Table of Contents

 

14       Conclusions.. 14-1

14.1       Introduction.. 14-1

14.2       Summary of Environmental Outcomes.. 14-1

14.3       Summary of Environmental Impacts.. 14-5

14.4       Documentation of Public Concerns.. 14-5

 

Appendices

Appendix 14.1                 Key assumptions and limitations

Appendix 14.2                 Summary of environmental impacts

 

 

 


14    Conclusions

14.1             Introduction

14.1.1.1      This EIA Report has provided an assessment of the potential environmental impacts associated with the construction and operation of the Project, based on the engineering design information available at this stage.

14.1.1.2     The assessment has been conducted, in accordance with the EIA Study Brief (No. ESB-287/2015) under the EIAO for the Project and the EIAO-TM, covering the following environmental issues:

·         Air Quality Impact

·         Noise Impact

·         Water Quality Impact

·         Sewerage and Sewage Treatment Implications

·         Waste Management Implications

·         Land Contamination

·         Ecological Impact (Terrestrial and Marine)

·         Fisheries Impact

·         Landscape and Visual Impacts

14.1.1.3     The findings of this EIA study have determined the likely nature and extent of environmental impacts predicted to arise from the construction and operation of the Project. During the EIA process, environmental control measures have been identified and incorporated into the planning and design of the Project, to achieve compliance with environmental legislation and standards during both the construction and operation phases. The Implementation Schedule listing the recommended mitigation measures are presented in Section 13. A summary of key assessment assumptions and limitation of methodologies are presented in Appendix 14.1.

14.1.1.4     The sections below summarise the environmental outcomes/benefits that have accrued from the environmental considerations and analysis during the EIA process and the implementation of environmental control measures of the Project.

14.2             Summary of Environmental Outcomes

14.2.1           Estimated Populations and Environmentally Sensitive Areas Protected from Various Environmental Impacts

14.2.1.1     The Project is located at the waterfront immediately in front of the village houses of the LYM villages and at the east of the LYM lighthouse. Population and environmental sensitive areas in the vicinity of the Project site have been protected through the avoidance and/or minimisation of environmental impacts from the construction and operation of the Project. Population protected from noise impacts due to the construction of the Project comprise Lei Yue Mun Village, Ma Wan Tsuen, Che Ting Tsuen, Ma Pui Tsuen and Tin Hau Temple. Adverse air quality impacts on sensitive receivers within the assessment area would not be anticipated. Environmental sensitive areas protected from adverse water quality impacts include Sam Ka Tsuen Typhoon Shelter, Yau Tong Flushing Water Intake, Secondary Recreation Zone at Tseung Kwan O, fish culture zones and nearby coral colonies.  


 

14.2.2           Environmental Designs Recommended, Environmental Friendly Option Considered and Incorporated in the Preferred Option

Avoidance of encroachment into recognized sites of conservation importance

14.2.2.1     The recognized sites of conservation importance have been identified and avoided during the planning and site selection process.  The selected project site will not encroach into any recognized sites of conservation importance.

Minimisation of Dredging Extent 

14.2.2.2     The proposed size and configuration of the dredging area are based on the minimum extent required to provide sufficient depth of water for vessels using the proposed landing facility, which is determined by detailed engineering and environmental assessments in order to minimise the associated waste generation as well as the direct disturbance to marine water quality, ecology and fisheries.

Minimisation of Underwater Rock Excavation

14.2.2.3     The current design of the landing facility has minimised underwater rock excavation while maintaining safe berthing of vessels. The breakwater is designed to be at the minimum length to cause the least environmental impact.

Enhancement of LYM Environment

14.2.2.4     As part of the Project, the proposed beautification works for the promenade, five lookout points and an existing viewing platform as well as streetscape improvement works would improve the overall environment and sustain heritage culture of LYM. The proposed pavilion, carp-shaped platform and promenade extension would be designed to blend in with the adjacent landscape and visual context. Green landscaping including trees, shrubs, ground covers and climbers would be provided at open spaces, viewing platform and lookout points to provide green transition between the waterfront and the existing urban areas that are lacking in the existing promenade.

