Table of Contents
1.2 Project Scope and Programme
1.4 Structure of the EM&A Manual
4.5 Baseline Monitoring for Construction Noise
4.6 Impact Monitoring for Construction Noise
5.5 Laboratory Measurement / Analysis
6 Sewerage & Sewage Treatment Implications
7 Waste Management Implications
9 Ecological Impact (Terrestrial and Marine)
11 Landscape and Visual Impacts
12.2 Compliance with Legal and Contractual Requirements
13.2 Baseline Monitoring Report
13.4 First Monthly EM&A Report
13.5 Subsequent Monthly EM&A Report
13.8 Interim Notifications of Environmental Quality Limit
Exceedances
List of Tables
Table 4.1 Proposed Noise Monitoring Stations for
Baseline and Impact Monitoring
Table 4.2 Action and Limit Levels for Construction Noise
Table 4.3 Event and Action Plan for Construction Noise
Table 5.1 Proposed Marine Water Quality Stations for
Baseline and Impact Monitoring
Table 5.2 Analytical Methods to be applied to Marine
Water Quality Samples
Table 5.3 Proposed Marine Water Quality Monitoring
Frequency and Parameters
Table 5.4 Action and Limit Levels for Marine Water
Quality
Table 5.5 Event and Action Plan
Table 14.1 Summary of EM&A Requirements
Figures
Figure 1.1 Layout
Plan of Lei Yue Mun Waterfront Enhancement Project
Figure 2.1 Project
Organisation
Figure 4.1 Locations
of Noise Monitoring Stations
Figure 5.1 Locations
of Water Quality Monitoring Stations
Appendices
Appendix A tentative
construction programme
Appendix B implementation
schedule of the proposed mitigation measures
Appendix C sample
data record sheet
Appendix D sample
of the interim notification
1.1.1.1
Since
2000, the Tourism Commission (TC) has been implementing the Tourism District
Enhancement Programme to enrich Hong Kong’s appeal to visitors. Lei Yue Mun
(LYM), being one of the most popular tourist attractions in Hong Kong for its
pleasant seaside ambience and excellent seafood, had been identified to accord
priority for improvement under the Programme. The TC completed several initial
minor improvements along the LYM waterfront in 2003 and planned to further
improve the facilities along the LYM waterfront area.The
Lei Yue Man Waterfront Enhancement Project (the Project) consists of two components:
§ Construction of a Public Landing Facility and Improvement Works to
Existing Lookout Points and Viewing Platform; and
§ Development of a Waterfront Promenade and Related
Improvement Works.
Construction
of a Public Landing Facility and Improvement Works to Existing Lookout Points
and Viewing Platform (by CEDD)
Development of a Waterfront
Promenade and Related Improvement Works (by ArchSD)
•
Responsibilities of the Contractor, the
Engineer or Engineer’s Representative (ER), Environmental Team (ET) and
Independent Environmental Checker (IEC) with respect to the environmental monitoring
and audit requirements during the course of the Project;
•
Project organisation for the Project;
•
The basis for, and description of the
broad approach underlying the EM&A programme;
•
Requirement with respect to the
construction programme schedule and the necessary environmental monitoring and
audit programme to track the varying environmental impact;
•
Details of the methodologies to be
adopted, including all field laboratories and analytical procedures, and
details on quality assurance and quality control programme;
•
Definition of Action and Limit Levels;
•
Establishment of Event and Action Plans;
•
Requirements for reviewing pollution
sources and working procedures required in the event of non-compliance with the
environmental criteria and complaints;
•
Requirements for presentation of
environmental monitoring and audit data and appropriate reporting procedures;
and
• Requirements for reviewing the EIA predictions and the effectiveness of the mitigation measures / environmental management systems and the EM&A programme.
•
Section 1 – Introduction
•
Section 2 – Project Organisation
•
Section 3 – Air Quality Impact
•
Section 4 – Noise Impact
•
Section 5 – Water Quality Impact
•
Section 6 – Sewerage and Sewage Treatment
Implications
•
Section 7 – Waste Management Implications
•
Section 8 – Land Contamination
•
Section 9 – Ecological Impact
(Terrestrial and Marine)
•
Section 10 – Fisheries Impact
•
Section 11 – Landscape and Visual Impacts
•
Section 12 – Site Environmental Audit
•
Section 13 – Reporting
•
Section 14 - Conclusion
Engineer or Engineer’s Representative
(ER)
•
Supervise the Contractor’s activities and
ensure that the requirements in the Environmental Permit (EP), the approved EIA
Report, EM&A Manual and other government’s standards are fully complied
with;
•
Inform the Contractor when action is
required to reduce environmental impacts in accordance with the Event and
Action Plans;
•
Comply with the agreed Event Contingency
Plan in the event of any exceedance;
•
Participate in joint site inspections and
audits undertaken by the ET; and
•
Adhere to the procedures for carrying out
complaint investigation.
