2.1.1.1
Since
2000, the Tourism Commission (TC) has been implementing the Tourism District
Enhancement Programme to enrich Hong Kong’s appeal to visitors. Lei Yue Mun
(LYM), being one of the most popular tourist attractions in Hong Kong for its
pleasant seaside ambience and excellent seafood, had been identified to accord
priority for improvement under the Programme. The TC completed several initial
minor improvements along the LYM waterfront in 2003 and planned to further
improve the facilities along the LYM waterfront area.
2.1.1.2
The objective of this
Project aims at providing better access and supporting facilities for tourists
visiting there with a view to enhancing LYM’s
attractiveness for tourism.
2.2.1.1
The
Project site is located at the waterfront, east of LYM lighthouse, and close to
the LYM villages and attractions in LYM. It lies outside the eastern extent of
the Victoria Harbour. Figure 1.1
shows the location plan of the Project.
2.2.1.2
The current zonings of
the Project site under
the approved Cha Kwo Ling, Yau Tong, Lei Yue Mun Outline Zoning Plan (OZP) (No.
S/K15/25) include “Open Space” (“O”), “Other Special
Uses” (“OU”) annotated “Breakwater” and “Village Type Development” (“V”). The
rocky outcrop, oyster shell beach and the lighthouse (a total of about 0.07ha)
located at the southern coast of LYM is about 10m from the Project site and is
zoned as “Coastal Protection Area” (“CPA”) since 2011. As refer to the Notes of the
OZP, CPA is intended to conserve, protect and retain the lighthouse, the natural
coastlines and the sensitive coastal natural environment, including area of
scenic value, with a minimum of built development.
2.3.1.1
LYM,
which is conveniently situated near the urban area is a famous seafood tourist destination
internationally and locally. Coupled with identifiable cultural heritage
such as the Tin Hau Temple, the lighthouse and an abandoned quarry, LYM is
considered to be a potential site for further tourism development.
2.3.1.2
To
enhance the attractiveness of LYM, TC has initiated the LYM Waterfront
Enhancement Project (the Project) in 2005. Members of the Kwun Tong
District Council (KTDC) unanimously supported the Project when they were
consulted on the conceptual framework and design of the Project in 2005 and
2007 respectively.
2.3.1.3
At present, there is
still a strong local aspiration for the implementation of the Project. The
local community including KTDC, local residents, business operators and a number of
Legislative Council members have all along been pressing for the early
implementation of the LYM Project over the past few years.
2.4
Project Scope and Design
2.4.1.1
The proposed Project
consists of two main components:
1)
Construction of a
Public Landing Facility; and
2)
Development of a
Waterfront Promenade and Related Improvement Works.
2.4.1.2
The scope of the
components comprises the following works elements:
Construction
of a Public Landing Facility and Improvement Works
to Existing Lookout Points and Viewing Platform (by CEDD)
·
Construction of a
promenade with a public landing facility (i.e. landing step) which is capable
of accommodating vessels up to 30m long with draughts of about 3m;
·
Construction of a
breakwater;
·
Dredging of seabed to
provide sufficient water depth for navigation of vessels; and
·
Improvement works for
five existing lookout points and an existing viewing platform to improve their
structural capacity.
Development of a Waterfront
Promenade and Related Improvement Works (by ArchSD)
·
Construction of a
carp-shaped platform and a pavilion with children play area;
·
Beautification works
for the promenade, five lookout points and an existing viewing platform to
improve their visual appearance; and
·
Streetscape improvement
works.
2.4.1.3
Figure 2.1 shows the general layout plan of the Project.
2.4.1.4
A sloping seawall was
proposed to be constructed underneath the landing facility to protect its
future operation from the action of tides and waves. Two different scenarios
(existing rock head at -0.55mPD or above and existing rock head below -0.55mPD)
were considered and the respective designs are illustrated in Appendix
2.4.
2.4.1.5
The breakwater was
proposed to be in the form of a piled deck structure with a screen wall
incorporated on the eastern side of the deck structure, as shown in Appendix
2.5.
