5.1.1
This section presents the
assessment on potential water quality impact arising from construction and
operation of the Project, which has been conducted in accordance with the
criteria and guidelines as stated in Annexes 6 and 14 of the Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM) as well as the
requirements given in Clause 3.4.5 and Appendix C of the EIA Study Brief (No.
ESB-302/2017).
5.1.2
The potential water quality
impact arising from operational phase of the Project has been assessed with the
use of the computational modelling approach. The proposed calibration and validation,
the modelling parameters, model coverage area, and grid schematization for
water quality model simulation, and cumulative impacts due to other projects,
activities or pollution sources within a boundary have been agreed with the
Director of EPD in accordance with
Appendix C-1 of the EIA Study Brief (No.
ESB-302/2017).
Technical Memorandum on Environmental Impact
Assessment Ordinance (EIAO-TM)
5.2.1
The EIAO-TM was issued by EPD
under Section 16 of the EIAO.
Reference sections in the EIAO-TM provide the details of assessment
criteria and guidelines that are relevant to the water quality assessment,
including:
¡P
Annex 6 - Criteria for
Evaluating Water Pollution; and
¡P
Annex 14 - Guidelines for
Assessment of Water Pollution.
Water Quality Objectives
5.2.2
The Water Pollution Control
Ordinance (WPCO) provides the major statutory framework for the protection and
control of water quality in Hong Kong.
According to the WPCO and its subsidiary legislation, Hong Kong waters
are divided into ten Water Control Zones (WCZs). Corresponding statements of Water
Quality Objectives (WQOs) are stipulated for different water regimes (marine
waters, inland waters, bathing beaches subzones, secondary contact recreation
subzones and fish culture subzones) in the WCZs based on their beneficial
uses. The Project site is located
within the North Western WCZ. The
WQOs for the North Western WCZ is listed in Table 5.1. These WQOs were used as the water
quality assessment criteria for the Project.
Table 5.1 Summary
of Water Quality Objectives for North Western WCZ
Parameters
|
Objectives
|
Sub-Zone
|
Offensive Odour, Tints
|
Not to be present
|
Whole zone
|
Visible foam, oil scum, litter
|
Not to be present
|
Whole zone
|
Dissolved Oxygen (DO) within 2 m of the seabed
|
Not less than 2.0 mg/L for 90% of sampling occasions during the whole
year
|
Marine waters
|
Depth-averaged DO
|
Not less than 4.0 mg/L
|
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones, Water Gathering
Ground Subzones and other inland waters
|
|
Not less than 4.0 mg/L for 90 % of the sampling occasions during the
whole year
|
Marine waters
|
pH
|
To be in the range of 6.5 - 8.5, change due to
human activity not to exceed 0.2
|
Marine waters excepting Bathing Beach Subzones
|
|
To be in the range of 6.5 ¡V 8.5
|
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones
|
|
To be in the range of 6.0 ¡V9.0
|
Other inland waters
|
|
To be in the range of 6.0 ¡V9.0 for 95% samples collected during the
whole year and waste discharges shall not cause the natural pH range to be
extended by more than 0.5 units
|
Bathing Beach Subzones
|
Salinity
|
Change due to human activity not to exceed 10% of ambient
|
Whole zone
|
Temperature
|
Change due to human activity not to exceed 2 oC
|
Whole zone
|
Suspended solids (SS)
|
Waste discharge not to raise the ambient level by
30% caused, nor cause the accumulation of suspended solids which may
adversely affect aquatic communities
|
Marine waters
|
|
Not to cause the annual median to exceed 20 mg/L
|
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones
|
|
Not to cause the annual median to exceed 25 mg/L
|
Inland waters
|
Unionized Ammonia (UIA)
|
Annual mean not to exceed 0.021 mg/L as unionized form
|
Whole zone
|
Nutrients
|
Shall not cause excessive algal growth
|
Marine waters
|
Total Inorganic Nitrogen (TIN)
|
Annual mean depth-averaged inorganic nitrogen not
to exceed 0.3 mg/L
|
Castle Peak Bay Subzone
|
|
Annual mean depth-averaged inorganic nitrogen not to exceed 0.5 mg/L
|
Marine waters excepting Castle Peak Bay Subzone
|
Bacteria
|
Not exceed 610 per 100ml, calculated as the
geometric mean of all samples collected in one calendar year
|
Secondary Contact Recreation Subzones
|
|
Should be less than 1 per 100 ml, calculated as
the running median of the most recent 5 consecutive samples taken between 7
and 21 days.
|
Tuen Mun (A) and Tuen Mun (B) Subzones and Water
Gathering Ground Subzones
|
|
Not exceed 1000 per 100 ml, calculated as the
running median of the most recent 5 consecutive samples taken between 7 and
21 days
|
Tuen Mun (C) Subzone and other inland waters
|
|
Not exceed 180 per 100 ml, calculated as the geometric mean of all
samples collected from March to October inclusive. Samples should be taken at
least 3 times in one calendar month at intervals of between 3 and 14 days.
|
Bathing Beach Subzones
|
Colour
|
Not to exceed 30 Hazen units
|
Tuen Mun (A) and Tuen Mun (B) Subzones and Water
Gathering Ground Subzones
|
|
Not to exceed 50 Hazen units
|
Tuen Mun (C) Subzone and other inland waters
|
5-Day Biochemical Oxygen Demand (BOD5)
|
Not to exceed 3 mg/L
|
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones
|
|
Not to exceed 5 mg/L
|
Inland waters
|
Chemical Oxygen Demand (COD)
|
Not to exceed 15 mg/L
|
Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C)
Subzones and Water Gathering Ground Subzones
|
|
Not to exceed 30 mg/L
|
Inland waters
|
Toxins
|
Should not cause a risk to any beneficial uses of
the aquatic environment
|
Whole zone
|
|
Waste discharge shall not cause the toxins in water significant to
produce toxic carcinogenic, mutagenic or teratogenic effects in humans, fish
or any other aquatic organisms.
|
Whole zone
|
Phenol
|
Quantities shall not sufficient to produce a specific odour or more
than 0.05 mg/L as C6 H5OH
|
Bathing Beach Subzones
|
Turbidity
|
Shall not reduce light transmission substantially from the normal
level
|
Bathing Beach Subzones
|
Source: Statement
of Water Quality Objectives (North Western Water Control Zone)
Technical Memorandum on Effluent Discharge
Standard
5.2.3
Besides setting the WQOs, the
WPCO controls effluent discharging into the WCZs through a licensing
system. Guidance on the permissible
effluent discharges based on the type of receiving waters (foul sewers, stormwater
drains, inland and coastal waters) is provided in the ¡§Technical Memorandum
on Standards for Effluents Discharged into Drainage and Sewerage Systems,
Inland and Coastal Waters¡¨ (TM-DSS), issued under Section 21 of the WPCO. The limits given in the TM-DSS cover the
physical, chemical and microbial quality of effluents. Any discharge during the construction
and operational stages should comply with the standards for effluent discharged
into the foul sewers, inshore waters and marine waters of the North Western WCZ
as stipulated in the TM-DSS.