The Contractor
•
Implement the EIA’s recommendations and
requirements;
•
Provide assistance to ET in carrying out
relevant environmental monitoring;
•
Accompany joint site inspection
undertaken by the ET and undertake correction actions;
•
Submit proposals on mitigation measures
in case of exceedances of Action and Limit Levels in accordance with the Event
and Action Plans;
•
Implement measures to reduce impacts
where Action and Limit Levels are exceeded; and
•
Adhere to the procedures for carrying out
environmental complaint investigation.
Environmental Team (ET)
•
Monitor various environmental parameters
as required in this EM&A Manual;
•
Carry out regular site inspections to
investigate and audit the Contractors’ site practice, equipment and work
methodologies with respect to pollution control and environmental mitigation,
and initiate proactive action to pre-empt problems; carry out ad hoc site
inspections if significant environmental problems are identified;
•
Audit and prepare reports on the
environmental monitoring data and the site environmental conditions;
•
Analyse the EM&A data and review the
success of EM&A programme to confirm the adequacy of mitigation measures
implemented and the validity of the EIA predictions, and to identify any
adverse environmental impacts arising and report EM&A results to the IEC,
and the ER;
•
Report on the environmental monitoring
and audit results to the IEC, Contractor, the ER and EPD or its delegated
representative;
•
Recommend suitable mitigation measures to
the Contractor in the case of exceedance of Action and Limit Levels in
accordance with the Event and Action Plans;
•
Review the proposals of remedial measure
from the Contractor in the case of exceedances of Action and Limit Levels, in accordance
with the Event and Action Plans;
•
Advise Contractor on environmental
improvement, awareness, enhancement matters, etc.;
•
Timely submission on the EM&A report
to the Project Proponent and the EPD; and
•
Adhere to the procedures for carrying out
environmental complaint investigation.
Independent Environmental
Checker (IEC)
•
Review and audit in an independent,
objective and professional manner in all aspects of the EM&A programme
performed by the ET;
•
Validate and confirm the accuracy of
monitoring results, monitoring equipment, monitoring locations, monitoring
procedures and locations of sensitive receivers;
•
Audit the EIA recommendations and EP requirements
against the status of implementation of environmental protection measures on
site;
•
Review the effectiveness of environmental
mitigation measures and project environmental performance;
•
On as-needed basis, verify and certify
the environmental acceptability of the Environmental Permit (EP) holder’s
construction methodology, relevant design plans and submissions under the EP;
•
Carry out random sample check and audit
on monitoring data and sampling procedure;
•
Conduct random site inspection (at least
once a month);
•
Verify the investigation results of
environmental complaints cases and the effectiveness of corrective measures;
•
Verity EM&A report that has been
certified by the ET Leader; and
•
Provide feedback on the audit results to the
ET or the EP holder according to Event and Action Plans in the Manual.
a) locate
close to the major site activities which are likely to have noise impacts;
b) locate
close to the most affected existing NSRs; and
c) take
into account the possibility of minimizing disturbance to occupants at the NSRs
during monitoring.
Table 4.1 Proposed Noise Monitoring Stations
for Baseline and Impact Monitoring
Station |
Noise Assessment Point ID in EIA Report |
Noise Monitoring Station |
NM1 |
HRPCV1 |
Village house in Lei Yue Mun Hoi Pong Road Central |
NM2 |
HPRE81 |
No.81, Lei Yue Mun Hoi Pong Road East |
NM3 |
LYMP |
Jockey Club Lei Yue Mun Plus |
NM4 |
HPRE21C |
No. 21C, Lei Yue Mun Hoi Pong Road East |
Table 4.2 Action and Limit Levels for
Construction Noise
Time Period |
Action Level |
Limit Level |
0700 – 1900
hours |
When one documented complaint is received |
75 dB(A) for residential premises and places of public worship |
70 dB(A) for schools
and 65 dB(A) during examination period |
Notes:
·
If works are to be
carried out during restricted hours, the conditions stipulated in the
Construction Noise Permit (CNP) issued by the Noise Control Authority have to
be followed.
Table
4.3 Event and Action Plan for
Construction Noise
EVENT |
ACTION |
|||
ET |
IEC |
ER |
Contractor |
|
Action Level |
1. Notify IEC, ER and
Contractor; 2. Carry out
investigation; 3. Report the results of
investigation to the IEC, ER and Contractor; 4. Discuss with the
Contractor and formulate remedial measures; and 5.
Increase monitoring frequency to check mitigation effectiveness. |
1. Review the analysed
results submitted by the ET; 2. Review the proposed
remedial measures by the Contractor and advise the ER accordingly; and 3.
