8                                          Waste Management Implications

8.1                                   Introduction

This Section identifies the potential waste management implications arising from the construction and operation of the Project and the potential environmental impacts associated with the storage, handling, transportation and disposal of the wastes.

8.2                                   Legislative Requirements and Evaluation Criteria

The criteria for evaluating waste management implications are stated in Annex 7 of the EIAO-TM.  Annex 15 of the EIAO-TM prescribes the general approach and methodology for assessing the waste management implications caused by a project or proposal.

The following legislation covers the handling, treatment and disposal of wastes in Hong Kong which are relevant to the types of waste to be generated from the Project, and has been considered in the assessment.

¡P                Waste Disposal Ordinance (WDO) (Cap 354);

¡P                Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C);

¡P                Buildings Ordinance (Cap 123);

¡P                Land (Miscellaneous Provisions) Ordinance (Cap 28);

¡P                Public Health and Municipal Services Ordinance (Cap 132) - Public Cleansing and Prevention of Nuisances Regulation;

¡P                Dumping at Sea Ordinance (DASO) (Cap. 466); and

¡P                Merchant Shipping (Prevention and Control of Pollution) Ordinance (Cap 413).

8.2.1                           Waste Disposal Ordinance (WDO) (Cap 354)

The WDO prohibits the unauthorised disposal of wastes, with waste defined as any substance or article which is abandoned.  Under the WDO, wastes can only be disposed of at licensed waste disposal sites.  A breach of these regulations can lead to the imposition of a fine and/or a prison sentence.  The WDO also provides for the issuing of licences for the collection and transport of wastes.  Licences for the collection and transport of construction waste or trade waste, however, are not issued currently.

The Waste Disposal (Charges for Disposal of Construction Waste) Regulation defined construction waste as any substance, matters or things that are generated from construction work and abandoned, whether or not it has been processed or stockpiled before being abandoned, but does not include any sludge, screening, or matter removed in or generated from any desludging, desilting or dredging works.

The Construction Waste Disposal Charging Scheme came into operation on 1 December 2005.  Processing of account applications by the EPD started on the same day.  A Contractor who undertakes construction work with value of HK$1 million or above is required to open a billing account solely for the contract.  Charging for the disposal of construction waste started on 20 January 2006.

Depending on the percentage of inert materials in the material, construction waste can be disposed of at public fill reception facilities, construction waste sorting facilities, landfills and outlying islands transfer facilities, where differing disposal costs would be applied.  This scheme encourages waste reduction and hence minimise the costs of the Contractor or the Project Proponent.

Table 8.1 summarises the Government waste disposal facilities for construction waste and various charge levels.

Table 8.1        Government Waste Disposal Facilities for Construction Waste

Government Waste Disposal Facilities

Type of Construction Waste Accepted

Charge per Tonne (a)

Public fill reception facilities

Consisting entirely of inert construction waste (b)

HK$71

Sorting facilities

Containing more than 50% by weight of inert construction waste (b)

HK$175

Landfills (c)

Containing not more than 50% by weight of inert construction waste (b)

HK$200

Outlying Islands Transfer Facilities (c)

Containing any percentage of inert construction waste (b)

HK$200

Notes:

(a)      Except for the Outlying Islands Transfer Facilities, the minimum charge load is 1 tonne, i.e. if a load of waste weighs 1 tonne or less, it will be charged as 1 tonne.  A load of waste weighing more than 1 tonne will be charged at 0.1 tonne increment.  For Outlying Islands Transfer Facilities, the charge is $20 per 0.1 tonne and the minimum charge load is 0.1 tonne.  

(b)      Inert construction waste means rock, rubble, boulder, earth, soil, sand, concrete, asphalt, brick, tile, masonry or used bentonite.

(c)      If a load of waste contains construction waste and other wastes, that load will be regarded as consisting entirely of construction waste for the purpose of calculating the applicable charge.

 

8.2.2                           Waste Disposal (Chemical Waste) (General) Regulation (Cap 354C)

Chemical waste as defined under the Waste Disposal (Chemical Waste) (General) Regulation includes any substance being scrap material, or unwanted substances specified under Schedule 1 of the Regulation, if such a substance or chemical occurs in such a form, quantity or concentration so as to cause pollution or constitute a danger to health or risk of pollution to the environment.

Chemical waste producers shall register with the EPD.  Any person who contravenes this requirement commits an offence and is liable to a fine and imprisonment.  Producers of chemical wastes must treat their wastes, utilising on-site plants licensed by the EPD or have a licensed collector take the wastes to a licensed facility.  For each consignment of wastes, the waste producer, collector and disposer of the wastes must sign all relevant parts of a computerised trip ticket.  The system is designed to allow the transfer of wastes to be traced from cradle-to-grave.

The Regulation prescribes the storage facilities to be provided on site including labelling and warning signs.  To minimise the risks of pollution and danger to human health or life, the waste producer is required to prepare and make available written procedures to be observed in the case of emergencies due to spillage, leakage or accidents arising from the storage of chemical wastes.  He/she must also provide employees with training in such procedures.

8.2.3                           Buildings Ordinance (Cap 123)

Regulation of private projects, as opposed to government public works projects, is subject to the Buildings Ordinance (BO) and relevant Practice Notes for Authorised Persons, Registered Structural Engineers and Registered Geotechnical Engineers (PNAPs).  Measures have been introduced under PNAP ADV-19 Construction and Demolition Waste, to enhance the management of construction and demolition (C&D) materials, and to minimise its generation at source.  The enhancement measures include:

¡P             Identifying opportunities to prevent waste during both the project planning and design stage as well as construction stage; and

¡P             Requiring the Contractor to prepare a Waste Management Plan (WMP) including areas described in PNAP ADV-19 and submit to the Project Proponent for agreement.

8.2.4                           Land (Miscellaneous Provisions) Ordinance (Cap 28)

The inert portion of construction waste ([1]) (also called public fill) may be taken to public fill reception facilities.  Public fill reception facilities are operated by the Civil Engineering and Development Department (CEDD).  The Land (Miscellaneous Provisions) Ordinance requires that individuals or companies who deliver public fill to the public fill reception facilities need to obtain Dumping Licences.  The licences are issued by the CEDD under delegated authority from the Director of Lands.

Under the licence conditions, public fill reception facilities will only accept inert earth, soil, sand, rock, boulder, rubble, brick, tile, concrete, asphalt, masonry or used bentonite.  In addition, in accordance with paragraph 11 of Development Bureau (DevB) Technical Circular (Works) (DevB TC(W)) No. 6/2010), the Public Fill Committee will advise on the acceptance criteria (e.g. no mixing of construction waste, nominal size of the materials less than 250mm, etc).  The material should, however, be free from marine mud, household refuse, plastic, metal, industrial and chemical wastes, animal and vegetable matter and any other materials considered unsuitable to the public fill reception facility.

