8 Landscape and visual Impacts
8.2 Environmental Legislation, Standards and Criteria
8.3 Landscape Assessment Methodology
8.4 Visual Impact Assessment Methodology
8.5 Review of Planning and Development Control Framework
8.7 Landscape Impact Assessment
8.9 Landscape and Visual Mitigation Measures
8.12 Environmental Monitoring and Audit
TABLES
Table 8.1 Relationship
between Landscape Sensitivity to Change and Magnitude of Change in Defining
Impact Significance
Table 8.2 Relationship
between VSRs Sensitivity to Change and Magnitude of Change in Defining Impact
Significance
Table 8.3 Summary
of the Review of Planning and Development Control Framework
Table 8.4 Sensitivity
to Change of the Landscape Resources
Table 8.5 Sensitivity
of Landscape Character Areas
Table 8.6 Baseline
Visually Sensitive Receivers (VSRs) and their Sensitivity to Change
Table 8.7 Magnitude
of Change on Landscape Resources (LRs) and Landscape Character Areas (LCAs)
under Unmitigated Condition
Table 8.8 Locations
and Development Details of Permanent Man-made Structures
Table 8.9 Magnitude
of Visual Changes during Construction and Operation Phases under Unmitigated
Condition
Table 8.10 Landscape
and Visual Mitigation Measures for Construction and Operation Phases
Table 8.11 Significance
of Landscape Impacts during Construction and Operation Phases
Table 8.12 Significance
of Visual Impacts during the Construction and Operation Phases Before and After
Mitigated Condition
Table 8.13 Potential
Cumulative Landscape and Visual Impact
FIGURES
Figure 8.1 Review
of Planning Framework
Figure 8.2 Landscape
Resources
Figure 8.3 Landscape
Character Areas
Figure 8.4 Photos
of Landscape Resources and Landscape Character Areas
Figure 8.5 Locations
of Visually Sensitive Receivers
Figure 8.6 Visually
Sensitive Receivers Photos (Sheet 1 of 2)
Figure 8.7 Visually
Sensitive Receivers Photos (Sheet 2 of 2)
Figure 8.8 Viewpoint
1 Photomontages
Figure 8.9 Viewpoint
2 Photomontages
Figure 8.10 Viewpoint
3 Photomontages
Figure 8.11 Viewpoint
4 Photomontages
Figure 8.12 Landscape
and Visual Mitigation Plan (Sheet 1 of 2)
Figure 8.13 Landscape
and Visual Mitigation Plan (Sheet 2 of 2)
APPENDIX
Appendix 8.1 Broad
Brush Tree Survey Plan and Schedule
Appendix 8.2 Indicative
Location of Planned Trees to be Planted Under HKBCF
|
|
¡P
EIAO (Cap.499 S.16) and the
EIAO-TM, particularly Annexes 10 and 18;
¡P
EIAO Guidance Note No.
8/2010;
¡P
Town Planning Ordinance
(Cap. 131);
¡P
Protection of Endangered
Species of Animals and Plants Ordinance (Cap. 586);
¡P
Hong Kong Planning
Standards and Guidelines (HKPSG) Chapters 4, 10 and 11;
¡P
AFCD Nature Conservation
Practice Note No. 2 ¡V Measurement of Diameter at Breast Height (DBH);
¡P
AFCD Nature Conservation
Practice Note No. 3 ¡V The Use of Plant Names;
¡P
ETWB TCW No. 29/2004 ¡V Registration
of Old and Valuable Trees (OVT), and Guidelines for their Preservation;
¡P
ETWB TCW No. 8/2005 ¡V Aesthetic
Design of Ancillary Buildings in Engineering Projects;
¡P
DevB TCW No. 2/2012 ¡V Allocation
of Space for Quality Greening on Roads;
¡P
DevB TCW No. 3/2012 ¡V Site
Coverage of Greenery for Government Building Projects;
¡P
DevB TCW No. 6/2015 ¡V Maintenance
of Vegetation and Hard Landscape Features;
¡P
DevB TCW No. 7/2015 ¡V Tree
Preservation;
¡P
Geotechnical Engineering
Office (GEO) Publication No. 1/2011 ¡V Technical Guidelines on Landscape
Treatment and Bio-Engineering for Man-Made Slopes and Retaining Walls;
¡P
Guidelines on Tree
Transplanting (September 2014) issued by Greening, Landscape and Tree
Management (GLTM) Section of DevB;
¡P
Guidelines on Tree
Preservation during Development (April 2015) issued by GLTM Section of DevB;
and
¡P
Study on Landscape Value
Mapping of Hong Kong.
