Table of Contents

 

8    Land Contamination. 8-1

8.1         Introduction. 8-1

8.2         Environmental Guidelines, Standards and Criteria. 8-1

8.3         Assessment Methodology. 8-1

8.4         Description of the Environment. 8-2

8.5         Site Appraisal. 8-2

8.6         Prediction and Evaluation of Land Contamination Impacts. 8-4

8.7         Environmental Monitoring and Audit. 8-4

8.8         Conclusion. 8-4

 

List of Tables

Table 8.1   Aerial Photographs Reviewed. 8-2

 

Figures

Figure 8.1          Photo Records of Site Reconnaissance – Key Plan

Figure 8.1A       Photo Records of Site Reconnaissance (Region A)

Figure 8.1B       Photo Records of Site Reconnaissance (Region B)

Figure 8.1C       Photo Records of Site Reconnaissance (Region C)

Figure 8.1D       Photo Records of Site Reconnaissance (Region D)

Figure 8.1E       Photo Records of Site Reconnaissance (Region E)

 

Appendices

Appendix 8.1    Selected Aerial Photos

Appendix 8.2    Replies from Environmental Protection Department

Appendix 8.3    Replies from Fire Services Department

Appendix 8.4    Site Walkover Checklist

 

 

 

 


8              Land Contamination

8.1                  Introduction

8.1.1.1          This section presents the potential implications of land contamination associated with the Project.

8.2                  Environmental Guidelines, Standards and Criteria

8.2.1.1          The relevant environmental guidelines and standards on land contamination aspect include the following:

          Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM)

          Guidance Note for Contaminated Land Assessment and Remediation (Guidance Note)

8.2.1.2          The Guidance Note sets out the requirements for proper assessment and management of potentially contaminated sites such as oil installations (e.g. oil depots, petrol filling stations), gas works, power plants, shipyards / boatyards, chemical manufacturing / processing plants, steel mills / metal workshops, car repairing / dismantling workshops and scrap yards. In addition, this Guidance Note provides guidelines on how site assessments should be conducted and analysed and suggests practical remedial measures that can be adopted for the clean-up of contaminated sites.

          Practice Guide for Investigation and Remediation of Contaminated Land (Practice Guide)

8.2.1.3          This guide outlines typical investigation methods and remediation strategies for the range of potential contaminants typically encountered in Hong Kong.

          Guidance Manual for Use of Risk-based Remediation Goals for Contaminated Land Management (Guidance Manual)

8.2.1.4          The Guidance Manual introduces the risk based approach in land contamination assessment and present instructions for comparison of soil and groundwater data to the Risk-Based Remediation Goals (RBRGs) for 54 chemicals of concern commonly found in Hong Kong.  The RBRGs were derived to suit Hong Kong conditions by following the international practice of adopting a risk-based methodology for contaminated land assessment and remediation and were designed to protect the health of people who could potentially be exposed to land impacted by chemicals under four broad post restoration land use categories. The RBRGs also serve as the remediation targets if remediation is necessary.

8.3                  Assessment Methodology

8.3.1.1          The following tasks have been undertaken to identify any potentially contaminated areas:

          Desktop study to review the current and historical land uses; and

          Site reconnaissance to identify potentially contaminated areas as necessary.

8.3.1.2          To facilitate the land contamination assessment, the following sources of information have also been collated and reviewed:

          Aerial photographs from Survey and Mapping Office of Lands Department;

          Records (if any) on dangerous goods (DGs), chemical wastes, chemical spillage/leakage and fire incidents from Environmental Protection Department (EPD) or Fire Services Department (FSD);

          Photographs from site visit;

          Preliminary Environmental Review – Final Report, Agreement no. PW 1/2006 Lei Yue Mun Waterfront Enhancement Project – Preliminary Environmental Review and Marine Traffic Impact Assessment, Meinhardt Environment Limited, 2007; 

          2011 Updated Preliminary Environmental Review (Draft), Agreement no. PW 1/2006 Lei Yue Mun Waterfront Enhancement Project – Preliminary Environmental Review and Marine Traffic Impact Assessment, Meinhardt Environment Limited, 2011;

          Site Investigation Report, EDD Contract No. 10/GCO/83 W.O. PW7/2/11.89 Public Toilet & Bathhouse at Lei Yue Mun, Gammon (Hong Kong) Limited, 1985;

          Final Fieldwork Report, ASD Contract No. TC R311 W.O. ASD 010746 Lei Yue Mun Waterfront, Geotechnics & Concrete Engineering (Hong Kong) Ltd, 2008; and

          Final Fieldwork Report, GE/2011/06 W.O. GE/2011/06.3 Existing Footpath Leading to Tin Hau Temple at Lei Yue Mun, VIBRO (H.K.) Ltd.

8.4                  Description of the Environment

8.4.1.1          The Site is located at the waterfront immediately in front of the village houses of the Lei Yue Mun villages and lies outside the eastern extent of the Victoria Harbour and located at east of the Lei Yue Mun lighthouse.  The location and the extent of the Site (including all work areas associated with the Project) is illustrated in Figure 1.1.

8.5                  Site Appraisal

8.5.1               Review of Historical Land Use

8.5.1.1          A review of aerial photographs has been undertaken to evaluate the likelihood of potential contamination associated with past land uses within the Site.  The development history of the Site is summarised in Section 8.5.1.2 and the list of aerial photographs reviewed is shown in Table 8.1.  Selected aerial photos are provided in Appendix 8.1.