8.2.5                           Public Cleansing and Prevention of Nuisances Regulation (Cap 132)

This Regulation provides further control on the illegal dumping of wastes on unauthorised (unlicensed) sites.  The illegal dumping of wastes can lead to a fine and/or imprisonment.

8.2.6                           Dumping at Sea Ordinance (DASO) (Cap 466)

Under the DASO, a permit from the Director of Environmental Protection is required if anyone intends to dispose and dump from vessels in the sea.  The permit is valid for specific periods of time and stipulates the (1) type and quantity of substances to be dumped; (2) location of the disposal grounds; (3) requirement of equipment for monitoring the disposal operations; and (4) environmental monitoring requirements.

PNAP ADV-21 ¡V Management Framework for Disposal of Dredged/ Excavated Sediment (April 2007), sets out the procedures for seeking approval to dredge/ excavate sediment and the management framework for marine disposal of such sediment.  This PNAP outlines the requirements to be followed in assessing and classifying the sediment and explains the marine disposal arrangement for the classified material.

Table 8.2 summarises the HKSAR Government charging system for proponents of private projects to dispose of dredged sediment.

Table 8.2        HKSAR Government Charging System for Disposal of Dredged Sediment

Sediment Type

Charge Rate per Cubic Metre (measured in situ at dredging site)

Type 1 - Open Sea Disposal of Category L Sediment

HK$1.67

Others

HK$87.00

 

8.2.7                           Merchant Shipping (Prevention and Control of Pollution) Ordinance (Cap 413)

The Merchant Shipping (Prevention and Control of Pollution) Ordinance and its subsidiary regulations prohibit the discharge of wastewater and garbage from vessels.

Hong Kong has implemented the International Convention for the Prevention of Pollution from Ships 1973 as amended by the 1978 Protocol (universally known as MARPOL) and the MARPOL related requirements are mainly implemented under the Merchant Shipping (Prevention and Control of Pollution) Ordinance.  Under the requirements, liquid oil waste or any other mixtures which contain oil and noxious liquid substances or any such residues shall not be discharged into the sea.  In Hong Kong, the Chemical Waste Treatment Centre (CWTC) is the reception facility for oily waste discharged from vessels.

8.2.8                           Other Relevant Guidelines

Other relevant guidance documents, which detail how the Project Proponent or the Contractor should comply with the local regulations, are as follows:

¡P                Waste Disposal Plan for Hong Kong (December 1989), Planning, Environment and Lands Branch Government Secretariat, HKSAR Government;

¡P                Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), EPD, HKSAR Government;

¡P                Hong Kong Planning Standards and Guidelines Planning (2014), Planning Department, HKSAR Government;

¡P                WBTC No. 2/93 - Public Dumps, Works Branch, HKSAR Government;

¡P                WBTC No. 2/93B - Public Filling Facilities, Works Branch, HKSAR Government;

¡P                WBTC No. 16/96 - Wet Soil in Public Dumps, Works Branch, HKSAR Government;

¡P                Waste Reduction Framework Plan, 1998 to 2007, Planning, Environment and Lands Bureau, Government Secretariat, 5 November 1998;

¡P                WBTC No. 4/98 and 4/98A - Use of Public Fill in Reclamation and Earth Filling Projects, Works Bureau, HKSAR Government;

¡P                WBTC No. 12/2000 - Fill Management, Works Bureau, HKSAR Government;

¡P                WBTC No. 19/2001 - Metallic Site Hoardings and Signboards; Works Bureau, HKSAR Government;

¡P                Project Administration Handbook for Civil Engineering Works, Section 21.25 of Chapter 7 and Section 9.12 of Chapter 5 - Control of Site Crushers, HKSAR Government;

¡P                WBTC No. 12/2002 - Specifications Facilitating the Use of Recycled Aggregates, Works Bureau, HKSAR Government;

¡P                Project Administration Handbook for Civil Engineering Works, Section 4.1.3 of Chapter 4 - Management of Construction and Demolition Material Including Rock, HKSAR Government;

¡P                ETWB TC(W) No. 19/2005 - Environmental Management on Construction Sites, Environment, Transport and Works Bureau, HKSAR Government; and

¡P                DevB TC(W) No. 6/2010 - Trip Ticket System for Disposal of Construction & Demolition Materials, Development Bureau, HKSAR Government.

8.3                                   Expected Waste Arisings during the Construction Phase

During the construction phase of the Project, the main activities include marine piling works, concreting, assembly of pre-fabricated equipment, electrical and mechanical installations, subsea pipeline construction, including marine dredging and jetting, and onshore pipework fabrication.  These activities will potentially result in the generation of wastes.

The typical waste types associated with these activities include:

¡P             Dredged marine sediment from the construction of the BPPS Pipeline and the LPS Pipeline;

¡P             C&D materials from the construction of the GRSs at the BPPS and the LPS and the Jetty, and onshore pipeline trenching and pipework fabrication;

¡P             Chemical waste from maintenance of construction plant and equipment for both land and marine-based works; and

¡P             General refuse from land and marine-based construction workforce and floating refuse.

Options will be further developed and evaluated to reduce waste generation and enhance re-use and recycling of waste generated during the detailed design and construction phases of the Project.  The consideration of options for layout, construction methods and programme, and the proposed scheme will comprise the proposed best balance. 

8.3.1                           Dredged Marine Sediment

For the construction of the BPPS Pipeline and the LPS Pipeline, dredging will be limited to those areas where non-dredged is not appropriate.  Justification for the proposed pipeline construction methods has been provided in Section 2 of this EIA Report and elaborated below.  It is noted that the construction of the Jetty has avoided marine dredging.

For the BPPS and LPS Pipelines, a number of subsea pipeline construction methods have been considered.  Options are examined based on a number of environmental parameters where minimizing the dredged sediment volumes is one of the key factors (alongside WQOs compliance and minimizing ecological impacts) for the overall environmental acceptability of the Project.  Ploughing, Horizontal Directional Drilling (HDD) and jetting are non-dredged options which do not generate dredged sediments.  However, ploughing and HDD are not considered as viable pipeline construction methods for the Project for several reasons.  Ploughing is not suitable for the soft marine clay that is found on the seabed along the routes of the pipelines and cannot provide sufficient burial depth for pipeline protection.  In addition, a full-scale trial and detailed site survey will be required to establish its engineering and environmental viability prior to its adoption in Hong Kong, lengthening the duration of environmental impacts from the Project.  HDD¡¦s technical challenges, including the need to maintain an open drill hole in the soft marine clay on the seabed along the routes of the pipelines and the use of long pipelines with large pipeline diameters, make its feasibility questionable.  The HDD operations will also have significant environmental impact e.g. waste management and water quality impacts from the spoil generation which may be lengthy in nature given the potential programme and costs constraints.  In addition, HDD operations may require a number of intermediate offshore working stations which in turn increase the environmental impact and marine operational risks.

