considered relevant to the QRA Study
for the Project are as follows:
¡P
Environmental
Impact Assessment Ordinance (EIAO), Cap. 499;
¡P
Technical
Memorandum on EIA Process (EIAO-TM);
¡P
Gas
Safety Ordinance, Cap. 51;
¡P
Dangerous
Goods Ordinance, Cap. 295;
¡P
Merchant
Shipping (Safety) Ordinance (Cap. 369) and its subsidiary regulations such as
Merchant Shipping (Safety) (Gas Carriers) Regulations (Cap. 369Z);
¡P
Merchant
Shipping (Local Vessels) Ordinance (Cap. 548) and its subsidiary regulations.
Section
2
of Annex 4 of the EIAO-TM specifies the individual risk
and societal risk guidelines that will apply to the Project.
Individual risk is the
predicted increase in the chance of fatality per year to a hypothetical
individual who remains at a given stationary point for 100% of the time. The individual risk guidelines specify
that the maximum level of off-site individual risk associated with a hazardous
installation should not exceed 1 in 100,000 per year, i.e. 1 ¡Ñ 10-5
per year.
Societal risk expresses the
risks to the surrounding off-site population in the vicinity of a hazardous
installation. The societal risk
guidelines for acceptable risk levels are presented graphically in Figure 5.2. The societal risk is expressed in terms
of frequency (F) of fatalities against number of fatalities (N) in the
population from incidents at a hazardous installation. Two F-N risk lines are used to demark
¡§Acceptable¡¨ or ¡§Unacceptable¡¨ regions.
The region between the two F-N risk lines indicates the acceptability of
the societal risk is borderline and should be reduced to As Low As Reasonably
Practicable (ALARP) level. This
seeks to ensure that all practicable and cost-effective mitigation measures
which can reduce societal risk are considered. In order to avoid major incidents
resulting in more than 1,000 fatalities, there is a vertical cut-off line at
the 1,000 fatalities level extending down to a frequency of 1 in a billion
years.
With
due consideration of the Project key components and activities and to address
requirements of the EIA Study Brief, the remainder of this Section has been divided
into four components of the QRA Study. Sections 5.4 to Section 5.7 detail the four
components. The key hazardous
materials assessed in each section are illustrated in Table 5.1.
Table 5.1 QRA Study Components and
Associated Hazard Evaluations
QRA Study Components: Description of Hazard
Evaluation |
Associated Hazards |
Section |
||
LNG |
Natural Gas |
Other
Dangerous Goods |
||
Evaluation of risks associated with LNGC and FSRU
Vessel transit routes within Hong Kong waters to the LNG Terminal (including
transits for temporary sheltering under adverse weather condition), as well
as emergency transits of LNGC and FSRU Vessel |
ü |
ü |
ü |
Section 5.4: LNGC / FSRU Vessel Transits to the LNG Terminal |
Evaluation of risks of LNG / natural gas / other
dangerous goods associated with the LNG Terminal operation |
ü |
ü |
ü |
Section 5.5: LNG Terminal Operation |
Evaluation of risks of natural gas associated with
subsea pipelines connecting the Jetty and the proposed GRSs at the BPPS and
the LPS |
N/A |
ü |
N/A |
Section 5.6 : Subsea Pipelines |
Evaluation of risks of natural gas associated with
the proposed GRSs at the BPPS and the LPS |
N/A |
ü |
ü |
Section 5.7 : GRS Facilities |
Notes: ü: Applicable, N/A: Not Applicable
Other
risk factors which could induce potential risk on the Project components, as
specified in Section 3.4.5 and Appendix B of the EIA Study Brief, are
also assessed in the corresponding sections illustrated in Table 5.2.
Table 5.2 Other Assessed Risk
Factors
Section
Description |
Risk of Collision from High Speed Ferries |
Adverse
Weather (e.g. typhoon, storm surge, extreme tide) |
Risk from Operation of Helicopters / Aircrafts |
Risk Associated with Existing GRSs |
Section 5.4: Marine
Transits of LNGC / FSRU Vessel to the LNG Terminal |
ü |
ü |
ü |
N/A |
Section 5.5: LNG
Terminal Operation |
ü |
ü |
ü |
N/A |
Section 5.6: Subsea
Pipelines |
N/A |
N/A |
N/A |
N/A |
Section 5.7: GRS
Facilities |
N/A |
ü |
ü |
ü |
Notes: ü: Applicable, N/A: Not Applicable.
It should
be noted that during the construction of the Jetty and both subsea pipelines,
LNG, natural gas and other dangerous goods will not be present other than for
commissioning purposes. Therefore,
construction phase associated risk has not been further assessed.
During the construction of
the proposed GRSs at the BPPS and LPS, the hazards arising from the associated
construction works may impact the existing neighbouring GRS
facilities, leading to
natural gas potential loss of containment.
The associated risk has been assessed in Section 5.7.6.
The
overall assessment approach is illustrated in Figure
5.1. The methodology adopted for the QRA
Study is consistent with other studies that have been approved by the EPD and
other relevant authorities, including both EIA and safety case studies, such
as:
¡P
ERM,
EIA for 1,800 MW Gas-fired Power Station at Lamma Extension (Register No.:
AEIAR-010/1999), February 1999;
¡P
ERM, EIA for
Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities (Register No.:
AEIAR-106/2007), December 2006;
¡P
ERM,
EIA for Black Point Gas Supply Project, Revision 3 (Register No.:
AEIAR-150/2010), February 2010; and
¡P
ERM, EIA for
Additional Gas-fired Generation Units
Project (Register
No.: AEIAR-197/2016), June 2016.
The assumptions
and methodology used for the QRA Study are in line with the Method Statement
that was approved by EPD on 28 September 2017.
The
general approach taken for each step of the QRA Study is provided below.
Relevant
information on the Jetty, Subsea Pipelines and GRS such as layout drawings,
design basis, weather data, surrounding off-site population data, etc. were
collected, reviewed and incorporated in the QRA Study.
A
Hazard Identification (HAZID) analysis including a HAZID workshop for the
Project components was conducted to identify all potential hazards. A review of literature and incident /
accident database was also conducted to identify all potential hazardous
scenarios for consideration in the QRA Study.
The
failure frequencies / likelihood of the various hazardous scenarios outcomes
were derived from historical failure databases and by using event tree
analysis. Where necessary and
applicable, fault tree analysis was also conducted to take into account Project
specific factors.
All
identified hazardous materials (LNG, natural gas, and other dangerous goods)
were assessed in the QRA Study. The
consequence modelling for these hazardous materials was performed using an
internationally recognized consequence modelling package, PHAST.
The
consequence and frequency data, together with surrounding off-site population
data, was subsequently combined using approved software packages, SAFETITM and RiskplotTM,
which is in line with previous EIA studies that have been approved by EPD and
other relevant authorities ([1]) ([2]) and as stated in
the Method Statement for the QRA Study.
The results from the cumulative risk assessment were compared against
the risk criteria stipulated in Section 2
of Annex 4 of the EIAO-TM.
Practicable
and cost-effective risk mitigation measures were proposed, as required based on
the findings of the QRA Study.
The proposed assessment years adopted for the QRA
Study are as follows:
¡P Year
2020: Target year for the Project to start commercial operations; and
¡P Year
2030: Future scenario for the Project.
In addition, the proposed GRS facilities at the BPPS
and LPS are expected to be under peak construction time in the beginning of
2020. The GRS construction works
may induce additional risks to the neighbouring operating GRS facilities. Therefore, Year 2020 has been also
adopted as the assessment year for the construction activities at both GRS
locations.
The marine traffic data in the vicinity of the Project
components was collected and used to estimate the marine vessel population for
consideration in the QRA Study.
The marine traffic that was identified in the vicinity
of the Project components included fishing vessels, river trade, ocean-going
vessels, fast ferries, and other types of smaller vessels. A forecasting exercise for marine
traffic was also conducted and the increment in marine traffic volume was
derived by trend analysis for each vessel class so that a representative
pattern was developed for the 2020 and 2030 timeframes.
The population of all marine vessels was treated as an
area averaged density, except for fast ferries which were treated as point
receptors. The approach to estimate
the marine vessel population for the proposed assessment years was consistent
with the previous EIA studies that have been approved by the EPD and
other relevant authorities ([3]) ([4]) and as included in the Method Statement for the QRA
Study.
The detailed marine traffic data and marine vessel
population estimation assumptions and methodology are summarised in Annex 5A.
Based on a review of the GeoInfo Map ([5]), there is no land based population in the vicinity
of any of the Project components, and the detailed discussion on the land
population is summarised in Annex 5A.
There is no road traffic population in the vicinity of
the GRS at the LPS. Road traffic
population was identified in the vicinity of the GRS at the BPPS. The detailed discussion on the road traffic
population is summarised in Annex 5A.
Safety management measures will be put in place to
minimize the potential risk exposure to all personnel at the BPPS and LPS facilities,
including operational staff during the operation phase and construction workers
during the construction phase.
The key safety management measures for all personnel
at the BPPS and LPS will include:
¡P
All personnel within the BPPS shall comply with CLP safety policy and
requirements;
¡P
All personnel within the LPS shall comply with HK Electric safety policy
and requirements;
¡P All
operation work procedures shall be complied with the operating plant procedures
or guidelines and regulatory requirements;
¡P All
personnel shall be equipped with appropriate personal protective equipment
(PPE) when working at the BPPS and LPS facilities;
¡P Safety
training and briefings shall be provided to all personnel; and
¡P Regular
site safety inspections/ audits shall be conducted.
The key safety management
measures to manage the risk associated with construction workers during the
construction phase will include:
¡P Method
statements and risk assessments shall be prepared and safety control measures
shall be in place before the commencement of construction works;
¡P Work
permit system, on-site pre-work risk assessment and emergency response
procedure shall be in place before commencement of construction works; and
¡P All
construction workers shall be under close site supervision during the
construction phase of the GRSs.
With the implementation
of the above safety management measures at the BPPS and LPS, the potential
risks to all personnel on-site, including operational staff during the operation phase
and construction workers during the construction phase in the BPPS and LPS,
are expected to be insignificant; hence they were not considered as off-site
population and has not be taken into account in the QRA Study.
Safety management measures will also be put in place
to minimize the potential risk exposure to all personnel at the LNG Terminal,
including operational staff during the operation phase and construction workers
during the construction phase.
The key safety management measures for all personnel
at the LNG Terminal will include:
¡P
All personnel within the LNG Terminal shall comply with relevant safety
policy and requirements;
¡P All
operation work procedures shall be complied with relevant codes and standards (e.g. SIGTTO)
and regulatory requirements;
¡P Work
permit system and emergency response procedure shall be
in place;
¡P Robust
and extended process control system, safety control system, fire-fighting
system and security system shall be provided;
¡P Sufficient
and trained / competent staff shall be
provided to operate the LNG Terminal; and
¡P Regular
safety inspections/audits shall be conducted.
The key safety management measures to manage the risk
associated with construction workers during the construction phase of the LNG
Terminal will include:
¡P Method
statements and risk assessments shall be
prepared and safety control measures should be in place before the commencement
of construction works;
¡P Work
permit system, on-site pre-work risk assessment and emergency response procedure
shall be in place before commencement of construction
works; and
¡P All
construction workers shall be under close site supervision during the
construction phase of the LNG Terminal.
With the implementation
of the above safety management measures at the LNG Terminal, the potential
risks to all personnel on-site, including operational staff during the operation phase
and construction workers during the construction phase in the LNG Terminal,
are expected to be insignificant; hence they were not considered as off-site
population and has not be taken into account in the QRA Study.
The 5-year meteorological data from Year 2012 to Year
2016 from the Hong Kong Observatory (HKO) has been selected to represent local
meteorological conditions including wind speed, wind direction, atmospheric
stability class, temperature, and relative humidity.
The weather stations in the vicinity of the Project
components were reviewed, and the following weather stations listed in Table 5.3 were
selected for the QRA Study.
Table 5.3 Selected
Weather Stations for the QRA Study
Component / Weather Station |
Cheung
Chau |
Sha Chau |
Lamma
Island |
LNGC
/ FSRU Vessel Transits to the LNG Terminal |
ü |
N/A |
N/A |
FSRU
Vessel, the Jetty and LNGC Unloading at the LNG Terminal |
ü |
N/A |
N/A |
Subsea
BPPS Pipeline |
N/A |
ü |
N/A |
Subsea
LPS Pipeline |
ü |
N/A |
N/A |
GRS
Facility at the BPPS |
N/A |
ü |
N/A |
GRS
Facility at the LPS |
N/A |
N/A |
ü |
Notes:
ü:
Applicable, N/A: Not Applicable.
The meteorological data of these selected weather
stations are summarised in Annex 5A.
This Section presents the QRA Study for
the evaluation of the risks associated with the LNGC and FSRU Vessel along the
transit routes to the LNG Terminal during normal operations (including transits
for temporary sheltering under adverse weather condition), as well as emergency
transits of the LNGC and FSRU Vessel.
Two
(2) types of LNGC with double hull are typically used in the market to deliver LNG
cargoes, namely:
¡P Membrane type; and
¡P
MOSS
type (spherical LNG storage tank).
More
than 90% LNGCs are membrane type at the current LNGC market, as such, the LNGC of membrane type was selected as the
representative case for the QRA Study.
The QRA Study was conducted based on two (2) sizes of
LNGC (each with five (5) membrane-type LNG Cargo Tanks):
¡P
Small
LNGC (170,000 m3 capacity, with each LNG storage tank capacity of
about 34,000 m3); and
¡P
Large
LNGC (270,000 m3, capacity, with each LNG storage tank capacity of
about 54,000 m3).