2.4.1.6
To facilitate safe
navigation of vessels up to 30m long with draughts of about 3m, dredging to the
level of -3.646mPD is required at the proposed landing facility. The dredging
extent and site boundary were reviewed and updated as shown in Figure
2.1 based on the existing geological profile and the required dredging
level. The dredging extent, at about 3,820m2, is slightly larger than that shown in the EIA
Study Brief to meet the operational requirement of the proposed landing
facility. Approximately 12,625m3 of sediment and underwater rock are
required to be dredged and excavated.
2.4.1.7
The detailed design for
structural improvement of viewing platform and lookout points 1, 3, 4, and 5
are presented in Appendices 2.6, 2.7,
2.8,
2.9,
and 2.10 respectively. No structural
improvement works is proposed for existing lookout point 2 owing to its good
structural condition. Excavation is required for the strengthening works of
existing lookout points and viewing platform. The excavation and construction
works will be carried out within the limit of the existing seawall. Modification
of the existing seawall will be required for lookout points 1 and 5, and
viewing platform, but no dredging works is expected. The area behind the
proposed seawalls have to be backfilled after its construction.
2.4.1.8
Upon
commissioning of the Project, the additional number of visitors to LYM
waterfront area was estimated to be
around 7,910. About 10
vessel trips (rounded-number) using the new LYM landing facility was estimated during peak hour.
2.5.1.1
The
key benefits of the proposed Project is to enhance LYM’s attractiveness for
tourism as well as improve the general environment for the residents
there.
2.5.1.2
The proposal to build a landing facility was
made in response to the request of the LYM community, whereas the proposed
location was agreed with KTDC. Seafood
restaurants and other attractions in LYM are geographically separated and away
from the existing Sam Ka Tsuen Public Pier, which is inconvenient for visitors
and sight-seeing vessels, and hence affecting its visitor-friendliness. The provision of a new landing facility near
the seafood restaurants would facilitate access by sea for visitors and also to
the inner parts of the Lei Yue Mun Village and other attractions in the area
(such as the LYM lighthouse and Tin Hau Temple), thereby enhancing their
visiting experience. In this way, it is expected that the Project would help develop tourism in LYM further.
2.5.1.3
The
Project would benefit the residents in LYM as well. The proposed beautification
works for the promenade, lookout points and viewing platform, streetscape
improvement works together with the construction of a carp-shaped platform and
a pavilion with children play area not only can enhance the outlook
attractiveness of LYM, but also improve the environment and living conditions
of the area. Aesthetic design and green landscaping including trees, shrubs, ground
covers and climbers would be provided at lookout platforms, streetscape and
pavilion to create a pleasant environment, which can further enhance the
landscape and visual quality of LYM waterfront area. The living environment of local community
will also be improved by the additional open space with landscape features and
the proposed leisure facilities for their enjoyment.
2.5.1.4
Apart
from the aforementioned benefits to be brought from the Project, the Project
also helps expedite the implementation of a new sewerage system for the Lei Yue
Mun area under the Lei Yue Mun Village Sewerage project undertaken by DSD. The
implementation of a new sewerage system for the Lei Yue Mun area is scheduled
to be carried out concurrently with the Project (see Section 2.12) to
address the hygiene and sewerage treatment concerns in the area, would bring
improvements to the water quality and environmental hygiene conditions. Such
improvement would be a vital element in enhancing tourist appeal and would not
only benefit the business sector but also the residents. The Project together with DSD’s Lei Yue Mun
Village Sewerage project will help promote a sustainable tourism growth for Lei
Yue Mun, in particular in strengthening its competiveness among other seafood
dining destinations over the territory and improving the overall water quality
and environmental hygiene conditions with a view to benefiting the visitors and
local residents there.
2.6
Scenario without the Project
2.6.1.1
Without the Project,
LYM will soon be deprived as a seafood dining destination because of the
arising competitors and falling performances. Even if its attraction is somehow
maintained, LYM can only support a small extent of tourism growth with the
existing facilities and infrastructures condition, the tourism development may
not be sustainable. Furthermore, the environmental benefits of the Project as
discussed in Section 2.5, could not
be attained if without the Project.
2.7.1.1
The
Project will bring benefits in enhancing tourism appeal and environment of LYM
as discussed in Section 2.5. Nevertheless, the implementation of the
Project would inevitably induce potential environmental impacts during
construction and operational phases. With careful consideration of various
siting and layout options for the Project, the preferred option would pose much
less environmental impacts while achieving the objective to support tourism
development of LYM in a sustainable manner. The potential environmental impacts
associated with the Project have been assessed in Sections 3 to 11 and
mitigation measures have been recommended if necessary to alleviate the impacts
to acceptable levels.