Identification
of the Baseline Landscape Resources (LRs) and Landscape Character Areas (LRAs) Found
within the Study Area
Assessment of the Degree
of Sensitivity to Change of the LRs and LCAs
High: |
Important LR or LCA of particularly distinctive characteristics or
high importance, which is sensitive to relatively small change. |
Medium: |
LR or LCA of moderately valued landscape characteristics, which is
reasonably tolerant to change. |
Low: |
LR or LCA with low landscape characteristics and value, which is
largely tolerant to change. |
Identification of Sources of Landscape Impacts
Assessment of Magnitude of Change
Large: |
LR or LCA will suffer a major change. |
Intermediate: |
LR or LCA would suffer a moderate change. |
Small: |
LR or LCA would suffer slight or barely perceptible change. |
Negligible: |
LR or LCA will suffer no discernible change. |
Identification of Potential Landscape Mitigation Measures
Prediction of Significance of Landscape Impacts before and after the Implementation
of the Mitigation Measures
Substantial: |
Adverse / beneficial impact where the proposal would cause significant
deterioration or improvement in existing landscape quality. |
Moderate: |
Adverse / beneficial impact where the proposal would cause a
noticeable deterioration or improvement in existing landscape quality. |
Slight: |
Adverse / beneficial impact where the proposal would cause a barely
perceptible deterioration or improvement in existing landscape quality. |
Insubstantial: |
No discernible change in the existing landscape quality. |
Table 8.1 Relationship
between Landscape Sensitivity to Change and Magnitude of Change in Defining
Impact Significance
Magnitude of Change |
Large |
Moderate |
Moderate / Substantial |
Substantial |
Intermediate |
Slight / Moderate |
Moderate |
Moderate / Substantial |
|
Small |
Insubstantial / Slight |
Slight / Moderate |
Moderate |
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
|
|
Low |
Medium |
High |
|
LRs
and LCAs Sensitivity to Change |
Note: All impacts are adverse unless
otherwise noted with beneficial.
Prediction of Acceptability of Landscape Impacts
¡P
The impact is beneficial if the project will
complement the landscape character of its setting, will follow the relevant
planning objectives and will improve overall landscape quality;
¡P
The impact is acceptable if the assessment
indicates that there will be no significant effects on the landscape causes by
the project;
¡P
The impact is acceptable with mitigation measures if
there will be some adverse effects, but these can be eliminated, reduced or
offset to a large extent by specific measures;
¡P
The impact is unacceptable if the adverse
effects are considered too excessive and area unable to mitigate practically;
¡P
The impact is undetermined if significant
adverse effects are likely, but the extent to which they may occur or may be
mitigated cannot be determined from the study. Further detailed study will be
required for the specific effects in question.
Identification of the Visual Envelope
Identification of the Visually Sensitive Receivers (VSRs)
Assessment of the Degree of Sensitivity to Change of the VSRs
¡P
It is classified
according to whether the person is at home, at work, at play or travelling.
¡P
Viewers
from residences ¡V they are considered to be highly sensitive. The
attractiveness or otherwise of the outlook from their home will have a
substantial effect on their perceived quality and acceptability of their home
environment, as well as their general quality of life.
¡P
Viewers
from workplaces ¡V less sensitive than the above due to visual amenity being less
important within the work environment; the degree to which this applies depends
on whether the workplace is industrial, retail or commercial.
¡P
Viewers from recreational
areas ¡V including all areas apart from the above, e.g. public parks, recreation
grounds, waterfront etc. Sensitivity
of this group depends on the type of outdoor leisure activity, e.g. relaxing in
an open space, jogging, children play etc.
¡P
Viewers from
public thoroughfare ¡V they include those who are queuing for public
transportation, travelling on a highway, walking along pedestrian path etc. They would display varies sensitivity
depending on the speed of travel.
¡P
The sensitivity
of each VSRs group is also influenced by its location and direction of view
relative to the proposed development. The assessment will relate to the typical
viewpoints within each of the visually sensitive receiver group, as identified above,
and their existing and potential views subsequent to the proposed development.
¡P
Factors as
required by EIAO GN 8/2010 including the value and quality of existing views,
availability and amenity of alternative views, the duration or frequency of
view and degree of visibility shall be considered in the assessment.
High: |
The VSR is highly sensitive to any change in their viewing experience. |
Medium: |
The VSR is moderately sensitive to any change in their viewing
experience. |
Low: |
The VSR is only slightly sensitive to any change in their viewing
experience. |
Identification of Relative Numbers of VSRs
Identification of Sources of Visual Impacts
Assessment of Magnitude of Change
¡P
compatibility
with the surrounding landscape;
¡P
duration of the
impact;
¡P
reversibility of
the impact;
¡P
scale of the
impact;
¡P
distance of the
source of impact from the viewer;
¡P
degree of
visibility of source(s) of the impact, and
¡P
potential
blockage of existing views.