The typical safeguards for LNGC design
and operations have been summarised in Section 3 of the EIA Report.
Typically, an LNGC has the following main process
systems:
¡P LNG
Storage System;
¡P LNG
Unloading Arms;
¡P Diesel
Storage System;
¡P Lubricating
Oil System; and
¡P Fuel
Oil Storage System.
The detailed description of the above process systems
is summarised in Annex 5B,
while the key description of FSRU Vessel is summarised in Section 5.5.1.
Figure 5.3
presents the indicative LNGC transit routes to the LNG Terminal, and the FSRU
Vessel will also use the same LNGC transit routes as the initial marine transit
to the LNG Terminal. The length of
the LNGC transit route is about 30 km, and the description of the route
segments is presented in Table 5.4.
Table 5.4 LNGC
Transit Route Segment
Segment Code |
Segment Description |
Length of Segment |
Segment
¡¥a¡¦ |
Transit
|
27.1
km |
Segment
¡¥b¡¦ |
Approaching
the LNG Terminal |
3.1
km |
According to the Marine Traffic Impact Assessment
(MTIA) Report for the LNG Terminal ([6]), the support of a tug fleet for access to/from the
LNG Terminal ensures that even with engine or control system failure on the
LNGC or FSRU Vessel during the approaching the LNG Terminal, there will be
adequate control capability to mitigate such events. A total of four (4) tugs, of 80T bollard
pull or higher are anticipated to support all LNGC¡¦s scheduled arrivals and
departures, and FSRU Vessel arrival and departures due to typhoon. In addition, tugs will also be required
to assist departures prior to the onset of a typhoon. These tugs will have the necessary
electrical system compliance and gas detection to be safe to work in close
proximity with the LNG Terminal.
Based on the estimated LNG Terminal throughput, it is envisaged
that the frequency of LNGC visits on average will be one LNGC arriving every
five to eight days. As a
conservative approach, the QRA Study was conducted based on the following
maximum annual visit frequency:
¡P 75
visits per year (equivalent to every 4.8 days) for Small LNGC; and
¡P 50
visits per year (equivalent to every 7.3 days) for Large LNGC.
With regard to the LNGC transit to the LNG Terminal,
the following transit conditions were considered in the QRA Study:
¡P The
LNGC transit is conducted by the Small LNGC as the worst-case scenario since
the number of LNGC transit and associated transit risk is higher; and
¡P The
maximum annual visit frequency of the Small LNGC to the LNG Terminal is seventy
five (75) visits per year.
For the initial transit to the LNG Terminal, the FSRU
Vessel will transit and approach the LNG Terminal on the same route as the LNGC
normal transit route shown in Figure 5.3.
Prior to the transit of an LNGC to the LNG Terminal
for LNG unloading operation, the transit route and the weather forecast for the
transit area will be reviewed and analyzed to determine the suitability and
safety of the LNGC transit. It is
expected that the LNGC will only be allowed to transit and enter Hong Kong
waters if the forecasted weather condition is within an agreed weather
envelope. Therefore, it is highly
unlikely that an LNGC will be at berth at the Jetty when a typhoon is
predicted. Nevertheless, a
frequency of once per five (5) years was conservatively assumed to be adopted
in the QRA Study.
In case the on-set of a typhoon occurs during the LNG
unloading operation at the Jetty, the LNGC will, depending on weather
conditions and at the discretion of the Master head, depart the berth to an
area of open sea outside HKSAR waters.
Once the weather conditions have returned to acceptable operating limits
for berthing, the LNGC will return to the LNG Terminal using the same LNGC
normal transit route as presented in Figure 5.3.
In case of adverse weather condition (e.g. typhoon,
monsoon), the FSRU Vessel berthed at the Jetty will also, depending on weather
conditions and at the discretion of the Master head, depart the berth to an
area of open sea outside HKSAR waters.
Although it was identified from the prior mooring
capability assessment that the FSRU Vessel could maintain at the LNG Terminal
in winds associated with Typhoon Signal 3 (sustained speeds of 41-62 km/hr) ([7]), it was conservatively assumed that departure of the
FSRU Vessel would be required upon Typhoon Signal No. 3 or higher for the QRA
Study.
According to the HKO, the average number of days per
year with Typhoon Signal No. 3 or higher in Hong Kong between 1961 and 2010 is
9.56 days ([8]), and the average annual frequency of Typhoon Signal
No. 3 or higher in Hong Kong between 1956 and 2014 is 8.7 times (2). With the
aim to build conservatism in this study, the FSRU Vessel¡¦s departure frequency
from the Jetty under adverse weather condition was conservatively selected as
ten (10) times per year.
Once the weather conditions have returned to
acceptable operating limits for berthing, the FSRU Vessel will return to the
LNG Terminal using the same LNGC normal transit route as presented in Figure 5.3.
A Typhoon Departure Plan will be put in place (and
agreed with Marine Department). The plan will fully document the procedure to
be followed in the event of a typhoon affecting LNG Terminal operation.
In the case of an emergency situation (e.g.
uncontrolled fire event at the Jetty), the FSRU Vessel berthed at the Jetty and
any LNGC that may be on berth at the time of the emergency will be required to
depart the berth to an area of open sea outside HKSAR waters. In addition, a standby vessel is
available to provide an emergency response and will have the capability to
assist the FSRU Vessel and LNGC depart the berth. The frequency of this scenario was
conservatively assumed as once every five (5) years for the QRA Study.
Once the emergency situation is over and the Jetty is
made safe, the LNGC and FSRU Vessel will return to the LNG Terminal using the
same LNGC transit route as presented in Figure 5.3.
An emergency response plan will be put in place which
fully documents the procedures to be followed in the event of an emergency.
The hazardous scenarios associated with the marine transits
of the LNGC and FSRU Vessel to the LNG Terminal were identified though the
following tasks:
¡P
Review
of hazardous materials;
¡P
Review
of potential Major Accident Events (MAEs);
¡P
Review
of relevant industry incidents;
¡P
Review
of potential initiating events leading to MAEs; and
¡P
HAZID
Workshop.
LNG on board the LNGC and FSRU Vessel was the major hazardous material
considered in the QRA Study, while other dangerous goods including diesel,
marine diesel oil, and lubricating oil were also considered. The details of the storage of LNG and
other dangerous goods on board the LNGC and FSRU Vessel during marine transit
are summarised in Table 5.5 and Table 5.6 respectively.
Table 5.5 LNG and Other Dangerous
Goods Associated with LNGC during Marine Transit
Chemicals |
|
Dangerous Goods Classification* |
Maximum Storage Quantity |
Temperature (¢XC) |
Pressure (barg) |
LNG for Large LNGC |
|
- |
270,000
m3 |
-156 |
0.7
|
LNG for Small LNGC |
|
- |
170,000
m3 |
-156 |
0.7 |
Diesel (Heavy Fuel Oil) |
|
Category
5 |
~6,000
m3 |
25 |
ATM |
Marine Diesel Oil |
|
Category
5 |
≤
800 m3 |
25 |
ATM |
Lubricating Oil |
|
- |
≤
100 m3 |
25 |
ATM |
Calibration Gas^ |
|
Category 2 |
1 cylinder |
25 |
137 |
Notes:
*: The dangerous goods category is classified based on
¡§Fire Protection Notice No. 4, Dangerous Goods General¡¨ by Fire Services
Department ([9]).
^: The key composition of the calibration gas for Gas
Chromatograph is methane (90 vol%), ethane (5 vol%), Nitrogen (2.5 vol%), and
carbon dioxide (1 vol%) and propane (1 vol%).
Table
5.6 LNG
and Other Dangerous Goods Associated with FSRU
Vessel during Marine Transit
Chemical |
Dangerous Goods Classification* |
Maximum Storage Quantity |
Temperature (¢XC) |
Pressure (barg) |
LNG |
- |
270,000
m3 |
-156 |
0.7 |
Diesel (Heavy Fuel Oil) |
Category
5 |
~6,000
m3 |
25 |
ATM |
Marine Diesel Oil |
Category
5 |
≤
800 m3 |
25 |
ATM |
Lubricating Oil |
- |
≤
100 m3 |
25 |
ATM |
Calibration Gas^ |
Category 2 |
1 cylinder |
25 |
137 |
Notes:
*: The dangerous goods category is classified based on
¡§Fire Protection Notice No. 4, Dangerous Goods General¡¨ by Fire Services Department.
(1)
^:
The key composition of the calibration gas for Gas
Chromatograph is methane (90 vol%), ethane (5 vol%), Nitrogen (2.5 vol%), and
carbon dioxide (1 vol%) and propane (1 vol%).
The detailed
description of each identified hazardous material is provided below.
LNG
LNG
is an extremely cold, non-toxic, non-corrosive and flammable substance.
If
LNG is accidentally released from a temperature-controlled container, it is
likely to come in contact with relatively warmer surfaces and air that will
transfer heat to the LNG. The heat
will begin to vapourise some of the LNG, returning it to its gaseous
state.
The
relative proportions of liquid LNG and gaseous phases immediately following an accidental
release depends on the release conditions.
The released LNG will form a LNG pool on the surface of the sea in the
vicinity of the FSRU Vessel/ LNGC/ Jetty which will begin to ¡§boil¡¨ and
vapourise due to heat input from the surrounding environment. The vapour cloud may only ignite if it
encounters an ignition source while its concentration is within its
flammability range.
Any
person coming into contact with LNG in its cryogenic condition will be
subjected to cryogenic burns.
Diesel
(Heavy Fuel Oil), Marine Diesel Oil and Lubricating Oil
Diesel, marine diesel oil and
lubricating oil have a relatively higher flash point (greater than 66 ¢XC),
which is above ambient temperature, and with a high boiling point. Thus, evaporation from a liquid pool is
expected to be minimal.
Calibration Gas
The
volume of the compressed gas inside the cylinders is limited and the associated
inventory available is small, and those compressed gas cylinders are located at
machinery room. Should loss of
containment occur for the compressed gas cylinders, there is no off-site impact
on surrounding marine population.
Hence, it is not further assessed in the QRA Study.
The possible hazardous scenarios considered in the QRA
Study, upon the ignition of any released LNG during the marine transits of the
LNGC or FSRU Vessel with consideration of operating conditions, are:
¡P Pool
fire; and
¡P Flash
fire.
Diesel (Heavy Fuel Oil), Marine Diesel Oil and
Lubricating Oil
Considering
the high flash point temperature of the other dangerous goods such as marine
diesel oil present in the LNGC and FSRU Vessel, the possible hazardous
scenarios considered in the QRA Study are pool fire and flash fire.
Detailed characteristics of the above hazardous
scenarios (i.e. pool fire and flash fire) are described in Annex 5G.
To
further investigate possible hazardous scenarios from the LNGC and FSRU Vessel,
review of the applicable past industry incidents at similar facilities
worldwide was conducted based on the following incident/ accident database:
¡P Institution
of Chemical Engineers (IChemE) accident database;
¡P eMARS
([10]);
¡P ERNS ([11]);
¡P Major
Hazard Incident Data Service (MHIDAS) database ([12]); and
¡P Society
of International Gas Tanker and Terminal Operators (SIGTTO) ([13]).
Details of the past industry incident analysis are presented
in Annex 5C.
The key potential hazardous scenarios arising from
marine transits of the LNGC and FSRU Vessel were identified as loss of
containment of LNG. The potential
initiating events which could result in the loss of containment of LNG are
listed below:
¡P Ship
Collision;
¡P Groundings;
¡P Sinking
or foundering;
¡P General
equipment/piping failure (due to corrosion, construction defects etc.);
¡P LNG
containment system failure; and
¡P External
effects - adverse weather (typhoon, poor visibility, storm surge, extreme
tide), tsunami, and lightning.
Descriptions of
these potential initiating events are presented in Annex 5D.
A HAZID workshop was conducted to confirm and further
identify the potential initiating events which may lead to MAEs along the LNGC
and FSRU Vessel transit route based on the HAZID team
representatives¡¦ experience, past industry accidents, lessons learnt and
guideword checklists. The HAZID
workshop worksheet is presented in Annex 5E. The HAZID workshop output served as a
basis for the identification of potential initiating events and hazardous scenarios
for the QRA Study.
A number of hazardous sections for detailed analysis
in the QRA Study based on location of emergency shutdown valves and process
conditions were developed. The
details of each hazardous section are presented in Annex 5D.
A ship collision frequency analysis was conducted
following the approach adopted in the previous EIA Report that was approved by the EPD ([14]). DYMTRI
(Dynamic Marine Traffic simulation) model ([15]) was adopted as the platform for the
marine traffic simulation to predict the collision frequencies along the LNGC
and FSRU Vessel transit route.
The key steps of the ship collision frequency analysis
included:
¡P
Identification of Modelled Marine Traffic;
¡P Hazard
Identification;
¡P Model Validation;
¡P Marine
Traffic Forecasts;
¡P
Scenario Development ;
¡P
Collision Frequency Assessment; and
¡P Collision
Energy Distribution.
The description
of these key steps is described in Annex 5F.
The total
collision frequencies leading to the loss of containment of LNG are provided in
Table 5.7 and Table 5.8.