2.8
Consideration of Alternative Options
Alternative Location
2.8.1.1
The
prime objective of the proposed landing facility is to provide a more
convenient marine access for visitors to the seafood restaurants and other
tourism attractions in LYM. Hence, the
location of the proposed landing facility should be as close to these
attractions as possible. The proposed
public landing facility is designed to accommodate potential largest vessels of
up to 30m long (e.g. tour group vessels).
Having taken into account factors including site conditions, marine safety,
environmental considerations, proximity to the seafood restaurants and other
attractions in LYM, availability of a suitable hinterland as passengers holding
area etc., three possible locations: existing berthing (Location 1) and village
jetty (Location 2) outside the Sam Ka Tsuen Typhoon Shelter and waterfront on
the south coast of LYM (Location 3) had been identified (illustrated in Appendix 2.2). A broad comparison
is summarised in Table 2.1.
Table 2.1 Comparison of Possible Locations of Landing Facility
Consideration
Factors
|
Location 1
|
Location 2
|
Location 3
(Selected)
|
Site Conditions
|
· Proposed
construction of a pier
· Involve
larger scale clearance of residential squatters and/ or seafood restaurants
to provide adequate passengers holding area
· Larger
impact on local community
· Larger
impact on the operation of Sam Ka Tsuen Typhoon Shelter due to its close
proximity to the entrance of the typhoon shelter
|
· Proposed
construction of a pier
· Involve
larger scale clearance of residential squatters and/ or seafood restaurants
to provide adequate passengers holding area
· Larger
impact on local community
· Larger
impact on the operation of Sam Ka Tsuen Typhoon Shelter due to its close
proximity to the entrance of the typhoon shelter
|
· Proposed
construction of a public landing facility
· Involve
smaller scale clearance of residential squatters
· Less
impact on local community
· Less
impact on the operation of the Sam Ka Tsuen Typhoon Shelter as it is located
further away from the typhoon shelter
|
Environmental Considerations
|
· Closer
to air and noise sensitive areas
· Larger
amount of waste materials will be generated due to larger scale of clearance
is required
· No
encroachment on recognized sites of conservation importance
· Potential
impact on water quality and marine ecology due to small-scale marine works
could be minimized with appropriate mitigation measures
|
· Closer
to air and noise sensitive areas
· Larger
amount of waste materials will be generated due to larger scale of clearance
is required
· No
encroachment on recognized sites of conservation importance
· Potential
impact on water quality and marine ecology due to small-scale marine works
would be minimized with appropriate mitigation measures
|
· Comparatively
further away from air and noise sensitive areas
·
Less waste materials will be generated due to smaller scale of clearance of residential squatters
· No
encroachment on recognized sites of conservation importance
· Potential
impact on water quality and marine ecology due to small-scale marine works
could be minimized with appropriate mitigation measures
|
Impact on Victoria Harbour
|
Yes1
|
Yes1
|
No
|
Project programme
|
Hard
to predict2
|
Hard
to predict2
|
About
43 months
|
Notes:
1. Locations
1 and 2 lie within the limit of the Victoria Harbour, which is subject to the
statutory presumption against reclamation of the Harbour under the Protection
of the Harbour Ordinance. Government must be satisfied that the “overriding
public need” test as stipulated in the judgment of the Court of Final Appeal
regarding reclamation within the Harbour has been met, before a proposal
involving reclamation within the Harbour will be selected.
2. It
is difficult to predict the time required for “overriding public need” (see
Note 1) establishment.
2.8.1.2
Amongst
the three locations proposed, Location 3 is selected as it is conveniently
located with a reasonable walking distance to the seafood restaurants and other
attractions in LYM and has less impact on the local community and the operation
of Sam Ka Tsuen Typhoon Shelter. For
Locations 1 and 2, larger scale of clearance of residential squatters and/ or
restaurants is required and hence pose larger impact on local community. In addition, they are located closer to the
entrance of Sam Ka Tsuen Typhoon Shelter, construction of a pier at these two
locations would have larger impact on the operation of the typhoon shelter due
to the increased marine traffic density in the surrounding waters, especially
during peak hours.