14.2.3           Key Environmental Problems Avoided and Compensation Area Included

14.2.3.1     With the consideration of various alternative options in Project design and construction methods, the Project has avoided or minimised the following environmental problems:

·         Avoidance of encroachment into recognized sites of conservation importance;

·         Avoidance of loss of trees;

·         Minimisation of loss of ecological habitats;

·         Minimisation of generation of excavated and dredged materials; and

·         Minimisation of the number of environmental sensitive receivers to be affected.

14.2.4           Environmental Benefits of Environmental Protection Measures Recommended

14.2.4.1     Environmental benefits of environmental protection measures recommended in this EIA Report are summarised below.

Air Quality Impact

14.2.4.2     With implementation of sufficient dust suppression measures as stipulated under the Air Pollution Control (Construction Dust) Regulation and good site practices, no adverse construction dust impact would be anticipated on the surrounding ASRs.  Odour impact would be not expected from the dredging activities. Nonetheless, covering of dredged materials is recommended to further avoid any odour emissions.

14.2.4.3      Potential air quality impact from induced marine traffic emission from the operation of the Project has been predicted and the results indicate that no adverse air quality impacts on the nearby ASRs would be anticipated. No mitigation measure is therefore recommended.

Noise Impact

14.2.4.4     With the adoption of good site practice, quiet PME and noise barriers/enclosure, the noise levels at all the representative NSRs would comply with the EIAO-TM noise criteria. All practicable direct mitigation measures are considered to be exhausted to minimise the impacts.   

Water Quality Impact

14.2.4.5     During construction phase, the key source of potential water quality impact is associated with dredging and filling activities, which have potential to release contaminants and increase suspended solid levels in marine water. With the adoption of the recommended mitigation measures including use of closed grab, restriction of dredging production rate (no more than 100m3 per hour) and deployment of silt curtains during capital and maintenance dredging, no unacceptable residual water quality impact would be resulted.

14.2.4.6      The key source of potential water quality impacts during the operation phase would be the change in hydrodynamic regime, sewage effluent from the increased touristic and commercial activities, surface run-off associated with the new paved areas and maintenance dredging.  LYM waterfront was predicted to maintain its good flushing ability and no adverse water quality impact would be attributed to the establishment of landing facility and breakwater.  Meanwhile, as Lei Yue Mun Village Sewerage project will be commissioned concurrently to provide sewerage system to LYM, including the Project area, it is expected that water quality would be improved upon the completion of this concurrent project. For the potential impacts of surface run-off, it is anticipated that with proper implementation of the recommended mitigation measures, the potential adverse water quality impact would be minimised.

Sewerage and Sewage Treatment Implications

14.2.4.7     According to the latest construction programme, no programme gap is envisaged between the Lei Yue Mun Waterfront Enhancement Works by CEDD & ArchSD and the new sewerage networks constructed by DSD under Lei Yue Mun Village Sewerage project.  Hence, any sewerage plug-in and additional sewage arising from the increase in visitors will be discharged into the newly constructed sewerage system.

14.2.4.8     The existing Kwun Tong Preliminary Treatment Works has adequate treatment capacity to handle the sewage flow generated from the visitors in Lei Yue Mun after the completion of the waterfront enhancement works. Hence, no adverse sewage impact arising from the operation of the Project is anticipated.

Waste Management Implications

14.2.4.9     During the construction phase, waste generated from the Project include C&D materials, general refuse from workforce and chemical waste from the maintenance of construction plant and equipment.  Provided that these identified waste are handled, transported and disposed of following the relevant legislative and recommended requirements and that the recommended mitigation measures are properly implemented, no adverse environmental impact is anticipated.

14.2.4.10 Marine sediment would be generated from the dredging activities of the Project during construction phase and operation phase for maintenance purpose.  The marine sediment to be dredged was classified as Category L and (Type 1 – Open Sea Disposal) and Category H (Type 2 - Confined Marine Disposal) based on a review of the sediment quality data from the site investigation and previous study. With the implementation of recommended mitigation measures and management procedures in accordance with ETWB TCW No. 34/2002, no adverse environmental impact is anticipated. 

14.2.4.11 During the operation phase, the key waste generated would be general refuse from recreational activities and dredged marine sediment from maintenance dredging. With the implementation of recommended mitigation measures, no adverse environmental impacts would be anticipated.