Practice Note
5.2.4
A practice note for
professional persons has been issued by the EPD to provide guidelines for
handling and disposal of construction site discharges. The Practice Note for Professional
Persons on Construction Site Drainage (ProPECC PN 1/94) "Construction
Site Drainage" provides good practice guidelines for dealing with ten
types of discharge from a construction site. These include surface runoff,
groundwater, boring and drilling water, bentonite slurry, water for testing and
sterilisation of water retaining structures and water pipes, wastewater from
building construction, acid cleaning, etching and pickling wastewater, and
wastewater from site facilities. Guidelines
given in the ProPECC PN 1/94 should be followed as far as possible during
construction to minimise the water quality impact due to construction site
drainage.
5.2.5
The ProPECC PN 5/93 "Drainage
Plans subject to Comments by Environmental Protection Department"
provides guidelines and practices for handling, treatment and disposal of
various effluent discharges to stormwater drains and foul sewers. The design of site drainage and disposal
of various site effluents generated within the Project should follow the
relevant guidelines and practices as given in the ProPECC PN 5/93.
5.3.1
Key marine Water Sensitive
Receivers (WSRs) within the study area in North Western WCZ are identified with
reference to Annex 14 of the EIAO-TM and their indicative locations are shown
in Figure 5.1. The identified WSRs include.
¡P
Cooling Water Intakes;
¡P
Flushing Water Intakes;
¡P
Bathing Beaches (both gazetted
and non-gazetted);
¡P
Typhoon Shelter;
¡P
Marine Park;
¡P
Corals;
¡P
Artificial Reefs;
¡P
Horseshoe Crab;
¡P
Seagrass;
¡P
Fish Spawning Ground;
¡P
Site of Special Scientific
Interest (SSSI);
¡P
Proposed Marina at Tung Chung
East Reclamation
¡P
Mangrove Communities; and
¡P
Committed / Potential Marine
Park.
5.4.1
The marine water quality
monitoring data routinely collected by EPD were used to establish the baseline
condition. A summary of marine
water quality data collected in 2016 is presented in Table 5.2 for the
monitoring stations in North Western WCZ (NM1, NM2, NM3, NM5, NM6 and
NM8). Monitoring data for North
Western Supplementary WCZ was not available from EPD's routine monitoring
programme. Descriptions of the
baseline conditions for individual WCZ provided in the subsequent sections are
directly extracted from the EPD's report "Marine Water Quality in Hong
Kong 2016".
5.4.2
In 2016, the North Western WCZ
attained an overall WQO compliance rate of 72%. All stations in the WCZ fully complied
with the UIA and DO objectives.
Apart from NM1, all the other five stations in this WCZ did not meet the
TIN objective. The relatively high
levels of TIN (annual mean 0.44-0.78 mg/L) were likely attributed to the higher
background level of Pearl River, and some local discharges and surface runoff
from the Northwestern New Territories as well as North Lantau.
5.4.3
Sediment Sampling and Testing
Plan (SSTP) has been conducted to establish the sediment quality within the
study area. Details on the sediment
quality can be referred to Section 6 and Appendix 6.3.
Table
5.2 Summary
of Water Quality Statistics for the North Western WCZ in 2016
|
Lantau Island (North)
|
Pearl Island
|
Pillar Point
|
Urmston Road
|
Chek Lap Kok
|
WPCO WQO
(in marine waters)
|
(North)
|
(West)
|
Parameter
|
NM1
|
NM2
|
NM3
|
NM5
|
NM6
|
NM8
|
Temperature (oC)
|
23.3
(16.2
- 28.5)
|
23.6
(15.6
- 28.7)
|
23.7
(15.9
- 28.6)
|
23.7
(15.8
- 28.8)
|
24.0
(15.5
- 28.8)
|
24.0
(15.8
- 28.7)
|
Not
more than 2 oC in daily temperature range
|
Salinity
|
28.6
(22.4
- 30.7)
|
26.0
(15.9
- 30.2)
|
26.2
(16.0
- 30.7)
|
24.9
(17.2
- 29.7)
|
22.5
(13.5
- 29.7)
|
24.2
(9.4
- 30.8)
|
Not
to cause more than 10% change
|
Dissolved
Oxygen (DO) (mg/L)
|
Depth average
|
5.6
(4.0
- 8.0)
|
5.8
(4.0
- 8.2)
|
5.6
(4.2
- 8.1)
|
5.7
(4.1
- 7.9)
|
6.0
(4.8
- 8.5)
|
6.1
(4.6
- 7.8)
|
Not
less than 4 mg/L for 90% of the samples
|
Bottom
|
5.2
(2.2
- 8.1)
|
5.5
(3.7
- 8.3)
|
5.4
(3.0
- 8.1)
|
5.3
(2.6
- 8.0)
|
5.8
(4.1
- 8.2)
|
5.8
(4.1
- 7.5)
|
Not
less than 2 mg/L for 90% of the samples
|
Dissolved
Oxygen (DO) (% Saturation)
|
Depth average
|
76
(57
- 98)
|
78
(60
- 100)
|
76
(62
- 99)
|
76
(56
- 96)
|
81
(64
- 103)
|
83
(65
- 99)
|
Not
available
|
Bottom
|
71
(31
- 99)
|
75
(53
- 102)
|
73
(42
- 99)
|
72
(37
- 98)
|
77
(57
- 99)
|
79
(56
- 99)
|
Not
available
|
pH
|
7.8
(7.4
- 8.3)
|
7.9
(7.4
- 8.3)
|
7.8
(7.4
- 8.3)
|
7.8
(7.4
- 8.1)
|
7.8
(7.4
- 8.3)
|
7.9
(7.4
- 8.3)
|
6.5
- 8.5 (¡Ó 0.2 from natural range)
|
Suspended
Solids (SS)
(mg/L)
|
7.5
(1.6
- 24.3)
|
6.7
(1.5
- 18.7)
|
9.3
(1.9
- 25.0)
|
10.2
(2.4
- 20.3)
|
8.6
(2.5
- 23.1)
|
13.9
(1.9
- 31.5)
|