2.8.1.3
With
respect to environmental aspects, Location 3 is located further away from air
and noise sensitive areas and hence would pose less air quality and noise
impacts. In addition, construction of the landing facility at Location 3 would
require smaller scale clearance of residential squatters and therefore would
generate less waste materials. The
potential impact on water quality and marine ecology arising from the
small-scale marine works is anticipated to be minor. With implementation of appropriate mitigation
measures as discussed in Sections 5 and 9, adverse impact on water quality and
marine ecology would not be anticipated.
2.8.1.4
With the consideration
of various options, Location 3 is considered as the most practical and feasible
option for the landing facility that can achieve the objective of the Project
with less impact on the local community and operation of Sam Ka Tsuen Typhoon
Shelter and environmentally viable. Based on feedback
from KTDC, Location 3 is also considered to be a better option than the other
two locations.
Alternative
Layout Design
2.8.1.5
Alternative
project layouts were considered to select the optimum option to minimize
environmental impacts whilst fulfil the operational requirements. The different
designs (original, alternative, and preferred) are illustrated in Appendix 2.3.
2.8.1.6
The
original design of the landing facility, which comprises a seawall of
approximately 88m long by 6m wide and a breakwater protrudes from the eastern end
of the seawall by about 35m to protect berthing vessels from waves was
proposed. The breakwater in the original design was proposed to be constructed
by a pre-formed caisson to form a solid structure, with sand filling at its
foundation.
2.8.1.7
In
order to reduce underwater rock excavation, an alternative layout has been
developed by optimising the quantity of rock to be excavated, while maintaining
the safe berthing of vessels and feasibility in terms of wave attenuation,
tidal movement and other marine traffic aspects. In the alternative design, the cope wall is
moved further seawards by about 4m (at 10m wide) and the breakwater will be in
the form of a piled deck structure with a screen wall installed on the outer (eastern)
side of the deck structure. With this alternative design, the amount of rock to
be excavated would be reduced and thus more environmentally acceptable. In addition, less noise impacts to the nearby noise
sensitive receivers is expected and the potential resuspension of fine and
possibly contaminated material from the seabed will be reduced as the
alternative breakwater design requires less dredging volume.
2.8.1.8
The preferred design
option, which is the current design adopted in this EIA study, is a
modification of the alternative design with added benefits. In this preferred
design option, the length of the breakwater is reduced to 30m long which allows
more room for smaller boats to sail within the nearshore area whilst
maintaining a suitable berthing condition at the landing facility. The environmental
benefits as discussed in Section 2.5
still holds, making this design the best out of the three and is thus selected.
2.9.1.1
The
construction method and sequence to be adopted for the Project are based on
engineering, site constraints and environmental considerations. Details of the
construction methods are presented in sections below.
Construction
of a Public Landing Facility and Improvement Works to Existing Lookout Points
and Viewing Platform
2.9.1.2
The
proposed works comprises construction of a promenade with public landing
facility, a breakwater, dredging of the seabed and improvement works for five
existing lookout points and an existing viewing platform. The construction
methods and sequences of the proposed works are presented in Table 2.2.
