2.1 Description of Site Location of the Project and
History
2.2 Size, Scale, Shape and Design of the Project
2.4 The Need and Justification of the Project
2.5 “Without Project” Scenario – Franchised Bus Approach
2.8 Consequences of Not Proceeding with the Project
2.9 Construction Methods and Engineering Requirements
TABLES
Table 2.1 Summary
of Passenger Convenience Considerations
Table 2.2 Summary
of Engineering Considerations
Table 2.3 Summary
of Environmental Considerations
Table 2.4 Merits
and Demerits of the Construction Methods for the Proposed Bonded Vehicular
Bridge
Table 2.5 Summary
of the other Projects in the Vicinity of the Project Site
FIGURES
Figure 2.1 Illustration
of “Without Project” Scenario – Franchised Bus Approach, Route A
Figure 2.2 Illustration
of “Without Project” Scenario – Franchised Bus Approach, Route B
Figure 2.3 Illustration
of Option 1 – Bonded Vehicle on Public Road Approach
Figure 2.4 Illustration
of Option 2 – Bonded Vehicle on Bonded Road Approach
Figure 2.5 Illustration
of Option 3 – Bonded Vehicular Bridge Approach
Figure 2.6 Locations
of Concurrent Projects
Table 2.1 Summary of
Passenger Convenience Considerations
Trip Description |
No. of CIQ Process |
Travel Distance and Travelling Time |
Passenger Convenience Considerations |
||||
Travelling Distance between HKBCF & ITT (m) |
Journey
Time for ATB or BTA transit (mins) |
Provide Direct Access to Coach Station (ATB) |
Disturbance to HKIA Landside Traffic |
Disturbance to HKBCF Island Traffic |
|||
“Without Project” Scenario |
|
|
|
|
|
||
Franchised Bus Approach |
2 |
5500 m |
An extra hour including travelling time and CIQ clearance time is
required in the “Without Project” scenario |
Not Direct Access |
Significantly affected |
Moderately affected |
|
“With Project” Scenario |
|
|
|
|
|
||
Option 2 |
Bonded Vehicle on Bonded Road Approach |
0 |
1640 m |
Direct Access ü |
Moderately affected |
Not affected ü |
|
Option 3 |
Bonded Vehicular Bridge Approach |
0 |
1060 m |
Direct Access ü |
Not affected ü |
Not affected ü |
Table 2.2 Summary of Engineering
Considerations
Trip
Description |
Engineering
Considerations |
||||
Reduction
of Construction Time |
Reduction
of Traffic Impact during Construction |
Reduction
of Disturbance of Landside Air Permeability |
Effective
Utilisation of Land |
||
“Without Project” Scenario |
|
|
|
|
|
(a) Franchised Bus Approach |
N/A (see note 2) |
N/A (see note 2) |
N/A (see note 2) |
N/A (see note 2) |
|
“With Project” Scenario |
|
|
|
|
|
(b)
Option
2 |
Bonded Vehicle on Bonded Road Approach |
Faster ü |
Moderate Impact |
Moderate disturbance |
Extra Land Take for Land Connection on Airport
Island and HKBCF Island |
(c)
Option
3 |
Bonded Vehicular Bridge Approach (see note 1) |
Moderate |
Least Impact ü |
Least Disturbance ü |
Less extra Land Take for Land Connection on HKBCF
Island ü |
Remarks:
Note 1 – Precast construction method will improve
environmental performance and quality control in terms of site safety,
reduction of formworks, construction time and carbon emission, transportation
of construction material and subsequent adverse impact on existing landside
traffic, also reduce the dust and noise pollution during construction.
Note 2 – Traffic under
“Without Project” scenario will make use of existing HKIA and HKBCF road
network, no significant road construction anticipated.