Not
more than 30% increase
|
5-day
Biochemical Oxygen Demand (BOD5) (mg/L)
|
0.8
(0.3
- 1.5)
|
0.7
(0.3
- 1.5)
|
0.7
(0.3
- 1.1)
|
0.7
(0.4
- 1.6)
|
1.1
(0.3
- 5.0)
|
0.7
(0.1
- 1.7)
|
Not
available
|
Ammonia
Nitrogen (NH3-N)
(mg/L)
|
0.103
(0.033
- 0.197)
|
0.114
(0.053
- 0.273)
|
0.122
(0.054
- 0.283)
|
0.138
(0.054
- 0.303)
|
0.112
(0.030
- 0.347)
|
0.071
(0.024
- 0.227)
|
Not
available
|
Unionised
Ammonia (UIA)
(mg/L)
|
0.003
(0.001
- 0.008)
|
0.003
(0.001
- 0.010)
|
0.004
(0.002
- 0.011)
|
0.003
(0.002
- 0.006)
|
0.003
(0.001
- 0.007)
|
0.002
(<0.001
- 0.004)
|
Not
more than 0.021 mg/L for annual mean
|
Nitrite
Nitrogen (NO2-N)
(mg/L)
|
0.045
(0.016
- 0.086)
|
0.058
(0.019
- 0.096)
|
0.056
(0.019
- 0.107)
|
0.072
(0.024
- 0.115)
|
0.077
(0.027
- 0.143)
|
0.056
(0.019
- 0.094)
|
Not
available
|
Nitrate
Nitrogen (NO3-N)
(mg/L)
|
0.296
(0.167
- 0.547)
|
0.434
(0.183
- 0.893)
|
0.397
(0.190
- 0.643)
|
0.516
(0.217
- 0.837)
|
0.591
(0.280
- 1.133)
|
0.486
(0.103
- 1.367)
|
Not
available
|
Total
Inorganic Nitrogen (TIN)
(mg/L)
|
0.44
(0.31
- 0.63)
|
0.61
(0.34
- 1.04)
|
0.58
(0.34
- 0.80)
|
0.73
(0.39
- 1.15)
|
0.78
(0.41
- 1.31)
|
0.61
(0.20
- 1.54)
|
Not
more than 0.5 mg/L for annual mean
|
Total
Nitrogen (TN)
(mg/L)
|
0.84
(0.56
- 1.10)
|
0.85
(0.42
- 1.22)
|
0.95
(0.54
- 1.35)
|
1.03
(0.57
- 1.57)
|
1.05
(0.60
- 1.47)
|
0.94
(0.45
- 1.72)
|
Not
available
|
Orthophosphate
Phosphorus (PO4) (mg/L)
|
0.025
(0.004
- 0.053)
|
0.029
(0.004
- 0.054)
|
0.030
(0.008
- 0.056)
|
0.033
(0.005
- 0.060)
|
0.031
(0.002
- 0.062)
|
0.021
(0.003
- 0.048)
|
Not
available
|
Total
Phosphorus (TP)
(mg/L)
|
0.07
(0.04
- 0.12)
|
0.10
(0.04
- 0.14)
|
0.10
(0.05
- 0.16)
|
0.11
(0.06
- 0.17)
|
0.11
(0.05
- 0.16)
|
0.09
(0.03
- 0.13)
|
Not
available
|
Chlorophyll-a
(µg/L)
|
2.7
(0.7
- 12.4)
|
3.0
(0.5
- 13.3)
|
2.1
(0.7
- 7.1)
|
2.2
(0.5
- 6.7)
|
5.2
(0.7
- 24.0)
|
4.1
(1.0
- 18.0)
|
Not
available
|
E.
coli
(cfu/100 mL)
|
27
(3 -
78)
|
35
(5 -
70)
|
54
(7 -
420)
|
210
(46
- 2000)
|
26
(2 -
120)
|
5
(<1
- 79)
|
Not
available
|
Note:
1. Except as specified, data presented are
depth-averaged values calculated by taking the means of three depths: surface,
mid-depth, bottom.
2. Data presented are annual arithmetic
means of depth-averaged results except for E.coli and faecal coliforms that are
annual geometric means.
3. Data in brackets indicate the ranges.
Construction Phase
5.5.1
The major sources of water
quality impacts during construction phase of the Project would potentially
include the following:
¡P
Construction of marine bridge
piles for the Bonded Vehicular Bridge;
¡P
Wastewater discharges from
general construction activities;
¡P
Drainage and construction site
runoff from land-based construction;
¡P
Sewage effluent produced by
construction workforce; and
¡P
Accidental spillage of
chemicals.
Operational Phase
5.5.2
The key operational phase
issues would be related to the change in hydraulic friction due to the
formation of bridge piles of the Bonded Vehicular Bridge, which may result in
change of flow regime in the sea channel between the HKIA and the HKBCF, and
its adjacent waters in North Western WCZ.
5.5.3
Potential water quality impacts
may also arise from the road surface runoff with suspended solids and sewage flow
generated from the proposed toilets during operational phase. Proper drainage systems with silt traps
should be installed, maintained and cleaned at regular intervals. All the sewage flow generated from the
proposed toilets should be collected and conveyed to the existing HKBCF
sewerage system and sewage treatment plant for treatment.
Construction Phase
5.6.1
No open sea dredging will be
involved for construction of the Bonded Vehicular Bridge. It is expected that the installation of steel
pile casing would only cause minor displacement of marine sediment, which will
quickly settle without significant increase in suspended solids. Other land-based construction works,
including construction site runoff, wastewater from general construction
activities and accidental spillage of chemicals, have been identified and
qualitatively assessed in Section 5.7. Appropriate good practice measures such
as the practices outlined in ProPECC PN 1/94 ¡§Construction Site Drainage¡¨
would be recommended to minimise the potential water quality impacts during
construction phase.
Operational Phase
5.6.2
Hydrodynamic modelling is
required to evaluate the change in the hydrodynamic regime due to the
Project. Two hydrodynamic modelling
scenarios have been conducted to evaluate the change in the hydrodynamic regime
due to the bridge piers from this Project as follow:
¡P
Scenario 1 - Scenario without
the Bonded Vehicular Bridge; and
¡P
Scenario 2 - Scenario with the
Bonded Vehicular Bridge.
