TABLE OF
CONTENTs
11 Summary of environmental outcomes
11.2 Environmental
Benefits of the Project
11.3 Incorporation of
Environmentally Friendly Options
11.4 Environmental
Design Recommended
11.5 Key Environmental
Problems Avoided and Environmentally Sensitive Areas Protected
11.6 Environmental
Protection Measures Recommended
11.7 Estimation of
Population Protected
TABLES
Table 11.1 Summary
of Key Environmental Problems Avoided and Sensitive Areas Protected
Table 11.2 Key
Recommended Mitigation Measures
Avoidance of use diesel bonded vehicle
Avoidance of open sea dredging
Avoidance of direct impact on the intertidal habitats
¡P Adoption of environmental friendly construction method;
¡P Adoption of proactive measures to avoid illegal dumping;
¡P Implementation of environmental monitoring and auditing system.
Adoption of Environmental Friendly Construction
Method
Adoption of Proactive Measures to Avoid Illegal
Dumping
Implementation of Environmental Monitoring and
Auditing System
Table 11.1 Summary of Key Environmental
Problems Avoided and Sensitive Areas Protected
Design Approach |
Environmental
Problems Avoided and Sensitive Areas Protected |
Avoidance of use diesel bonded vehicle (Section 11.3.2) |
¡P
The
vehicular emissions are avoided during operation phase so that the nearby air
sensitive receivers are protected.
|
Avoidance of open sea dredging (Section 11.3.3) |
¡P
Avoid release of suspended solids, contaminants and nutrients
from sediment excavation to compliance with WQOs |
Avoidance of direct impact on the intertidal habitats (Section 11.3.4) |
¡P
Avoid loss of intertidal habitats. |
Adoption of environmental friendly construction method (Section
11.4.2) |
¡P
Adoption of quiet piling method to minimise the
construction noise impact |
Avoidance of illegal dumping (Section 11.4.3) |
¡P
The recommended preventive measures would
avoid/minimise the chance of illegal dumping. |
Implementation of Environmental Monitoring and Auditing System |
¡P
Ensure all the recommended measures are properly
in place and their effectiveness. |
Table 11.2
Key Recommended Mitigation Measures
Environmental Aspect |
Mitigation Measure and any Associated Benefit |
Air Quality Impact |
¡P
Implementing relevant control measures as
required in the Air Pollution Control (Construction Dust) Regulation to
minimise dust generation. |
Noise Impact |
¡P
Implementing good site practices to minimise the construction
noise impact. |
Water Quality Impact |
¡P
Implementation
of the proposed mitigation measures including installation of steel pile
casing and watertight cofferdam at the pier site, provision of appropriate
desilting or sedimentation device for treatment of water from dewatering
process, deployment of silt curtains, and use of suitable size of vessels for
marine bridge pile construction. ¡P
Implementation
of site practices as outlined in ProPECC Note PN 1/94 to control and minimise
site runoff and drainage. ¡P
Adoption
of proper site management and good housekeeping practices to minimise the
potential water quality impact due to spillage events. ¡P
Provision
of silt trap for road drainage for removal of pollutants from storm water. ¡P
Collection and conveyance of sewage effluent from
the proposed toilets to the existing sewerage system on HKBCF Island. |
Waste Management Implications |
¡P
Implementation of good site practices and waste
reduction measures (e.g. reuse of construction and demolition (C&D)
materials before off-site disposal or develop a materials recovery and
recycling programme during construction and operation). ¡P
Preparation of a Waste Management Plan (WMP), as
part of the Environmental Management Plan (EMP). ¡P
Implement a trip-ticket system for each works
contract in accordance with DevB TC(W) No. 6/2010 to ensure that the disposal
of C&D materials are properly documented and verified. ¡P
Handling of chemical waste in accordance with the
Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes,
and disposal of chemical waste at licensed chemical waste recycling /
treatment facilities. ¡P
Excavation, treatment, transportation and disposal
of sediments in accordance with the Air Pollution Ordinance (Construction
Dust) Regulation. ¡P
Any treatment area for the land-based sediment
should be confined for carrying out the treatment process and any temporary