Table 2.3 Summary of
Environmental Considerations
Trip
Description |
Environmental
Considerations |
||||
Environmental
Benefits |
Environmental
Disbenefits |
||||
“Without
Project” Scenario |
|
||||
(a)
Franchised Bus Approach |
·
The franchised buses would make use of the existing HKIA and HKBCF
public road network, no significant road construction is anticipated. Therefore there will be less construction
impact to the surrounding sensitive receivers. |
·
The bulk of the franchised buses are not electric vehicles which could
generate carbon emission and air pollutants. ·
To cater for the travel time between HKBCF and HKIA Passenger
Terminal, and to meet time-critical demand of air passengers, more franchised
buses are required for transfer services, resulting in more vehicular
emissions. ·
The franchised buses serving the air passengers will have greater
traffic impact to existing road networks and give rise to potential
congestion. ·
With the longest travelling distance from the ITT to HKBCF (or vice
and verse), the “Without Project” scenario gives rise to the highest energy
consumption by the vehicles and carbon emissions by power plants. |
|||
“With Project” Scenario |
|
|
|
|
|
(b)
Option
2 Bonded Vehicle on Bonded Road Approach |
·
All bonded vehicles will be electric vehicles which would eliminate carbon
emission and air pollutant emissions on site. ·
Since the bonded vehicles would not be using public roads, there will
be no disturbance to airport landside and HKBCF Island traffic. |
·
Extra land take is required for the bonded land connection section on
both Airport Island and HKBCF Island.
Mitigation measures may be required to minimise the construction
impact to the surrounding sensitive receivers. ·
The erection of fences and/or guard posts for the bonded land
connection would pose visual impact on nearby Visual Sensitive Receivers
(VSRs), and undermine the amenity and landscaping value which could otherwise
be created at the waterfront of Airport Island. ·
Land based construction works for the bonded roads and land connection
section on land will give rise to more construction & demolition
(C&D) materials and waste compared to sea-based construction works. ·
Among the options under “With Project” scenario, the travelling
distance from ITT to HKBCF (or vice and verse) via a Bonded Road is the
longest, leading to higher energy consumption by vehicles and carbon
emissions by power plants. |
|||
(c)
Option
3 Bonded Vehicular Bridge Approach |
·
All bonded vehicles will be electric vehicles which would eliminate
carbon emission and air pollutant emission on site. ·
With the least travelling distance from the ITT to HKBCF (or vice and
verse), it will not only significantly improve passenger convenience, but
also help reduce road traffic, energy consumption by vehicles and the
associated environmental impacts. ·
The option has the most
extensive pre-cast construction among other options, thus minimising impact
to local environment. ·
Security fences on the marine section of the Bonded Vehicular Bridge
are not required (subject to agreement with law enforcement
agencies), hence visual impact to surrounding VSRs can be further reduced. |
·
Compared to other options/scenario, the Bonded Vehicular Bridge is
located closer to visual sensitive receivers such as SkyCity Marriott Hotel
and Passenger Clearance Building of HKBCF, hence, mitigation measures may be
required to minimise the visual impact. ·
As bridge
columns are required within the sea channel between HKIA and HKBCF, water
quality and hydraulic impact on the sea channel is therefore anticipated due
to the additional structures and construction activities within the sea
channel. Though the sea channel is not known for having significant marine
ecological resources due to its proximity to the SkyPier, suitable mitigation
measures are required to reduce the impact to an acceptable level. |
|||
Table 2.4 Merits and Demerits of the Construction Methods for the
Proposed Bonded Vehicular Bridge
Construction Methods |
Cast In-place Concrete |
Prefabricated Steel Structure |
Precast Concrete |
Merits |
·
Conventional construction method and require relatively less special
skilled when comparing with other construction methods considered. ·
Durable and less maintenance cost. |
·
Conduct prefabrication works in fabrication yard away from the site. ·
Better control of quality and workmanship for works in fabrication
yard. ·
Fabricate the whole bridge deck structure by steel plates / members
and no formworks. ·
More efficient construction works as the deck structure can be