Supervise the implementation of remedial measures. |
1. Confirm receipt of
notification of failure in writing; 2. Notify Contractor; 3. Require Contractor to
propose remedial measures for the analysed noise problem; and 4. Ensure remedial
measures are properly implemented. |
1. Submit noise
mitigation proposals to IEC, ET and ER; and 2. Implement noise
mitigation proposals. |
Limit Level |
1. Identify source; 2. Inform IEC, ER, EPD
and Contractor; 3. Repeat measurements to
confirm findings; 4. Increase monitoring
frequency; 5. Carry out analysis of
Contractor’s working procedures to determine possible mitigation to be
implemented; 6. Inform IEC, ER and EPD
the causes and actions taken for the exceedances; 7. Assess effectiveness
of Contractor’s remedial actions and keep IEC, EPD and ER informed of the
results; and 8. If
exceedance stops, cease additional monitoring. |
1. Discuss amongst ER,
ET, and Contractor on the potential remedial actions; 2. Review Contractors
remedial actions whenever necessary to assure their effectiveness and advise
the ER accordingly; and 3. Supervise the implementation of remedial
measures. |
1. Confirm receipt of
notification of failure in writing; 2. Notify Contractor; 3. Require Contractor to
propose remedial measures for the analysed noise problem; 4. Ensure remedial
measures properly implemented; and 5. If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated. |
1. Take immediate action
to avoid further exceedance; 2. Submit proposals for
remedial actions to IEC within 3 working days of notification; 3. Implement the agreed
proposals; 4. Resubmit proposals if
problem still not under control; and 5. Stop
the relevant portion of works as determined by the ER until the exceedance is
abated. |
a)
at
locations close to and preferably at the boundary of the mixing zone of the
major site activities as indicated in the EIA Report, which are likely to have
water quality impacts;
b)
close
to the sensitive receivers which are directly or likely to be affected;
c)
for
monitoring locations located in the vicinity of the sensitive receivers, care
shall be taken to cause minimal disturbance during monitoring; and
d) two or more control stations which
shall be at locations representative of the project site in its undisturbed
condition. Control stations shall be located, as far as is practicable, both
upstream and downstream of the works area.
Table
5.1 Proposed Marine Water Quality Stations
for Baseline and Impact Monitoring
Monitoring Station |
ID in EIA Report |
Description |
Easting |
Northing |
C1 |
- |
Control Station |
842134 |
816765 |
C2 |
- |
Control Station |
842946 |
816172 |
M1 |
C2 |
Coral Communities (Impact Monitoring Station) |
842062 |
817247 |
M2 |
- |
100m away from the dredging site (Impact Monitoring Station) |
842329 |
816615 |
M3 |
C3 |
Coral Communities (Impact Monitoring Station) |
842639 |
816410 |
M4 |
VT3 |
Sam Ka Tsuen Typhoon Shelter (Impact Monitoring Station) |
842515 |
816878 |
5.4.1
Dissolved Oxygen and Temperature Measuring Equipment
5.4.1.1
The instrument should be a
portable and weatherproof DO measuring instrument complete with cable and
sensor, and use a DC power source. This equipment should be capable of
measuring:
·
a DO level in the range of 0-20 mg/L and 0 -200%
saturation; and
·
a temperature of 0-45 degree Celsius.
5.4.1.2
It should have a membrane
electrode with automatic temperature compensation complete with a cable (for
example, YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with
reel and cable or an approved similar instrument). Sufficient stocks of spare
electrodes and cables should be available for replacement where necessary.
5.4.1.3
Should salinity
compensation not be built-in to the DO equipment, in-situ salinity
should be measured to calibrate the DO equipment prior to each DO measurement.
5.4.2
Turbidity Measurement Instrument
5.4.2.1
Turbidity should be
measured in-situ by the nephelometric method. The instrument should be
portable and weatherproof using a DC power source complete with cable, sensor
and comprehensive operation manuals. It should have a photoelectric sensor
capable of measuring turbidity between 0 – 1000 NTU (for example, Hach model
2100P or an approved similar instrument). The cable should not be less than 25m
in length. The meter should be calibrated in order to establish the
relationship between NTU units and the levels of suspended solids. The
turbidity measurement should be carried out on split water sample collected
from the same depths of suspended solids samples.
5.4.3
pH Measurement Instrument
5.4.3.1
The instrument should
consist of a potentiometer, a glass electrode, a reference electrode and a
temperature-compensating device. It
should be readable to 0.1 pH in a range of 0 to 14. Standard buffer solutions of at least pH 7
and pH 10 should be used for calibration of the instrument before and after
use.
5.4.4
Sampler
5.4.4.1
A water sampler is
required. It should comprise a transparent PVC cylinder, with a capacity of not
less than 2 litres, which can be effectively sealed with latex cups at both
ends. The sampler should have a positive latching system to keep it open and
prevent premature closure until released by a messenger when the sampler is at
the selected water depth (for example, Kahlsico Water Sampler or an approved
similar instrument).
5.4.5
Water Depth Detector
5.4.5.1
A portable, battery-operated
echo sounder should be used for the determination of water depth at each
designated monitoring station. If echo sounder is not applicable due to low
water depth, various sized stainless steel rulers would be used to determine
the water depth. These units can either be held or affixed to the bottom of the
work boat, if the same vessel is to be used throughout the monitoring
programme.