Table 5.7 Total
Ship Collision Frequency Leading to Loss of Containment of LNG (Year 2020)
Type of LNGC |
Release Frequency in Sub-Segment ¡§a¡¨ (/m/year) |
Release Frequency in Sub-Segment ¡§b¡¨ (/m/year) |
Small
LNGC |
1.6
¡Ñ 10-8 |
1.5
¡Ñ 10-9 |
Large
LNGC |
1.6
¡Ñ 10-8 |
1.5
¡Ñ 10-9 |
Table 5.8 Total Ship Collision
Frequency Leading to Loss of Containment of LNG (Year 2030)
Type of LNGC |
Release Frequency in Sub-Segment ¡§a¡¨ (/m/year) |
Release Frequency in Sub-Segment ¡§b¡¨ (/m/year) |
Small
LNGC |
1.7
¡Ñ 10-8 |
4.9
¡Ñ 10-10 |
Large
LNGC |
1.8
¡Ñ 10-8 |
5.2
¡Ñ 10-10 |
The anticipated grounding frequency for the LNGC and
FSRU Vessel during their transits to and from the LNG Terminal has been developed
from a review of historical incidents in Hong Kong waters associated with
vessels over 200 m Length Overall (LOA).
Considering the number of marine transits per year and the probability
of loss of LNG containment due to grounding events, the grounding release
frequency adopted in the QRA Study was 1.2 ¡Ñ 10-9 per m per
year. The derivation of this
grounding frequency is provided in Annex 5F.
The release hole sizes and associated penetration
energy selected are as per the previous EIA Report ([16]) that was approved by the EPD, are
presented in Table 5.9.
Table 5.9 Release
Hole Sizes and Penetration Energy
Release Hole Size |
Penetration Energy (MJ) |
250
mm |
100
to 110 MJ |
750
mm |
111
to 150 MJ |
1,500
mm |
>150
MJ |
As per the previous EPD (1) approved
EIA Report, the
immediate ignition probability for the collision scenarios was selected as 0.8;
and the immediate ignition probability for the grounding scenarios was selected
as 0.2 for the QRA Study.
An event tree analysis was performed to model the
development of each hazardous scenario outcomes (pool fire and flash fire) from
an initial release scenario. The
event tree analysis considered whether there is immediate ignition or delayed
ignition, with consideration of the associated ignition probability as
discussed above. The development of
the event tree is presented in Annex 5F.
PHAST was used to perform the physical effects modelling to
assess the effects zones for the following hazardous scenarios:
¡P Pool
fire; and
¡P Flash
fire.
Detailed description of the physical effects modelling is
presented in Annex 5G.
For thermal radiation impact, the associated fatality/
injury from a pool fire was estimated based on the following probit equation ([17]):
Y
= -36.38 + 2.56 ln (t I 4/3)
where:
Y is the probit
I is the radiant thermal flux
(W m-2)
t is duration of exposure (s)
The
exposure time, t, is limited to a maximum of twenty (20) seconds.
With
regard to a flash fire, the criterion chosen is that a 100% fatality was
adopted for any person outdoor within the flash fire envelope, which was
conservatively selected as 0.85 of the Lower Flammable Limit (LFL).
Details
of the consequence modelling results are presented in Annex 5G.
The risk summation for the LNGC and FSRU Vessel
transits was modelled using SAFETI,
which is in line with the previous EIA Report that was approved by EPD ([18]).
The individual
risk contours associated with the LNGC and FSRU Vessel transits are shown in Figure 5.4
and Figure 5.5.
The
individual risk contour of 1 ¡Ñ 10-5 per year was not reached for the
LNGC and FSRU Vessel transit route in the Operational Year in 2020 and Future
Scenario Year in 2030, as such the individual risk criterion stipulated in Section 2
of Annex 4 of the EIAO-TM is met.
The
societal risk for the LNGC and FSRU Vessel transits, in terms of F-N curve, was
calculated based on the surrounding off-site marine vessel populations in the
vicinity of the transit route. The societal risks in terms of
F-N curves for the Operational Year in 2020 and Future Scenario Year in 2030,
as shown in Figure 5.6,
lie within the Acceptable Region, as such the societal risk
criteria stipulated in Section 2 of Annex 4 of the EIAO-TM
are met.
Both individual risk and societal risk associated with the
transits of the LNGC and FSRU Vessel are in compliance with the risk
criteria stipulated in Section 2 of Annex 4 of the EIAO-TM.
This Section
presents the QRA Study for the risks evaluation associated with the LNG
Terminal, including FSRU Vessel, the Jetty, and the LNGC unloading operation at
the Jetty.
The
Jetty
The
Jetty is designed for simultaneous mooring of both the FSRU Vessel and an LNGC,
and is a typical double berth marine structure that uses mooring / fender
facilities to safely moor the FSRU Vessel and LNGC.
The
LNGC at the Jetty transfers LNG at 5 barg and -156 ¢XC via unloading arms across
the Jetty to the FSRU Vessel, and the LNG unloading rate is a maximum of
12,000 m3/hr. For
the LNG unloading operation, the unloading arm configuration between the Jetty
and the LNGC as well as between the Jetty and the FSRU Vessel consist of two
(2) unloading arms dedicated for LNG service, one (1) hybrid arm normally
transferring LNG but also capable of transferring LNG vapour, and one (1)
dedicated vapour return arm. Upon
completion of the LNG unloading operation, all unloading arms will be isolated,
de-inventorised and purged with nitrogen inert gas before being disconnected.
The
LNG transferred from the LNGC is stored in the FSRU Vessel¡¦s storage tanks.
FSRU Vessel
The
LNG in the FSRU Vessel¡¦s storage tanks is pumped to the regasification unit by
LNG Storage Tank Pumps and LNG Booster Pumps. The regasification unit comprises of
regasification trains, with a maximum installed capacity of 1,000 mmscfd.
The natural
gas at 5 ¢XC and 88 barg is then sent from the regasification trains, via the
metering system, to the Jetty at a maximum flow rate of 800 mmscfd to two (2)
high pressure (HP) Gas Send-out Arms (1 duty and 1 standby) that supply the
natural gas to the GRS at the BPPS via the 30¡¨ BPPS Pipeline, and to the GRS at
the LPS via the 20¡¨ LPS Pipeline.
The
LNG Terminal has the capability to receive LNG from LNGC while simultaneously
sending out natural gas, and the FSRU Vessel also has the capability to reload
LNG onto an LNGC or, in future, onto a LNG bunker vessel or barge.
Type of FSRU
Vessel
Two (2) types of FSRU Vessel
with double hull are typically used in the market to receive, store, regasify
and send out natural gas, namely:
¡P Membrane type; and
¡P
MOSS
type (spherical LNG storage tank).
Membrane
type storage tanks are favoured for new build FSRU Vessels, as their
configuration provides a higher storage capacity for a given ship size due to
no space between the storage tanks, as well as flat deck providing a better
platform for the regasification facilities.
As
such, membrane-type FSRU Vessel with LNG storage capacity of 270,000 m3
and five (5) LNG Cargo Tanks was selected as the representative case for the
QRA Study.
Typically,
an FSRU Vessel has the following main process systems:
¡P LNG
Regasification: LNG Send-out Booster Pump System;
¡P LNG
Regasification: LNG Vapourisation System;
¡P BOG
Handling and Recovery System;
¡P Seawater
Intake System;
¡P Sodium
Hypochlorite System;
¡P Diesel
Storage System;
¡P Lubricating
Oil System;
¡P Fuel
Oil Storage System; and
¡P Nitrogen
Generation System.
Detailed
process description of the above process systems is summarised in Annex 5B.
The
following safety systems are typically provided on the FSRU Vessel, the Jetty
and on the visiting LNGC:
¡P Emergency
Release Coupling System for Unloading Arms;
¡P Process
Overpressure Protection System;
¡P Emergency
Shutdown System;
¡P Fire
and Gas Detection System;
¡P LNG
Spillage Protection System;
¡P Escape
Routes / Paths and Escape System; and
¡P Security
Control System.
Detailed
description of the above safety systems is summarised in Annex 5B.
With regard to the LNGC
unloading operations at the LNG Terminal, the following
operating conditions were considered in the QRA Study:
¡P The LNG
unloading operation is conducted by the Small LNGC as the worst-case scenario
since the unloading operation frequency and associated process risk is higher;
¡P The
maximum annual visit frequency of the Small LNGC to the LNG Terminal is seventy
five (75) visits per year;
¡P The
maximum unloading time for the Small LNGC at the LNG Terminal is twenty four
(24) hours; and
¡P The
maximum staying time of the Small LNGC at the LNG Terminal is forty eight (48)
hours.
As
per previous project experience for similar facilities, the number of bunkering
operations for marine diesel oil using marine service vessels is typically
three (3) times per year. As such,
it was conservatively assumed that the bunkering operation of marine diesel oil
for the LNG Terminal will be performed three (3) times per year and that each
operation is up to six (6) hours duration.
The risks associated with marine diesel bunkering operation as well as
the associated escalation effect have been considered in the QRA hazard to life
assessment. The associated risk
impacts to the off-site population is insignificant.
Hazardous
scenarios associated with the operation of the LNG Terminal, including an LNGC
unloading at the LNG Terminal and sending out natural gas were identified
through the following tasks:
¡P Review
of hazardous materials;
¡P Review
of potential MAEs;
¡P Review
of relevant industry incidents;
¡P Review
of potential initiating events leading to MAEs; and
¡P HAZID
Workshop.
LNG on board the LNGC and FSRU Vessel, and natural gas associated with the LNG Terminal were the major
hazardous material considered
in the QRA Study, while the other dangerous goods including diesel, marine
diesel oil, lubricating oil, sodium
hypochlorite,
hydrogen and nitrogen
were also taken into account in the QRA Study.
The details of the storage of LNG and other
dangerous goods associated with the LNG Terminal are summarised in Table 5.10.
Table 5.10 LNG and Other Dangerous Goods
Associated with the LNG Terminal
Chemical |
Location |
Dangerous
Goods Classification* |
Maximum
Storage Quantity |
Temperature (¢XC) |
Pressure (barg) |
LNG |
FSRU
Vessel |
- |
270,000
m3 |
-163 |
5 |
Natural gas |
FSRU
Vessel |
- |
On-site
generation |
5 |
88 |
Diesel (Heavy
Fuel Oil) |
FSRU
Vessel |
Category
5 |
~6,000
m3 |
25 |
ATM |
Marine Diesel
Oil |
FSRU
Vessel |
Category
5 |
≤ 800 m3 |
25 |
ATM |
Diesel Oil |
Jetty |
Category
5 |
~50 m3 |
25 |
ATM |
Lubricating
Oil |
FSRU
Vessel |
- |
≤ 100 m3 |
25 |
ATM |
Sodium Hypochlorite |
FSRU
Vessel |
Category
4 |
On-site
generation |
- |
- |
Hydrogen |
FSRU Vessel |
Category 2 |
By-product of Electrochlorination System |
- |
- |
Nitrogen |
FSRU Vessel |
Category 2 |
On-site
generation |
- |
- |
Calibration
Gas^ |
FSRU Vessel |
Category 2 |
1 cylinder |
25 |
137 |
Notes:
*: The dangerous goods category is classified based on
¡§Fire Protection Notice No. 4, Dangerous Goods General¡¨ by Fire Services
Department (1).
^:
The
key composition of the calibration gas for Gas Chromatograph is methane (90
vol%), ethane (5 vol%), Nitrogen (2.5 vol%), and carbon dioxide (1 vol%) and
propane (1 vol%).
A detailed description of the LNG, diesel, marine
diesel oil and lubricating oil hazards is provided in Section 5.4.2, while
natural gas,
sodium hypochlorite,
hydrogen, and nitrogen hazards are discussed in the following section.
Natural
Gas
Upon
the regasification of LNG, natural gas is formed. Natural gas is composed of primary
methane gas with other fossil fuels such as ethane, propane, butane and
pentane, etc. Natural gas is
extremely flammable when mixed with appropriate concentration of air or oxygen
in the presence of an ignition source.
Not
only is the maximum surface emissive power of pure methane higher, but the
consequence distances for both flash fire and jet fire hazardous scenarios
associated with pure methane is larger than that of natural gas. Therefore, pure methane has been conservatively
selected as representative material for natural gas in the consequence
modelling conducted using PHAST.
The
major hazards arising from loss of containment of natural gas may lead to
hazardous scenarios including jet fire, flash fire, and vapour cloud explosion
(VCE).
Sodium
Hypochlorite (NaOCl)
Chemical Abstracts Service
(CAS) number of NaOCl is 7681-52-9, and NaOCl solution is a corrosive liquid
with the appearance of colourless to yellowish, and with a chlorine-like
odour. NaOCl is not flammable, but
it can decompose and release corrosive chorine gas if in contact with
acids. NaOCl is produced by an
electrochlorination system on board the FSRU Vessel which is a continuous
process and does not rely on any stored chlorine gas or hypochlorite brought
from off-site.
The expected off-site impact
associated with decomposition of the solution is limited. Also, once generated on board the FSRU
Vessel, NaOCl is consumed immediately for treatment of seawater. Therefore, NaOCl was not further
assessed in the QRA Study.
Hydrogen
CAS
number of hydrogen is 1333-74-0, and hydrogen is a colourless and odourless gas
at ambient temperature and pressure.
It has a boiling point of -253 ¢XC at 1 bara, critical temperature of -240 ¢XC and critical
pressure of 13 bara.
Hydrogen
gas, produced as by-product during the sodium hypochlorite generation process,
flows through the outlet header to the hydrocyclones. Hydrogen degassing happens in the
hydrocyclones, and hydrogen is diluted by an air blower before venting to atmosphere. Considering no heat source in the
vicinity of the vent stack, the likelihood for small amount of hydrogen to be
ignited is limited and any risk impact will only be localized. As such, the risks associated with
sodium hypochlorite generation process have not been modelled in the QRA
Study.
