1.1.1.1
Since
2000, the Tourism Commission (TC) has been implementing the Tourism District
Enhancement Programme to enrich Hong Kong’s appeal to visitors. Lei Yue Mun (LYM), being one of the most popular tourist
attractions in Hong Kong for its pleasant seaside ambience and excellent
seafood, had been identified to accord priority for improvement under the
Programme. The TC completed several initial minor improvements along the LYM
waterfront in 2003 and planned to further improve the facilities along the LYM
waterfront area.The Lei Yue Man Waterfront Enhancement Project (the
Project) consists of two components:
a) Construction
of a Public Landing Facility and
Improvement Works to Existing Lookout Points and Viewing Platform; and
b) Development
of a Waterfront Promenade and Related Improvement Works.
1.1.1.2
As the Project will involve
dredging operation less than 500m from the nearest boundary of an existing
coastal protection area, it has been identified as a designated project
according to Item C.12 (a) (vii) in Part I, Schedule 2 of the Environmental
Impact Assessment Ordinance (EIAO):
“A dredging operation exceeding 500,000m3
or a dredging operation which is less than 500m from the nearest boundary of an
existing or planned coastal protection area”.
1.1.1.3
A project profile (No. PP-525/2015) was
submitted to the Environmental
Protection Department (EPD) on 23 June 2015 and an Environmental Impact
Assessment (EIA) Study Brief (No. ESB-287/2015) for the Project was issued by
EPD on 30 July 2015.
1.1.1.4
AECOM
Asia Company Limited (AECOM) was commissioned by Civil Engineering and
Development Department (CEDD) to undertake the EIA study for the Project under
Agreement No. CE 54/2015 (EP) Lei Yue Mun Waterfront
Enhancement Project – Environmental and Traffic Impact Assessment Studies –
Investigation.
1.2
Purpose of this
Executive Summary
1.2.1.1
This Executive Summary (ES) summarizes the key
findings, recommendations and conclusions of the EIA Report for the Project. The ES contains the following information:
·
Section 2
presents the purpose and nature of the Project, consideration of alternative
options and construction methods for the Project;
·
Section 3
presents the key findings of the environmental impact assessment;
·
Section 4
describes the proposed environmental monitoring and audit for the Project; and
·
Section 5
presents the conclusions.
2.1
Purpose and Scope of
Project
2.1.1.1
The
Project aims primarily at providing more convenient access and better
supporting facilities for tourists visiting LYM with a view to enriching their experience.
2.1.1.2
The
Project comprises the following works elements:
Construction of a Public Landing Facility and
Improvement Works to Existing Lookout Points and Viewing Platform (by CEDD)
·
Construction
of a promenade with a public landing facility (i.e. landing steps) capable of
accommodating vessels with lengths up to 30m and draughts of about 3m;
·
Construction
of a breakwater;
·
Dredging
of seabed to provide sufficient water depth for navigation of vessels; and
·
Improvement
works for five existing lookout points and an existing viewing platform to
improve their structural capacity.
Development of a Waterfront Promenade and Related
Improvement Works (by Architectural Services Department (ArchSD))
·
Construction
of a carp-shaped platform and a pavilion with children’s play area;
·
Beautification
works for the promenade, five lookout points and an existing viewing platform
to improve their visual appearance; and
·
Streetscape
improvement works.
2.1.1.3
The location, site boundary and general layout of
the Project are shown in Figure 2.1.
2.2.1.1
The
Project has been initiated by the TC to serve the purpose of enhancing LYM’s
attractiveness for tourism. Unanimous support has been obtained from Kwun Tong District Council (KTDC) and the local community of LYM, including local
residents and business operators, who have been pressing for the early implementation of the
Project over the past few years.
2.2.1.2
The
Project would not only enhance LYM’s attractiveness for tourism but also
improve the general environment for the local residents. The provision of a
waterfront promenade, carp-shaped platform and pavilion together with
improvement of the existing lookout points and viewing platform would provide
excellent vantage points for visitors/ local residents appreciating the harbour
view within a leisurely environment. The landscaping and greening works which include
planting of trees, shrubs, ground covers and climbers at the lookout points and
viewing platforms, along the streets and around the pavilion, would create a
pleasant environment and further enhance the landscape and visual quality of
the LYM waterfront area. The living environment
of the local community would also be improved with the provision of additional
open space incorporating landscape features and leisure facilities for their
enjoyment.