5.4.6
Salinity
5.4.6.1
A portable, salinometer
capable of measuring salinity in the range 0 – 40 mg/L shall be provided for
measuring salinity of the water at each monitoring location.
5.4.7
Sample Containers and Storage
5.4.7.1
Water samples for SS
should be stored in high density polythene bottles with no preservative added,
packed in ice (cooled to 4 0C without being frozen) and delivered to
the laboratory and analysed as soon as possible after collection. Sufficient
volume of samples should be collected to achieve the detection limit.
5.4.8
Monitoring Position Equipment
5.4.8.1
A hand-held or boat-fixed
type digital Differential Global Positioning System (DGPS) with way point
bearing indication and Radio Technical Commission for maritime (RTCM) Type 16
error message ‘screen pop-up’ facilities (for real-time auto-display of error
messages and DGPS corrections from the Hong Kong Hydrographic Office), or other
equipment of similar accuracy, should be provided and used during water quality
monitoring work to ensure that the water sampling locations are correct before
taking measurements.
5.4.9
Calibration of In-Situ Instruments
5.4.9.1
All in-situ
monitoring instruments should be checked, calibrated and certified by a
laboratory accredited under HOKLAS or any other international accreditation
scheme before use and subsequently re-calibrated at three monthly intervals
throughout all stages of the water quality monitoring programme. Responses of
sensors and electrodes should be checked with certified standard solutions
before each use. Wet bulb calibration for a DO meter should be carried out
before measurement at each monitoring location.
5.4.9.2
For the on-site
calibration of field equipment, the BS 127:1993, Guide to Field and On-Site
Test Methods for the Analysis of Water should be observed.
5.4.9.3
Sufficient stocks of
spare parts should be maintained for replacements when necessary. Backup
monitoring equipment should also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
5.5.1.1
Analysis of SS level
should be carried out in a HOKLAS or other international accredited laboratory.
Water samples of about 1000ml should be collected at the monitoring stations
for carrying out the laboratory SS determinations. The determination work
should start within 24 hours after collection of the water samples. The
analyses should follow the American Public Health Association (APHA) Standard
Methods for the Examination of Water and Wastewater or an equivalent method
subject to the approval of EPD. The suggested testing method and lowest
detection limit are provided in Table 5.2.
Table 5.2 Analytical
Methods to be applied to Marine Water Quality Samples
Determinant |
Suggested Method |
Suggested Detection
Limit |
Suspended Solids |
APHA 2540D1 |
1 mg/L or better |
Notes:
1.
APHA
American Public Health Association Standard Methods for the Examination of
Water and Wastewater
5.5.1.2
The testing of SS should
be HOKLAS accredited (or if not, approved by EPD) and comprehensive quality
assurance and control procedures in place in order to ensure quality and
consistency in results.
5.5.1.3
The ET should provide the
Contractor with a copy of the relevant chapters of the “Standard Methods for
the Examination of Water and Wastewater” updated edition and any other relevant
document for his reference.
5.5.1.4
Detailed testing methods,
pre-treatment procedures, instruments use, Quality Assurance / Quality Control
(QA/QC) details (such as blank, spike recovery, number of replicate samples per
batch, etc.), detection limit and accuracy shall be submitted to EPD for approval
prior to the commencement of monitoring programme. EPD may also request the
laboratory to carry out analysis of known standards provided by EPD for quality
assurance. The QA / QC shall be in accordance with the requirements of HOKLAS
or international accredited scheme. The QA/ QC results shall be reported. The
testing methods and related proposal should be checked and certified by IEC
before submission to EPD for approval.
5.5.1.5
Additional duplicate
samples may be required by EPD for inter laboratory calibration. Remaining
samples after analysis should be kept by the laboratory for 3 months in case
repeat analysis is required. If in-house or non-standard methods are proposed,
details of the method verification may also be required to submit to EPD. In
any circumstance, the sample testing should have comprehensive quality
assurance and quality control programmes. The laboratory should prepare to
demonstrate the programme to EPD or EPD’s representatives when requested.
Table 5.3 Proposed
Marine Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Key Parameters2 |
During the
4-week baseline monitoring period |
Three days
per week, at mid-flood and mid-ebb tides |
Turbidity,
Dissolved Oxygen (DO), Suspended Solids (SS) |
During the dredging and filling operation of the
Project |
Three days
per week, at mid-flood and mid-ebb tides |
Turbidity,
Dissolved Oxygen (DO), Suspended Solids (SS) |
Notes:
1. For
selection of tides for in-situ
measurement and water sampling, tidal range of individual flood and ebb tides
should be not less than 0.5m.
2. Turbidity
and DO should be measured in-situ
whereas SS should be determined by laboratory.