Hydrogen
gas is extremely flammable in oxygen and air, and has the widest range of
flammable concentrations in air among all common gaseous hydrocarbons. A limited amount of hydrogen is
generated on-board and hence not foreseen to have risk impact on off-site
population. Therefore, hydrogen gas
was not further assessed in the QRA Study.
Nitrogen
CAS
number of nitrogen is 7727-37-9,
nitrogen is a nontoxic, odourless, colorless, non-flammable compressed gas generated
on board the
FSRU Vessel. However, it can cause
rapid suffocation when concentrations are sufficient to reduce oxygen levels
below 19.5%.
The expected off-site impact
associated with nitrogen is limited as nitrogen is generated for the purpose of
inert gas purging after LNG unloading operation. Therefore, nitrogen was not further
assessed in the QRA Study.
Calibration Gas
The
volume of the compressed gas inside the cylinders is limited and the associated
inventory available is small, and also those compressed gas cylinders are
located at machinery room. Should
loss of containment occur for compressed gas cylinders, there is no off-site
impact on the surrounding marine population. Hence, it is not further assessed in the
QRA Study.
The possible hazardous
scenarios considered in the QRA Study upon the release of LNG with
consideration of operating conditions are:
¡P Jet fire;
¡P Pool
fire;
¡P Flash
fire; and
¡P VCE.
The possible hazardous scenarios
considered in the QRA Study upon the release of high pressure natural gas with
consideration of operating conditions are:
¡P Jet fire;
¡P Flash
fire;
¡P Fireball;
and
¡P VCE.
Considering that the Jetty
and the regasification unit on board the FSRU Vessel are relatively congested,
a VCE may potentially occur if flammable gas cloud accumulate in these
congested areas and is ignited, leading to damaging overpressure.
Considering the high flash
point temperature of other dangerous goods such as marine diesel oil present in
the FSRU Vessel, the possible hazardous scenarios considered in the QRA Study
are a pool fire and flash fire.
Detailed
characteristics and modelling of the above hazardous scenarios are described in
Annex 5G.
To investigate further the
possible hazardous scenarios from the FSRU Vessel, the Jetty and the LNGC unloading
operation, a review of the applicable past industry incidents at similar
facilities worldwide was conducted based on the following incident/ accident
database:
¡P Institution
of Chemical Engineers (IChemE) accident database;
¡P
eMARS ([19]);
¡P
ERNS ([20]);
¡P MHIDAS
database ([21]);
and
¡P SIGTTO
([22]).
Details of the past industry incident analysis are
presented in Annex 5C.
The potential
hazardous scenarios arising from the LNG Terminal were identified as loss of
containment of LNG, natural gas and other dangerous goods. The potential initiating events which
could result in the loss of containment of flammable material including LNG,
natural gas and diesel are listed below:
¡P Collision
with other passing / visiting marine vessels;
¡P Mooring
line failure;
¡P Dropped
objects from crane operations on FSRU Vessel;
¡P General
equipment/piping failure (due to corrosion, construction defects etc.);
¡P Sloshing;
¡P LNG
containment system failure; and
¡P External
effects - adverse weather (typhoon, poor visibility, storm surge, extreme
tide), tsunami, lightning, aircraft crash and helicopter crash.
Descriptions
of the potential initiating events are presented in Annex 5D.
A
HAZID workshop was conducted to confirm and further identify the potential
initiating events which may lead to MAEs at the LNG Terminal based on the HAZID team representative¡¦s
experience, past industry accidents, lessons learnt and guideword
checklists. The HAZID workshop
worksheet is summarised in Annex 5E.
The HAZID workshop output served as a basis for the identification of
potential initiating events and hazardous scenarios for the QRA Study.
The
collision frequency at the Jetty was estimated based on the frequency of marine
vessels that are likely to be in the vicinity of the LNG Terminal. As a conservative approach, the ship
collision frequency in Segment ¡§b¡¨ in Table 5.4 (Approaching
the LNG Terminal) was adopted as the Jetty collision frequency in the QRA
Study.
A
total of twenty five (25) hazardous sections were identified from the LNG
Terminal, with consideration of the location of emergency shutdown valves and
process conditions (e.g. operating temperature and pressure). The details of each hazardous section
(including temperature, pressure, flow rate, etc.) are summarised in Annex 5D. These hazardous sections formed the
basis for the development of loss of containment scenarios.
The
historical database from the International Association of Oil and Gas Producers
(OGP) ([23])
was adopted in the QRA Study for estimating the release frequency of
hazardous scenarios associated with the LNG Terminal. The release frequency in OGP is based on
the analysis of the HSE hydrocarbon release database (HCRD) which collected all
offshore releases of hydrocarbon in the UK (including the North Sea) reported
to the HSE Offshore Division from 1992-2006. Considering that the LNG Terminal is
located in an offshore environment in HKSAR waters, this database was
considered adequate for purpose of this QRA Study.
The
release frequencies of various equipment items are summarised in Table 5.11, and
the detailed discussion on the failure frequency is presented in Annex 5F.
Table 5.11 Release Frequency
Equipment |
Release
Scenario |
Release Phase |
Release Frequency |
Unit |
Reference |
Piping 2¡¨ to
6¡¨ |
10 mm hole |
Liquid/ Gas |
3.45E-05 |
per metre per
year |
OGP |
|
25 mm hole |
Liquid/ Gas |
2.70E-06 |
per metre per
year |
OGP |
|
50 mm hole |
Liquid/ Gas |
6.00E-07 |
per metre per
year |
OGP |
Piping 8¡¨ to
12¡¨ |
10 mm hole |
Liquid/ Gas |
3.06E-05 |
per metre per
year |
OGP |
|
25 mm hole |
Liquid/ Gas |
2.40E-06 |
per metre per
year |
OGP |
|
50 mm hole |
Liquid/ Gas |
3.70E-07 |
per metre per
year |
OGP |
|
>150 mm
hole |
Liquid/ Gas |
1.70E-07 |
per metre per
year |
OGP |
Piping 14¡¨ to
18¡¨ |
10 mm hole |
Liquid/ Gas |
3.05E-05 |
per metre per
year |
OGP |
|
25 mm hole |
Liquid/ Gas |
2.40E-06 |
per metre per
year |
OGP |
|
50 mm hole |
Liquid/ Gas |
3.60E-07 |
per metre per
year |
OGP |
|
>150 mm
hole |
Liquid/ Gas |
1.70E-07 |
per metre per
year |
OGP |
Piping 20¡¨ to
24¡¨ |
10 mm hole |
Liquid/ Gas |
3.04E-05 |
per metre per
year |
OGP |
|
25 mm hole |
Liquid/ Gas |
2.40E-06 |
per metre per
year |
OGP |
|
50 mm hole |
Liquid/ Gas |
3.60E-07 |
per metre per
year |
OGP |
|
>150 mm
hole |
Liquid/ Gas |
1.60E-07 |
per metre per
year |
OGP |
Piping 26¡¨ to
48¡¨ |
10 mm hole |
Liquid/ Gas |
3.04E-05 |
per metre per
year |
OGP |
|
25 mm hole |
Liquid/ Gas |
2.30E-06 |
per metre per
year |
OGP |
|
50 mm hole |
Liquid/ Gas |
3.60E-07 |
per metre per
year |
OGP |
|
>150 mm
hole |
Liquid/ Gas |
1.60E-07 |
per metre per
year |
OGP |
Pressure Vessel - Large Connection (> 6¡¨) |
10 mm hole |
Liquid/ Gas |
5.90E-04 |
per year |
OGP |
25 mm hole |
Liquid/ Gas |
1.00E-04 |
per year |
OGP |
|
50 mm hole |
Liquid/ Gas |
2.70E-05 |
per year |
OGP |
|
>150 mm
hole |
Liquid/ Gas |
2.40E-05 |
per year |
OGP |
|
Pump Centrifugal - Small Connection (up to 6¡¨) |
10 mm hole |
Liquid |
4.40E-03 |
per year |
OGP |
25 mm hole |
Liquid |
2.90E-04 |
per year |
OGP |
|
50 mm hole |
Liquid |
5.40E-05 |
per year |
OGP |
|
Pump Centrifugal - Large Connection (> 6¡¨) |
10 mm hole |
Liquid |
4.40E-03 |
per year |
OGP |
25 mm hole |
Liquid |
2.90E-04 |
per year |
OGP |
|
50 mm hole |
Liquid |
3.90E-05 |
per year |
OGP |
|
>150 mm
hole |
Liquid |
1.50E-05 |
per year |
OGP |
|
Compressor Reciprocating - Large Connection (> 6¡¨) |
10 mm hole |
Gas |
3.22E-02 |
per year |
OGP |
25 mm hole |
Gas |
2.60E-03 |
per year |
OGP |
|
50 mm hole |
Gas |
4.00E-04 |
per year |
OGP |
|
>150 mm
hole |
Gas |
4.08E-04 |
per year |
OGP |
|
Shell and Tube Heat Exchanger - Large Connection (>
6¡¨) |
10 mm hole |
Liquid/Gas |
1.20E-03 |
per year |
OGP |
25 mm hole |
Liquid/Gas |
1.80E-04 |
per year |
OGP |
|
50 mm hole |
Liquid/Gas |
4.30E-05 |
per year |
OGP |
|
>150 mm
hole |
Liquid/Gas |
3.30E-05 |
per year |
OGP |
|
Unloading Arm |
10 mm hole |
Liquefied Gas |
4.00E-06* |
per transfer operation |
UK HSE ([24]) |
|
25 mm hole |
Liquefied Gas |
4.00E-06* |
per transfer operation |
UK HSE (1) |
|
>150 mm
hole |
Liquefied Gas |
7.00E-06 |
per transfer operation |
UK HSE (1) |
Riser |
10 mm hole |
Gas |
7.2E-05 |
per year |
OGP |
|
25 mm hole |
Gas |
1.8E-05 |
per year |
OGP |
|
>150 mm
hole |
Gas |
3.0E-05 |
per year |
OGP |
Diesel Storage
Tank |
10 mm hole |
Liquid |
1.6E-03 |
per year |
OGP |
25 mm hole |
Liquid |
4.6E-04 |
per year |
OGP |
|
50 mm hole |
Liquid |
2.3E-04 |
per year |
OGP |
|
Rupture |
Liquid |
3.0E-05 |
per year |
OGP |
|
Unloading Hose |
10 mm hole |
Liquid |
1.3E-05# |
per hour |
Purple Book ([25]) |
|
25 mm hole |
Liquid |
1.3E-05 |
per hour |
Purple Book |
|
50 mm hole |
Liquid |
1.3E-05 |
per hour |
Purple Book |
|
Rupture |
Liquid |
4.0E-06 |
per hour |
Purple Book |
LNG Storage
Tank |
10 mm hole |
Liquid |
3.3E-06! |
per year |
OGP |
|
25 mm hole |
Liquid |
3.3E-06! |
per year |
OGP |
|
50 mm hole |
Liquid |
3.3E-06! |
per year |
OGP |
|
Rupture |
Liquid |
2.5E-08 |
per year |
OGP |
*Notes: The leak
frequency of unloading arm, presented in the UK HSE (1), has been
evenly distributed into 10 mm and 25 mm hole sizes.
#Notes: The leak
frequency of unloading hose, presented in the Purple Book (2), has been
evenly distributed into 10 mm, 25 mm and 50 mm hole sizes.
!Notes: The leak frequency of LNG storage tank,
presented in OGP, has been evenly distributed into 10 mm, 25 mm and 50 mm hole sizes.
The
release hole sizes presented in Table 5.12,
which are consistent with the OGP ([26]) database, were
adopted in the QRA Study.
Table 5.12 Hole Sizes Considered in the QRA Study
Leak Description |
Hole Size |
Very Small
Leak |
10 mm |
Small Leak |
25 mm |
Medium Leak |
50 mm |
Rupture |
>150 mm |
With
reference to the Purple Book ([27]),
the effect of block valve system is determined by various factors, such as the
position of gas detection monitors and the distribution thereof over the
various wind directions, the direction limit of the detection system, the
system reaction time and the intervention time of an operator. The probability of failure on demand of
the block valve system as a whole is 0.01 per demand.
Considering
that the LNG Terminal is provided with gas detection systems and automatic
emergency shutdown systems, the probability of executing the isolation
successfully when required was selected as 99% in the QRA Study.
The
immediate ignition probability was estimated based on offshore ignition
scenarios No. 24 from the OGP Ignition Probability Database (1). For flammable liquids with flash point
of 55¢XC or higher (e.g. diesel, fuel oil etc.), a modification factor of 0.1
was applied to reduce the ignition probability as suggested in OGP (1).
The
delayed ignition for various ignition sources was referred to Appendix 4.A of
the Purple Book (2).
The probability of explosion
given an ignition was taken from the Cox, Lees and Ang model ([28]), as shown in Table 5.13. VCE occurs upon a delayed ignition from
a flammable gas release at a congested area. Details of the identified congested area
and congestion volume are provided in Annex 5G.
Table 5.13 Probability of
Explosion
Leak Size (Release Rate) |
Explosion Probability |
Minor (< 1 kg s-1) |
0.04 |
Major (1 ¡V 50 kg s-1) |
0.12 |
Massive (> 50 kg s-1) |
0.30 |
An initially
small release may escalate into a larger, more serious event if a jet fire or
pool fire impinges on neighbouring equipment/ piping for an extended time. This is taken into account in the
modelling for isolation fail branch of the event tree, depicted in Figure 5F.3.
If
neighbouring equipment/ piping is within range of the jet fire event flame
zone, an escalation probability of 1/6 ([29]) ([30])
has been taken to conservatively estimate the directional probability and
chance of impingement. In case pool
fire events, the escalation probability was conservatively estimated without
considering any directional probability.