2.2.1.3
Apart
from the aforementioned benefits to be brought from the Project, the Project
also helps expedite the implementation of a new sewerage system for the Lei Yue
Mun area under the Lei Yue Mun
Village Sewerage project undertaken by Drainage Services Department (DSD). The
implementation of a new sewerage system for the Lei Yue Mun
area is scheduled to be carried out concurrently with the Project to address
the hygiene and sewerage treatment concerns in the area, would bring
improvements to the water quality and environmental hygiene conditions. Such
improvement would be a vital element in enhancing tourist appeal and would not
only benefit the business sector but also the residents. The Project together with DSD’s sewerage
project will help promote a sustainable tourism growth for LYM, in particular
in strengthening its competiveness among other seafood dining destinations over
the territory and improving the overall water quality and environmental hygiene
conditions with a view to benefiting the visitors and local residents there.
2.3.1.1
Various alternatives and options with respect to the location and design of the
Project were considered in detail in the EIA study. Highlights of the
considerations given to alternatives and options are presented in the following
paragraphs.
2.3.1.2
Taking into account factors including site
conditions, marine safety, environmental considerations, operational
requirements and convenience of access for visitors, three possible locations,
namely the existing berthing (Location 1) and village jetty (Location 2)
outside the Sam Ka Tsuen Typhoon Shelter and the
waterfront on the south coast of LYM (Location 3), were identified for the
landing facility (see Appendix 2.1).
Among these locations, Location 3 was selected as the preferred option for the
landing facility for the following reasons:
·
It is conveniently located within a
reasonable walking distance to the seafood restaurants and other attractions in
LYM, thereby meeting the primary objective of the Project;
·
It is located further away from Sam Ka Tsuen Typhoon Shelter, thereby minimizing impacts on the
operation of the typhoon shelter;
·
It would involve a smaller extent of
squatters clearance and is located further away from air and noise sensitive
areas, thereby minimizing impacts on the local community and environment; and
·
The potential impact on water quality and
marine ecology arising from the small-scale marine works is anticipated to be
minor. With implementation of recommended mitigation measures, adverse impact
on water quality and marine ecology would not be anticipated.
2.3.1.3
Different design layouts
for the public landing facility were considered to arrive at the optimum option
such that environmental impacts would be minimized without compromising its
operational requirements. The
preferred design option was selected with the following advantages:
·
The length of the breakwater was reduced
as far as practicable to allow more room for smaller boats to sail within the
nearshore waters without compromising suitable berthing conditions at the
public landing facility;
·
The extent of underwater rock
excavation/dredging was reduced as far as practicable to minimize the amount of
excavated materials, impact on marine ecological
habitats and associated wildlife, noise impacts on the nearby noise sensitive
receivers and potential resuspension of fine and possibly contaminated
materials from the seabed; and
·
To avoid
the impact on coral colonies, the dredging volume has been minimized as far as
practicable, which will only affect about 0.05ha of the subtidal hard substrate
habitat. To mitigate the impact, coral translocation and other best practicable
mitigation measures will be implemented. A coral mitigation plan will be
prepared subject to comment by the Agriculture, Fisheries and Conservation
Department (AFCD) prior to implementation of the proposal.
2.4
Construction Method
2.4.1.1
Construction
of the promenade with public landing facility and the breakwater will mainly
involve dredging of seabed, underwater rock excavation, construction of sloping
seawall, pile construction and construction of deck structures. The improvement
works for the existing lookout points and the existing viewing platform will
involve demolition of existing structures, installation of new concrete
structures and backfilling. To
minimise the potential environmental impacts, the following construction
methods and sequences have been considered and adopted for the Project as far
as possible:
·
Minimise
active marine works area by phased construction and adopting piled deck structure
for the public landing facility and breakwater to reduce the amount of dredging
works;
·
Utilise
pre-cast elements for construction of the public landing facility and
breakwater as far as practicable to minimise in-situ construction works so as
to reduce the construction period and environmental impacts, such as waste
generation, noise and dust impacts;
·
Incorporate
ecological features such as seawall enhanced with rough texture and irregular
pattern into the design of vertical seawall as far as practicable to provide
shades and refuge for organisms. A submission on the
detailed design of the ecological features to be adopted will be prepared subject to comment by the AFCD prior
to the installation of the ecological features;
·
Install
silt curtain and restrict dredging operation to a production rate of no more
than 100m3 per hour to minimise the potential water quality impact
(e.g. prevent the dispersion of suspended sediments) arising from the dredging
works; and
·
Implement
good site practice and appropriate environmental mitigation/control measures.