Modelling
Tools
5.6.3
The Delft3D suite of models
will be utilised in this modelling exercise as the modelling platform with the
Deflt3D-FLOW module used for hydrodynamic simulation.
5.6.4
Delft3D-FLOW is a 3-dimensional
hydrodynamic simulation programme which calculates non-steady flow and
transport phenomena that result from tidal and meteorological forcing on a
curvilinear, boundary fitted grid.
Model
Grid Layout and Properties
5.6.5
The development of the detailed
model to be adopted under this study is based on the model setup of the
regional Update model which was developed under the "Update on
Cumulative Water Quality and Hydrological Effect of Coastal Developments and
Upgrading of Assessment Tool'' (Agreement No. CE 42/97, hereafter
"Update Study"). The
Update Model developed under the Update Study covers the entire Hong Kong
waters, the Pearl Estuary and the Dangan Channel to incorporate all major
influences on hydrodynamic and water quality. The detailed model to be used for this study
makes reference to the Update Model.
The model grid was refined in the study area to give a better
representation of the hydrodynamic condition. The areas covered by the detailed model
include the North Western WCZ and the adjacent outer waters. Appendix 5.1 shows the grid layout of the detailed model at the study area.
5.6.6
The detailed model consists of
34,950 grid cells. The areas
covered by the detailed model include the North Western, Western Buffer and
Deep Bay Water Control Zones (WCZs) and the adjacent Mainland waters including
the Pearl River Estuary. Grid size
at the open waters is less than 400m in general. The smallest grid cells are located in
the western waters which are less than 70m x 70m. A close up of the model grid at the
western waters is shown in Appendix 5.1.
5.6.7
The grid quality of the
detailed model is generally good except in some areas at or close to the land
boundary. In view of the small flow
velocity at the land boundary, numerical errors associated with the change of orthogonality
should be small. Therefore, the
closed grid cells at the coastlines have been adjusted to form a grid line that
is parallel to land boundary (rather than keeping these closed grid cells
orthogonal). Orthogonality at open
grid cells has been checked to be adequate. The grid properties of detailed model
grid including orthogonality, N-smoothness and M-smoothness are shown in Appendix 5.1.
Vertical
Layers
5.6.8
The hydrodynamic model is
3-dimensional with a total of 10 vertical water layers. The thickness of each water layer is
defined in the model as a percentage of the water depth where the total sum of
all the vertical layers should be 100%.
All the vertical layers have been assigned to have the same vertical
contribution. Thus, each of the
vertical layers contributes 10% of the total water depth.
Boundary
Conditions
5.6.9
The detailed model is linked to
or nested within the Update Model, which was constructed, calibrated and
verified under the Update Study.
Computations are first carried out using the Update Model to provide
open boundary conditions to the detailed model. The Update Model covers the whole Hong
Kong and the adjacent outer waters including the Pearl River Estuary and Dangan
Channel. The influence on
hydrodynamics and water quality in these outer regions would be fully
incorporated into the detailed model.
Simulation
Periods
5.6.10
For each modelling scenario,
the hydrodynamic simulations have been performed for both dry and wet seasons,
and the simulation period covered a 15-day full spring-neap cycle (excluding
the spin-up period) for each of the dry and wet seasons. A spin-up period of 7 days was adopted
for hydrodynamic simulation. Hence,
the hydrodynamic model simulation period will consist of a spin-up period of 7
days plus an actual simulation period of 15 days (total 22 days). This spin-up period has been checked
under the past EIA study to be sufficient for producing acceptable modelling
results.
Wind
5.6.11
For the purpose of water
quality assessment, a north-eastern wind with a belonging wind speed of 5 m/s
will be used for the dry season computations. The wet season computations will apply a
south western wind of 5 m/s. These
conditions are the same as those used for the Update Study.
Roughness
5.6.12
The roughness varies over the
model area. For areas with a depth
larger than -10 mPD (Principle Datum) a Manning value of 0.026 was used. For depths in between -5 and -10 mPD a
value of 0.023 was applied. The
shallow areas was given a Manning value of 0.022. This roughness schematization originates
from the Update model calibration carried out under the EPD Update Study.
Eddy
Viscosity and Diffusivity
5.6.13
The horizontal eddy viscosity
and diffusivity will be set to a uniform value of 1.0 m2/s as
applied in the Update Model. The
minimum value for the background vertical eddy viscosity and diffusivity will
be set to 0.00005 m2/s, as applied in the Update Model.
Coastline
Configuration
5.6.14
Table 5.3 below indicates the
committed / on-going / planned coastal developments incorporated into the
coastline configurations for hydrodynamic modelling under this modelling
exercise. The layouts for specific
projects are shown in Figure 5.2.
Table 5.3 Coastal
Developments Incorporated in Water Quality Modelling Scenarios
Coastal Development
|
Information Source on Project Layout
|
TM-CLKL
|
EIA
Report for ¡§Tuen Mun - Chek Lap Kok Link¡¨ (EIAO Register No.: AEIAR-146/2009)
|
Hong Kong - Zhuhai - Macao Bridge (HZMB) Hong Kong Boundary (BCF)
|
EIA
Report for ¡§Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing
Facilities¡¨ (EIAO Register No.: AEIAR-145/2009)
|
HZMB Hong Kong Link Road (HKLR)
|
EIA Report
for ¡§Hong Kong - Zhuhai - Macao Bridge Hong Kong Link Road¡¨ (EIAO Register
No.: AEIAR-144/2009)
|
Tung Chung New Town Development Extension (TCNTDE)
|
EIA
Report for ¡§Tung Chung New Town Extension¡¨ (EIAO Register No. AEIAR-196/2016)
|
Expansion of Hong Kong International Airport into
a Three-Runway System (HKIA3RS)
|
EIA
Report for ¡§Expansion of Hong Kong International Airport into a Three-Runway
System¡¨ (EIAO Register No.: AEIAR-185/2014)
|
Contaminated Mid Pit (CMP) at South Brothers
|
EIA
Report for ¡§New Contaminated Mud Marine Disposal Facility at Airport East /
East Sha Chau Area¡¨ (EIAO Register No.: AEIAR-082/2004)
(Remark:
The hydrodynamic effect of the capped CMP was incorporated into the
hydrodynamic model. The final
level after capping of the CMP was assumed in the model under the 2 modelling
scenarios)
|
CMP at East Sha Chau
|
Model
Bathymetry
5.6.15
The bathymetry schematization
of the detailed model is based on the depth data from the Charts for Local
Vessels 2013 produced by the Hydrographic Office, Marine Department of
HKSAR. The hydrodynamic effect of
the Contaminated Mid Pit (CMP) at East Sha Chau and The Brothers has also been
incorporated and the final level at the CMP after capping was assumed in the modelling
scenarios.