Table 5.4 Action
and Limit Levels for Marine Water Quality
Parameters |
Action Level |
Limit Level |
1SS in mg/L |
Depth-average SS ≥ 95%-ile
of baseline data or 120% of control station’s SS at the same tide of the same
day |
Depth-average SS ≥ 99%-ile
of baseline data or 130% of control station’s SS at the same tide of the same
day and specific sensitive receiver water quality requirements (e.g. required
SS level for concerned seawater intakes) |
DO in mg/L |
Surface &
Middle ≤5%-ile of
baseline data for surface and middle layers Bottom ≤5%-ile of
baseline data for bottom layer |
Surface &
Middle ≤4 mg/L or
1%-ile of baseline data for surface and middle layers Bottom ≤2 mg/L or
1%-ile of baseline data for bottom layer |
1Turbidity
in NTU |
Depth-average
Turbidity ≥ 95%-ile
of baseline data or 120% of control station’s turbidity at the same tide of
the same day |
Depth-average
Turbidity ≥ 99%-ile
of baseline data or 130% of control station’s turbidity at the same tide of
the same day |
Remarks:
1. “Depth-averaged”
is calculated by taking the arithmetic means of reading of all sampling depths.
2. For
turbidity and SS, non-compliance of the water quality limits occurs when
monitoring result is higher than the limits.
3. For
DO, non-compliance of the water quality limits occurs when monitoring result is
lower than the limits.
4. All
the figures given in the table are used for reference only and EPD may amend
the figures whenever it is considered as necessary.
Table 5.5 Event and Action Plan
EVENT |
ACTION |
|||
ET |
IEC |
ER |
CONTRACTOR |
|
Action level being exceeded by one sampling day |
1.
Repeat in-situ measurement to confirm
findings; 2.
Identify
reasons for non-compliance and source(s) of impact; 3.
Inform IEC
and Contractor; 4.
Check
monitoring data, all plants, equipment and Contractor's working methods; 5.
Discuss
mitigation measures with IEC and Contractor; 6.
(The above
actions should be taken within 1 working day after the exceedance is
identified) 7.
Repeat
measurement on next day of exceedance. |
1.
Discuss
with ET and Contractor on the mitigation measures; 2.
Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; 3.
Assess the
effectiveness of the implemented mitigation measures. 4.
(The above
actions should be taken within 1 working day after the exceedance is
identified) |
1.
Discuss
with IEC on the proposed mitigation measures; 2.
Make
agreement on the mitigation measures to be implemented. 3.
Assess the
effectiveness of the implemented mitigation measures 4.
(The above
actions should be taken within 1 working day after the exceedance is
identified) |
1.
Inform the
ER and confirm notification of the non-compliance in writing; 2.
Rectify
unacceptable practice; 3.
Check all
plants and equipment; 4.
Consider
changes of working methods; 5.
Discuss
with ET and IEC and propose mitigation measures to IEC and ER; 6.
Implement
the agreed mitigation measures. 7.
(The above
actions should be taken within 1 working day after the exceedance is
identified) |
Action level being exceeded by more than one consecutive sampling days |
1.
Repeat in-situ measurement to confirm
findings; 2.
Identify
reasons for non-compliance and source(s) of impact; 3.
Inform IEC
and Contractor; 4.
Check
monitoring data, all plants, equipment and Contractor's working methods; 5.
Discuss
mitigation measures with IEC and Contractor; 6.
Ensure
mitigation measures are implemented; 7.
Prepare to
increase the monitoring frequency to daily; 8.
(The above
actions should be taken within 1 working day after the exceedance is
identified) 9.
Repeat
measurement on next working day of exceedance. |
1.
Discuss
with ET and Contractor on the mitigation measures; 2.
Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; 3.
Assess the
effectiveness of the implemented mitigation measures. 4.
(The above
actions should be taken within 1 working day after the exceedance is
identified) |
1.
Discuss
with IEC on the proposed mitigation measures; 2.
Make
agreement on the mitigation measures to be implemented; 3.
Assess the
effectiveness of the implemented mitigation measures. 4.
(The above
actions should be taken within 1 working day after the exceedance is
identified) |
1.
Inform the
ER and confirm notification of the non-compliance in writing; 2.
Rectify
unacceptable practice; 3.
Check all
plants and equipment; 4.
Consider
changes of working methods; 5.
Discuss
with ET and IEC and propose mitigation measures to IEC and ER within 3
working days; 6.
Implement
the agreed mitigation measures. 7.
(The above
actions should be taken within 1 working day after the exceedance is
identified) |
Limit level being exceeded by one sampling day |
1.
Repeat in-situ measurement to confirm
findings; 2.
Identify
reasons for non-compliance and
source(s) of impact; 3.
Inform
IEC, Contractor and EPD; 4.
Check
monitoring data, all plants, equipment and Contractor's working methods; 5.
Discuss
mitigation measures with IEC, ER and Contractor; 6.
Ensure
mitigation measures are implemented; 7.
Increase
the monitoring frequency to daily until no exceedance of Limit level. 8.