Escalation
has been assumed to cause only a full bore rupture of the affected equipment
and piping, leading to fireball event as the worst-case scenario.
An
event tree analysis was performed to model the development of each hazardous
scenario outcome (jet fire, pool fire, flash fire, fireball and VCE) from an
initial release scenario. The event
tree analysis considered whether there is immediate ignition, delayed ignition
or no ignition, with consideration of the associated ignition probability as
discussed above. The development of
the event tree is presented in Annex 5F.
PHAST was used to estimate the release
rates, which were used to determine the ignition probability. Source term modelling was carried out to
determine the maximum (e.g. initial) release rate that may be expected should a
loss of containment occur.
With reference to the Purple Book ([31]), the closing time of
an automatic block valve system is two (2) minutes; hence a release duration of
two (2) minutes was adopted for isolation success case in the QRA Study. Detection and shutdown system may
however fail due to some reasons.
As per the Purple Book (3), the release duration is limited to a maximum
of thirty (30) minutes, therefore this was conservatively adopted for the
isolation failure case in the QRA Study.
The
orientation of a release can have some effects on the hazard footprint
calculated by PHAST. The models take into account the
momentum of the release, air entrainment, vapourisation rate and liquid rainout
fraction.
¡§Horizontal
non-impinging¡¨ was selected for modelling the jet fire and flash fire scenarios
since the associated hazard footprint is more conservative. ¡§Downward impinging¡¨ was selected for
modelling the pool fire scenario since the momentum of the release is reduced,
thereby increasing the liquid rainout fraction.
PHAST was used to perform the physical effects modelling to
assess the effects zones for the following hazardous scenarios:
¡P Jet
fire;
¡P Pool
fire;
¡P Flash
fire;
¡P Fireball;
and
¡P VCE.
Detailed description of the physical effects modelling
is presented in Annex 5G.
Similarly, as stated in Section
5.4.4, the
probit equation was used for assessing the thermal radiation impact and the end
point criteria for flash fire, were also adopted in the QRA Study for the LNG
Terminal.
The
fatality rate within the fireball diameter is assumed to be 100%.
In
terms of overpressure, a relatively high overpressure is necessary to lead to
significant fatalities for persons outdoor. Indoor population tends to have a higher
harm probability due to the risk of structural collapse and flying debris such
as breaking windows. Table 5.14
presents the explosion overpressure levels from the Purple Book ([32]),
which were adopted in the QRA Study.
Table 5.14 Effect of Overpressure - Purple Book
Explosion
Overpressure (barg) |
Fraction of People Dying |
|
|
Indoor |
Outdoor |
> 0.3 |
1.000 |
1.000 |
> 0.1 to 0.3 |
0.025 |
0.000 |
Details of the consequence
modelling results are presented in Annex 5G.
The
risk summation for the LNG Terminal was modelled using SAFETI, which is in line with the previous EIA Report that was
approved by EPD ([33]). The hazardous scenarios, the associated
frequencies, meteorological data, surrounding off-site population data, and
suitable modelling parameters identified were input into SAFETI.
Before
commissioning, no LNG, natural gas and other dangerous goods are present at the
LNG Terminal in the baseline condition (Year 2017); therefore, the baseline
condition assessment was not considered in the QRA Study. In addition, there is no other hazardous
installation such as a Potentially Hazardous Installation (PHI) in the vicinity
of the LNG Terminal which leads to an increase in cumulative risk.
The
cumulative risk was calculated by summing various types of process risks from
the LNG Terminal, including the FSRU Vessel, the Jetty and LNGC unloading
operation as summarised in Table 5.15.
Table 5.15 Potential Risks Considered in the
Cumulative Risk Assessment
Potential Risk |
2020 |
2030 |
FSRU Vessel,
covering LNG, natural gas, other dangerous goods, for all operating modes |
Yes |
Yes |
Jetty with
topsides equipment, for all operating modes |
Yes |
Yes |
LNGC during LNG
unloading operations |
Yes |
Yes |
The
individual risk contours for the LNG Terminal are shown in Figure 5.7
to Figure 5.8. The individual risk contour of 1 ¡Ñ 10-5
per year in the Operational Year in 2020 and Future Scenario Year in 2030 is
identified to be within the Safety Zone within the Project Site (Section 3.3). All access into the Project Site must be
authorized by the Terminal Operator such that no off-site population will be
present within the Project Site.
Consequently, the
maximum level of off-site individual risk (i.e. outside Safety Zone of the LNG
Terminal) associated with the Hong Kong Offshore LNG Terminal Project would not
exceed 1¡Ñ10-5 per year and the individual risk
criterion stipulated in Section 2 of Annex 4 of the EIAO-TM
is met.
The
societal risk for the LNG Terminal was calculated based on the associated
process risks and the surrounding off-site marine traffic populations in the
vicinity of the Project Site. The societal risk, in terms
of F-N curves, for Operational Year in 2020 and Future Scenario Year in 2030,
as shown in Figure 5.9,
lie within the Acceptable Region, as such the societal risk criteria stipulated
in Section 2 of Annex 4 of the EIAO-TM are met.
The key risk contributors, in
terms of potential loss of life, associated with the LNG Terminal are summarised
in Annex 5H.
The individual risk
associated with the LNG Terminal is in compliance with the individual risk
criterion stipulated in Section 2 of Annex 4 of the EIAO-TM.
The
societal risks, in terms of F-N curves, are within the Acceptable Region and
are in
compliance with societal risk criteria stipulated in Section 2 of Annex 4
of the EIAO-TM.
This Section
presents the
QRA Study for the evaluation of the risks associated with the subsea BPPS and
LPS Pipelines from the Jetty to the proposed GRS facilities at the BPPS and the
LPS.
The 30¡¨
diameter subsea BPPS Pipeline route commences at the tie-in point to the pig
launcher on the Jetty and ends at the proposed GRS at the BPPS. The length of the subsea BPPS
pipeline is approximately 45 km.
The
20¡¨ diameter subsea LPS Pipeline route commences at the tie-in point to the pig
launcher on the Jetty and ends at the proposed GRS at the LPS. The length of the subsea LPS pipeline is
approximately 18 km.
In
order to examine the risks along the BPPS and LPS Pipeline, it is first
necessary to identify the types of vessel that will traverse across the
pipeline then segregate the alignment accordingly for assessment and this has
been defined as ¡§segment¡¨. This has
been done on the basis of water depth which is linked with marine traffic
activity (summarised from Table 5A.7 to Table 5A.10 of Annex 5A),
as water depth (indicated in Figure
1.2 of Annex 7B)
is a constraint to navigation. The
water depth along both BPPS and LPS Pipeline route was reviewed within a GIS
system based on Hong Kong Electronic Navigational Chart.
The segmentation
is also used for trench design of pipeline routes; the principle being that the
busier pipeline sections with the larger vessels (hence larger anchor size)
required a greater level of trench design and rock berm pipeline protection in
these BPPS Pipeline and LPS Pipeline segments.
Based
on above considerations, the BPPS and LPS Pipeline routes were divided into
eleven (11) and four (4) segments respectively as shown in Figure 5.10
and are presented in Table 5.16 and Table 5.17 respectively.
Table 5.16 BPPS Pipeline Segmentation*
Segment |
KP- From (km) |
KP- To (km) |
Water
Depth# (m) |
Length (km) |
Trench type* |
Protection Anchor Size (T) ([34]) |
||
X |
Jetty Approach to South of Soko
Islands |
0.0 |
8.9 |
15 |
9.2 |
8.9 |
4 |
<24 |
A |
Southwest of Soko Islands |
8.9 |
12.1 |
9.2 |
12.0 |
3.2 |
5 |
<5 |
B |
Southwest of Fan Lau |
12.1 |
15.6 |
12.0 |
12.9 |
3.5 |
5 |
<5 |
C |
Southwest Lantau |
15.6 |
21.3 |
12.9
|
10.6 |
5.7 |
2 |
< 7.3 |
D |
West of Tai O |
21.3 |
26.2 |
10.6 |
7.7 |
4.9 |
5 |
<5 |
E |
West of HKIA |
26.2 |
31.5 |
7.7 |
4.6 |
5.3 |
5 |
<5 |
F |
West of Sha Chau |
31.5 |
36.0 |
4.6 |
6.0 |
4.5 |
5 |
<5 |
G |
West of Lung Kwu Chau |
36.0 |
37.5 |
6.0 |
3.1 |
1.5 |
3 |
< 10.6 |
H |
Lung Kwu Chau to Urmston Anchorage |
37.5 |
41.1 |
3.1
|
4.8 |
3.6 |
5 |
<5 |
I |
Urmston Road |
41.1 |
42.9 |
4.8 |
5.6 |
1.8 |
4 |
< 24 |
J |
West of BPPS |
42.9 |
45.0 |
5.6 |
1.6 |
2.1 |
5/1 |
<5 |
*Proposed pipeline
construction methods and trench types are subject to further review with
government departments. The
lowest protection anchor size for each segment was used for the risk modelling.
#:Source: 2016, Charts for Local Vessels, The
Hydrographic Office Marine Department; depths are measured at KP Point in
meters and are reduced to Chart Datum
Table 5.17 Subsea LPS
Pipeline Segmentation*
Segment |
KP- From (km) |
KP- To (km) |
Water
Depth# (m) |
Length (km) |
Trench type* |
Protection Anchor Size (T) (1) |
||
A |
Jetty Approach
to South of Shek Kwu Chau |
0.0 |
5.0 |
15.0 |
14.4 |
5.0 |
4 |
<24 |
B |
South of
Cheung Chau |
5.0 |
14.5 |
14.4 |
15.5 |
9.5 |
5 |
<5 |
C |
West Lamma
Channel |
14.5 |
17.4 |
15.5 |
15.7 |
2.9 |
5 |
<5 |
D |
Alternative
Shore Approach |
17.4 |
18.2 |
15.7 |
2.6 |
0.8 |
1 |
<5 |
*Proposed
pipeline construction methods and trench
types are subject to further review with government departments.
#:Source:
2016, Charts for Local Vessels, The Hydrographic Office Marine Department; depths
are measured at KP Point in meters and are reduced to Chart Datum
Different
levels of armour rock protection will be provided for each segment of the
proposed BPPS and LPS Pipelines based on the identified potential anchor drag
and drop hazards. The cross sections of the
trench designs and associated armour rock protection are illustrated in Section
3 of the EIA Report.
With
consideration of the armour rock protection for the subsea pipelines, the
following pipeline protection factors ([35]) were adopted in the
QRA Study:
¡P 99.99%
is applied, if the vessel anchor size is smaller than the intended design
capacity of the pipeline protection; and
¡P
0% is applied, if the vessel anchor size is larger than
the intended design capacity of the pipeline protection.
The
hazardous scenarios associated with the two subsea pipelines were identified
through the following tasks:
¡P Review
of hazardous materials;
¡P Review
of potential MAEs;
¡P Review
of relevant industry incidents;
¡P Review
of potential initiating events leading to MAEs; and
¡P HAZID
Workshop.
The
high pressure natural gas is sent out from the LNG Terminal through the BPPS
and LPS subsea Pipelines to the GRSs at the BPPS and the LPS. The only identified hazard arising from
loss of containment of high pressure natural gas from these subsea pipelines is
flash fire. The properties of
natural gas have been described in Section 5.5.2.
In
the event of any leakage or rupture of either the BPPS or LPS Pipelines leading
to loss of containment, the flammable gas will bubble to the surface of the
sea, and then disperse. The only
possible hazardous scenario associated with any leakage or rupture of either of
the subsea pipelines is flash fire if the dispersing flammable gas cloud comes
in contact with an ignition source, most likely from a passing marine vessel.
Detailed
characteristics of the above hazardous effect are described in Annex 5G.
To investigate further the
possible hazardous scenarios related to BPPS and LPS pipelines, a review of the
applicable past industry incidents at similar facilities worldwide was
conducted based on following incident/ accident database:
¡P MHIDAS
database;
¡P Institution
of Chemical Engineers (IChemE) accident database;
¡P US
Gas Pipeline Incident Database;
¡P Pipeline
and Riser Loss of Containment (PARLOC); and
¡P Incident
Records for Subsea Pipelines in Hong Kong waters.
Details of
the past industry incident analysis are presented in Annex 5C.
The
key potential hazardous scenarios arising from the subsea pipelines were
identified as the loss of containment of natural gas. The potential initiating events which
could result in the loss of containment of natural gas are listed below:
¡P Anchor
drop and drag;
¡P Grounding;
¡P Vessel
sinking;
¡P Aircraft
crash;
¡P Fishing
activity;
¡P Dredging
activity;
¡P Subsea
cable maintenance activity;
¡P General
pipeline failure (due to corrosion, construction defects etc.);
¡P Pressure
cycling; and
¡P External
effects - adverse weather (typhoon, storm surge, extreme tide), subsidence, and
tsunami.
Descriptions
of the potential initiating events are presented in Annex 5D.
A
HAZID workshop was conducted to confirm and further identify the potential
initiating events which may lead to MAEs along the subsea pipelines, based on the HAZID team
representative¡¦s experience, past industry accidents, lessons learnt and
guideword checklists. The HAZID
workshop worksheet is summarised in Annex 5E.
The HAZID workshop output was served as a basis for identification of
potential initiating events and hazardous scenarios for the QRA Study.
The
whole BPPS and LPS pipelines were considered as the hazardous section with the
consideration of emergency shut down valves available at the Jetty and the GRS
area at the BPPS and the LPS respectively.