Pile
Frictions
5.6.16
As the dimensions of the bridge
piers of the Bonded Vehicular Bridge are much smaller than the grid size, the
exact pier configurations cannot be adopted in the model simulation. Instead, only the overall influence of the
piles on the flow will be taken into account. This overall influence has been modelled
by a special feature of the Delft3D-FLOW model, namely porous plate. Porous plates represent transparent
structures in the model and will be placed along the model gridline where
momentum can still be exchanged across the plates. The porosity of the plates is controlled
by a quadratic friction term in the momentum to simulate the energy losses due
to the presence of the piles. The
forces on the flow due to a vertical pile or series of piles have been used to determine
the magnitude of the energy loss terms.
The mathematical expressions for representation of piles friction is
based on the Delft 3D-FLOW module developed by Delft Hydraulics as given in Appendix 5.2.
Model
Validation
5.6.17
The performance of the detailed
model has been checked against with Update Model results. The results of the actual simulation
periods (with sufficient spin-up periods) for water level, depth averaged flow
speed, depth averaged flow directions, salinity predicted by the two models
have been compared at two indicator points within the modelled area. The results of momentary flows and
accumulated flows have been compared at two selected cross sections to check
for the consistency. Locations of
the selected indicator points and cross sections are shown in Figure 5.3. Momentary flow represents the
instantaneous flow rate at a specific time in m3/s whereas
accumulated flow represents the total flow accumulated at a specific time in m3. The comparison plots are given in Appendix 5.3. The comparison plots indicated that the
model results predicted by both models were in general consistent with each
other which implied that the model settings of the detailed model as well as
the nesting procedures were carried out correctly. The difference in accumulated flows was
caused by the difference in grid resolutions between the two models. As the detailed model has relatively
finer grid resolution, it should have a more accurate representation of the
bathymetry and coastline in the western waters as compared to the Update Model
and hence the deviation are considered to be reasonable.
Model
Output
5.6.18
The modelling results including
accumulated flow, momentary flow and depth averaged current velocities from the
two hydrodynamic modelling scenarios have been compared in Section 5.7 in
order to evaluate the hydrodynamic change in the study area.
Construction Phase
Construction of Marine Bridge Piles
5.7.1
The bridge deck section will be
designed to allow for the use of precast concrete construction method. The deck will be formed from precast
concrete sections which will be manufactured at a casting yard offsite and
joined together at their final positions on-site. This approach will minimise the extent
and duration of construction activities required on-site and hence the
potential environmental impacts on nearby sensitive receivers during
construction.
5.7.2
Construction of the viaducts
will generally involve the use of in-situ bored piles foundations
founded on bedrock or seabed. All
piling equipment would be set up on a barge after the installation of silt
curtain, then the pile construction would be through the placing of steel pile
casing at the pier site in which the seawater trapped inside the casing. A funnel would be placed at the top of
pile casing during excavation. This
construction method of creating a confined environment for excavation could
minimise the release of contaminant into the water column and hence reduce the
risk of disturbance to the seabed and the adjacent marine environment. Mechanical Grab and Reverse Circulation
Drill will be used for excavation of soil and rock socket respectively and then
installing steel reinforcement fixing with permanent casing for
concreting. No open sea dredging of
seabed will be involved for the Bonded Vehicular Bridge construction. The marine viaduct pile cap above
high-tide level will be installed through construction of a cofferdam, which
consists of using permanent precast panel.
The seawater trapped inside the cofferdam would be pumped out to
generate a dry working environment throughout the construction process. The bridge piers will be then
constructed by traditional means.
5.7.3
No open sea dredging will be
involved for construction of the Bonded Vehicular Bridge. It is expected that the installation of
steel pile casing would only cause minor displacement of marine sediment, which
will quickly settle without significant increase in suspended solids. Sediment excavation will only be carried
out in a confined dry working environment.
As mentioned in Section 6, the excavated marine-based sediments
will be loaded onto the barge and transported to the designated disposal sites
allocated by Marine Fill Committee (MFC).
No barging points or conveyor systems will be established in the Project
area. Notwithstanding the above,
accidental release of excavated sediment during transport to the disposal areas
by barges which will increase the SS and contaminant level of receiving water
and deteriorate water quality.
Adoption of the guidelines and good site practices for handling and
disposal of the excavated marine-based sediments as specified in Section 5.9.12
would minimise the potential impacts.
Potential water quality impact due to release of suspended solids,
contaminants and nutrients from sediment excavation is therefore not
expected. No adverse water quality
impact due to construction of marine bridge piles is anticipated.
General Construction Activities
5.7.4
Various types of construction
activities may generate wastewater.
These include general cleaning and polishing, wheel washing, dust
suppression and utility installation.
These types of wastewater would contain high concentrations of suspended
solids (SS). Various construction
works may also generate debris and rubbish such as packaging, construction
materials and refuse. Uncontrolled
discharge of site effluents, rubbish and refuse generated from the construction
works could lead to deterioration in water quality.
5.7.5
Effluent discharged from
temporary site facilities should be controlled to prevent direct discharge to
the neighbouring marine waters and storm drains. Such effluent may include wastewater
resulting from wheel washing of site vehicles at site entrances. Debris and rubbish such as packaging,
construction materials and refuse generated from the construction activities
should also be properly managed and controlled to avoid accidental release to
the local storm system and marine waters.
Adoption of the guidelines and good site practices for handling and
disposal of construction discharges as specified in Sections 5.9.4 to 5.9.15
would minimise the potential impacts.
Drainage and Construction Site Runoff
5.7.6
Potential pollution sources of
site runoff may include:
¡P
Runoff and erosion of exposed
bare soil and earth, drainage channel, earth working area and stockpiles;
¡P
Release of any bentonite
slurries, concrete washings and other grouting materials with construction
runoff or storm water;
¡P
Wash water from dust
suppression sprays and wheel washing facilities; and
¡P
Fuel, oil and lubricants from
maintenance of construction vehicles and equipment.