Large: |
The VSRs would suffer a major change in their viewing experience. |
Intermediate: |
The VSRs would suffer a moderate change in their viewing experience. |
Small: |
The VSRs would suffer a small change in their viewing experience. |
Negligible: |
The VSRs would suffer no discernible change in their viewing
experience. |
Identification of Potential Visual Mitigation Measures
Prediction of Significance of Visual Impacts before and after the Implementation
of the Mitigation Measures
Substantial: |
Adverse /
beneficial impact where the proposal would cause significant deterioration or
improvement in existing visual quality. |
Moderate: |
Adverse /
beneficial impact where the proposal would cause a noticeable deterioration
or improvement in existing visual quality. |
Slight: |
Adverse /
beneficial impact where the proposal would cause a barely perceptible
deterioration or improvement in existing visual quality. |
Insubstantial: |
No discernible
change in the existing visual quality. |
Table 8.2 Relationship
between VSRs Sensitivity to Change and Magnitude of Change in Defining Impact
Significance
Magnitude of Change |
Large |
Moderate |
Moderate / Substantial |
Substantial |
Intermediate |
Slight / Moderate |
Moderate |
Moderate / Substantial |
|
Small |
Insubstantial / Slight |
Slight / Moderate |
Moderate |
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
|
|
Low |
Medium |
High |
|
VSRs
Sensitivity to Change |
Note: All
impacts are adverse unless otherwise noted with beneficial.
Prediction of Acceptability of Residual Visual Impacts
¡P
The impact is beneficial if the project will
complement the visual character of its setting, will follow the relevant
planning objectives and will improve overall visual quality;
¡P
The impact is acceptable if the assessment
indicates that there will be no significant visual effects causes by the
appearance of the project, or no interference with key views;
¡P
The impact is acceptable with mitigation measures if
there will be some adverse effects, but these can be eliminated, reduced or
offset to a large extent by specific measures;
¡P
The impact is unacceptable if the adverse
effects are considered too excessive and area unable to mitigate practically;
¡P
The impact is undetermined if significant
adverse effects are likely, but the extent to which they may occur or may be mitigated
cannot be determined from the study. Further detailed study will be required
for the specific effects in question.
Table 8.3 Summary
of the Review of Planning and Development Control Framework
OZP Plan Title and No.
|
Land use Zoning
|
Approx. Area of the Land Use Zones to be
affected
|
Current Design and Conservation Intention
in the OZP
|
Approved Chek Lap Kok
Outline Zoning Plan No. S/I-CLK/14
|
Other Specified Uses
(OU)
|
8,320 m2
|
Intended primarily for
¡¦Boundary Crossing Facilities¡¦ only.
|
Table
8.4 Sensitivity to Change of the Landscape
Resources
LRs |
Description |
Sensitivity |
LR1 |
Coastal
Waters of North Lantau Island This LR consists the vast seawater body around
the HKBCF. It possesses strong sense of openness frequented by commercial and
pleasure craft marine traffic. This
valuable resource also contributes to the unique waterfront setting of Tung
Chung. Considering its physical
characteristics and its regional importance, it has low ability to
accommodate change. In general,
the landscape quality and value of this LR is considered high. |
High |
LR2 |
Roadside
Landscape Areas within the HKIA It mainly comprises of themed roadside amenity
planting along Airport roads and internal roads around the buildings. The planting areas are generally defined
by low hedges, large grassed area, groundcovers, small shrubs, ornamental
palms and small semi-mature trees. Identified common landscape tree
species include Ficus
benjamina, Grevillea robusta, Hibiscus tiliaceus, Juniperus chinensis,
Chrysalidocarpus lutescens, Cocos nucifera and Ravenala madagascariensis.