The
selected release frequency database is consistent with the previous EIA Reports
which have been approved
by the EPD ([36])
([37]). The frequency of the major causes such
as corrosion, material defect, anchor drop and impact incidents leading to a
loss of containment from the subsea pipelines was estimated based on the international
database, including PARLOC 2012 ([38])
and PARLOC 2001 ([39]). A local incident database was also
reviewed and compared with the PARLOC
database. The detailed discussion
and analysis of the release frequency estimation are presented in Annex 5F. The release frequencies adopted in the
QRA Study are summarized in Table 5.18 and Table 5.19.
Table 5.18 Summary of
Release Frequency along BPPS Pipeline
Pipeline
Section |
Trench Type |
Anchor Impact (/km/yr) |
Corrosion/ Defects (/km/yr) |
Others (/km/yr) |
Total (/km/yr)* |
Jetty Approach to South of
Soko Islands (X) |
4 |
1.25E-05 |
1.18E-06 |
7.90E-07 |
2.30E-06 |
Southwest of Soko Islands
(A) |
5 |
1.25E-05 |
1.18E-06 |
7.90E-07 |
2.69E-06 |
Southwest of Fan Lau (B) |
5 |
1.77E-04 |
1.18E-06 |
7.90E-07 |
1.99E-06 |
Southwest Lantau (C) |
2 |
9.49E-05 |
1.18E-06 |
7.90E-07 |
5.85E-06 |
West of Tai O (D) |
5 |
9.49E-05 |
1.18E-06 |
7.90E-07 |
1.98E-06 |
West of HKIA (E) |
5 |
9.49E-05 |
1.18E-06 |
7.90E-07 |
1.98E-06 |
West of Sha Chau (F) |
5 |
9.49E-05 |
1.18E-06 |
7.90E-07 |
1.98E-06 |
West of Lung Kwu Chau (G) |
3 |
1.77E-04 |
1.18E-06 |
7.90E-07 |
1.99E-06 |
Lung Kwu Chau to
Urmston Anchorage (H) |
5 |
1.77E-04 |
1.18E-06 |
7.90E-07 |
1.99E-06 |
Urmston Road (I) |
4 |
1.77E-04 |
1.18E-06 |
7.90E-07 |
1.99E-06 |
West of BPPS (J) |
5/1 |
9.49E-05 |
1.18E-06 |
7.90E-07 |
1.98E-06 |
Note: The armour
rock protection factor for the subsea pipeline has been taken into account in
the total release frequency.
Table 5.19 Summary of
Release Frequency along LPS Pipeline
Pipeline
Section |
Trench Type |
Anchor Impact (/km/yr) |
Corrosion/ Defects (/km/yr) |
Others (/km/yr) |
Total (/km/yr) * |
Jetty
Approach to South of Shek Kwu Chau (A) |
4 |
1.32E-05 |
1.18E-06 |
7.90E-07 |
1.97E-06 |
South
of Cheung Chau (B) |
5 |
1.32E-05 |
1.18E-06 |
7.90E-07 |
1.97E-06 |
West
Lamma Channel (C) |
5 |
1.32E-05 |
1.18E-06 |
7.90E-07 |
1.97E-06 |
Alternative
Shore Approach (D) |
1 |
5.95E-05 |
1.18E-06 |
7.90E-07 |
1.98E-06 |
Note: The armour
rock protection factor for the subsea pipeline has been taken into account in
the total release frequency.
The
international databases (such as PARLOC
2012 and PARLOC 2001) were
reviewed. The hole size
distributions for anchor impact scenarios and corrosion/other scenarios are
given in Table 5.20 and Table 5.21, are
consistent with previous EIA Reports which have been approved by the EPD ([40]). Detailed analysis of the derivation of
the hole size distribution is provided in Annex 5F.
Table 5.20 Hole Size Distribution for Anchor
Impact Cases
Category |
Hole Size (Subsea BPPS Pipeline) |
Hole Size (Subsea LPS Pipeline) |
Proportion |
Rupture (Full
Bore) |
Full Bore |
Full Bore |
10% |
Major |
15¡¨or 381 mm
(Half Bore) |
10¡¨or 254 mm
(Half Bore) |
20% |
Minor |
4¡¨or 100 mm |
4¡¨ or 100 mm |
70% |
Table 5.21 Hole Size
Distribution for Corrosion and Other Failure Cases
Category |
Hole Size (Subsea BPPS Pipeline) |
Hole Size (Subsea LPS Pipeline) |
Proportion |
Rupture (Half
Bore) |
15¡¨ or 381 mm |
10¡¨ or 254 mm |
5% |
Puncture |
4¡¨or 100 mm |
4¡¨or 100 mm |
15% |
Hole |
2¡¨or 50 mm |
2¡¨or 50 mm |
30% |
Leak |
<25 mm |
<25 mm |
50% |
The
ignition of any release natural gas is expected only from passing vessels in the
vicinity of either subsea pipeline.
The ignition probabilities consistent with previous EIA Reports which have
been approved by the EPD ([41])
([42]),
were adopted in the QRA Study and are summarised in Table 5.22.
Table 5.22 Ignition Probability for Subsea
Pipeline
Release Case |
Ignition Probability |
|
|
Passing
Vessels* |
Vessels in
Vicinity# |
<25 mm |
0.01 |
n/a |
50 mm |
0.05 |
n/a |
100 mm |
0.10 |
0.15 |
Half bore |
0.20 |
0.30 |
Full bore |
0.30 |
0.40 |
Note:
*: Values
applied to passing vessels for all types of incidents, i.e. corrosion, others
and anchor impact.
#: Values applied only to scenarios
where the vessel causing pipeline damage due to anchor impact is still in the
vicinity.
An
event tree analysis was performed to model the development of each hazardous
scenario outcome (flash fire) from an initial release scenario. The event tree analysis considered
whether there is delayed ignition or no ignition, with consideration of the
associated ignition probability as discussed above. The development of the event tree
analysis is presented in Annex 5F.
The
release rate was estimated based on standard equations for discharge through an
orifice. As per previous EIA
Reports which have
been approved by the EPD ([43])
([44]), for
large release with hole size greater than 100 mm, the empirical correlation
developed by Bell and modified by Wilson ([45]) was adopted in the
QRA Study. Detailed explanation of
source term modelling is provided in Annex 5G.
In
the event of a flammable gas release from the subsea pipelines, the flammable
gas will bubble to the sea surface and disperse. As per previous EIA Reports (1) (2) which have
been approved by the EPD, a simple cone model was adopted to determine the
release area on the sea surface.
For the deepest water depth (i.e. about 25 m around Southwest of Fan Lau)
along the subsea pipelines, it was predicted by the cone model that the
diameter of the release area was about 10 m. Detailed explanation of the cone model
is provided in Annex 5G.
The flammable
gas disperses into atmosphere upon reaching the sea surface. The distance to which the flammable gas
envelope extends depends on ambient conditions such as wind speed and
atmospheric stability as well as source conditions. As per previous EIA Reports which have
been approved by the EPD (1)
(2), the extent of
the flammable area was taken as the distance to 0.85 LFL. PHAST
was used to model the plume dispersion as an area source on the sea
surface. Detailed explanation of
the dispersion modelling above sea surface is provided in Annex 5G.
The
consequence and impact assessment, as described below, was conducted as per
previous EIA Reports which
have been approved by the EPD (1) (2).
A
flash fire could cause injury to personnel on marine vessels. It may also cause secondary fires on the
marine vessel. If a marine vessel
passes close to the ¡¥release area¡¦ (where bubbles of natural gas break through
the sea surface), the consequences will be more severe and a 100% fatality
probability was taken for this scenario.
Once a fire has ignited, it is presumed that no further marine vessels
will be involved because the fire will be visible and other marine vessels can
take action to avoid the area. In
other words, at most only one marine vessel may be affected.
The
hazardous impact area of the flammable cloud was taken to be the distance to
0.85 LFL. Taking into account the
protection factors of various types of marine vessel, the fatalities adopted in
the QRA Study are as given in Table 5.23.
Table 5.23 Fatality Probability for Subsea
Pipelines¡¦ MAEs
Marine
Vessel Class |
Fatality Probability |
|
|
Release
Area |
Cloud
Area |
Fishing vessels |
1 |
0.9 |
Rivertrade coastal vessel |
1 |
0.3 |
Ocean-going vessels |
1 |
0.1 |
Fast launches |
1 |
0.9 |
Fast ferries |
1 |
0.4 |
Others |
1 |
0.3 |
Note: Release area indicates the area where gas
bubbles break through the sea surface; and cloud area indicates the hazardous
distance of 0.85 LFL of the flammable gas cloud.
In addition,
the probability that a marine vessel will pass through the flammable plume was
calculated based on the size of the plume (obtained from dispersion modelling)
and the marine traffic density.
Detailed
discussion on the estimation of the above probabilities is presented in Annex 5G.
The
BPPS Pipeline will pass under the Hong Kong Link Road (HKLR) at a location
within the West of Tai O Section.
The transient road traffic population on the bridge may be affected if a
flammable gas cloud is ignited under / in the vicinity of the bridge area. This hazardous scenario was considered
in the consequence analysis for the West of Tai O Section of the BPPS
Pipeline. The associated risk
impact did not make a significant contribution to the overall risk
results. Detailed assessment result
is presented in Annex 5G.
The
West of HKIA Section of the BPPS Pipeline is located in the vicinity of the
Hong Kong International Airport (HKIA).
Large gas releases from the BPPS Pipeline, such as those that occur from
a full bore or half bore rupture, may have the potential to produce a flammable
gas cloud that extends higher than 200 m.
It is therefore possible that an aircraft on its approach to landing may
pass through a gas cloud within the flammability limits. This scenario was considered in the
consequence analysis and it was observed that the associated risk did not make
a significant contribution to the overall risk results. Detailed assessment result is presented
in Annex 5G.
Helicopters
shuttling to and from Macau pass over the Southwest of Fan Lau
Section of the BPPS Pipeline at about 500 feet (150 m) altitude. Similarly, the above large gas releases
may impact on the helicopters. The hazard
distance was taken to be the maximum width of the gas cloud above 150 m
altitude. The associated risk
did not make a significant contribution to the overall risk results. Detailed assessment result is presented
in Annex 5G.
The
hazard distances that were used in the QRA Study were determined from the gas
dispersion modelling. The hazard
distance for marine vessels was defined as the maximum width of the gas cloud
below a height of 50 m above sea level.
Similarly, the hazard distance for aircraft was defined above as
200 m and for helicopters was defined as above 150 m from sea level. The hazard distances obtained from
dispersion modelling are summarised in Annex 5G.
The
risk summation for the BPPS and LPS Pipelines combines the estimation of the
consequences of an event with the event probabilities to give an estimate of
the resulting frequency of varying levels of fatalities. Risk summation was implemented in ERM¡¦s
proprietary risk integration package, which took into account input data for
initiating event frequency, event frequency, event tree branch probabilities,
number of exposed persons and fatality probability.
The individual risk contours associated with the BPPS
Pipeline and LPS Pipeline are shown in Table 5.24, Table 5.25, Table 5.26 and
Table
5.27 respectively for Operational Year in
2020 and Future Scenario Year in 2030.
The individual risk contour of 1 ¡Ñ 10-5 per
year was not reached for all sections of the subsea BPPS and LPS Pipelines in
both assessment years, as such the individual risk criterion stipulated in Section 2 of Annex 4 of the EIAO-TM is
met for the current proposed subsea pipeline design.