Table 2.2 Construction
Methods of the Proposed Public Landing Facility and Improvement Works to Existing
Lookout Points and Viewing Platform
Construction Method
|
Construction Sequence
|
Landing Facility and Breakwater
|
Installation of pipe pile wall along existing shore to
support the land for dredging
|
·
Install
silt curtain and marine marking buoys
·
Drill
hole from ground level to the required rockhead level for installation of
pipe pile
·
Place
rebar cage into the hole; grout or concrete the hole to pile cut off level or
other designated level
·
Grout the
landside face of pipe pile wall for prevention of loss of fill
|
Dredging of marine sediment to the design level and
disposal of material off-site
|
Derrick lighter (or
alternatively crane barge) equipped with close grab and hopper barge with
motor tugs to be deployed for dredging and disposal of marine sediment:
·
Dredge
the west side first to expose area required subsequent rock excavation
·
Dredge
layer by layer and follow the sediment categorization plan for various
disposal requirements
|
Underwater rock excavation at the western side of
the site
|
Rock excavation
to be carried out by chiseling method from derrick lighter (or alternatively
by excavator with underwater breaker mount on a flat top barge):
·
Carry out
excavation
·
Remove
the broken rock fragments by derrick lighter similar to other dredging works
|
Installation of pre-bored H-piles for the deck
structure and breakwater
|
·
Drill
hole from seabed to the required rockhead level for installation of pre-bored
H-pile
·
Place the
H-pile into bored hole
·
Grout or
concrete the borehole to pile cut off level or other designated level
|
Construction of deck structure
|
·
Construct
in situ concrete pile caps within temporary
cofferdam with precast beam and inclined bracings at lower level
·
Reinstate
the existing sloping seawall profile. Existing blockwork wall at the slope
toe can be replaced with the proposed new tailor-made blockwork or new
precast L-shaped retaining wall units
·
Construct
capping beam, in situ deck beam and
slab
|
Construction of wave absorption chamber for the
breakwater
|
·
Construct
the in situ vertical wave absorbing
seawall within temporary cofferdam
·
Install
front panel (precast unit)
|
Lookout Points and Viewing Platform
|
Demolition of existing structures
|
·
Excavate
down to the required level by excavator or derrick lighter
·
For
lookout points 1 and 5, and the viewing platform, the existing seawall will
be modified. Excavation shall be limited to the toe of the existing seawall
|
Installation of seawall block/mass concrete or
reinforced concrete structure
|
·
Install
seawall block/mass concrete or reinforced concrete structure
·
For
lookout points 1 and 5, and the viewing platform, the seawall shall be formed
within the original footprint
|
Backfilling and reinstatement
|
·
Backfill
the area behind the proposed seawall
·
Reinstatement
of pavement
|
Development of a Waterfront
Promenade and Related Improvement Works
2.9.1.3
The
construction of the proposed waterfront promenade and related improvement works
comprises construction of a carp-shaped platform and a pavilion with children
play area, beautification works for the promenade, five lookout points and an
existing viewing platform; and streetscape improvement works.
2.9.1.4
The
proposed waterfront promenade and related improvement works will be land-based,
on built or strengthened infrastructures. No marine works will be involved.
Generally, this Project item involves removal or demolishing existing finishes,
screening, and plastering of floors and walls. Beautification works comprise
of, but not limited to, planting, decorative mosaic tiles and light fittings
installation, planter curb, planter wall, seawall and vertical green wall
construction, will be carried out at promenade, lookout points, viewing
platform and streetscape area. Improvement works, including protective
barriers, proprietary sitting bench and litter bins installation, will be
conducted at designated locations. Areas beyond the non-renovation areas will
be protected and remain unchanged or reinstated if affected by works.
Environmental Considerations
2.9.1.5
The
construction method and sequence of public landing facility, breakwater and
related improvement works have incorporated the following measures to minimise
the potential environmental impacts:
·
Minimise active marine works area
by phased construction and adopting piled deck structure for the landing
facility and breakwater to reduce the amount of dredging works;
·
Utilise pre-cast elements for construction of the landing facility and
breakwater as far as practicable to minimise in-situ construction works so as
to reduce the construction period and environmental impacts, such as waste
generation, noise and dust impacts; and
·
Install silt curtain and
restrict dredging operation to a production rate of no more than 100m3
per hour to minimise the potential water quality impact (e.g. prevent the
dispersion of suspended sediments) arising from the dredging works.
·
Implement good site practice and appropriate environmental
mitigation/control measures.
2.10.1.1
During
operation phase, periodic (maintenance) dredging of seabed is necessary to
maintain sufficient water depth for navigation of vessels. With reference to
the approved EIA for “Dredging Works for Proposed Cruise Terminal at Kai Tak”
(AEIAR-115/2007), siltation rates around the waters is approximately 50-60mm
per year. Bathymetric surveys will be carried out at regular intervals to
verify the actual siltation rates and estimate the number of years required for
maintenance dredging for safe navigation of vessels (e.g. preventing the seabed
to be raised by siltation by 0.5m higher than the required seabed level of
-3.646mPD) . The area of maintenance dredging would be the same as the proposed
capital dredging.
2.10.1.2
Based
on the siltation rate from the approved EIA for “Dredging Works for Proposed
Cruise Terminal at Kai Tak EIA” and allowing a 0.3m tolerance in maintenance
dredging from practical point of view, it is estimated that dredging of up to
0.8m of sediment will be required at an interval of about every 5 to 10 years.