Hence, a combination of dredging (either grab dredging or Trailing Suction Hopper Dredger (TSHD) dredging) or jetting is the preferred construction methods for the BPPS Pipeline and the LPS Pipeline where the selection of the actual methods to be adopted for pipeline construction are assessed based on the features along each pipeline route that will impact on the construction methods and the pipeline protection that is required at certain locations along the pipeline routes.  While dredging produces marine sediment that may require disposal, jetting on the other hand may, in comparison to dredging, impact water quality to a higher degree owing to the temporary increase in suspended sediment concentrations in the vicinity.  It is important to strike a balance in the selection of appropriate construction methods for the subsea pipelines.  The use of jetting is preferred to minimise the dredged sediment volumes and therefore the majority of the BPPS Pipeline and the LPS Pipeline routes are planned to be constructed by jetting except the pipeline segments (the Urmston Road, West of Lung Kwu Chau and Southwest Lantau BPPS Pipeline segments) which have to be constructed by dredging (grab dredging or TSHD dredging) to provide the required level of pipeline protection from large anchor drop and drag.  From an engineering point of view, protection from anchor drop and drag can be achieved using a combination of burial depth and rock armour which position the pipe below the normal dragging depth of the anchors.  However, along pipeline section that requires a higher level of protection, options for protection of a jetted pipeline include: (a) deep burial below existing seabed level where the larger anchors cannot reach, which is not feasible with existing jetting technology; or (b) provision of a fit-for-purpose rock armour berm, which may protrude above the seabed and is compromised by the fluidized state of the mud.  On the basis of these, jetting is considered to be not feasible for such pipeline sections.  Figure 8.1 shows the proposed extent of dredging required for the Project.  The total estimated in situ volume of dredged marine sediment is approximately 0.35Mm3.  It is expected that the dredging works will last for about six months. 

Marine Sediment Quality

Marine sediment sampling and testing has already been undertaken by other developments (for example, approved EIAs, EM&A programmes, and EPD monitoring stations) near the proposed dredging areas and the marine sediment quality information relevant to the Project was reviewed.  Details of the previous sampling and testing results are contained in the Marine Sediment Sampling and Testing Plan (MSSTP) prepared for this EIA Study in Annex 8A.  The previous testing results suggested that the marine sediment in the vicinity of the BPPS Pipeline route and the LPS Pipeline route was generally categorised as category L to M, and category L respectively ([2]), whereas the marine sediment in the vicinity of the Jetty was generally categorized as category L.

A sediment sampling programme was agreed with EPD and undertaken as part of this EIA Study to delineate the locations of the contaminated marine sediment potentially to be dredged by this Project and enable subsequent estimation of the different types of marine sediments (i.e. contaminated and uncontaminated) to be disposed of for the purpose of the EIA Study.  A MSSTP was prepared and submitted to the EPD for approval prior to the commencement of the field sampling works (see Annex 8A).  Marine sediment samples have been collected per plan.  At each location, sediment samples were collected at the top layer of the seabed by grab sampling in view of the trench design.  The marine sediment samples were then tested in accordance with the requirements stipulated in the PNAP ADV-21 issued by the Buildings Department.

The marine sediment analytical results for the 15 nos. of locations along the BPPS Pipeline and the LPS Pipeline where it was identified during the design development and optimisation that dredging may be required, as shown in Figure 8.2, are presented in Table 8.3 ([3]).  The full laboratory analytical results of the relevant sampling locations are contained in Annex 8B.  The testing results are compared against the Lower Chemical Exceedance Level (LCEL) and Upper Chemical Exceedance Level (UCEL) of respective parameters in Table 8.3.   


Table 8.3        Marine Sediment Testing Results

Sample Reference

Chemical Screening

Sediment Category

Biological Screening

Disposal Option

Heavy Metals (mg kg-1)

Organic (ug kg-1)

Organo-metallics

Sampling Location

Sampling Method

Ag(a)

As(a)

Cd(a)

Cr(a)

Cu(a)

Ni(a)

Pb(a)

Zn(a)

Hg(a)

Total PCB

LMW PAHs

HMW PAHs

Tributyl-tin

(ug TBT L-1)

Reporting Limits

 

0.1

1

0.2

8

7

4

8

20

0.05

3

55

170

0.015

LCEL

 

1

12

1.5

80

65

40

75

200

0.5

23

550

1,700

0.15

UCEL

 

2

42

4

160

110

40

110

270

1

180

3,160

9,600

0.15

X-GB01

Grab

0.2

12

<0.2

34

32

20

33

107

0.11

<18

<550

<1,700

<0.015

L

-

Type 1 Open Sea

B-GB01

Grab

0.1

13

<0.2

29

14

14

30

75

0.05

<18

<550

<1,700

<0.015

M

Pass

Type 1 Dedicated Sites

B-GB02

Grab

0.1

15

<0.2

32

15

12

30

67

0.05

<18

<550

<1,700

<0.015

M

Pass

Type 1 Dedicated Sites

B-GB03

Grab

0.1

15

<0.2

35

20

18

30

77

0.07

<18

<550

<1,700

<0.015

M

Pass

Type 1 Dedicated Sites

B-GB04

Grab

0.1

16

<0.2

36

24

21

28

87

0.07

<18

<550

<1,700

<0.015

M

Pass

Type 1 Dedicated Sites

B-GB05

Grab

0.2

18

<0.2

53

35

28

40

117

0.10

<18

<550

<1,700

<0.015

M

Pass

Type 1 Dedicated Sites

B-GB10

Grab

0.1

20

<0.2

47

28

24

33

101

0.09

<18

<550

<1,700

<0.015

M

Pass

Type 1 Dedicated Sites

B-GB11

Grab

0.1

16

<0.2

44

24

22

30

90

0.08

<18

<550

<1,700

<0.015

M

Pass

Type 1 Dedicated Sites

B-GB12

Grab

0.1

13

<0.2

35

20

20

33

86

0.09

<18

<550

<1,700

<0.015

M

Pass

Type 1 Dedicated Sites

B-GB13

Grab

0.1

14

<0.2

35

21

20

29

79

0.08

<18

<550

<1,700

<0.015

M

Pass

Type 1 Dedicated Sites

B-GB14

Grab

<0.1

21

<0.2

30

16

19

40

73

0.06

<18

<550

<1,700

<0.015

M

Pass

Type 1 Dedicated Sites

B-GB15

Grab

<0.1

12

<0.2

32

17

17

27

74

0.09

<18

<550

<1,700

<0.015

L

-

Type 1 Open Sea

F-GB01

Grab

0.1

8

<0.2

31

16

16

33

76

0.07

<18

<550

<1,700

<0.015

L

-

Type 1 Open Sea

F-GB02

Grab

0.1

9

<0.2

32

16

18

31

78

0.08

<18

<550

<1,700

<0.015

L

-

Type 1 Open Sea

L-GB01

Grab

0.2

8

<0.2

41

23

27

37

107

0.1

<18

<550

<1,700

<0.015

L

-

Type 1 Open Sea

Note:

(a)    Heavy metals tested includes: silver (Ag), arsenic (As), cadmium (Cd), chromium (Cr), copper (Cu), nickel (Ni), lead (Pb), zinc (Zn) and mercury (Hg).