stockpiling. The area should be
designed to prevent leachate from entering the ground. ¡P
For off-site disposal of excavated marine sediments,
the basic requirements and procedures specified under PNAP No.252 (ADV-21)
shall be followed. ¡P
Application of marine dumping permit under the
Dumping at Sea Ordinance for marine sediment disposal. ¡P
Collection and discharging of leachate in accordance
with the Water Pollution Control Ordinance. |
Marine Ecology |
¡P
Setting
up vessel speed limit (i.e. 10 knots) on all construction-related vessels to
minimise ship collision and acoustic disturbance to Chinese White Dolphins
based upon a precautionary approach. ¡P
Adopting
good site practices, guidelines and mitigation measures to further alleviate
water quality impacts on retained corals recorded along REA1 and REA3,
Chinese White Dolphins and other marine fauna. ¡P
Translocating
all 23 affected coral colonies recorded at REA2 to further reduce the direct
impact of habitat loss arising from the construction of proposed works as a
precautionary measure. A detailed
Coral Translocation Proposal would be prepared and subject to agreement with
the authority prior to the commencement of translocation works. ¡P
Conducting
precautionary post-translocation coral monitoring surveys on existing and
translocated corals at recipient site to ensure proper implementation of
coral translocation. |
Landscape and Visual Impact |
¡P
Preservation
of New Tree Planting ¡V All the planned new trees to be
retained and not to be affected by the Project shall be carefully protected
during construction in accordance with DevB TCW No. 7/2015 ¡V Tree
Preservation during Development issued by GLTM Section of DevB. Any existing vegetation in landscaped
area and natural terrain not to be affected by the Project shall be carefully
preserved. ¡P
Transplanting
of Affected Trees ¡V Planned trees to be planted under HKBCF unavoidably
affected by the works shall be transplanted within the project boundary or
off-site within the Airport Island as far as possible, in accordance with
DevB TCW No. 7/2015 ¡V Tree Preservation and the latest Guidelines on Tree
Transplanting issued by GLTM Section of DevB. ¡P
Compensatory
Tree Planting ¡V Any planned trees to be planted
under HKBCF to be felled under the Project shall be compensated within the project
boundary or off-site within the Airport Island
(i.e. within area of approx. 6.2km), in accordance with DevB TCW No. 7/2015 ¡V
Tree Preservation. The
compensatory planting shall be of a ratio not less than 1:1 in terms of
number, i.e. the number of compensatory trees shall not be lower than that of
the number of trees to be felled. Justification
shall be provided if tree compensation requirement could not be met. For trees to be compensated on slopes,
the guidelines for tree planting stipulated in GEO Publication No. 1/2011
will be followed. ¡P
Control
of night-time lighting glare ¡V Any lighting provision of the construction
works at night shall be carefully control to prevent light overspill to the
nearby VSRs and into the sky. ¡P
Erection
of Decorative Screen Hoarding ¡V Decorative Hoarding, which is compatible with
the surrounding settings, shall be erected during construction to minimise
the potential landscape and visual impacts due to the construction works and
activities. ¡P
Management
of Construction Activities and Facilities ¡V The facilities and activities at
works sites and areas, which include site office, temporary storage areas,
temporary works etc., shall be carefully managed and controlled on the
height, deposition and arrangement to minimise any potential adverse
landscape and visual impacts ¡P
Reinstatement
of Temporarily Disturbed Landscape Areas ¡V All hard and soft landscape areas
disturbed temporarily during construction shall be reinstated on like-to-like
basis, to the satisfaction of the relevant Government Departments. ¡P
Aesthetically
Pleasing Design of Aboveground / Above-sea Structures - The proposed
structures in regard of layouts, forms, materials and finishes shall be
sensitively designed so as to blend in the structures to the adjacent
landscape and visual context. ¡P
Provision
of Amenity Planting ¡V Amenity planting including groundcover and trees shall
be provided to soften the proposed above-ground structures on HKBCF as far as
appropriate. |