2.5
Project Programme
2.5.1.1
The
Project construction works are anticipated to commence in the third quarter of
2019 and be completed by the first quarter of 2023.
2.6.1.1
Based
on the best available information at the time of conducting the EIA study,
sewerage improvement works would be carried out in the vicinity of the Project
(i.e. within 500m of the boundary of the Project) by DSD from the third quarter
of 2018 to the first quarter of 2023, namely “Lei Yue Mun
Village Sewerage”. The works for the
Project may therefore potentially interact with the concurrent sewage
improvement works. The synchronizing of these projects will minimise the duration of environmental nuisance to the
nearby residents.
2.6.1.2
The
cumulative environmental impacts arising from this concurrent project during
the construction and operation of the Project have been assessed in the EIA
Report. To minimise the potential
cumulative environmental impacts arising from these two projects, ArchSD/ CEDD will closely liaise with DSD on planning of
the programme of various construction activities which include exploring the
feasibility of entrusting the interfacing streetscape improvement works to DSD
to avoid/ minimise repeated and concurrent construction works.
3.1.1.1
The EIA study has provided an assessment of the
potential environmental impacts associated with the construction and operation
of the Project based on the engineering design information available at this
stage. The assessment
has been conducted in accordance with the EIA Study Brief (No. ESB -287/2015)
issued for the Project and the Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM) and it covers the following aspects:
·
Air quality impact;
·
Noise impact;
·
Water quality impact;
·
Sewerage and sewage treatment
implications;
·
Waste management implications;
·
Land contamination;
·
Ecological impact (terrestrial and
marine);
·
Fisheries impact; and
·
Landscape and visual impacts.
3.2.1
Key Assessment Scope and Key Criteria
3.2.1.1
The air quality impact assessment was conducted
in accordance with the requirements in Annexes 4 and 12 of the EIAO-TM and the
requirements in Section 3.4.3 and Appendix A of the EIA Study Brief. In
accordance with the EIA Study Brief, the study area is defined by a distance of
500m from the boundary of the Project site, with consideration to be extended
to include major existing, planned and committed air pollutant emission sources
that may have a bearing on the environmental acceptability of the Project.
3.2.2
Construction Phase
3.2.2.1
The Project would involve construction of a
promenade with a public landing facility and a breakwater; structural
improvement works for five existing lookout points and an existing viewing
platform; construction of a carp-shaped platform and a pavilion with children
play area; beautification works for the promenade, five existing lookout points
and an existing viewing platform; and streetscape improvement works. Potential
air quality impacts from the construction works of the Project would mainly
arise from construction dust from demolishing of existing structures,
excavation, concreting works and backfilling works. Considering these
construction activities would be limited scale, localised
and in phasing as well as the construction period would be short, significant
dust emission is not anticipated and could be well controlled through
the dust suppression measures as stipulated in the Air Pollution Control
(Construction Dust) Regulation (Cap. 311R) of Air Pollution Control Ordinance
(APCO) (Cap. 311) and good site practices. Cumulative dust impact contributed
by this Project and
the concurrent project, Lei Yue Mun
Village Sewerage, is also not anticipated.
With the implementation of sufficient dust suppression measures and good
site practices (e.g. regular watering of exposed site surfaces and tarpaulin
covering of all dusty vehicle loads transported to, from and between site
locations, etc), adverse construction dust impact due
to the construction of the Project is not anticipated. Requirements of Air
Pollution Control (Construction Dust) Regulation and EPD’s Recommended
Pollution Control Clauses for Construction Contracts are proposed to be
incorporated into the future contract document.