(b)    Bold = Exceeding LCEL, classified as Category M

(c)    Bold and underlined = Exceeding UCEL, classified as Category H

 

 


As shown in Table 8.3 and Figure 8.2, the marine sediments to be dredged (i) near the Jetty, (ii) southwest of Lantau, (iii) near the LPS and (iv) near the BPPS were found to be uncontaminated, and would be disposed to Type 1 open sea disposal sites (i.e. South of Cheung Chau or East of Ninepin).  The estimated in situ volumes of uncontaminated sediment to be dredged under this Project are 0.01Mm3 for the BPPS Pipeline and 0.02Mm3 for the LPS Pipeline.  The allocation of disposal space will be subject to further review and approval by the Marine Fill Committee (MFC) of CEDD.

No category M marine sediments were found to be present along the LPS Pipeline in the proposed dredging areas.  Marine sediment to be dredged along the BPPS Pipeline from southwest of Lantau to the BPPS were found to be category M contaminated.  Tier III biological screening was conducted to identify the most appropriate disposal option for the category M contaminated materials in accordance with the PNAP ADV-21.  Results of the biological screening indicated that all sediment samples passed all three toxicity tests.  It is thus estimated that approximately 0.32Mm3 (in situ volume) of category M contaminated sediment which passed the biological screening test (Cat M pass sediment) would be generated from the BPPS Pipeline.

These findings of the marine sediment testing are consistent with the information from the review of the previous marine sediment quality information along the BPPS and LPS Pipelines in Annex 8A. 

The detailed breakdown of the estimated quantities of different types of marine sediments is summarised in Table 8.4.

Table 8.4        Estimated Quantities (in situ) of Different Types of Marine Sediment to be Dredged (Mm3) (a)

Sediment Type

BPPS Pipeline

LPS Pipeline

Total

Disposal Option

Category L

 

0.01

0.02

0.03

Type 1 Open Sea Disposal Site managed by the CEDD

 

Category M pass

0.32

-

0.32

Type 1 Dedicated Open Sea Disposal Site

Total

0.33

0.02

0.35

 

Note:

(a)     The estimated quantities of sediments are estimated based on the preliminary trench design but did not take into consideration the detailed dredged profile or the vertical distribution of contamination and the quantities presented in the table above are considered primary and conservative.  A detailed sampling, testing and estimation of contaminated sediment will be carried out under the Dumping at Sea Ordinance (DASO) Cap .466 and a DASO permit would be obtained prior to the commencement of the marine construction works.

The options of on-site or off-site treatment and reuse of the dredged sediment have been explored.  The Project does not require natural backfilling material and thus the potential of on-site re-use of dredged marine sediment is very limited.  Off-site re-use of the dredged marine sediment after decontamination and treatment of contaminated marine sediment into earth filling material has been considered.  The cement-stabilisation process converts soft marine mud into a green recycled earth filling material which is safe to the environment and can be compacted by normal compaction machinery to achieve the necessary engineering properties similar to the parent ground, such that after backfilled it can provide similar resistance to foundations of the proposed development.  The specific performance criteria for quality control at both the cement-stabilisation stage and the backfilling/compaction state consist of particular major technical requirements in terms of shear strength, dry density, etc.  Pilot trials on mixing and field operations on site and quality control tests to demonstrate the suitability of the cement-stabilisation and backfilling/compaction processes would be required.  Some on-site re-use of such treated material may be considered for the Jetty substructure seabed area, subject to detailed design and construction plan.  Nevertheless, a considerably large stockpile area will be required for the storage and drying of dredged marine sediments of high water content before they can be mixed with cement and granular materials to form backfilling materials.  Therefore, in order to make the option of off-site treatment both cost effective and environmentally friendly, it would be necessary to secure a plot of land with barging facilities (e.g. under a short-term tenancy agreement) and within reasonable transportation distance from where the dredged sediments will be generated.  The feasibility of off-site treatment and beneficial reuse, including the quantity of dredged sediment that could be handled, will be confirmed during the detailed design and implementation phase of the Project. 

Surplus dredged marine sediment that cannot be reused will require off-site disposal.  Various disposal options of category M sediment have been considered, including both land-based and marine-based disposal options with reference to the recommended sediment disposal options for submarine utilities installation in the final report of CEDD¡¦s Study on Options for Management of Contaminated Sediment in Hong Kong ([4]).  On land-based options, the applicability to reuse marine sediment as construction fill or sanitary landfill cover depends on the type, size and quality of the dredged material and requires dewatering, screening and remediation treatment prior to reuse (see earlier text on the consideration of treatment options).  In fact, for fill material for construction projects and landfill cover, reuse of inert excavated materials rather than reuse of dredged sediment after treatment is still preferred because it does not require treatment and hence more environmentally friendly and cost effective.  Hence, the demand for dredged marine sediment on land application is uncertain which affects the viability of land-based disposal options.  Given the above, marine disposal option is considered more appropriate for surplus dredged sediment that cannot be reused.

At present the East of Sha Chau Mud Pits are designated for confined marine sediment disposal of contaminated sediment.  The current capacity of these pits is around 4.6Mm3 for contaminated sediment and these pits could be considered as the disposal site for the category M contaminated marine sediments generated from this Project.  In accordance with PNAP ADV-21, the project proponent will liaise with MFC and EPD at an early stage of the project, as to the allocation arrangement for sediment disposal.  The Project Proponent will continue to liaise with the relevant authorities to ensure compliance with PNAP ADV-21.

The testing results and the disposal options presented in this EIA Report are for EIA purposes only.  To confirm the marine sediment disposal quantity and location, a separate MSSTP and Sediment Quality Report (SQR) will be prepared in accordance with the requirement stated in PNAP ADV-21 for EPD approval as required under the Dumping at Sea Ordinance.  The actual quantity and allocation of the disposal site(s) will be based on the results of the SQR to be approved by MFC/ CEDD and a dumping permit will be obtained from EPD prior to the commencement of the dredging works.

The dredged marine sediments will be loaded on to the barge immediately.  With the assumption of typical barge capacity of 800m3 to 1,000m3, approximately 7 to 8 barge trips per day are anticipated to transfer the marine sediments to the disposal sites during the pipeline construction period.  The barges to be used will be fitted with seals to prevent leakage of marine sediment, and no overloading of marine sediment and marine sediment laden water will be allowed during loading or transportation.  As such no adverse impact on water quality and marine ecology associated with the barge transport of marine sediments and their disposal is expected.