Table 5.24 Risk Results for BPPS Pipeline in 2020
¡V Operational Year
Segment |
IR (/km/year) |
IR (/year) |
|
X |
Jetty Approach to South of Soko
Islands |
3.53 ¡Ñ 10-8 |
3.14 ¡Ñ 10-7 |
A |
Southwest of Soko Islands |
4.20 ¡Ñ 10-8 |
1.34 ¡Ñ 10-7 |
B |
Southwest of Fan Lau |
7.80 ¡Ñ 10-9 |
2.73 ¡Ñ 10-8 |
C |
Southwest Lantau |
3.41 ¡Ñ 10-7 |
1.94 ¡Ñ 10-6 |
D |
West of Tai O |
3.10 ¡Ñ 10-8 |
1.52 ¡Ñ 10-7 |
E |
West of HKIA |
3.59 ¡Ñ 10-9 |
1.90 ¡Ñ 10-8 |
F |
West of Sha Chau |
1.18 ¡Ñ 10-9 |
5.31 ¡Ñ 10-9 |
G |
West of Lung Kwu Chau |
3.81 ¡Ñ 10-9 |
5.72 ¡Ñ 10-9 |
H |
Lung Kwu Chau to Urmston Anchorage |
3.54 ¡Ñ 10-9 |
1.27 ¡Ñ 10-8 |
I |
Urmston Road |
3.80 ¡Ñ 10-8 |
6.84 ¡Ñ 10-8 |
J |
West of BPPS |
5.69 ¡Ñ 10-9 |
1.19 ¡Ñ 10-8 |
Table
5.25 Risk Results for
LPS Pipeline in 2020 ¡V Operational Year
Segment |
IR (/km/year) |
IR (/year) |
|
A |
Jetty Approach
to South of Shek Kwu Chau |
5.63 ¡Ñ 10-9 |
2.82 ¡Ñ 10-8 |
B |
South of
Cheung Chau |
2.01 ¡Ñ 10-8 |
1.91 ¡Ñ 10-7 |
C |
West Lamma
Channel |
6.49 ¡Ñ 10-8 |
1.88 ¡Ñ 10-7 |
D |
Alternative
Shore Approach |
1.41 ¡Ñ 10-7 |
1.13 ¡Ñ 10-7 |
Table 5.26 Risk Results for
BPPS Pipeline in 2030 ¡VFuture Scenario Year
Segment |
IR (/km/year) |
IR (/year) |
|
X |
Jetty Approach to South of Soko
Islands |
3.56 ¡Ñ 10-8 |
3.17 ¡Ñ 10-7 |
A |
Southwest of Soko Islands |
4.23 ¡Ñ 10-8 |
1.35 ¡Ñ 10-7 |
B |
Southwest of Fan Lau |
8.78 ¡Ñ 10-9 |
3.07 ¡Ñ 10-8 |
C |
Southwest Lantau |
3.41 ¡Ñ 10-7 |
1.94 ¡Ñ 10-6 |
D |
West of Tai O |
3.12 ¡Ñ 10-8 |
1.53 ¡Ñ 10-7 |
E |
West of HKIA |
4.14 ¡Ñ 10-9 |
2.19 ¡Ñ 10-8 |
F |
West of Sha Chau |
1.48 ¡Ñ 10-9 |
6.66 ¡Ñ 10-9 |
G |
West of Lung Kwu Chau |
4.40 ¡Ñ 10-9 |
6.60 ¡Ñ 10-9 |
H |
Lung Kwu Chau to Urmston Anchorage |
4.06 ¡Ñ 10-9 |
1.46 ¡Ñ 10-8 |
I |
Urmston Road |
4.21 ¡Ñ 10-8 |
7.58 ¡Ñ 10-8 |
J |
West of BPPS |
6.51 ¡Ñ 10-9 |
1.37 ¡Ñ 10-8 |
Table
5.27 Risk Results for
LPS Pipeline in 2030 ¡V Future Scenario Year
Segment |
IR (/km/year) |
IR (/year) |
|
A |
Jetty Approach
to South of Shek Kwu Chau |
6.93 ¡Ñ 10-9 |
3.47 ¡Ñ 10-8 |
B |
South of
Cheung Chau |
2.23 ¡Ñ 10-8 |
2.12 ¡Ñ 10-7 |
C |
West Lamma
Channel |
6.62 ¡Ñ 10-8 |
1.92 ¡Ñ 10-7 |
D |
Alternative
Shore Approach |
1.51 ¡Ñ 10-7 |
1.21 ¡Ñ 10-7 |
The societal risk in terms of F-N curves
for all sections of the BPPS and LPS Pipelines in Operational Year 2020 and
Future Scenario Year 2030 lie within the Acceptable Region, as shown from Figure 5.11
to Figure 5.14. Therefore, the societal risk criteria
stipulated in Section 2 of Annex 4 of the EIAO-TM are met.
The societal risk, in terms
of potential loss of life, associated with each segment of the BPPS and LPG
subsea pipelines are summarised in Annex 5H.
An uncertainty analysis was
conducted to assess the sensitivity of the subsea pipeline protection factors
adopted in the QRA Study. In the
uncertainty analysis, the subsea pipeline protection factors adopted in
previous EIA Report that has been approved by the EPD ([46]) were adopted as shown in Table 5.28. This effectively considers a worst case
protection factor for the subsea pipeline protection factor.
Table 5.28 Subsea Pipeline Protection Factors for
Uncertainty Analysis
Anchor Size |
Trench Type Design |
Subsea Pipeline Protection Factor |
<2 tonnes |
Protect
against 20 tonnes |
99.9% |
>2 tonnes |
Protect
against 20 tonnes |
99.0% |
<2 tonnes |
Protect
against 2 tonnes |
99.0% |
>2 tonnes |
Protect against
2 tonnes |
50.0% |
Based
on the uncertainty analysis results, even if a worst case protection factor is
assumed, the individual risk remains less than 1 ¡Ñ 10-5
per year for all segments of the BPPS Pipeline. The societal risk remains within the
Acceptable Region in Year 2020 (Figure 5.15) for the uncertainty analysis. In Year 2030 the societal risk generally
remains within the Acceptable Region (Figure 5.16) for the uncertainty analysis. Therefore the risk criteria stipulated
in Section 2 of Annex 4 of the EIAO-TM
are met.
The BPPS Pipeline segments, including Southwest of Fan Lau and
Lung Kwu Chau to Urmston Anchorage, were identified as the highest risk because
of those segments are with high marine traffic (high failure frequency) and
high marine traffic population.
Based
on the uncertainty analysis results, even if a worst case protection factor is
assumed, the individual risk remains less than 1 ¡Ñ 10-5
per year for all segments of the LPS Pipeline. The societal risk was within the
Acceptable Region in Year 2020 and Year 2030, as shown in Figure 5.17 and Figure 5.18. Therefore the risk criteria
stipulated in Section 2 of Annex 4 of the EIAO-TM are met.
The
LPS Pipeline segments, Alternative Shore Approach and West Lamma Channel, were
identified as the relatively high risk because this segments are with
relatively high failure frequency considering marine traffic and segment
length.
It is concluded that the risks associated with the
BPPS and LPS Pipelines in terms of individual risk and societal risk are in
compliance with risk criteria stipulated in Section
2 of Annex 4 of the EIAO-TM for
the current proposed subsea pipeline design.
This section presents the QRA Study for the evaluation
of the risks associated with the GRSs at the BPPS and the LPS.
The GRS at the BPPS receives high pressure natural gas
(at the maximum allowable operating pressure of 88 barg at 5 ¢XC)
transported through the 30¡¨ subsea BPPS Pipeline from the Jetty. The maximum flow rate is 700 mmscfd, and
the GRS controls the pressure that the natural gas enters the BPPS, prior to
entering the gas turbines for power generation. The section of the interconnecting
onshore gas pipeline within the GRS site boundary was also considered in the QRA
Study.
The major equipment items associated with the GRS
include (the detailed process description is provided in Annex 5B):
¡P Pig
Receiver;
¡P Gas
Filter;
¡P Gas
Metering;
¡P Pipeline
Gas Heater;
¡P Pressure
Reduction Skid; and
¡P Mixing
Station.
The
GRS at the LPS receives high pressure natural gas (at the maximum allowable
operating pressure of 88 barg at 5 ¢XC) transported through the 20¡¨ subsea
LPS Pipeline from the Jetty. The
maximum total flow rate is 254 mmscfd. Four (4) natural gas conditioning trains
are provided at the GRS, with maximum flow rate of 63.5 mmscfd for each
train. The GRS allows final natural
gas conditioning prior to entering the gas turbines for power generation. The section of the interconnecting
onshore gas pipeline within the GRS site boundary was also considered in the
QRA Study.
The
major equipment items associated with the GRS include the detailed process
description is provided in Annex 5B.
¡P Pig
Receiver;
¡P Gas
Filter;
¡P Gas
Metering;
¡P Mixer;
¡P Water
Bath Heater; and
¡P Pressure
Reduction Skid.
The
following safety systems are provided at the GRSs at the BPPS and LPS, and the
detailed description of the safety system is provided in Annex 5B.
¡P Emergency
Shutdown System;
¡P Blowdown
System;
¡P Overpressure
Protection System; and
¡P Fire
and Gas Detection System.
The
hazardous scenarios associated with the operation of the GRSs at the BPPS and
LPS were identified through the following tasks:
¡P Review
of hazardous materials;
¡P Review
of potential MAEs;
¡P Review
of relevant industry incidents;
¡P Review
of potential initiating events leading to MAEs; and
¡P HAZID
Workshop.
Natural
gas is received at the GRSs at the BPPS and LPS before being sent out to the
gas turbines for power generation.
The properties of natural gas have been described in Section
5.5.2.
Other Non-Fuel Gas Dangerous Goods
Calibration
gas and carrier gas cylinders will be provided at the GRSs at the BPPS and LPS
for Gas Chromatography (GC). The
types of gas cylinders provided in the proposed GRS at the BPPS and LPS are
given in Table 5.29 and Table 5.30 respectively.
Table 5.29 Non-Fuel Gas Dangerous Goods
Associated with the Proposed GRS at the BPPS
Chemical |
Dangerous Goods Classification (1) |
Maximum Cylinder Quantity |
Cylinder Volume (m3) |
Storage Pressure (barg) |
Calibration
Gas (2) |
Category 2 |
2 cylinders |
0.02
m3 per cylinder |
137 |
Helium Gas |
Category 2, Cl.1 |
4 cylinders |
0.07
m3 per cylinder |
137 |
Calibration
Gas (3) |
Category 2 |
1 cylinders |
0.07
m3 per cylinder |
137 |
Calibration
Gas (4) |
Category 2 |
1 cylinders |
0.07
m3 per cylinder |
137 |
Hydrogen Gas |
Category 2, Cl.1 |
2 cylinders |
0.07
m3 per cylinder |
137 |
Note:
(1): The dangerous
goods category is classified based on ¡§Fire Protection Notice No. 4, Dangerous
Goods General¡¨ by Fire Services Department. ([47])
(2): The key
composition of the calibration gas for Gas Chromatograph is methane (90 vol%),
ethane (5 vol%), Nitrogen (2.5 vol%), and carbon dioxide (1 vol%) and propane
(1 vol%).
(3): The key
composition of the calibration gas 1 for Sulfur analyzer is 27 ppm H2S,
balance with Nitrogen.
(4): The key composition
of the calibration gas 2 for Sulfur analyzer is 270 ppm H2S, balance
with Nitrogen.
Table 5.30 Non-Fuel Gas Dangerous Goods
Associated with the Proposed GRS at the LPS
Chemical |
Dangerous Goods Classification (1) |
Maximum Cylinder Quantity |
Cylinder Volume (m3) |
Storage Pressure (barg) |
Hydrogen (4) |
Category 2, Cl.1 |
1 cylinder |
0.06 m3 per cylinder |
150 |
Nitrogen (5) |
Category 2, Cl.1 |
1 cylinder |
0.06
m3 per cylinder |
150 |
Synthetic Air |
Category 2, Cl.1 |
1 cylinder |
0.06
m3 per cylinder |
150 |
Reference Gas
for H2S Meter (2) |
Category 2 |
1 cylinder |
0.03
m3 per cylinder |
150 |
Reference Gas
for GC (3) |
Category 2 |
1 cylinder |
0.06
m3 per cylinder |
150 |
Helium (5) |
Category 2, Cl.1 |
1 cylinder |
0.06
m3 per cylinder |
150 |
(1): The dangerous goods category is classified based
on ¡§Fire Protection Notice No. 4, Dangerous Goods General¡¨ by Fire Services
Department (1).
(2): The key composition of the reference gas for H2S
meter is methane (90 vol%), ethane (10 vol%), H2S (4 ppm).
(3): The key composition of the reference gas for GC
is methane (90 vol%), ethane (7 vol%) and propane (2.5 vol%).
(4).
High Purity Grade
(5).
Ultra High Purity Grade
The
volume of the compressed gas inside the cylinders is limited and the associated
inventory available is small, and also those compressed gas cylinders are
located within control room building.
Considering the above, should loss of containment occur for the
compressed gas cylinders, there is no off-site impact on the surrounding marine
population. Hence, it is not
further assessed in the QRA Study.
Leakage
or rupture scenarios of process equipment, pipeline or pipework handling
flammable natural gas can result in a flammable gas cloud, which may be ignited
if it encounters an ignition source while its concentration lies within the
flammable range. In some cases,
static discharge may also cause immediate ignition of flammable gas release.
The
possible hazardous scenarios considered in the QRA Study upon the ignition of
any released natural gas at the GRSs are:
¡P Jet
fire;
¡P Flash
fire;
¡P Fireball;
and
¡P VCE.
Detailed
characteristics of the above hazardous effect are described in Annex 5G.
To investigate further the
possible hazardous scenarios, a review of the applicable past industry
incidents at similar facilities worldwide was conducted based on the following
incident/ accident database:
¡P
IChemE
accident database
¡P
eMARS;
¡P
ERNS;
and
¡P MHIDAS
database.
Details of
the past industry incident analysis are presented in Annex 5C.
The
potential hazardous scenarios arising from the operation of the GRSs at the
BPPS and LPS was identified as the loss of containment of natural gas. The potential initiating events which
could result in loss of containment of natural gas are listed below:
¡P General
equipment/piping failure (due to corrosion, construction defects etc.); and
¡P External
effects - earthquake, subsidence, tsunami, lightning, hill fire, storm surge
and flooding, aircraft crash and helicopter crash.
Descriptions
of the potential initiating events are presented in Annex 5D.
A
HAZID workshop was conducted to confirm and further identify the potential
initiating events which may lead to MAEs at the GRSs, based on the HAZID team representatives¡¦
experience, past industry accidents, lessons learnt and guideword
checklists. The HAZID workshop
worksheet is summarised in Annex 5E.
The HAZID workshop output was served as a basis for the identification
of potential initiating events and hazardous scenarios for the QRA Study.
During the peak construction
period of the GRSs in the beginning of 2020, the associated construction activities
may cause potential external hazards on the existing GRSs facilities located in
the nearby area. The construction
activities considered in the QRA Study are listed below:
¡P Movement
of large equipment/ construction vehicles in the vicinity of the existing GRS
facilities area;
¡P Dropped
object from crane operation;
¡P General
construction hazards such as hot work, drilling, etc.; and
¡P Tie-in
works to existing facilities.
Detailed
analysis of each identified construction activities are presented in Annex 5D.
The new GRSs and existing GRSs at the BPPS and LPS
were divided into a number of hazardous sections for detailed analysis in the
QRA Study based on location of emergency shutdown valves and process conditions
(e.g. operating temperature and pressure).
The details of each hazardous section (including temperature, pressure,
flow rate, inventory etc.) are presented in Annex 5D.
