TABLE OF CONTENTs

 

12         CONCLUSION

12.1      Conclusion of EIA Study

 

 

TABLES

Table 12.1             Summary of Key Environmental Outcomes and Benefits

 

APPENDICES

Appendix 12.1      Key Assessment Assumptions and Limitation of Assessment Methodologies

Appendix 12.2      Summary of Environmental Impact

 

 

 

 

 

 

 

                                                                                                                                       


12                     CONCLUSION

12.1                  Conclusion of EIA Study

12.1.1              This EIA Report has provided an assessment of the potential environmental impacts associated with the construction and operation of the Project, based on the engineering design information available during the course of EIA study.

12.1.2              The assessment has been conducted, in accordance with EIAO-TM, covering the following environmental issues:

¡P         Air Quality Impact;

¡P         Noise Impact;

¡P         Water Quality Impact;

¡P         Waste Management Implications;

¡P         Marine Ecological Impact;

¡P         Landscape and Visual Impacts; and

¡P         Impact of Cultural Heritage.

12.1.3              The findings of this EIA study have determined the likely nature and extent of environmental impacts predicted to arise from the construction and operation of the Project.  During the EIA process, environmental control measures have been identified and incorporated into the planning and design of the Project, to achieve compliance with environmental legislation and standards during both the construction and operation phases.  The Implementation Schedule listing the recommended mitigation measures is presented in Appendix 10.1.

12.1.4              With the implementation of the mitigation measures, the Project would be environmentally acceptable with no unacceptable residual impacts on the environmentally sensitive receivers and resources.  Table 12.1 below summarises the key environmental outcomes and benefits that have accrued from the environmental considerations and analysis during the EIA process and the implementation of environmental control measures of the Project.  Appendix 12.1 presents the summary of key assessment assumptions and limitation of methodologies.  Appendix 12.2 presents the summary of environmental impacts and related Prior Agreements with Director.

12.1.5              The various sections of this EIA Report have presented the measures to minimise the potential environmental impacts associated with the Project throughout the construction and operational phases.  The key measures to minimise the environmental impacts are summarised in Section 11.6.

12.1.6              Environmental monitoring and audit (EM&A) requirements have been recommended, where necessary, to check on project compliance of environmental legislation and standards.  These are presented in a separate, stand-alone EM&A manual.


Table 12.1   Summary of Key Environmental Outcomes and Benefits

Environmental / Social Benefits of the Project

¡P     The Project is designed to provide a seamless and hassle-free connection between the ITT of HKIA and HKBCF Island to facilitate the intermodal modal travel of air passengers, in line with and further strengthening HKIA¡¦s strategic positioning and function as an international aviation hub in the region.

¡P     The Project incorporates environmental protection measures such as 100% adoption of electric vehicles and associated charging facilities in the ITT.

Environmentally Friendly Design and Options

¡P     Avoidance of use diesel bonded vehicle.

¡P     Avoidance of open sea dredging.

¡P     Avoidance of direct impact on the intertidal habitats.

¡P     Adoption of environmental friendly construction method.

¡P     Avoidance of illegal dumping.

¡P     Implementation of Environmental Monitoring and Auditing System.

Air Quality Impact

Construction Phase:

¡P     Potential dust impact generated from construction activities, such as site clearance, minor excavation with limited backfilling, and wind erosion of exposed area, and emission from PMEs would not be significant.  With implementation of suitable practice and mitigation measures, potential impacts on nearby ASRs in the vicinity of the Project would not be significant and would be controlled to within relevant standards.

Operation Phase:

¡P     As 100% electric vehicles will be used, there will be no air pollutants emission during the operation of the Project, adverse air quality impact is not anticipated.  Therefore, no mitigation measure will be required during the operation phase.

Noise Impact

¡P         As no existing and planned NSRs which rely on opened windows for ventilation is identified within the assessment area, no adverse noise impact will be generated from the construction and operation of the Project.

Water Quality Impact

Construction Phase:

¡P      No open sea dredging will be involved for construction of the Bonded Vehicular Bridge.  Sediment excavation will only be carried out in a confined dry working environment.  With implementation of mitigation measures including installation of steel pile casing and watertight cofferdam at the pier site, provision of appropriate desilting or sedimentation device for treatment of water from dewatering process, deployment of silt curtains, and use of suitable size of vessels for marine construction works, no adverse water quality impact is expected due to marine construction of the Bonded Vehicular Bridge.