They are mostly in fair quality with limited individual value. It is a common landscape resource in
Hong Kong with medium ability to accommodate change. In overall, the landscape quality and
value of this LR is considered medium. |
Medium |
LR3 |
Planned
Amenity / Compensatory Planting Area on HKBCF Based on the planned development of HKBCF, there
would be proposed hydroseeding and peripheral planting. Predominant proposed species include Iris tectorum, Spathiphyllum commutatum,
Aglaia odorata Ficus microcarpa ¡¥golden leaves¡¦, Ligustrum ovalifolium,
Malvaviscus arboreus etc. Since
this recent instalment of proposed planting would be easily replaceable, the
ability of this landscape resources to accommodate change shall be high. The general landscape quality and value
of this LR is considered medium to low. |
Low |
Table 8.5 Sensitivity of Landscape Character
Area
LCAs |
Description |
Sensitivity |
LCA1 |
Inshore
Water Landscape This water body is mainly bounded by the Airport
Island and HKBCF. Due to its
vastness, it has medium ability to accommodate change without compromising
its essential nature i.e. sense of openness and wilderness. The general
landscape quality and value is considered medium. |
High |
LCA2 |
Reclaimed
HKIA and HKBCF This LCA is characterised by flat and extensive
coverage of runways, traffic corridors, large footprint of low-rise buildings
and associated infrastructure from the Airport and HKBCF. Amenity planting mostly located at
roadside or around periphery of buildings. The ability to accommodate change is
medium to high. In overall, the landscape quality and value of the character
area is medium. |
Low |
Table 8.6 Baseline Visually
Sensitive Receivers (VSRs) and their Sensitivity to Change
O =
Occupational VSRs; RE = Recreational VSRs; R = Residential VSRs; T= Travelling VSRs
VSR
ID. |
Visually
Sensitive Receiver (VSR) |
No. of Individual (Many/ Few) |
Approx. Closet Viewing Distance to Project Site (m) |
Value and Quality of Existing View (Good/Fair/ |
Availability
of Alternative Views of similar or better quality (Yes/No) |
Degree
of Visibility to project site |
Frequency
of View (Frequent/ Occasional/Rare) |
Duration
of View |
Sensitivity (High/Medium |
||
Construction |
Operation |
Construction |
Operation |
||||||||
R1 |
Tung
Chung Town |
Many |
Many |
2570 |
Good |
Yes |
Full |
Frequent |
Long |
Medium |
Medium |
R2 |
Tung
Chung New Town Extension |
N/A[1] |
Many |
2160 |
Good |
Yes |
Full |
Frequent |
Long |
N/A1 |
Medium |
RE1 |
Visitors
at AsiaWorld-Expo |
Many |
Many |
560 |
Fair |
No |
Full |
Occasional |
Short |
Low |
Low |
RE2 |
Visitors
at Hong Kong SkyCity Marriott Hotel |
Many |
Many |
230 |
Fair |
No |
Full |
Occasional |
Medium |
High |
High |
RE3 |
Visitors
to North Commercial District |
N/A1 |
Medium |
180 |
Fair |
No |
Full |
Occasional |
Medium |
N/A1 |
High |
RE4 |
Recreational
users at Tung Chung New Town Extension |
N/A1 |
Many |
2570 |
Good |
Yes |
Obscured |
Occasional |
Medium |
N/A1 |
Medium |
RE5 |
Recreational
users at Scenic Hill |
Few |
Few |
2800 |
Good |
Yes |
Full |
Occasional |
Medium |
Medium |
Medium |
O1 |
Workers
at AsiaWorld-Expo |
Medium |
Medium |
560 |
Fair |
No |
Full |
Frequent |
Short |
Low |
Low |
O2 |
Workers
at Hong Kong SkyCity Marriott Hotel |
Medium |
Medium |
230 |
Fair |
No |
Full |
Frequent |
Medium |
Medium |
Medium |
O3 |
Workers
at North Commercial District |
Medium |
Medium |
183 |
Fair |
No |
Full |
Frequent |
Medium |
Medium |
Medium |
O4 |
Workers
at Civil Aviation Department Headquarters Office Building |
Medium |
Medium |
1520 |
Fair |
Yes |
Obscured |
Frequent |
Medium |
Low |
Low |
O5 |
Workers
at Tung Chung New Town Extension |
Many |
Many |
2160 |
Good |
Yes |
Full |
Frequent |
Medium |
Medium |
Medium |
O6 |
Workers
at HKBCF |
Medium |
Medium |
<100 |
Fair |
Yes |
Full |
Frequent |
Medium |
Medium |
Medium |
T1 |
Visitors
at HKBCF |
Many |
Many |
Varies |
Fair |
Yes |
Full |
Occasional |
Short |
Low |
Low |
T2 |
Sea Travelers |
Many |
Many |
Varies |
Fair
to Good |
Yes |
Varies |
Occasional |
Short |
Medium |
Medium |
T3 |
North
Lantau Highway |
Many |
Many |
Varies |
Good |
No |
Obscured |
Occasional |
Short |
Low |
Low |
Table 8.7 Magnitude
of Change on Landscape Resources (LRs) and Landscape Character Area (LCAs) under
Unmitigated Condition
ID |
Landscape Resources/ Character Areas |
Potential Sources of Impacts |
Description of Impacts |
Magnitude of Change |
|
Construction |
Operation |
||||
Landscape Resources |
|||||
LR1 |
Coastal
Waters of North Lantau Island |
¡P
Construction
of the Bonded Vehicular Bridge foundation using marine bored piles |
There
would be permanent, irreversible small scale of change. Since no open sea dredging of seabed
would be involved, the affected area would be relatively localized with
approx. 19,178 m2 to be disturbed. The foundations and piers on top would
also located away and will not disturb the sea wall during the construction. |
Small |
Small |
LR2 |
Roadside
landscape area within the HKIA |
Nil |
Nil |
Negligible |
Negligible |
LR3 |
Planned
Amenity / Compensatory Planting Area on HKBCF |
¡P
Construction
of viaducts, associated staging facilities and underground utilities |
Approx.
24,855 m2 out of 557,000 m2 (i.e. equivalent to about
4.46%) of this LR would be affected, including permanent loss of approx.