5.7.7
During rainstorms, site runoff
would wash away the soil particles on unpaved lands and areas with the topsoil
exposed. The runoff is generally characterised
by high concentrations of SS. Release
of uncontrolled site runoff would increase the SS levels and turbidity in the
nearby water environment. Site
runoff may also wash away contaminated soil particles and therefore cause water
pollution.
5.7.8
Wind blown dust would be
generated from exposed soil surfaces in the works areas. It is possible that wind blown dust
would fall directly onto the nearby water bodies when a strong wind
occurs. Dispersion of dust within
the works areas may increase the SS levels in surface runoff causing a
potential impact to the nearby sensitive receivers.
5.7.9
Construction site runoff and
drainage may cause local water quality impacts. Increase in SS arising from the
construction site could block the drainage channels. High concentrations of suspended
degradable organic material in marine water could lead to reduction in
dissolved oxygen (DO) levels in the water column.
5.7.10
It is important that proper
site practice and good site management (as specified in the ProPECC PN 1/94
"Construction Site Drainage") be followed to prevent runoff
with high level of SS from entering the surrounding waters. With the implementation of appropriate
measures to control runoff and drainage from the construction site, disturbance
of water bodies would be avoided and deterioration in water quality would be
minimal. Thus, unacceptable impacts
on the water quality are not expected, provided that the relevant mitigation
measures as specified in the ProPECC PN 1/94 "Construction Site
Drainage" as described in Sections 5.9.4 to 5.9.15 are properly
implemented.
Sewage Effluent from Construction Workforce
5.7.11
During the construction of the
Project, the workforce on site will generate sewage effluents, which are characterised
by high levels of BOD, ammonia and E.coli counts. Potential water quality impacts upon the
local drainage and fresh water system may arise from these sewage effluents, if
uncontrolled.
5.7.12
The construction sewage should
be handled by interim sewage treatment facilities, such as portable chemical
toilets. Appropriate numbers of
portable toilets should be provided by a licensed contractor to serve the large
number of construction workers over the construction site. Based on the Drainage Services
Department (DSD) Sewerage Manual, the sewage production rate for construction
workers is estimated at 0.35 m3 per worker per day. For every 100 construction workers
working simultaneously at the construction site, about 35 m3 of
sewage would be generated per day.
Provided that sewage is not discharged directly into the storm drains or
marine waters adjacent to the construction site, and temporary sanitary
facilities are used and properly maintained (as given in Sections 5.9.16 to
5.9.17), it is unlikely that sewage generated from the site would have a
significant water quality impact.
Accidental Spillage of Chemicals
5.7.13
A large variety of chemicals
may be used during construction activities. These chemicals may include petroleum
products, surplus adhesives, spent lubrication oil, grease and mineral oil,
spent acid and alkaline solutions/solvent and other chemicals. The use of these chemicals and their
storage as waste materials has the potential to create impacts on the water
quality of adjacent marine waters or storm drains if spillage occurs. Waste oil may infiltrate into the
surface soil layer, or runoff into local water courses, increasing hydrocarbon
levels. The potential impacts could
however be mitigated by practical mitigation measures and good site practices
(as given in Sections 5.9.18 to 5.9.20).
Operational Phase
Change of
Hydrodynamic Regime
Table 5.4 Depth
Averaged Current Velocities at Assessment Points
Assessment Point
(refer to Figure 5.4)
|
Depth Averaged Current Velocities (m/s)
|
Dry Season
|
Wet Season
|
Scenario 1
|
Scenario 2
|
Scenario 1
|
Scenario 2
|
P1
|
0.06
(
0.02 ¡V 0.17 )
|
0.06
(
0.01 ¡V 0.16 )
|
0.09
(
0.02 ¡V 0.25 )
|
0.09
(
0.02 ¡V 0.25 )
|
P2
|
0.04
(
0.01 ¡V 0.12 )
|
0.04
(
0.01 ¡V 0.12 )
|
0.08
(
0.01 ¡V 0.17 )
|
0.08
(
0.01 ¡V 0.18 )
|
P3
|
0.01
(
<0.01 ¡V 0.06 )
|
0.01
(
<0.01 ¡V 0.06 )
|
0.03
(
0.01 ¡V 0.11 )
|
0.03
(
<0.01 ¡V 0.12 )
|
Notes:
1. Data
presented are arithmetic means of depth-averaged results in dry and wet seasons.
2. Data
in brackets indicate the ranges.
5.7.15
According to the hydrodynamic modelling
results as shown in Table 5.4,
there is no significant change in averaged current velocities at all assessment
points under both modelling scenarios.
There are slightly change in the prevailing velocities at all assessment
points (at P1 in dry season, at P2 and P3 in wet season) but the change in the
tidal speeds are only up to 0.01 m/s.
As the predicted change in current velocity would be small and localised
at the sea channel, significant change in flow regime is not anticipated.
5.7.16
The timeseries plots for momentary
flow and accumulated flow across the three representative cross-sections
(namely C1, C2 and C3 as indicated in Figure
5.4) under both modelling scenarios are also presented in Appendix 5.4. The momentary flow and accumulated flow
across the three representative cross-sections are summarised in Table 5.5
and Table 5.6 respectively.
Table 5.5 Comparison
Results of Momentary Flow at Representative Cross-sections
Cross-section
(refer to Figure
5.4)
|
Seasons
|
Momentary Flow (m3/s)
|
Scenario
1
|
Scenario
2
|
Difference
|
(m3/s)
|
(%)
|
C1
|
Dry
|
-54
~ 61
|
-54
~ 61
|
<0
|
<1%
|
Wet
|
-58
~ 70
|
-58
~ 69
|
<0
~ 1
|
2%
|
C2
|
Dry
|
-37
~ 41
|
-37
~ 41
|
<0
|
<1%
|
Wet
|
-39
~ 47
|
-39
~ 46
|
<0
~ 1
|
2%
|
C3
|
Dry
|
-14
~ 15
|
-14
~ 15
|
<0
|
<1%
|
Wet
|
-15
~ 18
|
-15
~ 17
|
<0
~ 1
|
2%
|
Table 5.6 Comparison
Results of Accumulated Flow at Representative Cross-sections
Cross-section
(refer to Figure
5.4)
|
Seasons
|
Accumulated Flow (m3)
|
Scenario
1
|
Scenario
2
|
Difference
|
(m3)
|
(%)
|
C1
|
Dry
|
7.32
x105
|
7.32
x105
|
<0.01
x105
|
<1%
|
Wet
|
7.76
x105
|
7.76
x105
|
<0.01
x105
|
<1%
|
C2
|
Dry
|
4.80
x105
|
4.80
x105
|
<0.01
x105
|
<1%
|
Wet
|
5.10
x105
|
5.09
x105
|
0.01
x105
|
<1%
|
C3
|
Dry
|
1.80
x105
|
1.80
x105
|
<0.01
x105
|
<1%
|
Wet
|
1.91
x105
|
1.91
x105
|
<0.01
x105
|
<1%
|
5.7.17
The predicted momentary flow
and accumulated flow across the three representative cross-sections would
decrease with the presence of the marine bridge piles of the Bonded Vehicular
Bridge. However, the change in
momentary flow and accumulated flow is considered to be small (difference only
up to 1 m3/s (2%) and 1,000 m3 (<1%) for momentary
flow and accumulated flow respectively).