(The above
actions should be taken within 1 working day after the exceedance is
identified) |
1.
Discuss
with ET and Contractor on the mitigation measures; 2.
Review proposals
on mitigation measures submitted by Contractor and advise the ER accordingly; 3.
Assess the
effectiveness of the implemented mitigation measures. 4.
(The above
actions should be taken within 1 working day after the exceedance is
identified) |
1.
Discuss
with IEC, ET and Contractor on the proposed mitigation measures; 2.
Request
Contractor to critically review the working methods; 3.
Make
agreement on the mitigation measures to be implemented; 4.
Assess the
effectiveness of the implemented mitigation measures. 5.
(The above
actions should be taken within 1 working day after the exceedance is
identified) |
1.
Inform the
ER and confirm notification of the non-compliance in writing; 2.
Rectify
unacceptable practice; 3.
Check all
plants and equipment; 4.
Consider
changes of working methods; 5.
Discuss
with ET, IEC and ER and Propose mitigation measures to IEC and ER within 3
working days; 6.
Implement
the agreed mitigation measures |
Limit level being exceeded by more than one consecutive sampling day |
1.
Repeat in-situ measurement to confirm
findings; 2.
Identify
reasons for non-compliance and
source(s) of impact; 3.
Inform
IEC, Contractor and EPD; 4.
Check
monitoring data, all plants, equipment and Contractor's working methods; 5.
Discuss
mitigation measures with IEC, ER and Contractor; 6.
Ensure
mitigation measures are implemented; 7.
Increase
the monitoring frequency to daily until no exceedance of Limit level for 2
consecutive days. 8.
(The above
actions should be taken within 1 working day after the exceedance is
identified) |
1.
Discuss
with ET and Contractor on the mitigation measures; 2.
Review
proposals on mitigation measures submitted by Contractor and advise the ER
accordingly; 3.
Assess the
effectiveness of the implemented mitigation measures. 4.
(The above
actions should be taken within 1 working day after the exceedance is identified) |
1.
Discuss
with IEC, ET and Contractor on the proposed mitigation measures; 2.
Request
Contractor to critically review the working methods; 3.
Make
agreement on the mitigation measures to be implemented; 4.
Assess the
effectiveness of the implemented mitigation measures. 5.
Consider
and instruct, if necessary, the Contractor to slow down or to stop all or
part of the dredging and sand filling work until no exceedance of Limit
level. 6.
(The above
actions should be taken within 1 working day after the exceedance is
identified) |
1.
Inform the
ER and confirm notification of the non-compliance in writing; 2.
Rectify
unacceptable practice; 3.
Check all
plants and equipment; 4.
Consider
changes of working methods; 5.
Discuss
with ET, IEC and ER and Propose mitigation measures to IEC and ER within 3
working days; 6.
Implement
the agreed mitigation measures; 7.
As
directed by the ER, to slow down or stop all or part of the dredging and sand
filling work. |
·
investigate
the problems and the causes;
·
issue
action notes to the Contractor which is responsible for the works;
·
implement
remedial and corrective actions immediately;
·
re-inspect
the site conditions upon completion of the remedial and corrective actions; and
·
record
the event and discuss with the Contractor for preventive actions.
•
In the vicinity of Lei Yue Mun / Junk Bay
where the marine conditions e.g. water depth, flow rate and temperature etc.
are similar to the donor site.
•
Presence of healthy coral communities of
the same species.
•
Sufficient space available for the newly
translocated coral
•
Not to be impacted by construction works
·
The EIA Report and EM&A recommendations on
environmental protection and pollution control mitigation measures;
·
Ongoing results of the EM&A programme;
·
Works progress and programme;
·
Individual works methodology proposals (which should
include proposal on associated pollution control mitigation measures);
·
Contract specifications on environmental protection
and pollution prevention control;
·
Relevant environmental protection and pollution
control legislations; and
·
Previous site inspection results undertaken by the ET
and others.
i.
The Contractor to log complaint and date of receipt
onto the complaint database and inform the ER, ET and IEC immediately;
ii.
The Contractor to investigate the complaint with the
ER and ET to determine its validity, and assess whether the source of the
problem is due to construction works of the Project, with the support of
additional monitoring frequency and stations, if necessary;
iii.
The Contractor to identify mitigation measures in
consultation with the IEC, ET and ER if a complaint is valid and due to the
construction works of the Project;
iv.
The Contractor to implement the mitigation measures as
required by the ER and to agree with the ET and IEC any additional monitoring
frequency and stations, where necessary, for checking the effectiveness of the
remedial measures;
v.
The ER, ET and IEC to review the effectiveness of the
Contractor’s mitigation measures and the updated situation;
vi.
The ET / Contractor to undertake additional monitoring
and audit to verify the situation if necessary, and oversee that circumstances
leading to the complaints do not recur;
vii.