13,163 m2 planting area. Approx. 145 no. of planned trees would
be affected. Such scale of
affected area is considered relatively small. |
Small |
Small |
Landscape Character Area |
|||||
LCA1 |
Inshore
Water Landscape |
¡P
Construction
of the Bonded Vehicular Bridge with foundation using marine bored piles |
Approx.
19,178 m2 of the LCA would be affected. There would be perceivable disruption
to the overall unity of the inshore water landscape from the erection of the
proposed vehicular bridge and associated construction equipment setup during
construction phase. |
Intermediate |
Intermediate |
LCA2 |
Reclaimed
HKIA and HKBCF |
¡P
Construction
of the Bonded Vehicular Bridge, including the foundation using marine bored
piles |
Approx.
34,007 m2 out of 13,745,052 m2 (i.e. equivalent to
about 0.25%) of this LCA would be affected. The change would be of small scale,
permanent and irreversible. |
Small |
Small |
¡P
Construction
of the Bonded Vehicular Bridge foundation using marine bored piles
¡P
Construction
of viaducts, associated staging facilities and underground utilities
¡P
Construction
of proposed man-made structures, including fence, toilets transformer rooms
etc.
¡P Temporary works area within the HKBCF and the inshore seawater area with associated construction equipment and setup
¡P
Removal
of the planned amenity / compensatory planting on the HKBCF
Table 8.8 Locations
and Development Details of Permanent Man-made Structures
Location |
Approximate Height and Level (mPD) of the structure (1) |
Approximate Coverage (m)(1) |
Bonded
Vehicular Bridge (marine section) |
23.6 mPD at top level, 20.2 m above ESL at 3.4
mPD |
360 m(L) x 11m(W) (50 m at ITT end) |
Bonded
Vehicular Bridge (on
land section) |
22.7 mPD at top level, 16.2 m above ground |
164 m(L) x 11 m(W) |
Transformer
Room and LV Switch Room x 3 |
17.0
mPD at top level, 10.5 m above ground |
¡P
13 m (L) x 6.6 m (W) ¡P
20 m (L) x 6.6 m (W) |
AA
Kiosk for Security Control x 2 |
9.5 mPD,
3 m above ground |
5 m(L)
x 4 m(W) |
C&ED
Kiosk x 3 |
9.5 mPD, 3 m above ground |
5 m(L)
x 4 m(W) |
Toilets
x 4 |
9.5 mPD, 3 m above ground |
¡P
4 m (L) x 2 m (W) ¡P
6 m (L) x 5 m (W) |
Note:
(1) Subject to detailed design
Table
8.9 Magnitude of Visual Changes
during Construction and Operation Phases under Unmitigated Condition
Cons = construction phase; Op = operation
phase
VSR ID |
VSR |
Approx. Closest Viewing Distance to Project Site (m) |
Compatibility of the Project with the visual backdrop (High/ Medium/
Low) |
Duration of Impacts (Long/ Medium/ Short) |
Scale of Development (Large / Medium/ Small) |
Reversibility of Change |
Degree of visibility to the project site |
Potential Blockage of View |
Magnitude of Change (Large/ Intermediate/ Small/ Negligible) |
||||||
Cons |
Op |
Cons |
Op |
Cons |
Op |
Cons |
Op |
Cons |
Op |
Cons |
Op |
||||
R1 |
Tung Chung Town |
2570 |
High |
High |
Medium |
Long |
Medium |
Yes |
No |
Full |
Full |
Negligible |
Negligible |
Small |
Small |
R2 |
Tung Chung New Town
Extension |
2160 |
N/A2 |
High |
N/A2 |
Long |
Medium |
N/A2 |
No |
N/A2 |
Full |
N/A2 |
Negligible |
N/A[2] |
Small |
RE1 |
Visitors at AsiaWorld-Expo |
560 |
Medium |
Medium |
Medium |
Long |
Medium |
Yes |
No |
Full |
Full |
Partial |
Slight |
Intermediate |
Small |
RE2 |
Visitors at Hong Kong
SkyCity Marriott Hotel |
230 |
Low |
Low |
Medium |
Long |
Medium |
Yes |
No |
Full |
Full |
Partial |
Slight |
Intermediate |
Small |
RE3 |
Visitors to North
Commercial Facilities |
180 |
N/A2 |
Low |
N/A2 |
Long |
Medium |
N/A2 |
No |
N/A2 |
Full |
N/A2 |
Partial |
N/A2 |
Intermediate |
RE4 |
Recreational users at Tung
Chung New Town Extension |
2570 |
N/A2 |
High |
N/A2 |
Long |
Medium |
N/A2 |
No |
N/A2 |
Obscured |
N/A2 |
Negligible |
N/A2 |
Negligible |
RE5 |
Recreational users at
Scenic Hill |
2800 |
High |
High |
Medium |
Long |
Medium |
Yes |
No |
Full |
Full |
Negligible |
Negligible |
Small |
Small |
O1 |
Workers at Asia-World-Expo
|
560 |
Medium |
Medium |
Medium |
Long |
Medium |
Yes |
No |
Full |
Full |
Partial |
Slight |
Intermediate |
Small |
O2 |
Workers at Hong Kong
SkyCity Marriott Hotel |
230 |
Low |
Low |
Medium |
Long |
Medium |
Yes |
No |
Full |
Full |
Partial |
Slight |
Intermediate |
Small |
O3 |
Workers at North
Commercial District |
180 |
Low |
Low |
Medium |
Long |
Medium |