8.3.2                           C&D Materials

C&D materials (consisting of waste concrete, packing materials, plastics, etc.) will mainly be generated from the construction of the GRSs at the BPPS and the LPS and the Jetty.  Since GRS construction will only involve minor fencing and trenching works and assembly of prefabricated equipment and the Jetty construction will involve some structural formation works, mainly consisting of the assembly of prefabricated equipment, the quantity of C&D materials generation is expected to be small.  The estimated total quantity of C&D materials to be generated under this Project is around 45,000m3, or around 2,100m3 per month on average during the construction period, of which about 90% would be inert (e.g. concrete, bricks and rocks, etc.) and the rest being non-inert.  The construction sequence will be carefully planned so as to avoid over-ordering of construction material.  The minor trenching works for GRS construction and onshore pipeline trenching and pipework would not require significant land excavation works, thus the potential concern about contaminated soil excavation is not expected.

Specific areas will be designated for C&D material segregation onsite (including land and marine-based construction sites and marine vessels used for the construction of marine works) into inert materials (public fill) and non-inert materials.  Recyclables, such as plastics and cardboard, will be segregated for recycling.  The public fill from the construction of the GRS and onshore pipeline at the BPPS, if any, will be transported by truck to the Tuen Mun Area 38 Fill Bank via Lung Kwu Tan Road while the non-inert C&D materials will be disposed of at WENT Landfill via Nim Wan Road.  Public fill and non-inert C&D materials generated from the GRS and onshore pipeline at the LPS, if any, and the Jetty will be transported by barge/marine vessel to the public fill reception facilities (e.g. Tuen Mun Area 38 or Mui Wo Temporary Public Fill Reception Facility which receive public fill only) or the Outlying Island Transfer Facilities (which receive both public fill and non-inert C&D material).  Given that the quantity of C&D materials for disposal is anticipated to be low, the handling and transportation of C&D materials are not expected to cause adverse dust, noise or water quality impacts with the implementation of good construction site practices.

About 0.84Mm3 and 0.26Mm3 of rock is required to be imported as pipeline protection material (rock armour) for the BPPS Pipeline and the LPS Pipeline, respectively.  Based on the construction programme, approximately 10 and 4 barge trips per day are required to deliver the rock to the floating storage barge along the BPPS Pipeline and the LPS Pipeline, respectively, during the pipeline construction period.  Water quality impacts associated with rock armour placement is addressed in Section 7.7.1.  To optimise the import and use of rock, where possible, liaison with concurrent rock-generating projects (e.g. Tseung Kwan O - Lam Tin Tunnel, Relocation of Sha Tin Sewage Treatment Works to Caverns and Central Kowloon Route projects) would be made to explore the feasibility of local matching.

8.3.3                           Chemical Waste

Chemical waste, as defined under the Waste Disposal (Chemical Waste) (General) Regulation, includes any unwanted substances specified under Schedule 1 of the Regulation.  Substances likely to be generated from the construction of GRSs at the BPPS and the LPS, the BPPS Pipeline and LPS Pipeline and the Jetty will include:

¡P                Used paint, engine oils, hydraulic fluids and waste fuel;

¡P                Spent mineral oils/cleaning fluids from mechanical machinery; and

¡P                Spent solvents/ solutions from equipment cleaning activities.

Chemical wastes may pose environmental, health and safety hazards if not stored and disposed of in an appropriate manner as outlined in the Waste Disposal (Chemical Waste) (General) Regulation and the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.  These hazards may include:

¡P                Toxic effects to workers;

¡P                Adverse effects on air, water and land from spills; and

¡P                Fire hazards.

It is difficult to quantify the exact amount of chemical waste that will arise from the construction activities since it will be highly dependent on the Contractor¡¦s on-site maintenance activities and the quantity and/or types of plant and equipment utilised.  With respect to the scale of the construction activities, it is anticipated that the quantity of chemical waste to be generated is about a few hundred litres of used lubricant oil per month during the construction period.  It is anticipated that the quantities of waste solvent and wasted paint will be minimal.  The chemical waste will be collected by a licensed chemical waste collector and delivered to the licensed chemical waste treatment facilities for disposal (at the Chemical Waste Treatment Centre (CWTC) at Tsing Yi).

With the incorporation of suitable arrangements for the storage, handling, collection, transportation and disposal of chemical wastes under the requirements stated in the Waste Disposal (Chemical Waste) (General) Regulation and the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, no adverse environmental (including air and odour emissions, noise and wastewater discharge) impacts, and hazards are anticipated.

8.3.4                           General Refuse

The presence of a construction site at the GRSs at the BPPS and the LPS with workers and associated site office will result in the generation of general refuse (mainly consists of food waste, aluminium cans, plastic bottles, waste paper and glass bottles) which requires off-site disposal.  The presence of a construction site in the open sea at the Jetty site, may also cause trapping of floating refuse ([5]) at the temporary structures and along barges or vessels stationed for the marine construction works.  Such refuse will require regular collection and off-site disposal as general refuse.  The storage of general refuse has the potential to give rise to adverse environmental impacts, if not properly managed.  These include odour if the general refuse is not collected frequently, floating/windblown litter and visual impact.

It is conservatively estimated that a maximum of about 500-600 construction workers will be working on the various Project construction sites at any one time. With a general refuse generation rate of 0.65kg per worker per day, the maximum amount of general refuse to be generated by the construction workforce will be about 390kg per day.  The amount of floating refuse, i.e. not generated by this Project as workers are not allowed to dump rubbish into the sea, is highly variable and influenced by the strength and direction of water currents.  As the Jetty is to be constructed in open seas with constant flushing of water currents, the amount of floating refuse, if any, to be trapped at the Site during construction is expected to be minimal.

To reduce the quantity of general refuse to be disposed of at landfill, recyclable materials (i.e. paper, plastic bottles, aluminium cans and glass bottles) will be segregated on-site (including land and marine-based construction sites and marine vessels used for the construction of marine works) for off-site recycling, as far as practicable.  Adequate number of enclosed waste containers and recycling bins will be provided to avoid over-spillage of waste and/ or recyclable materials. 

The non-recyclable general refuse on marine vessels will be collected for disposal on shore.  The non-recyclable refuse will be placed in bags/bins at both land and marine-based work sites and disposed of at WENT Landfill by truck via Nim Wan Road (for the GRS at the BPPS) or via the Outlying Island Transfer Facilities by barge/marine vessel (for the GRS at the LPS, LPS and BPPS Pipeline construction and Jetty) on a regular basis.  Given that the quantity of general refuse to be disposed of at landfill is small, no adverse impact on the operation of the landfill is anticipated.