As
per previous EIA Reports that have been approved by EPD ([48]) ([49])
([50]),
the release frequencies from Hawksley, as summarised in Table 5.31, were adopted in the QRA Study.
Table 5.31 Release Event Frequencies
Equipment |
Release
Scenario |
Release
Phase |
Release
Frequency |
Unit |
Reference |
Pipe size 600 mm to 750 mm |
i) 10 & 25 mm hole |
Liquid/ Gas |
1.00E-07 |
per metre-year |
Hawksley ([51]) |
ii) 50 & 100 mm hole |
Liquid/ Gas |
7.00E-08 |
per metre-year |
Hawksley |
|
iii) Full bore rupture |
Liquid/ Gas |
3.00E-08 |
per metre-year |
Hawksley |
|
Pipe size 150 mm to 500 mm |
i) 10 & 25 mm hole |
Liquid/ Gas |
3.00E-07 |
per metre-year |
Hawksley |
ii) 50 & 100 mm hole |
Liquid/ Gas |
1.00E-07 |
per metre-year |
Hawksley |
|
iii) Full bore rupture |
Liquid/ Gas |
5.00E-08 |
per metre-year |
Hawksley |
In addition,
in accordance with the methodology used in previous EIA Reports that have been
approved by EPD (2) a fault tree analysis was conducted to calculate
the frequency of construction vehicles impacting the existing GRS facilities
during the construction phase of the GRSs at the BPPS and LPS. The frequency of construction vehicle
impact on the existing BPPS GRS and LPS GRS was estimated as 1.53 ¡Ñ 10-6
per year and 9.20 ¡Ñ 10-7 per year respectively. Detailed discussion on the above failure
frequencies are presented in Annex 5F.
As
per previous EIA Reports that have been approved by EPD ([52])
([53])
([54]), the
hole sizes in Table 5.32 were considered in the QRA Study:
Table
5.32 Release Hole Sizes
Leak Description |
Hole Size |
Very Small
Leak |
10 mm |
Small Leak |
25 mm |
Medium Leak |
50 mm |
Large Leak |
100 mm |
Line Rupture |
Pipeline
Diameter |
As
discussed in Section 5.5.3, the
probability of executing the isolation successfully when required during
emergency shutdown was adopted as 99%.
However, as a conservative approach, the probability of failure on
demand for all detection and shutdown system was adopted as 100% in the QRA
Study for GRSs, as per previous EIA Reports that have been approved by EPD (2).
Table 5.33
summarises the ignition probabilities adopted in the QRA Study as per previous
EIA Reports that have been approved by EPD. The total ignition probability is 0.32
for large leaks/ruptures, and 0.07 for other leaks. These ignition probabilities are
consistent with the model of Cox, Lees and Ang. The ignition probabilities were
distributed between immediate ignition and delayed ignition. Delayed ignition was further divided
between delayed ignition 1 and delayed ignition 2 to take into account that a
dispersing gas cloud may be ignited at different points during dispersion.
Delayed
ignition 1 results in a flash fire and takes into account the possibility that
an ignition could occur within the GRS facilities area due to the presence of
ignition sources on-site. Delayed
ignition 2 gives a flash fire after the gas cloud has expanded to its maximum
(steady state) extent. If both delayed ignition 1 and 2 do not occur, the gas
cloud disperses with no hazardous effect.
Table 5.33 Ignition Probably Adopted in the QRA
Study for GRSs at the BPPS and LPS
Leak |
Immediate Ignition |
Delayed Ignition 1 |
Delayed Ignition 2 |
Delayed Ignition Probability |
Total Ignition Probability |
a) Large/
Rupture |
0.10 |
0.200 |
0.020 |
0.22 |
0.32 |
b) Leaks other
than Large/ Rupture |
0.02 |
0.045 |
0.005 |
0.05 |
0.07 |
It is
noted that a VCE could explosion could potentially occur at the BPPS and LPS
GRS areas where the flammable gas cloud could accumulate. Nevertheless, based on the consequence
modelling, the explosion effect is localized; hence flash fire with larger
hazard footprint was conservatively modelled in the QRA Study. Detailed comparison of the consequences
is presented in Annex 5G.
An initially
small release may escalate into a larger, more serious event if a jet fire
impinges on neighbouring equipment/ piping for an extended time. This is taken into account in the
modelling for the isolation fail branch of the event tree, depicted in Figure 5F.8). If neighbouring equipment and piping is
within range of the flame zone of a jet fire, an escalation probability of 1/6
has been taken to conservatively estimate the directional probability and
chance of impingement. Escalation
has been assumed to only cause a full bore rupture of the affected equipment
and piping, leading to fireball event as the worst-case scenario.
An
event tree analysis was performed to model the development of each hazardous
scenario outcome (jet fire, flash fire, fireball, and VCE) from an initial
release scenario. The event tree
analysis considered whether there is immediate ignition, delayed ignition or no
ignition, with consideration of the associated ignition probability as
discussed above. The development of
the event tree is presented in Annex 5F.
The
modelling assumptions, as illustrated in Section 5.5.4,
were also adopted in the QRA Study on the GRSs at the BPPS and the LPS.
PHAST was used to perform the physical effects modelling to
assess the effects zones for the following hazardous scenarios:
¡P Jet
fire;
¡P Flash
fire;
¡P Fireball;
and
¡P VCE.
Detailed
description of the physical effects modelling is
presented in Annex 5G.
The same consequence
end-point criteria, as illustrated in Section 5.5.4, were
also adopted in the QRA Study for the GRSs at the BPPS and the LPS.
The
risk summation for the GRS facilities was modelled using ERM¡¦s proprietary risk
integration package Riskplot™, as per previous EIA Reports that have been
approved by the EPD ([55])
([56]).
Since
the existing GRSs at the BPPS and LPS are located in the vicinity of the new
GRSs, the existing GRSs could be impacted by the hazardous events arising from
the new GRSs.
The
construction activities of the GRSs could induce additional risks to the
existing neighbouring GRS
facilities. Therefore, in the
proposed assessment year of 2020 for the peak construction phase, additional
risk arising from the construction of the GRSs was considered in the QRA Study.
It is
noted that an additional CCGT unit at the BBPS and LPS may also be under
construction concurrently. However
considering the locations of the additional CCGT units and GRS facilities, the
risk of construction hazards arising from the new CCGT units impacting on the
new GRS facilities is considered insignificant and hence not further assessed
in the QRA Study.
The
existing oil tanks with relative large inventory are separated from GRSs area by
more than 300 m while the non-fuel gas dangerous storage areas are within
buildings and separated from GRSs area by more than 50 m. The individual risk impacts from GRSs
area facilities to the existing dangerous goods facilities are in the order of
magnitude from 1E-07 to 1E-06 per year without consideration any obstacle
between them. The likelihood of
escalation effects from GRSs area facilities on those existing oil tanks and
non-fuel gas dangerous storage areas is not considered as significant and indeed
already included in the generic failure database. As such, they are not required in the
cumulative risk assessment for the QRA Study.
When
in full operation, the associated process risk of the existing and new GRS
facilities was assessed in the proposed assessment years of 2020 and 2030.
The
details of the cumulative risk assessment considered in each of the proposed
assessment years are summarised in Table 5.34.
Table 5.34 Details of Cumulative Risk Assessment
Potential Risk |
2019 |
2020 |
2030 |
a) Existing
GRS facilities at the BPPS and the LPS (Baseline Condition) |
Yes |
Yes |
Yes |
b)
Construction activities for proposed GRS
facilities leading to potential impact on nearby existing GRS facilities at
the BPPS and the LPS, respectively |
Yes |
|
|
c)
Proposed GRS facilities at the BPPS and the
LPS for natural gas intake from the LNG Terminal |
|
Yes |
Yes |
As
shown in Figure
5.19, the individual risk contour of 1 ¡Ñ 10-5 per year
was not identified, therefore the individual risk criteria stipulated in Section 2 of Annex 4 of the EIAO-TM is
met.
As
shown in Figure
5.20 and Figure 5.21, the individual risk contour of 1 ¡Ñ
10-5 per year is mostly within the proposed GRS site boundary, with
slight overlap in the sea area.
Nevertheless, when considering the exposure factor for the surrounding
off-site population, the individual risk criteria stipulated in Section 2 of Annex 4 of the EIAO-TM is
met.
As shown in Figure 5.22,
the societal risks in terms of F-N curves for Construction Year in the
beginning of 2020, Operational Year in 2020 and Future Scenario Year in 2030
lie within the Acceptable Region; as such the societal risk
criteria stipulated in Section 2 of Annex 4 of the EIAO-TM
are met.
The key risk contributors, in
terms of potential loss of life, associated with the GRS at the BPPS are
summarised in Annex 5H.
As
shown in Figure
5.23, the individual risk of 1 ¡Ñ 10-5 per year was not identified,
therefore the individual risk criteria stipulated in Section 2 of Annex 4 of
the EIAO-TM is met.
As
shown in Figure
5.24 and Figure 5.25, the individual risk contour of 1 ¡Ñ 10-5
per year is confined with the proposed GRS site boundary, therefore the
individual risk criteria stipulated in Section
2 of Annex 4 of the EIAO-TM is met.
As shown in Figure 5.26,
the societal risks in terms of F-N curves for Construction Year in the
beginning of 2020, Operational Year in 2020 and Future Scenario Year in 2030
lie within the Acceptable Region; as such the societal risk
criteria stipulated in Section 2 of Annex 4 of the EIAO-TM
are met.
The key risk contributors, in
terms of potential loss of life, associated with the GRS at the LPS are
summarised in Annex 5H.
It is concluded that the risks
associated with the GRSs at the BPPS and LPS, in terms of individual and
societal risks, are in compliance with risk criteria stipulated in Section 2 of Annex 4 of the EIAO-TM.
A QRA Study was conducted to
evaluate the risk level associated with the following activities and facilities
of the Project with consideration of the identified LNG, natural gas and other
dangerous goods:
¡P Marine
Transits of LNGC and FSRU Vessel to The LNG Terminal;
¡P The
LNG Terminal, including the FSRU Vessel, the Jetty and LNGC Unloading
Operations;
¡P Subsea
BPPS and LPS Pipelines; and
¡P GRSs
at the BPPS and LPS.
The assessment methodology and
assumptions were based EIA Reports that have been approved by EPD ([57])
([58]).
For marine transits of LNGC and FSRU
Vessel, subsea BPPS and LPS Pipelines, the LNG Terminal, and the GRSs at the
BPPS and LPS, the individual risk is in compliance with the risk criteria in Section 2 of Annex 4 of the EIAO-TM.
In
terms of societal risk, the
F-N curves for all Project components have been developed and shown to be in
compliance with risk criteria stipulated in Section 2 of Annex 4 of
the EIAO-TM.
([1])
ERM,
EIA for Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities
(Register No.: AEIAR-106/2007), December 2006.
([3])
ERM,
EIA for Liquefied Natural Gas (LNG) Receiving Terminal and Associated
Facilities (Register No.: AEIAR-106/2007), December 2006.
([14])
ERM, EIA for
Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities
(Register No.: AEIAR-106/2007), December 2006.
([16])
ERM, EIA for Liquefied
Natural Gas (LNG) Receiving Terminal and Associated Facilities (Register No.:
AEIAR-106/2007), December 2006.
([17])
TNO, Methods for
the Determination of Possible Damage to People and Objects Resulting from
Releases of Hazardous Materials (The Green Book), Report CPR 16E, The
Netherlands Organisation of Applied Scientific Research, Voorburg, 1992.
([18])
ERM, EIA for
Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities
(Register No.: AEIAR-106/2007), December 2006.
([29])
ERM, EIA
for Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities (Register
No.: AEIAR-106/2007), December 2006.
([33])
ERM, EIA for
Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities
(Register No.: AEIAR-106/2007), December 2006.
([36])
ERM, EIA
for Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities
(Register No.: AEIAR-106/2007), December 2006.
([38])
Energy Institute,
London and Oil & Gas UK, Pipeline and Riser Loss of Containment 2010 ¡V 2012 (PARLOC 2012), 6th Edition
of PARLOC Report Series, March 2015.
([39])
Mott MacDonald
Ltd., The Update of Loss of Containment Data for Offshore Pipelines (PARLOC
2001), Revision F, June 2003.
([40])
ERM, EIA
for Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities
(Register No.: AEIAR-106/2007), December 2006.
([41])
ERM, EIA
for Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities
(Register No.: AEIAR-106/2007), December 2006.
([43])
ERM, EIA
for Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities
(Register No.: AEIAR-106/2007), December 2006.
([45])
P J Rew, P
Gallagher, D M Deaves, Dispersion of Subsea Release: Review of Prediction
Methodologies, Health and Safety Executive, 1995.
([46])
ERM, EIA for
Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities
(Register No.: AEIAR-106/2007), December 2006.
([48])
ERM, EIA for
Additional Gas-fired Generation Units Project (Register No.: AEIAR-197/2016),
June 2016.
([50])
ERM, EIA for
Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities
(Register No.: AEIAR-106/2007), December 2006.
([51])
Hawksley, J.L.,
Some Social, Technical and Economic Aspects of the Risks of Large Plants,
CHEMRAWN III, 1984.
([52])
ERM, EIA for
Additional Gas-fired Generation Units Project (Register No.: AEIAR-197/2016),
June 2016.
([54])
ERM, EIA for
Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities
(Register No.: AEIAR-106/2007), December 2006.
([56]) ERM, EIA for Liquefied
Natural Gas (LNG) Receiving Terminal and Associated Facilities (Register No.:
AEIAR-106/2007), December 2006.