Yes |
No |
Full |
Full |
Partial |
Partial |
Intermediate |
Intermediate |
O4 |
Workers at Civil Aviation
Department Headquarters Office Building |
1520 |
High |
High |
Medium |
Long |
Medium |
Yes |
No |
Obscured |
Obscured |
Slight |
Negligible |
Small |
Negligible |
O5 |
Workers at Tung Chung New
Town Extension |
2160 |
High |
High |
Medium |
Long |
Medium |
Yes |
No |
Full |
Full |
Negligible |
Negligible |
Small |
Small |
O6 |
Workers at HKBCF |
<100 |
Medium |
Medium |
Medium |
Long |
Medium |
Yes |
No |
Full |
Full |
Partial |
Partial |
Intermediate |
Intermediate |
T1 |
Visitors at HKBCF |
<100 |
Medium |
Medium |
Medium |
Long |
Medium |
Yes |
No |
Full |
Full |
Partial |
Partial |
Intermediate |
Intermediate |
T2 |
Sea Travelers |
Varies |
Low |
Medium |
Medium |
Long |
Medium |
Yes |
No |
Varies |
Varies |
Partial |
Partial |
Intermediate |
Small |
T3 |
North Lantau Highway |
2640 |
High |
High |
Medium |
Long |
Medium |
Yes |
No |
Obscured |
Obscured |
Negligible |
Negligible |
Small |
Negligible |
¡P
The
viewpoints which cover the aboveground / above sea structure viewed from major public
viewpoint represents key VSRs or VSR groups who would be potentially affected
by the proposed Project; and
¡P
The
viewpoints which shall be able to represent the worst-case scenarios and
demonstrate the compatibility of the aboveground / above sea structures to the
adjacent visual context and illustrate the visual effect during Day 1 without
mitigation measures, Day 1 with mitigation measures and Year 10 with mitigation
measures.
Table 8.10 Landscape
and Visual Mitigation Measures for Construction and Operation Phases
ID |
Landscape Mitigation Measures |
Type of Mitigation Measures |
Parties to provide funding |
Implementation Agency |
Parties to be responsible for maintenance and
management |
|
Landscape |
Visual |
|||||
Construction Phase |
||||||
CM1 |
Preservation of New Tree Planting [1] All the
planned new trees to be retained and not to be affected by the Project shall
be carefully protected during construction in accordance with DevB TCW No.
7/2015 ¡V Tree Preservation during Development issued by GLTM Section of DevB.
Any existing vegetation in
landscaped area and natural terrain not to be affected by the Project shall
be carefully preserved. |
✔ |
✔ |
AAHK |
Project Proponent- |
AAHK |
CM2 |
Transplanting of Affected Trees [1] [3] Planned
trees to be planted under HKBCF unavoidably affected by the works shall be
transplanted within the project
boundary or off-site within the Airport Island (i.e. within area of approx. 6.2km) as far as
possible in accordance with DevB TCW No. 7/2015 ¡V Tree Preservation and the
latest Guidelines on Tree Transplanting issued by GLTM Section of DevB. |
✔ |
|
AAHK |
Project Proponent |
AAHK |
CM3 |
Compensatory Tree Planting [3] Any planned
trees to be planted under HKBCF to be felled under the Project shall be
compensated within the project
boundary or off-site within the Airport Island (i.e. within area of approx. 6.2km), in
accordance with DevB TCW No. 7/2015 ¡V Tree Preservation. The compensatory planting shall be of a
ratio not less than 1:1 in terms of number, i.e. the number of compensatory
trees shall not be lower than that of the number of trees to be felled. Justification shall be provided if tree
compensation requirement could not be met. For trees to be compensated on slopes,
the guidelines for tree planting stipulated in GEO Publication No. 1/2011
will be followed. |
✔ |
✔ |
AAHK |
Project Proponent |
AAHK |
CM4 |
Control of night-time lighting glare Any
lighting provision of the construction works at night shall be carefully
control to prevent light overspill to the nearby VSRs and into the sky. |
|
✔ |
AAHK |
Project Proponent |
AAHK |
CM5 |
Erection of Decorative Screen Hoarding Decorative
Hoarding, which is compatible with the surrounding settings, shall be erected
during construction to minimise the potential landscape and visual impacts
due to the construction works and activities. |
|
✔ |
AAHK |
Project Proponent |
AAHK |
CM6 |
Management of Construction Activities and
Facilities The
facilities and activities at works sites and areas, which include site
office, temporary storage areas, temporary works etc., shall be carefully
managed and controlled on the height, deposition and arrangement to minimise