With the implementation of the mitigation measures recommended in Section 8.5, no adverse environmental impacts (including potential hazard, dust and odour emissions, noise and wastewater discharge) caused by storage, handling, transport and disposal of general refuse are expected.

8.4                                   Expected Waste Arisings during Operation Phase

During the operation phase of the Project, the major waste types potentially to be generated include:

¡P             Industrial waste from maintenance activities at the GRSs at the BPPS and the LPS and LNG Terminal;

¡P             Chemical waste from maintenance of plant and equipment and the GRSs at the BPPS and the LPS and LNG Terminal;

¡P             Dredged marine sediment from maintenance dredging in the vicinity of the Jetty, if needed; and

¡P             General refuse from site operations at the GRSs at the BPPS and the LPS, the LNG Terminal and floating refuse collected at the LNG Terminal.

Options will be further developed and evaluated to reduce waste generation and enhance re-use and recycling of waste generated during the operation phase of the Project. 

8.4.1                           Industrial Waste

Industrial waste will arise from the maintenance activities at the GRSs and the LNG Terminal.  The wastes may include minimal quantity of filters and scrap materials from maintenance of plant and equipment and cleaning materials.  Scrap materials will be collected regularly for recycling, where appropriate, as such it is not expected that storage, handling, transport and disposal of industrial waste will cause any adverse environmental impacts.  General industrial waste, such as plastic, metal cans and waste paper, will be collected together with the general refuse for segregation.  Industrial wastes arising from the LNG Terminal will be temporarily stored on board the FSRU Vessel and disposed of by barge/marine vessel to the Outlying Island Transfer Facilities.  Industrial wastes arising from the GRSs at the BPPS and the LPS will be disposed of, together with the general waste arising from the operation of the BPPS and the LPS, by truck to the WENT Landfill via Nim Wan Road or Outlying Island Transfer Facilities by barge/marine vessel respectively.

8.4.2                           Chemical Waste

It is anticipated that a small amount of chemical waste, including MARPOL waste, will be generated from maintenance activities at the GRSs at the BPPS and the LPS and the LNG Terminal.  The chemical wastes may include empty chemical containers, oily rags etc and the quantity to be generated is expected to be insignificant.  The chemical waste will be collected by a licensed chemical waste collector and delivered to the licensed chemical waste treatment facilities for disposal at the CWTC at Tsing Yi.  With the incorporation of suitable arrangements for the storage, handling, collection and transportation and disposal of chemical waste under the requirements stated in the Waste Disposal (Chemical Waste) (General) Regulation and the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, no adverse environmental (including air and odour emissions, noise and waste water discharge) impacts and hazards are anticipated.

8.4.3                           Dredged Marine Sediment

It is anticipated that siltation may deposit of marine sediment at the Site of the LNG Terminal throughout the Project¡¦s operation.  In order to enable the safe navigation of the visiting LNGC and the FSRU Vessel, to and from the LNG Terminal site, maintenance dredging may be required once every 5 years (subjected to site conditions).  Maintenance dredging will be restricted to specific small areas around the LNG Terminal.  Bathymetric surveys will be carried out to ascertain the requirement for any maintenance dredging and the volume of marine sediment to be removed due to siltation.

Marine sediment quality testing results in the vicinity of the LNG Terminal (summarized in Table 8.3), indicate that the marine sediment resulting from maintenance dredging is anticipated to be uncontaminated and could be disposed at open sea disposal sites.  Separate marine sediment quality testing would be conducted prior to the maintenance dredging works to confirm the level of contamination and to identify the disposal method.  The marine sediment quality testing would follow the requirement set out in the PNAP ADV-21.  The final disposal site would be determined by the MFC and a dumping licence will be obtained from EPD prior to the commencement of the maintenance dredging works. 

The barges to be used for any marine sediment transport and disposal will be fitted with seals to prevent leakage of sediment, and no overloading of material and sediment laden water will be allowed during loading or transportation.  As such no adverse impact on water quality and marine ecology associated with this marine transport and disposal is expected.

8.4.4                           General Refuse

General refuse will arise from the operation staff and administrative activities at the LNG Terminal and the GRSs at the BPPS and the LPS.  General refuse may consist of food waste, plastic, aluminium can and waste paper.  Assuming that a 50 person crew is required to operate the LNG Terminal (including FSRU Vessel), with a general refuse generation rate of 0.65kg per worker per day ([6]), the amount of general refuse to be generated will be about 32.5kg per day.  The operation staff at the GRSs at the BPPS and the LPS is expected to be existing staff at the BPPS and the LPS who will carry out infrequent maintenance works.  Additional general refuse from the operation of the GRSs is thus limited.

Floating refuse may be trapped by the FSRU Vessel, a visiting LNGC and the structure of the Jetty.  However, the likelihood of entrapment of floating refuse at the LNG Terminal is low as (i) the LNG Terminal is located in open sea with constant of water currents, (ii) the Jetty will be constructed on a pile-type or jacket type structure which allows water flow under it, (iii) the body of the FSRU Vessel and a visiting LNGC are smooth in nature, which is not prone to trapping and accumulates of floating refuse, and (iv) a visiting LNGC will only be at berth for a short period.  Hence, the quantity of floating refuse is expected to be low.  Floating refuse, if any, will be collected on an ¡¥as needed¡¦ basis and disposed of as general refuse.

To reduce the quantity of general refuse to be disposed at landfill, recyclable materials (i.e. paper, plastic bottles, aluminium cans and glass bottles) will be segregated on-site and delivered to recyclers.  The non-recyclable general refuse from the LNG Terminal will be collected, stored and disposed of by barge/marine vessel to the Outlying Island Transfer Facilities on a regular basis.  General refuse arising from the GRS at the BPPS and the GRS at the LPS will be disposed of, together with the general waste arising from the operation of the BPPS and the LPS, by truck to the WENT Landfill via Nim Wan Road or the Outlying Island Transfer Facilities by barges/ marine vessel, respectively.  Given that the quantity of general refuse to be disposed of at landfill is small, no adverse environmental impacts (including potential hazard, dust and odour emissions, noise and wastewater discharge) associated with the handling and disposal of the general refuse is anticipated.

8.5                                   Mitigation Measures

8.5.1                           Waste Management Hierarchy

The various waste management options are categorised in terms of preference from an environmental viewpoint.  The options considered to be most preferable have the least environmental impacts and are more sustainable in the long term.  The hierarchy is as follows:

¡P            Avoidance and reduction;

¡P            Re-use of materials;

¡P            Recovery and recycling; and

¡P            Treatment and disposal.

The above hierarchy has been used to evaluate and select waste management options.  The aim has been to reduce waste generation and reduce waste handling and disposal costs. 

The Contractors will consult the relevant authorities for the final disposal of wastes and, as appropriate, implement the good site practices and mitigation measures recommended in this EIA Report and those given below.