fabricated off-site concurrently with the substructure works (i.e. allow time
overlap of construction activities). ·
Shorten construction time relatively, bridge deck construction can be
non-linear (multiple work fronts), with minimising on-site potential
environmental impacts. ·
Requires less temporary steel platforms, relatively, for construction
of light weight steel structure, thus resulting in smaller area of temporary
habitat loss. |
·
Conduct precasting works in fabrication yard away from the site. ·
Better control of quality and workmanship for works in fabrication
yard. ·
Use steel mould as formworks to maximise the reuse of formwork, which
is more environmental-friendly. ·
More efficient construction works as the deck segments can be casted
off-site concurrently with substructure works (i.e. allow time overlap of
construction activities). ·
Shorten construction time, bridge deck construction can be non-linear
(multiple work fronts), with minimising on-site potential environmental
impacts. ·
Durable and less maintenance cost. ·
Relatively requires less temporary steel platform for construction of
precast structure, thus resulting in smaller area of temporary habitat loss. |
Demerits |
·
Prepare concrete mix at a central batching plant, where controls of
the materials should be monitored much carefully. ·
For transporting concrete to the site, proper mixing in truck,
discharging from the truck and depositing in the forms, and handling for
placement, finishing and curing are all subject to the level of
responsibility and craft exercised by the workers involved. ·
Site conditions in terms of accessibility and weather can be highly
critical to the work, requirement of extreme measures in some situations to
control all stages in the production process. Possibility of site run-off
might be higher under bad weather conditions. ·
Use timber formwork, which is less environmental-friendly. ·
Longer construction time – carry out bridge deck construction only (1)
after substructure works is completed and (2) after completion of previous
span for cast in-place span by span. ·
Require substantial temporary steel platform / falsework for
construction of the marine bridge deck section. |
·
Subject to high risk of steel corrosion, while the application of
anti-corrosion paint might lead to the deterioration of water quality. ·
High maintenance cost. ·
Less durable. ·
Require another trade of skilled workers and additional construction
equipment for erecting steelwork structures. |
·
Require another trade of skilled workers and additional construction
equipment for erecting precast segments. |
Table 2.5 Summary of the other Projects in the Vicinity of the Project Site
Project |
Project Proponent |
Construction Programme |
Potential Cumulative
Impact |
||
Start |
Complete |
Construction |
Operation |
||
Expansion of Hong Kong International Airport into a Three-Runway System (3RS) |
Airport Authority Hong Kong |
August 2016 |
2024[1] |
ü |
ü |
Tung Chung New Town Extension and its Associated Infrastructures |
Civil Engineering and Development Department |
Mid 2017 |
End 2030[2] |
ü |
ü |
Tuen Mun – Chek Lap Kok Link (TMCLKL) |
Highways Department |
Nov 2011 |
2020[3] |
- |
ü |
Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HKZMB HKBCF) |
Highways Department |
Nov 2011 |
End 2017[4] |
- |
ü |
Planning, Engineering and Architectural Study for Topside Development at HKBCF Island of the HZMB – Feasibility Study |
Civil Engineering and Development Department & Planning Department |
Study is under feasibility study stage and yet to be concluded. The construction programme is yet to be confirmed. |
N/A |
N/A |
|
Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road (HKZMB HKLR) – Feasibility Study |
Highways Department |
May 2012 |
End 2017[5] |
- |
ü |
North Commercial District |
Airport Authority Hong Kong |
2017 |
2022[6] |
ü |
ü |
Intermodal Transfer Terminal |
Airport Authority Hong Kong |
2018[6] |
2021[6] |
ü |
ü |
“ü”= may have potential cumulative impact;
“-“ = potential cumulative impact is not
anticipated;
“N/A” = information not available
[1] Source: Hong Kong
International Airport Media Center Press Release
[2] Source: Approved
Tung Chung New Town Extension EIA Report (Register No.: AEIAR-196/2016)
[3] Source: Highway
Department’s website at https://www.hyd.gov.hk/en/road_and_railway/hzmb_projects/tmclkl/index.html
[4] Source: Highway
Department’s HZMB website at http://hzmb.hk/eng/index.html
[5] Source: Highway
Department’s HZMB website at http://hzmb.hk/eng/index.html
[6] Source: Information
provided by AAHK