Land Contamination

14.2.4.12 Based on the findings of site appraisal within the Site, no contaminating land use / activities were identified in the Site and adverse land contamination impact arising from Project is not anticipated. Thus, no Contamination Assessment Plan / Contamination Assessment Report / Remediation Assessment Plan are required to be prepared.

Ecological Impact (Terrestrial and Marine)

14.2.4.13 The proposed marine-based works would directly affect subtidal hard substrate habitats (0.05 ha), rocky shore (0.03 ha), sandy shore (0.02 ha) and artificial seawall (40 m); as well as temporary loss of subtidal soft bottom habitat (0.32 ha) and artificial seawall (85 m).  The proposed land-based works would only affect developed area near the seafront.  Given the small sizes and low ecological values of the affected habitats, the direct impacts are anticipated to be minor.  All temporarily affected works area will be reinstated. 

14.2.4.14 The subtidal hard substrata habitat within the study area supported sparse and patchy cover of locally common coral species.  Implementation of coral mitigation measures by means of translocation and/or other best practicable mitigation measures is recommended before the commencement of the works in order to minimise the impacts on the coral colonies.  To minimise the indirect impacts to marine environment, mitigation measures (e.g. use of closed grabs for dredging, deployment of silt curtain, etc.) would be implemented during construction phase and maintenance dredging in operation phase. 

14.2.4.15 Construction site runoff, noise, deteriorated water quality and other disturbance impacts resulting from the proposed marine-based and land-based works would have potential indirect impact to the nearby natural habitats (e.g. intertidal and subtidal habitats, mixed woodland and shrubland, etc.), wildlife, as well as fauna species of conservation importance.  Mitigation measures such as good site practice and water quality impact control measures are proposed to minimise the potential impacts.  With the proper implementation of mitigation measures, no adverse residual ecological impacts are expected from the Project.   

Fisheries Impact

14.2.4.16  The potential fisheries impacts due to the construction and operation of the Project are considered minor in view of the small scale of the works.  About 0.05 ha permanent loss and 0.6ha temporary loss of fishing ground are expected.   Indirect impact on fisheries due to change in water quality including elevation in suspended solids level, depletion of dissolved oxygen and release of contaminants, would be temporary and minimised with the implementation of recommended water quality mitigation measures such as adoption of silt curtain, reduced dredging rate, and use of closed grabs.

Landscape and Visual Impacts

14.2.4.17 During the construction phase, the key sources of landscape and visual impacts would include construction of new landing facility, dredging works, enhancement works of sitting out area and footpath and foundation work at lookout points. All existing trees within the proposed works boundary would be preserved.  The work areas for the Project are generally at ground level. The visual experience of the visual sensitive receivers (VSRs) would not be significantly changed. With the implementation of mitigation measures including preservation of existing trees, control of night-time lighting glare, erection of decorative screen hoarding, careful management of construction activities and facilities, provision of buffer zone (a minimum distance of about 10m) between the CPA and dredging works boundary, deployment of silt curtains and close supervision of dredging works, no unacceptable residual landscape and visual impacts from construction of the Project would be anticipated.

14.2.4.18  During the operation phase, the aboveground/above-sea-level structures/hardscape features such as the pavilion, the breakwater and the promenade with public landing facility, and maintenance dredging works would be the key sources of landscape and visual impacts. Nevertheless, the height of all the proposed aboveground/above-sea-level structures/features would not be prominent (not higher than 5m) and the maintenance dredging works would be limited scale and infrequent (interval of about every 5 to 10 years). With the recommended mitigation measures (e.g. provision of buffer zone between the CPA and dredging works boundary, deployment of silt curtains and close supervision of dredging works), the proposed aesthetic design for the aboveground/above-sea-level structures/hardscape features and buffer and amenity planting to fit into the local landscape and visual context, together with reinstatement of temporarily disturbed landscape areas, the overall landscape and visual impact of the Project would be beneficial.

14.3             Summary of Environmental Impacts

14.3.1.1      A summary of environmental impacts for the environmental issues assessed in this EIA is presented in Appendix 14.2.

14.4             Documentation of Public Concerns

14.4.1.1      Lei Yue Mun site is prioritized for improvement under The Tourism District Enhancement Programme that was implemented by Tourism Commission since 2000.  The Project was supported by the Kwun Tong District Council. Major concerns received from public during the course of the EIA Study are presented in Section 2.13.