any potential adverse landscape and visual impacts. |
✔ |
✔ |
AAHK |
Project Proponent |
AAHK |
CM7 |
Reinstatement of Temporarily Disturbed Landscape
Areas All
hard and soft landscape areas disturbed temporarily during construction shall
be reinstated on like-to-like basis, to the satisfaction of the relevant
Government Departments. |
✔ |
✔ |
AAHK |
Project Proponent |
AAHK |
Operation Phase |
||||||
OM1 |
Aesthetically Pleasing Design of Aboveground /
Above Sea Structures The
proposed structures in regard of layouts, forms, materials and finishes shall
be sensitively designed so as to blend in the structures to the adjacent
landscape and visual context |
|
✔ |
AAHK |
Project Proponent |
Long
term maintenance and management parties |
OM2 |
Provision
of Amenity Planting Amenity
planting, including groundcover and trees shall be provided to soften the
proposed above-ground structures on HKBCF as far as appropriate. |
✔ |
✔ |
AAHK |
Project Proponent |
Long
term maintenance and management parties [2] |
NOTES:
[1] The Project Proponent shall review the latest situation and
arrangement of the proposed treatment of the planned trees which is practical
and acceptable to the authorities.
[2] AAHK would liaise with
relevant government departments to agree on the subsequent maintenance agent
and would be responsible for maintenance and management of trees, vegetation before
any agreement is made.
[3] Transplanting of affected trees, proposed compensatory planting and
proposed amenity planting shall follow the latest Hong Kong International
Airport Approved Plant Species List.
[4] AAHK would liaise with relevant authorities to agree tree receptor
sites location for the proposed treatment.
ID. No. |
Landscape Resources /
Landscape Character
Areas |
Sensitivity (Low, Medium, High) |
Magnitude of Change (Negligible, Small,
Intermediate, Large) |
Impact Significance Threshold BEFORE Mitigation (Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual Impact Significance Threshold AFTER Mitigation (Insubstantial, Slight, Moderate, Substantial) |
||||
Construction |
Operation |
|||||||||
Construction |
Operation |
Construction |
Operation |
DAY 1 |
YEAR 10 |
|||||
LR1 |
Coastal Waters of North Lantau
Island |
High |
Small |
Small |
Slight |
Slight |
CM6 |
Slight |
Slight |
Slight |
LR2 |
Roadside landscaped area within
the HKIA |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
Nil |
Insubstantial |
Insubstantial |
Insubstantial |
LR3 |
Planned Amenity / Compensatory
Planting Area on HKBCF |
Low |
Small |
Small |
Slight |
Slight |
CM1 to CM3, CM6 to CM7, OM2 |
Slight |
Slight |
Slight |
LCA1 |
Inshore
Water Landscape |
High |
Intermediate |
Intermediate |
Moderate |
Slight |
CM6 |
Slight |
Slight |
Slight |
LCA2 |
Reclaimed HKIA and HKBCF |
Low |
Small |
Small |
Slight |
Slight |
CM1 to CM3, CM6 to CM7, OM1
to OM2 |
Slight |
Slight |
Slight |
Table 8.12 Significance of Visual Impacts during the Construction
and Operation Phases Before and After Mitigated Condition
VSR ID. |
Key Visually Sensitive Receiver (VSR) |
Receptor Sensitivity |
Magnitude
of Change (Negligible, Small, Intermediate, Large) |
Impact Significance Threshold Before Mitigation (Insubstantial, Slight, Moderate,
Substantial) |
Recommended Mitigation Measures |
Residual Impact Significance (Insubstantial, Slight, Moderate, Substantial) |
||||
Construction |
Operation |
|||||||||
Construction |
Operation |
Construction |
Operation |
DAY 1 |
YEAR 10 |
|||||
R1 |
Tung
Chung Town |
Medium |
Small |
Small |
Slight |
Slight |
CM6, OM1 |
Slight |
Slight |
Slight |
R2 |
Tung
Chung New Town Extension |
Medium |
N/A3 |
Small |
N/A3 |
Slight |
OM1 |
N/A[3] |
Slight |
Slight |
RE1 |
Visitors
at |
Low |
Intermediate |
Small |
Moderate |
Slight |
CM1, CM3 to CM7, OM1 to OM2 |
Moderate |
Slight |
Slight |
RE2 |
Visitors
at Hong Kong SkyCity Marriott Hotel |
High |
Intermediate |
Small |
Moderate |
Moderate |
CM1, CM3 to CM7, OM1 to OM2 |
Moderate |
Slight |
Slight |
RE3 |
Visitors
to North Commercial District |
High |
N/A3 |
Intermediate |
N/A3 |
Moderate |
CM1, CM3 to CM7, OM1 to OM2 |
N/A3 |
Slight |
Slight |
RE4 |
Recreational
users at Tung Chung New Town Extension |
Medium |
N/A3 |
Negligible |
N/A3 |
Insubstantial |
OM1 |
N/A3 |
Insubstantial |
Insubstantial |
RE5 |
Recreational