If the complaint is referred by the EPD, the
Contractor to prepare interim report on the status of the complaint
investigation and follow-up action stipulated above, including the details of
the mitigation measures and additional monitoring identified or already taken,
for submission to EPD within the time frame assigned by the EPD; and
viii.
The ET to record the details of the complaint, results
of the investigation, subsequent actions taken to address the complaints and
updated situation including the effectiveness of the mitigation measures,
supported by regular and additional monitoring results in the monthly EM&A
reports.
·
Monitoring methodology;
·
Name of laboratory and types of equipment used and
calibration details;
·
Parameters monitored;
·
Monitoring locations (and depth);
·
Monitoring date, time, frequency and duration; and
·
Quality assurance (QA) / quality control (QC) results
and detection limits.
·
Major activities, if any, being carried out on the
site during the period;
·
Weather conditions during the period; and
·
Other factors which might affect the monitoring
results.
i.
Executive
summary (1-2 pages):
·
Breaches
of Action and Limit Levels;
·
Complaint
log;
·
Notifications
of any summons and successful prosecutions;
·
Reporting
changes; and
·
Future
key issues.
ii.
Basic
project information:
·
Project
organisation including key personnel’s’ contact and any hotline telephone
number for the public to make enquiries;
·
Construction
programme;
·
Management
structure; and
·
Works
undertaken during the reporting month.
iii.
Environmental
status:
·
Advice
on the status of statutory environmental compliance, such as the status of
compliance with the EP conditions under the EIAO, submission status under the
EP and implementation status of mitigation measures;
·
Works
undertaken during the reporting month with illustrations (e.g. location of
works, etc.); and
·
Drawings
showing the Project area, any environmental sensitive receivers and the
locations of the monitoring and control stations.
iv.
Summary
of EM&A requirements:
·
All
monitoring parameters;
·
Environmental
quality performance limits (Action and Limit Levels);
·
Event
and Action Plans;
·
Environmental
mitigation measures, as recommended of the EIA Report; and
·
Environmental
requirements in contract documents.
v.
Implementation
status:
·
Advice
on the implementation status of environmental protection and pollution control
/ mitigation measures, as recommended in the EIA Report.
vi.
Monitoring
results (in both hard and diskette copies) together with the following
information:
·
Monitoring
methodology;
·
Name
of laboratory and types of equipment used and calibration details;
·
Monitoring
parameters;
·
Monitoring
locations;
·
Monitoring
date, time, frequency and duration;
·
Graphical
plots of the monitored parameters;
·
Major
activities being carried out on site during the period;
·
Weather
conditions during the period;
·
Any
other factors which might affect the monitoring results; and
·
QA
/ QC results and detection limits.
vii.
Report
on non-compliance, complaints, notifications of summons and status of
prosecutions:
·
Record
of all non-compliance (exceedances) of the environmental quality performance
limits (Action and Limit Levels);
·
Record
of all complaints received (written or verbal) including locations and nature
of complaints investigation, liaison and consultation undertaken, actions and
follow-up procedures taken, results and summary;
·
Record
of all notification of summons and successful prosecutions for breaches of
current environmental protection / pollution control legislation, including
locations and nature of the breaches, investigations, follow-up actions taken,
results and summary;
·
Review
of the reasons for and the implications of non-compliances, complaints, summons
and prosecutions including review of pollution sources and working procedures;
and
·
Description
of the actions taken in the event of non-compliance and deficiency reporting
and any follow-up procedures related to earlier non-compliance.
viii.
Others:
·
An
account of the future key issues as reviews from the works programme and method
statements of works;
·
Advice
on the solid and liquid waste management status;
·
A
forecast of the works programme, impact predictions and monitoring schedule for
the next reporting month;
·
Compare
the EM&A data in the reporting month with the EIA predictions and annotate
with explanation for any discrepancies; and
·
Comments
(e.g. the effectiveness and efficiency of the mitigation measures),
recommendations (for example, any improvement in the EM&A programme) and
conclusions.
i.
Executive
summary (1-2 pages):
·
Breaches
of Action and Limit Levels;
·
Complaint
log;
·
Notifications
of any summons and successful prosecutions;
·
Reporting
changes; and
·
Future
key issues.
ii.
Basic
project information:
·
Project
organisation including key personnel’s’ contact and any hotline telephone
number for the public to make enquiries;
·
Construction
programme;
·
Management
structure; and
·
Works
undertaken during the reporting month.
iii.
Environmental
status:
·
Advice
on the status of statutory environmental compliance, such as the status of
compliance with the EP conditions under the EIAO, submission status under the
EP and implementation status of mitigation measures;
·
Works
undertaken during the reporting month whit illustrations (e.g. location of
works, etc.); and
·
Drawings
showing the Project area, any environmental sensitive receivers and the
locations of the monitoring stations.
iv.
Implementation
status:
·
Advice
on the implementation status of environmental protection and pollution control
/ mitigation measures, as recommended in the EIA Report.
v.