As the predicted change in momentary flow and accumulated flow would be
small, significant change in flushing capacity is not anticipated. No adverse hydrodynamic impact would
therefore be expected.
Runoff from Road Surfaces
5.7.19
According to the DSD ¡§Stormwater
Drainage Manual¡¨, annual rainfall in Hong Kong is around 2,200 mm. However, the Update Study suggested that
only rainfall events of sufficient intensity and volume would give rise to
runoff and that runoff percentage is about 44% and 82% for dry and wet season,
respectively. Therefore, only 1,386
mm of 2,200 mm annual rainfall would be considered as effective rainfall that
would generate runoff (i.e. 1,386 mm = 2,200 mm ¡Ñ (82%+44%)/2).
5.7.20
Additional surface runoff would
be generated from the Project due to construction of bridge deck section above
the sea channel between the HKIA and the HKBCF. The additional area is about 4,034 m2. Making reference to the DSD ¡§Stormwater
Drainage Manual¡¨, about 0.9 as the runoff coefficient for paved areas is
assumed. The average daily runoff
generated from the construction area is estimated to be less than 14 m3/day
(= 0.9 ¡Ñ 1,386 mm/year ¡Ñ 4,034 m2).
5.7.21
It is also anticipated that with
proper implementation of recommended mitigation measures and best management
practices described in Sections 5.9.22, adverse impact associated with
the discharge of runoff is not anticipated.
Sewage Effluent from the Proposed Toilets
5.7.22
According to latest sewerage
review, the average dry weather flow (ADWF) generated from the proposed toilets
is estimated to be 3.96 m3/day.
All the sewage flow generated from the proposed toilets would be
collected and conveyed to the existing sewerage system on HKBCF Island which
conveys sewage towards the HKBCF sewage treatment plant. The downstream sewerage system and
sewage treatment plant at the HKBCF have sufficient capacity to treat the
additional sewage flow generated from the Project. No adverse water quality impacts would
therefore be anticipated.
5.8.1
The construction and operation
of the Project potentially overlap with the construction and operation of the
Intermodal Transfer Terminal (ITT) and other nearby concurrent projects as
identified in Table 5.3. However, with incorporation of the
recommended mitigation measures during the construction and operational phases
of this Project, no adverse cumulative water quality impacts would be expected.
Construction Phase
Construction of Marine Bridge Piles
5.9.2
During dewatering of the
cofferdam, appropriate desilting or sedimentation device should be provided on
site for treatment before discharge. The Contractor should ensure discharge
water from the sedimentation tank meeting the WPCO / TM-DSS requirements before
discharge.
Construction Site Runoff and General
Construction Activities
5.9.5
Surface run-off from
construction sites should be discharged into storm drains via adequately
designed sand/silt removal facilities such as sand traps, silt traps and
sedimentation basins. Channels or
earth bunds or sand bag barriers should be provided on site to properly direct
stormwater to such silt removal facilities. Perimeter channels at site boundaries
should be provided on site boundaries where necessary to intercept storm
run-off from outside the site so that it will not wash across the site. Catchpits and perimeter channels should
be constructed in advance of site formation works and earthworks.
5.9.6
Silt removal facilities,
channels and manholes should be maintained and the deposited silt and grit
should be removed regularly, at the onset of and after each rainstorm to
prevent local flooding. Before
disposal at the public fill reception facilities, the deposited silt and grit
should be solicited in such a way that it can be contained and delivered by
dump truck instead of tanker truck.
Any practical options for the diversion and re-alignment of drainage
should comply with both engineering and environmental requirements in order to
provide adequate hydraulic capacity of all drains.
5.9.7
Construction works should be
programmed to minimise soil excavation works in rainy seasons (April to
September). If excavation in soil
cannot be avoided in these months or at any time of year when rainstorms are
likely, for the purpose of preventing soil erosion, temporary exposed slope
surfaces should be covered e.g. by tarpaulin, and temporary access roads should
be protected by crushed stone or gravel, as excavation proceeds. Intercepting channels should be provided
(e.g. along the crest / edge of excavation) to prevent storm runoff from
washing across exposed soil surfaces.
Arrangements should always be in place in such a way that adequate
surface protection measures can be safely carried out well before the arrival
of a rainstorm.
5.9.8
Earthworks final surfaces
should be well compacted and the subsequent permanent work or surface
protection should be carried out immediately after the final surfaces are
formed to prevent erosion caused by rainstorms. Appropriate drainage like intercepting
channels should be provided where necessary.
5.9.9
Measures should be taken to minimise
the ingress of rainwater into trenches.
If excavation of trenches in wet seasons is necessary, they should be
dug and backfilled in short sections.
Rainwater pumped out from trenches or foundation excavations should be
discharged into storm drains via silt removal facilities.
5.9.10
Manholes (including newly
constructed ones) should always be adequately covered and temporarily sealed so
as to prevent silt, construction materials or debris from getting into the
drainage system, and to prevent storm run-off from getting into foul
sewers. Discharge of surface
run-off into foul sewers must always be prevented in order not to unduly
overload the foul sewerage system.
5.9.11
If bentonite slurries are
required for any construction works, they should be reconditioned and reused
wherever practicable to minimise the disposal volume of used bentonite
slurries. Temporary enclosed
storage locations should be provided on-site for any unused bentonite that
needs to be transported away after the related construction activities are
completed. Requirements as
stipulated in ProPECC Note PN 1/94 should be closely followed when handling and
disposing bentonite slurries.