Table 8.1         Aerial Photographs Reviewed

Year

Height (Feet)

Photograph Reference Number

1963*

2,700

5235

1973*

2,000

6661

1976

4,000

12582

1978*

4,000

23910

1982

3,000

43002

1985

5,000

CN862

1989

2,000

A16374

1993*

4,000

CN4593

1995

4,000

CN12619

1998

2,500

CN20957

2003*

4,000

CW47662

2005

4,000

CW66236

2009

3,000

CW83618

2013

2,000

CW102952

2016*

6,000

CS54247

Note:

* Aerial Photos are provided in Appendix 8.1.

8.5.1.2          The Site was generally occupied by cultivations, a pond, some village type housings (on the hill side) and beaches since 1963.  No significant change in land uses was observed until 1973.  In 1973, the cultivations were abandoned and additional village type housings were observed along the coast line.  In 1978, the pond was backfilled and Lei Yue Mun Rest Garden was observed.  No significant change in land uses within the Site was observed since then. No potentially contaminating land uses, such as shipyard / boatyards and vehicle repairing / maintenance, were observed in the review.

8.5.2               Site Geology

8.5.2.1          Based on the site investigation report and fieldwork reports mentioned in Section 8.3, the Site is majorly underlain by 0.10m to 0.20m thick of concrete surface overlaying fill with thickness of 0.32m to 5.90m and marine deposit (1.50m to 5.0m thick) which alluvium (2.70m thick) was encountered beneath.  Saprolitic soil and weathered rock are encountered beneath either fill, marine deposit or alluvium in the Site area. Grade lV or V granite is encountered between +0.78mPD and -22.22mPD. Bedrock of moderately decomposed and slightly decomposed medium grained granite (Grade lll or better granite) is encountered between +3.77mPD and -22.51mPD.

8.5.3               Acquisition of Information from Government Departments

8.5.3.1          The EPD and FSD have been contacted for (i) records on any leakage/spillage of chemicals and chemical waste, (ii) records of DGs, (iii) records of Chemical Waste Producer(s) and (iv) records of reported fire incidents within the Site. EPD and FSD’s replies on the requests have been received and attached in Appendix 8.2 and 8.3 respectively. Information is summarized below.

Environmental Protection Department

8.5.3.2          According to the information provided by EPD, there are no records of chemical waste producer and spillage/leakage of chemicals and chemical wastes at the Site.

Fire Services Department

8.5.3.3          According to the information provided by FSD, there are no records of DGs, fire incidents and spillage/leakage of chemical at the Site.

8.5.4               Site Reconnaissance

8.5.4.1          Site walkover was conducted on 21 June 2016 to investigate any contaminative issues associated with current land uses and activities within the Site.  In order to provide a clear picture of the current site condition, the Site is divided into 5 regions to illustrate the current land uses and activities observed during site reconnaissance and the photo records of site reconnaissance are provided in Figure 8.1 to Figure 8.1E. Additionally, site walkover checklist is provided in Appendix 8.4.

Region A (Refer to Figure 8.1A)

8.5.4.2          Based on the site observations, restaurants were observed alongside the pedestrian walkway. In the middle section of Region A, a lookout point and rest area were observed at northwestern side of the Region A. No contaminating activities were identified and no oil stains and/or stressed vegetation were observed.

Region B (Refer to Figure 8.1B)

8.5.4.3          Based on the site observations, a lookout point and viewing platform were observed at the northwestern side of Region B. A beach and Lei Yue Mun Rest Garden were noted on the southwestern and southeastern side of Region B respectively. No contaminating activities and land uses, such as shipyards / boatyards and vehicle repairing / maintenance workshops, were identified and no oil stains and/or stressed vegetation were observed.

Region C (Refer to Figure 8.1C)

8.5.4.4          Based on the site observations, a beach and public facilities, such as basketball court and Lei Yue Mun Ma Wan public toilet cum bathhouse, were observed at the southwestern and southeastern side of Lei Yue Mun Rest Garden respectively. Along the pedestrian walkway in Region C, village houses were noted on both sides. No contaminating activities and land uses, such as shipyards / boatyards and vehicle repairing / maintenance workshops, were identified and no oil stains and/or stressed vegetation were observed.

Region D (Refer to Figure 8.1D)

8.5.4.5          Based on the site observations, village houses were observed along the pedestrian walkway in Region D. No contaminating activities and land uses, such as shipyards / boatyards and vehicle repairing / maintenance workshops, were identified and no oil stains and/or stressed vegetation were observed.

 

Region E (Refer to Figure 8.1E)

8.5.4.6         Based on the site observations, village houses were observed along the pedestrian walkway in Region E. No contaminating activities and land uses, such as shipyards / boatyards and vehicle repairing / maintenance workshops, were identified and no oil stains and/or stressed vegetation were observed.

8.6                  Prediction and Evaluation of Land Contamination Impacts

8.6.1.1          Based on the site appraisal results, no potentially contaminating land use / activities were identified in the Site.  Therefore, no land contamination impact associated with present and past land uses/activities is anticipated.

8.7                  Environmental Monitoring and Audit

8.7.1.1          Since no land contamination impact is anticipated, no environmental monitoring and audit programme would be required.

8.8                  Conclusion

8.8.1.1          Based on the findings of site appraisal within the Site, no contaminating land use / activities were identified in the Site and adverse land contamination impact arising from Project is not anticipated. Thus, no Contamination Assessment Plan / Contamination Assessment Report / Remediation Assessment Plan and EM&A are required to be prepared.