¡P            Nomination of approved personnel to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility of all wastes generated at the site;

¡P            Training of site personnel in proper waste management and chemical handling procedures;

¡P            Provision of sufficient waste disposal points and regular collection for disposal;

¡P            Appropriate measures to reduce windblown/ floating litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers;

¡P            Separation of chemical wastes for special handling and appropriate treatment at the Chemical Waste Treatment Centre; and

¡P            A recording system for the amount of wastes generated, recycled and disposed of and the disposal sites.

Waste Reduction Measures 

Good management and control can prevent the generation of significant amount of waste.  Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices.  Recommendations to achieve waste reduction include:

¡P            Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance re-use or recycling of waste materials and their proper disposal;

¡P            Encourage collection of aluminium cans and waste paper by individual collectors during construction with separate labelled bins provided to segregate these wastes from other general refuse by the workforce;

¡P            Any unused chemicals, and those with remaining functional capacity, be recycled as far as possible;

¡P            Use of reusable non-timber formwork to reduce the amount of C&D materials;

¡P            Prior to disposal of C&D materials, wood, steel and other metals will be separated, to the extent practical for re-use and/or recycling to reduce the quantity of waste to be disposed in a landfill;

¡P            Proper storage and site practices to reduce the potential for damage or contamination of construction materials; and

¡P            Plan and stock construction materials carefully to reduce amount of waste generated and avoid unnecessary generation of waste.

8.5.2                           Construction Phase

The assessment indicates that with the implementation of the waste management practices at the land and marine-based work sites, no adverse environmental impacts are envisaged for the handling, collection and disposal of waste arising during the construction phase of the Project. 

This Section further describes the good construction site practices to avoid or further reduce the potential environmental impacts associated with the handling, collection and disposal of marine sediment, C&D materials, chemical waste and general refuse (including floating refuse) arising from the construction works.  

The Contractor(s) must ensure that all the necessary waste disposal and marine dumping permits or licences are obtained prior to the commencement of the construction works.

Management of Waste Disposal

The Contractor(s) will open a billing account with the EPD in accordance with the Waste Disposal (Charges for Disposal of Construction Waste) Regulation.  Every construction waste or public fill load to be transferred to Government waste disposal facilities (e.g. public fill reception facilities, sorting facilities and landfills) will be provided with a valid ¡§chit¡¨ which contains the information of the account holder to facilitate waste transaction recording and billing to the waste producer.  A trip-ticket system will also be established in accordance with DevB TC(W) No. 6/2010 to monitor the disposal of construction waste at landfill and to control fly-tipping.  The trip-ticket system will be included as one of the contractual requirements and implemented by the Contractor(s).

A waste management plan (WMP) as stated in the PNAP ADV-19 for the amount of waste generated, recycled and disposed of (including the disposal sites) will be established and implemented during the construction phase as part of the Environmental Management Plan (EMP).  The Contractor will be required to prepare the EMP and submit it to the Engineer with the Project Proponent under the Contract for approval prior to implementation. 

Measures for the Disposal of Dredged Marine Sediments

The management of dredged marine sediment requirement PNAP ADV-21 will be incorporated in the Contract for the construction of the Project.

Disposal vessels will be fitted with tight bottom seals in order to prevent leakage of material during transport.

Barges will be filled to a level, which ensures that of marine sediment and marine sediment laden water does not spill over during loading or transport to the disposal site and that adequate freeboard is maintained to ensure that the decks are not washed by wave action.

After dredging, any excess materials will be cleaned from decks and exposed fittings before the vessel is moved from the dredging area.

When the dredged material has been unloaded at the disposal areas, any material that has accumulated on the deck or other exposed parts of the vessel will be removed and placed in the hold or a hopper.  Under no circumstances will decks be washed clean in a way that permits material to be released overboard.

Dredgers will maintain adequate clearance between vessels and the seabed at all states of the tide and reduce operations speed to ensure that excessive turbidity is not generated by turbulence from vessel movement or propeller wash.

Measures for the Reduction of C&D Material

C&D materials will be segregated on-site into public fill and non-inert C&D materials and stored in different containers or skips to facilitate re-use of the public fill and proper disposal of the non-inert C&D materials.  Specific areas of the land and marine-based construction sites will be designated for such segregation and storage, if immediate re-use is not practicable.  Prefabrication will be adopted as far as practicable to reduce the C&D materials arising. 

Measures for Management of Chemical Waste

The Contractor(s) will register as a chemical waste producer with the EPD.  Chemical waste will be handled in accordance with the Code of Practice on the Packaging, Handling and Storage of Chemical Wastes as listed below. 

Containers used for storage of chemical wastes will:

¡P             Be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed;

¡P             Have a capacity of less than 450L unless the specifications have been approved by the EPD; and

¡P             Display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations.

The storage area for chemical wastes will:

¡P             Be clearly labelled and used solely for the storage of chemical waste;

¡P             Be enclosed on at least 3 sides;

¡P             Have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest;

¡P             Have adequate ventilation;

¡P             Be covered to prevent rainfall entering (water collected within the bund must be tested and disposed of as chemical waste, if necessary); and

¡P             Be arranged so that incompatible materials are appropriately separated.

Chemical waste will be disposed of:

¡P             Via a licensed waste collector; and

¡P             To a facility licensed to receive chemical waste, such as the CWTC which also offers a chemical waste collection service, and can supply the necessary chemical waste storage containers.

Measures for Management of General Refuse

General refuse (including the floating refuse collected) will be stored in enclosed bins separately from C&D materials and chemical wastes.  Floating refuse will be collected on an ¡¥as needed¡¦ basis for disposal as general refuse.  Workers will be prohibited from throwing rubbish into the sea and adequate bins will be provided on both land and marine-based sites and marine vessels.  General refuse will be delivered separately from C&D materials and chemical wastes for offsite disposal on a regular basis to reduce odour, pest and litter impacts.  General refuse from the marine vessels will be collected and disposed on shore.

Recycling bins will be provided at strategic locations within the land and marine-based construction site and marine vessels to facilitate recovery of recyclable materials (including aluminium can, waste paper, glass bottles and plastic bottles) from the Project Site.  Materials recovered will be sold for recycling.

In addition, to avoid any odour and litter impact, an appropriate number of portable toilets will be provided for workers on the land and marine-based sites.

Staff Training

At the commencement of the construction works, training will be provided to workers on the concepts of site cleanliness and appropriate waste management procedures, including waste reduction, re-use and recycling.  In particular, the training will emphasize no dumping of waste into the sea is allowed, particularly at marine-based work sites and on marine vessels.

8.5.3                           Operation Phase

Measures for Industrial Waste

Industrial waste arising from maintenance activities will be segregated.  Scrap metals and recyclables will be sent for recycling to reduce the overall quantity of waste disposed from these activities. 