¡P
Loading of the excavated
marine-based sediment to the barge shall be controlled to avoid splashing and
overflowing of the sediment slurry to the surrounding water;
¡P
The barge transporting the
excavated marine-based sediment to the designated disposal sites shall be
equipped with tight fitting seals to prevent leakage and shall not be filled to
a level that would cause overflow of materials or laden water during loading or
transportation; and
¡P
Monitoring of the barge loading
shall be conducted to ensure that loss of material does not take place during
transportation. Transport barges or
vessels shall be equipped with automatic self-monitoring devices as specified
by the Director of Environmental Protection (DEP).
Boring
and Drilling Water
5.9.13
Water used in ground boring and
drilling for site investigation or rock/soil anchoring should as far as
practicable be re-circulated after sedimentation. When there is a need for final disposal,
the wastewater should be discharged into storm drains via silt removal
facilities.
Wheel Washing Water
5.9.14
All vehicles and plant should
be cleaned before they leave a construction site to minimise the deposition of
earth, mud, debris on roads. A
wheel washing bay should be provided at every site exit if practicable and
wash-water should have sand and silt settled out or removed before discharging
into storm drains. The section of
construction road between the wheel washing bay and the public road should be
paved with backfall to reduce vehicle tracking of soil and to prevent site
run-off from entering public road drains.
Site
Effluent
Sewage Effluent from Construction Workforce
Accidental
Spillage of Chemicals
5.9.19
Any service shop and
maintenance facilities should be located on hard standings within a bonded
area, and sumps and oil interceptors should be provided. Maintenance of vehicles and equipment
involving activities with potential for leakage and spillage should only be
undertaken within the areas appropriately equipped to control these discharges.
¡P
Suitable containers should be
used to hold the chemical wastes to avoid leakage or spillage during storage,
handling and transport;
¡P
Chemical waste containers
should be suitably labelled, to notify and warn the personnel who are handling
the wastes, to avoid accidents; and
¡P
Storage area should be selected
at a safe location on site and adequate space should be allocated to the
storage area.
Operational Phase
Change of Hydrodynamic Regime
5.9.21
No adverse hydrodynamic impact would be expected during the operational
phase and hence no mitigation measures are considered necessary.
Runoff from Road Surfaces
Best Storm Water Management Practices and
Storm Water Pollution Control Plan
5.9.23
Mitigation measures including
Best Management Practices (BMPs) to reduce storm water pollution arising from
the Project are as follows:
Design
Measures
5.9.24
Exposed surface shall be
avoided within the roads to minimise soil erosion. The roads shall be hard paved.
5.9.25
The drainage system should be
designed to avoid flooding.
Devices
and Facilities
5.9.26
Screening facilities such as
standard gully grating and trash grille, with spacing which is capable of
screening large substances such as rubbish should be provided at the inlet of
drainage system.
5.9.27
Road gullies with standard
design and silt traps should be provided to remove particles present in
stormwater runoff, where appropriate.
Administrative
Measures
5.9.28
Good management measures such
as regular cleaning and sweeping of road surface/ open areas are
suggested. The road surface/ open
area cleaning should also be carried out prior to occurrence rainstorm.
5.9.29
Manholes, as well as stormwater
gullies, ditches provided at the Project site should be regularly inspected and
cleaned (e.g. monthly). Additional
inspection and cleansing should be carried out before forecast heavy rainfall.
Sewage Effluent from the Proposed Toilets
5.9.30
All the sewage flow generated
from the proposed toilets should be properly collected and conveyed to the
existing sewerage system on HKBCF Island.
No direct discharge of sewage effluent into the marine water will be
allowed.
Construction Phase
5.10.1
The construction phase water
quality impact would generally be temporary and localised during
construction. Therefore, no
unacceptable residual water quality impact is anticipated during the
construction of the Project, provided that all of the recommended mitigation
measures as stated in Sections 5.9.1 to 5.9.20 are implemented and all
construction site discharges comply with the TM-DSS standards.
Operational Phase
5.10.2
As presented in Sections
5.7.14 to 5.7.18, adverse hydrodynamic and water quality impacts associated
with the operation of the Project are not anticipated. Thus, there will be no adverse residual
impact associated with the operation of the Project.
Construction Phase
5.11.1
No adverse water quality impact
was expected during the construction phase of the Project. Appropriate mitigation measures are
recommended in Sections 5.9.1 to 5.9.20 to minimise potential water
quality impacts. Water quality
monitoring and audit is recommended during construction phase to ensure that
all the recommended mitigation measures are properly implemented. Details of the water quality monitoring
and audit programme and the Event and Action Plan are provided in the
stand-alone EM&A Manual.
Operational Phase
5.11.2
No adverse hydrodynamic and water quality impacts would be expected from
the Project. No monitoring
programme specific for operational phase of the Project would be required.
Construction Phase
5.12.1
No open sea dredging will be
involved for construction of the Bonded Vehicular Bridge. Sediment excavation will only be carried
out in a confined dry working environment.
With implementation of proposed mitigation measures as specified in Sections
5.9.1 to 5.9.3, no adverse water quality impact due to marine construction
of the Bonded Vehicular Bridge would be expected. A water quality monitoring and audit
programme will be implemented to ensure the effectiveness of the proposed water
quality mitigation measures.
5.12.2
The potential water quality
impacts from the land-based construction works are associated with the general
construction activities, construction site run-off, accidental spillage, and
sewage effluent from construction workforce. The site practices as outlined in the
ProPECCPN 1/94 "Construction Site Drainage" is recommended to
minimise the potential water quality impacts from the construction
activities. Proper site management
and good site practices are also recommended to ensure that construction wastes
and other construction-related materials would not enter the nearby marine
water. Sewage effluent arising from
the construction workforce would be handled through provision of portable
toilets. Water quality monitoring
and regular site inspection will be implemented for the construction works to
ensure that the recommended mitigation measures are properly implemented.
5.12.3
With the implementation of the
above recommended mitigation measures, the land-based construction works for
the Project would not result in adverse water quality impacts.
Operational Phase
5.12.4
Potential hydrodynamic impact
due to the presence of the marine bridge piles of the Bonded Vehicular Bridge
has been identified and assessed under this study with the use of computational
modelling approach. The model
results showed that the change in current velocity would be small and localised
at the sea channel between HKIA and HKBCF Island. No significant change in flow regime at the
sea channel is anticipated. The
predicted change in momentary flow and accumulated flow would also be minor,
significant change in flushing capacity is not anticipated. No adverse hydrodynamic impact would
therefore be expected.