Monitoring
results (in both hard and diskette copies) together with the following
information:
·
Monitoring
methodology;
·
Name
of laboratory and types of equipment used and calibration details;
·
Monitoring
parameters;
·
Monitoring
locations (and depth);
·
Monitoring
date, time, frequency and duration;
·
Graphical
plots of the monitored parameters in the month;
·
Major
activities being carried out on site during the period;
·
Weather
conditions during the period;
·
Any
other factors which might affect the monitoring results; and
·
QA
/ QC results and detection limits.
vi.
Report
on non-compliance, complaints, notifications of summons and status of
prosecutions:
·
Record
of all non-compliance (exceedances) of the environmental quality performance
limits (Action and Limit Levels);
·
Record
of all complaints received (written or verbal) including locations and nature
of complaints investigation, liaison and consultation undertaken, actions and
follow-up procedures taken, results and summary;
·
Record
of all notification of summons and successful prosecutions for breaches of
current environmental protection / pollution control legislation, including
locations and nature of the breaches, investigations, follow-up actions taken,
results and summary;
·
Review
of the reasons for and the implications of non-compliances, complaints, summons
and prosecutions including review of pollution sources and working procedures;
and
·
Description
of the actions taken in the event of non-compliance and deficiency reporting
and any follow-up procedures related to earlier non-compliance.
vii.
Others:
·
An
account of the future key issues as reviews from the works programme and method
statements of works;
·
Advice
on the solid and liquid waste management status;
·
A
forecast of the works programme, impact predictions and monitoring schedule for
the next reporting month;
·
Compare
the EM&A data in the reporting month with the EIA predictions and annotate
with explanation for any discrepancies; and
·
Comments
(e.g. the effectiveness and efficiency of the mitigation measures),
recommendations (for example, any improvement in the EM&A programme) and
conclusions.
viii.
Appendix:
·
Action
and Limit Levels;
·
Graphical
plots of trends of the monitoring parameters over the past four reporting
periods;
·
Major
Project activities being carried out on site during the reporting period;
·
Weather
conditions during the reporting period; Cumulative statistics on complaints,
notifications of summons and successful prosecutions; and
·
Outstanding
issues and deficiencies.
i.
Executive
summary (1-2 pages):
ii.
Drawings
showing the Project area, environmental sensitive receivers and locations of
the monitoring stations;
iii.
Basic
project information including a synopsis of the Project organisation, contacts
of key management, and a synopsis of works undertaken during the course of the
Project;
iv.
A
brief summary of EM&A requirements including:
·
Environmental
mitigation measures, as recommended in the EIA Report;
·
Environmental
impact hypotheses tested;
·
Environmental
quality performance limits (Actions and Limit Levels);
·
All
monitoring parameters; and
·
Event
and Action Plans;
v.
A
summary of the implementation status of environmental protection and pollution
control / mitigation measures, as recommended in the EIA Report, summarized in
the updated implementation schedule;
vi.
Graphical
plots and the statistical analysis of the trends of monitoring parameters over
the course of the Project for all monitoring stations;
vii.
Major
Project activities being carried out on site during the reporting period;
viii.
Weather
conditions during the reporting period;
ix.
Any
other factors which might affect the monitoring results;
x.
A
summary of non-compliance (exceedances) of the environmental quality
performance limits (Action and Limit Levels);
xi.
A
review of the reasons for and the implications of non-compliance including
review of pollution sources and working procedures as appropriate;
xii.
A
description of the actions taken in the event of non-compliance;
xiii.
A
summary record of all complaints received (written or verbal) for each media,
liaison and consultation undertaken, actions and follow-up procedures taken;
xiv.
A
summary record of notifications of summons and successful prosecutions for
breaches of the current environmental protection / pollution control
legislation, locations and nature of the breaches, investigation follow-up
actions taken and results;
xv.
A
review of the validity of EIA predictions and identification of shortcomings of
the recommendations proposed in EIA Report; and
xvi.
Comments
(for example, a review of the effectiveness and efficiency of the mitigations
measures and of the performance of the environmental management system, that is
, of the overall EM&A programme);
xvii.
Recommendations
and conclusions (for example, a review of success of the overall EM&A
programme to cost-effectively identify deterioration and to initiate prompt effective
mitigation action when necessary).
Table 14.1 Summary
of EM&A Requirements
Environmental
Aspect |
Environmental
Monitoring and Audit |
|
Construction
Phase |
Operation Phase |
|
Air Quality |
✓ |
✗ |
Noise |
✓ |
✗ |
Water Quality |
✓ |
✓(1) |
Sewerage and Sewage Treatment |
✗ |
✗ |
Waste Management |
✓ |
✗ |
Land
Contamination |
✗ |
✗ |
Ecology |
✓ |
✓(1) |
Fisheries |
✗ |
✗ |
Landscape and Visual |
✓ |
✗ |
Note:
(1)
EM&A to be conducted during
maintenance dredging operation