Based on the dredging area of about 3,820m2, the dredged volume is
estimated to be approximately 3,056m3. Similar to capital dredging,
mitigation measures on potential impacts on water quality and marine ecology
due to maintenance dredging, which include use of closed grab dredger,
restriction of dredging production rate of no more than 100m3 per
hour and deployment of silt curtains, will be implemented.
2.11
Project Programme
2.11.1.1
The
Project construction works are anticipated to commence in Q3 2019 and be completed by Q1 2023. A tentative construction programme
for the Project is presented in Appendix
2.1. The assessments in this report are based on this programme, using
reasonable worst-case scenarios.
2.12.1.1
During
construction of the Project, there is a concurrent project identified in the
vicinity (within 500m from the Project site), i.e. Lei Yue Mun Village Sewerage project commissioned by Drainage Service Department
(DSD). The Lei Yue Mun Village Sewerage project will construct 1km long new
underground gravity sewers within Lei Yue Mun Village and 460m long twin rising
mains. In addition, about 400m long of the existing gravity sewers at Lei Yue
Mun Praya Road and Lei Yue Mun Path will also be upgraded. According to the
DSD's study, the interim measure of constructing septic tanks and dry weather
flow interceptors was considered not necessary. Based on the available
information at the time of this EIA study, the Lei Yue Mun Village Sewerage
project would be carried out from Q3 2018 to Q1 2023. Therefore, the additional
sewage generated from Lei Yue Mun Waterfront Enhancement Project will be
collected by the newly constructed sewage system.
2.12.1.2
Potential
cumulative environmental impacts arising from this concurrent project during
the construction and operation phases of the Project have been assessed in the
EIA Report. During the detailed design
stage, ArchSD will closely liaise with DSD and their contractors to have a
proper planning of the interfacing works (e.g. exploring the possibility of
entrusting the streetscape improvement works to DSD) so as to minimise the
potential cumulative impacts by avoiding/minimising repeated and concurrent
construction works.
2.13
Public Consultations
2.13.1.1
Project
framework was submitted to KTDC for comments in May 2005, following with the
submission of conceptual design and design features in May 2007, May 2008 and
March 2010. The conceptual design of the Project was also presented to the
Sub-committee on Harbour Plan Review of the Harbour-front Enhancement Committee
in September 2008. Relevant stakeholders, including green groups and fishermen
had been consulted on the design and scope of the Project. A consultation
session for LYM residents was arranged in December 2008. The detailed Project
design was presented to the Sub-committee and Secretariat of the Task Force on
Harbourfront Developments in Kowloon, Tsuen Wan and Kwai Tsing (the Task Force)
on 4 October 2010.
2.13.1.2
During
the public inspection period of the project profile in 2015, comments received
were largely in favour of the Project, in particular, the seafood restaurateurs who considered that the Project
would bring benefits to the community.
2.13.1.3
Key
findings and concerns obtained from the public consultation meetings and the
public comments received during the public inspection period of project
profile, as well as the follow-up action taken are summarised in Table 2.3.
Table 2.3 Summary of Public Concerns and Follow-up Actions
Key Concerns
|
Follow-up Actions
|
Existing natural setting of LYM and preservation of
the rocky beach
|
The Project
design has taken into account this concern by preserving the existing natural
setting of LYM and the Oyster Shell Beach as well as the indigenous character
of LYM as a fishing village.
|
Hygiene and sewerage treatment problems in LYM
|
The Food
Business (Amendment) Regulation 2009 enacted on 1 August 2010 has prohibited
the extraction of seawater from prescribed areas, including the LYM coastal
area, for keeping live seafood. Food and Environmental Hygiene Department
(FEHD) would enforce the regulation through inspecting the water quality from
time to time.