Measures for Management of Chemical Waste

The measures for management of chemical waste during operation phase are similar to those outlined in Section 8.5.2.

Measures for the Disposal of Dredged Marine Sediments

The management of dredged marine sediment shall follow the requirements stipulated in PNAP ADV-21.

The measures for management of marine sediment during operation phase are similar to those outlined in Section 8.5.2.

Measures for Management of General Refuse

The management of general refuse from the GRSs at the BPPS and the LPS and LNG Terminal staff during the operation phase will be similar to that in the construction phase (see Section 8.5.2).  Floating refuse at the LNG Terminal will be collected on an ¡¥as needed¡¦ basis for disposal as general refuse.  General refuse and non-recyclables will be stored in enclosed bins and disposed offsite on a regular basis for avoidance of pest and odour nuisance.  Recycling bins for recyclable materials (including aluminium can, waste paper, glass bottles and plastic bottles) will be placed at the site office and transported off-site for recycling on a regular basis.

Staff Training

Similar to the training requirement described in Section 8.5.2, prior to the commencement of the operation phase, training will be provided to all staff working at the GRSs at the BPPS and the LPS and LNG Terminal on the concepts of site cleanliness and appropriate waste management procedures, including waste reduction, re-use and recycling.  In particular, the training will emphasize no dumping of waste into the sea is allowed, at the LNG Terminal.

8.6                                   Residual Environmental Impacts

No adverse residual waste management impact is anticipated during the construction and operation phases of the Project.

8.7                                   Environmental Monitoring and Audit

8.7.1                           Construction Phase

During construction, site audits at both land and marine-based work sites will be undertaken by the Project Proponent and the Contractor on a monthly basis to determine if wastes are being managed in accordance with the recommended good site practices in this EIA Report and the requirements in the WMP.  The audits will investigate all aspects of waste management, including waste generation, storage, handling, recycling, transportation and disposal, to prevent any dumping of waste into the sea or malpractice of waste disposal.

8.7.2                           Operation Phase

As the operation of the GRSs at the BPPS and the LPS and LNG Terminal will generate minimal quantity of waste and no adverse environmental impacts will arise with the implementation of standard waste management practices, waste monitoring and audit programme for the operation phase of the facilities will not be required.

8.8                                   Conclusions

With the implementation of good site practices, adverse environmental impacts (including potential hazards, dust and odour emissions, noise and wastewater discharge) arising from the management and disposal of waste during the construction phase and the operation phase are not anticipated.

The estimated waste arising and the recommend waste management arrangements during the construction phase and operations phase of the Project are summarised in Table 8.5.

Options will be further developed and evaluated to reduce waste generation and to enhance re-use and recycling of waste generated during the construction and operation phases of the Project.


 

Table 8.5        Summary of Estimated Waste Arisings and Recommended Waste Management Arrangements

Types of Waste

Approximate Quantity (a)

Disposal Locations

Construction Phase

 

 

Marine sediments

Total: 0.35Mm3 (in situ volume):

Category L sediment: 0.03Mm3

Category M sediment which passed the biological screening test: 0.32Mm3

 

 

Category L sediment ¡V to be disposed of at open sea disposal site managed by the CEDD

Category M sediment which passed the biological screening test - to be disposed of at Type 1 Open Sea (Dedicated Sites)

The disposal sites are to be allocated by MFC/ CEDD under the PNAP ADV-21.  The project proponent will implement the project in accordance with the DASO and the requirements as stipulated in PNAP ADV-21, prior to the application and allocation of space for dredging and disposal of sediment arising from the project. 

C&D materials

Total: 45,000m3

Inert: 40,500m3

Non-inert: 4,500m3

Public fill: Public fill reception facilities directly or Outlying Island Transfer Facilities

Non-inert C&D materials: WENT Landfill directly or via Outlying Island Transfer Facilities

Chemical waste

Few hundred litres per month

CWTC or other licensed chemical waste treatment facilities

General refuse, including floating refuse

390kg per day

Recyclable materials: on-site sorting and off-site recycling

Non-recyclable refuse: WENT Landfill directly or via Outlying Island Transfer Facilities

Operation Phase

 

 

Industrial waste

Insignificant quantity

Recyclable materials: on-site sorting and off-site recycling

Non-recyclable refuse: WENT Landfill directly or via Outlying Island Transfer Facilities

Marine sediment from maintenance dredging

Subjected to site conditions

Marine disposal site to be allocated by the MFC/CEDD based on the sediment quality

Chemical waste

Insignificant quantity

CWTC or other licensed chemical waste recycling or treatment facilities

 

General refuse, including floating refuse

32.5kg per day

Recyclable materials: on-site sorting and off-site recycling

Non-recyclable refuse: WENT Landfill directly or via Outlying Island Transfer Facilities

 



([1])     ¡¨Construction waste¡¨ refers to materials arising from any land excavation or formation, civil/building construction, road works, building renovation or demolition activities.  It includes various types of reusable materials, building debris, rubble, earth, concrete, timber and mixed site clearance materials.  When sorted properly, materials suitable for land reclamation and site formation (known as public fill) should be re-used at public fill reception facilities.  The rock and concrete can be crushed and processed to produce aggregates for various civil and building engineering applications.  The remaining construction waste (comprising timber, paper, plastics, and general refuse) are to be disposed of at landfills.

([2])     In accordance with PNAP ADV-21, the sediment is classified into three categories based on its contamination levels:

¡P         Category L: Sediment with all contaminant levels not exceeding the Lower Chemical Exceedance Level (LCEL).  The material must be dredged, transported and disposed of in a manner which reduces the loss of contaminants either into solution or by re-suspension.

¡P         Category M : Any one or more contaminants in the sediment exceeding the LCEL with none exceeding the Upper Chemical Exceedance Level (UCEL).  The material must be dredged and transported with care, and must be effectively isolated from the environment upon final disposal unless appropriate biological tests demonstrate that the material will not adversely affect the marine environment.

¡P         Category H: Any one or more contaminants in the sediment exceeding the UCEL.  The material must be dredged and transported with great care, and must be effectively isolated from the environment upon final disposal.

([3])     The analytical results of some sediment sampling locations proposed in the MSSTP were not assessed as they are located along the non-dredged pipeline sections.

([4])     Ove Arup & Partners Hong Kong Ltd (2008) Agreement No. FM 01/2007 ¡V Review of Options for Management of Contaminated Sediment in Hong Kong.  Report on Assessment of Management Options Final Report (RevA). August 2008

([5])     Floating refuse refers to those marine refuse washed to the LNG Terminal construction site by water current.  They are not generated by the Project as workers are not allowed to dump rubbish into the sea.

([6])     This is considered as a conservative estimate based on the number reported in a number of EIA reports approved under the EIAO.