¡P      Potential water quality impacts from the land-based construction works are associated with the general construction activities, construction site run-off, accidental spillage, and sewage effluent from construction workforce.  With implementation of site practices as outlined in ProPECC Note PN 1/94, no adverse water quality impact is expected due to the land-based construction works.

Operation Phase:

¡P      Potential hydrodynamic impact due to the presence of the marine bridge piles of the Bonded Vehicular Bridge has been identified and assessed with the use of computational modelling approach.  The model results showed that the change in current velocity would be small and localised at the sea channel between HKIA and HKBCF Island.  No significant change in flow regime at the sea channel is anticipated.  The predicted change in momentary flow and accumulated flow would also be minor, significant change in flushing capacity is not anticipated.  No adverse hydrodynamic impact would therefore be expected.

Waste Management Implications

Construction Phase:

¡P     Waste types generated by the construction of this Project are likely to include C&D materials, chemical waste from maintenance of construction plant and equipment, general refuse, excavated sediment, and potential floating refuse.  Provided that these wastes are handled, transported and disposed of according to the recommended good site practices, adverse environmental impacts are not expected.

¡P     The excavated sediment generated from the project comprised of marine-based sediment and land-based sediment. The marine-based sediment will be disposed in designated ways according to their categories, while the land-based sediment will be treated by S/S technique and reused on site.  No adverse environment impacts would be expected from excavation, treatment, transportation and disposal of sediment.

Operation Phase:

¡P     The main waste types generated during the operation of this Project would be chemical waste and MSW from maintenance activities and staff.  It is anticipated that no adverse impacts would arise if the mitigation measures were strictly followed.

Marine Ecological

Construction Phase:

¡P     Temporary loss of subtidal hard and soft bottom habitats/ marine waters due to the installation of steel pile casing would be 0.0087 ha in size approximately.  The direct impact is estimated to be minor given the affected area is small and scattered.

¡P     Marine mode of transportation within and outside of the Assessment Area could potentially cause vessel collision to Chinese White Dolphins (CWDs).  The impact of dolphin injury/ mortality is not likely to be critical as most construction vessels are large-sized and slow-moving.

¡P     Twenty three gorgonian coral colonies located on boulder surface along REA2 would be impacted directly by the construction works.  With the adoption of precautionary coral translocation and post-translocation coral monitoring surveys, direct ecological impact would be further reduced.  Indirect impacts on other coral colonies (REA1 and REA3) and other marine fauna would be controlled by implementation of good site practices such as the deployment of silt curtain and other water quality control measures.

¡P      Noise disturbance arising from construction works might indirectly reduce prey resources for CWDs, and affect dolphin communication, navigation and prey detection within the Brothers Marine Park. Since construction-related underwater noise has lower frequency than dolphin audiogram, while bored piling is adopted to reduce strong noise disturbance to marine wildlife, the acoustic impact is estimated to be acceptable.

Operation Phase:

¡P     Permanent loss of subtidal soft and hard bottom habitats/ marine waters due to the construction of the Project would be minimised to approximately 0.009ha.  The direct impact is anticipated to be minor given the affected area is small and scattered.

¡P     As no regular maintenance dredging would be required, additional direct impact of habitat loss or mortality of wildlife is not anticipated during operation phase.

¡P     Adverse hydrodynamic impacts on marine life are anticipated to be insignificant, given hydrological changes of flow regime, momentary flow, accumulated flow and flushing capacity are predicted to be negligible.

¡P     Potential impacts of water pollution arising from road surface runoff (e.g. chemical or oil spillage during traffic accident on bridge) are predicted to be minimal.

Landscape and Visual

¡P     On review of the potential residual impacts arising from construction and operation of the Project, all LRs and LCAs would be subjected to Insubstantial and Slight landscape impact, while all VSRs would be subjected to Insubstantial to Slight visual impact by operational Year 10.

¡P     The residual landscape and visual impacts are considered acceptable with mitigation measures implemented such as provision of amenity planting, aesthetically pleasing design of aboveground/above-sea structures during construction and operation phases.

Cultural Heritage

¡P     Baseline review on the previous studies and reports relating to the Project area was conducted.  It was concluded that the seabed of the Project area has no marine archaeological potential and further marine archaeological investigation is not required.

¡P     No terrestrial archaeological potential and built heritage resource are identified on reclaimed lands of HKIA and HKBCF Island within the Project boundary.  No impact is anticipated from the construction works of the project to cultural heritage resource during construction and operational phases.