users at Scenic Hill |
Medium |
Small |
Small |
Slight |
Slight |
CM6, OM1 |
Insubstantial |
Insubstantial |
Insubstantial |
O1 |
Workers
at |
Low |
Intermediate |
Small |
Moderate |
Slight |
CM1, CM3 to CM7, OM1 to OM2 |
Moderate |
Slight |
Slight |
O2 |
Workers
at Hong Kong SkyCity Marriott Hotel |
Medium |
Intermediate |
Small |
Moderate |
Moderate |
CM1, CM3 to CM7, OM1 to OM2 |
Moderate |
Slight |
Slight |
O3 |
Workers
at North Commercial District |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1, CM3 to CM7, OM1 to OM2 |
Moderate |
Slight |
Slight |
O4 |
Workers
at Civil Aviation Department Headquarters Office Building |
Low |
Small |
Negligible |
Slight |
Insubstantial |
CM6, OM1 |
Slight |
Insubstantial |
Insubstantial |
O5 |
Workers
at Tung Chung New Town Extension |
Medium |
Small |
Small |
Slight |
Slight |
CM6, OM1 |
Slight |
Slight |
Slight |
O6 |
Workers
at HKBCF |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate
|
CM1, CM3 to CM7, OM1 to OM2 |
Moderate |
Slight |
Slight |
T1 |
Visitors
at HKBCF |
Low |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1, CM3 to CM7, OM1 to OM2 |
Moderate |
Slight |
Slight |
T2 |
Sea
Travelers |
Medium |
Intermediate |
Small |
Moderate |
Moderate |
CM1, CM3 to CM7, OM1 to OM2 |
Moderate |
Slight |
Slight |
T3 |
North
Lantau Highway |
Low |
Small |
Negligible |
Slight |
Insubstantial |
OM1 |
Slight |
Insubstantial |
Insubstantial |
Table 8.13 Potential
Cumulative Landscape and Visual Impact
Project |
Tentative Construction
Programme |
Potential
Cumulative Landscape and Visual Impact |
Expansion of Hong Kong International Airport into a Three-Runway
System (3RS) |
Aug 2016 ¡V 2024 |
Located approx. 600m away from
the Project site. There would be
cumulative landscape impact on loss of Coastal Waters of North Lantau Island
(LR1) due to reclamation work for the proposed 3RS. In terms of cumulative visual
impact, the scale of reclamation work for 3RS would generally dominate the
perceived change in quality of view for VSRs in proximity. The overall change in visual character due
to the Project would not be significant in comparison to the 3RS. |
Tung Chung New Town Extension
and its associated infrastructures |
Mid 2017 ¡V End 2030 |
The extent of visual change
would be limited as it is located approx. 2,160m away. The cumulative visual impact is
expected to be slight. |
Planning, Engineering and Architectural
Study for Topside Development at HKBCF Island of the HZMB ¡V Feasibility Study |
Study is under feasibility
study stage and yet to be concluded.
The construction programme is yet to be confirmed. |
Owing to uncertainty of the implementation
programme, it is assumed that construction and operation of the proposed
topside development would not overlap with the proposed works under this
Project. |
North Commercial District
(NCD), Chek Lap Kok Lot No. 3 |
Feasibility study is currently being
undertaken |
NCD currently occupies the
vacant site of the decommissioned SkyCity Nine Eagles Golf Course, where
there is no identified landscape resources. Therefore, no additional impact on
landscape resources or landscape character would be expected. In terms of cumulative visual
impact, NCD would have a maximum building height of approx. 53 mPD. The perceived change in surrounding
view would be limited. |
Intermodal Transfer Terminal
(ITT) |
Oct 2018 ¡V Aug 2021 |
ITT is located right adjacent
to the project site, where there is no identified landscape resources. Hence,
no additional impact on landscape resources or landscape character would be
expected. For the cumulative visual
impact, as the maximum height of ITT would be about 18mPD, which has similar
height as the proposed bonded vehicular bridge. Given its development
footprint is relatively localized and small, the overall perceived change in
surrounding view would be limited. In general, the additional visual impact
during both construction and operation phase would anticipate to be limited. |
[1] These VSRs are from concurrent
projects, which no individuals would expect to be affected during construction.
[2] These VSRs are from concurrent projects, which no individual would
expect to be affected during construction.
[3] These VSRs are from concurrent projects, which no individuals would
expect to be affected during construction.