In conjunction
with the Project, proper sewerage facilities would be provided in Lei Yue Mun
under Lei Yue Mun Village Sewerage project initiated by DSD. With the
provision of new sewage system and dry weather flow interceptor, the polluted
flow from the
existing stormwater system will be intercepted. It is anticipated the hygiene conditions of the area
would be improved. In addition, sewage
generated from LYM area including sewage generated from visitors
arising from the Project will be
discharged to the new sewage system. Hence, adverse sewerage impact arising
from the Project is not anticipated.
|
Water quality impact brought from the increased
number of visitors
|
The water
quality impacts and sewerage impacts arising from the increased visitors has
been assessed in Sections 5 and 6 of this EIA Study respectively. With the completion
of the Lei Yue Mun Village Sewerage
project, there would be no adverse impact on water quality as a result of
sewage from the increased visitors as discussed in Section 5 of the EIA.
|
Possible impact of attracting coach traffic to the
area lacking of sufficient coach loading/unloading spaces
|
One of the main
objectives of the Project is to facilitate tourists visiting the LYM
waterfront area by sea upon commissioning of the public landing facility. The
use of coach traffic to visit the area is not encouraged and the issue of
coach loading/unloading spaces would not be anticipated.
|
The Project should be implemented as soon as
possible to improve the conditions of surrounding areas
|
The Project is
planned to implement as early as practicable. Construction of the Project are
planned to commence tentatively in Q3 2019 and completed in Q1 2023 (Section
2.11).
|
Potential noise and visual impacts during
construction
|
The EIA has
assessed the potential impacts during construction and operation of the
Project. Mitigation measures have been recommended to minimise the air
quality (Section 3.7), noise (Section 4.8) and visual impacts (Section
11.10), and proper waste disposal and minimisation measures (Section 7.7) to
avoid disruptive impacts to the villagers and tourists. A robust
environmental monitoring and audit (EM&A) programme detailed in the
EM&A Manual will be implemented.
|
Potential impact on the restaurants near the lookout
points and impact on the visitors during the construction stage
|
The EIA has
recommended various mitigation measures to minimize the potential environment
impacts during construction stage. In
addition, close liaison among CEDD, ArchSD and DSD will be kept to minimise
the cumulative impacts from the projects during construction stage which includes
setting up of community liaison groups as necessary. Hotlines will also be set up for the
projects to handle public enquiries and complaints. These measures have been incorporated in
the EM&A Manual.
|
Alternative sea-route access at Sam Ka Tsuen Pier is
available – there is not a need for a new landing facility
|
Seafood restaurants and other attractions in LYM are
geographically separated and away from the existing Sam Ka Tsuen Public Pier,
which is inconvenient for visitors and sight-seeing vessels, and hence
affecting its visitor-friendliness.
The provision of a new landing facility near the seafood restaurants
would facilitate access by sea for visitors and also to the inner parts of
the Lei Yue Mun Village and other attractions in the area (such as the LYM
lighthouse and Tin Hau Temple), thereby enhancing their visiting experience.
In this way, it is expected that the Project would help develop tourism in LYM further. The need for
the Project is discussed in Section 2.3 of the EIA.
|
Water quality objectives should be taken into
account for watersports activities including swimming in the area
|
Potential water
quality impacts associated with the Project have been assessed against
relevant Water Quality Objectives (WQOs) in Section 5 of the EIA in
accordance with the requirements of the EIA Study Brief and the EIAO-TM.
These relevant WCZs do not include the beneficial use for primary contact
recreation including swimming. The relevant EPD Water Quality Monitoring Data
in 2016 indicated that the baseline water quality at these relevant WCZs
complies with the WQO for E. coli
(< 610 count / 100 ml for geometric mean for secondary contact recreation
subzone). Given that a new public sewerage system will be provided for the
LYM area under a separate project undertaken by DSD to cater for the sewage
discharge from the existing LYM area including the additional sewage arising
from the Project, the water quality of the LYM area will be improved. It is
noticed that the latest route of the Annual Cross Harbour Swim has been
changed to Wan Chai to Tsim Sha Tsui. Should the routing of the Annual Cross
Harbour Swim is resumed to Lei Yue Mun, the dredging operation would be
properly scheduled such that no dredging works will be carried out during the
period of the Annual Cross Harbour Swim Race to be held.
|
Level of pollution of soil and sediment to be
dredged
|
A sediment
sampling and testing has been carried out to identify the contamination level
of soil and sediment within the dredging area. The disposal of dredged marine
sediment will follow the procedures in accordance with ETWB TCW No. 34/2002.
The level of contamination and the estimated quantity of dredged marine
sediment to be disposed of have been assessed in Section 7 of the EIA.
|