3.2.2.2
Odour impact is not
anticipated from the dredging activities in view of the low level of
acid-volatile sulphide (AVS) (<reporting limit of
1.00 mg/kg) in the sediment. Therefore, adverse odour
impact from dredged sediment is not anticipated. Nonetheless, the following
good site practices are recommended to minimize the potential odour emission during dredging and transportation of
dredged sediment:
·
Loading
of the dredged sediment to the barge should be controlled to avoid splashing
and overflowing of the sediment slurry to the surrounding water;
·
Any
dredged sediment should be stored in enclosed tanks or properly covered as far
as practicable to minimise its exposed area during its temporary storage and
should be placed as far away from the identified air sensitive receivers (ASRs)
as practically possible;
·
Dredging
rate should be controlled carefully;
·
The
dredged sediment is suggested to be delivered off-site for disposal every day
as far as possible to avoid the dredged sediment for storage at the barge
overnight;
·
Dredged
sediment placed on marine vessel for disposal should also be properly covered
during transportation; and
·
The
dredging activities should be conducted during non-summer season as far as
possible.
3.2.3
Operation Phase
3.2.3.1
During operation phase, marine traffic would be
induced from the Project. Considering that the induced marine traffic would be
minor, adverse air quality impacts on the nearby ASRs is not expected.
Nonetheless, potential cumulative air quality impacts due to the induced and
other marine emission, industrial emission and vehicular emission within the
study area during operation phase of the Project have been assessed. In
accordance with the Air Quality Objectives (AQO), Nitrogen Dioxide (NO₂), Sulphur Dioxide (SO₂), Respirable Suspended Particulates
(RSP) and Fine Suspended
Particulates (FSP) are the key criteria pollutants for assessment of the
air quality impact for this Project. The results indicated that the predicted
cumulative air pollutants concentrations
(hourly NO2, annual NO2, 10-min SO2, daily SO2, daily
FSP, annual FSP, daily RSP and annual RSP) at all ASRs would comply with the
AQO. No adverse air quality impact is anticipated and no mitigation measure is
deemed necessary.
3.2.3.2
No odour nuisance from
the operation of the Project is anticipated as there is no odour
emission source arising from the Project and no other odour
emission source is found within the Project area from odour patrol.
Similar to the capital dredging during construction phase, odour impact is not anticipated from the maintenance
dredging. Nevertheless, good site practices should be adopted to minimize any
potential odour emission during dredging and
transportation of dredged sediment.
3.3
Noise Impact
3.3.1
Key Assessment Scope and Key Criteria
3.3.1.1
The noise impact assessment was conducted in
accordance with the requirements set out under Annexes 5 and 13 of the EIAO-TM,
and Section 3.4.4 and Appendix B of the EIA Study Brief. In accordance with the
EIA Study Brief, the study area included areas within 300m from the boundary of
the Project site. The study area shall be expanded to include noise sensitive
receivers (NSRs) at distances over 300m from the Project boundary and
associated works if those NSRs are also affected by the construction of the
Project.
3.3.2
Construction Phase & Operation Phase
3.3.2.1
Noise impacts would be resulted from the
proposed construction activities with the use of powered mechanical equipment
(PME). The assessment results
indicated that the unmitigated noise levels at the representative NSRs would be
55 – 96 dB(A). With the implementation of all
practicable noise mitigation measures, including the use of quiet PME and
deployment of construction noise barriers and portable noise enclosure, the predicted noise levels at all the
representative NSRs would comply with the EIAO-TM noise criteria.
Hence, no unacceptable noise impact arising from the construction
of the Project is anticipated.
The mitigated cumulative construction noise impact would exceed the
criteria at five representative NSRs (four existing residential uses and one
existing performing arts centre cum educational
institution). Notwithstanding this, the exceedance would mainly be caused
by a concurrent project and transient in nature. The Contractor would liaise closely with the
affected NSRs and notify them before commencing the construction activities of
concern and should strive to complete the works in the shortest time
possible. In addition, to minimise
nuisance to nearby educational institution and seafood restaurants, noisy
construction works would not be carried out during the examination period of
the educational institution and the peak business hours of the restaurant.
Hence, adverse residual construction noise impact is not anticipated.
3.3.2.2
The
Project is not a noise pollution source and therefore noise impact arising from
the project during operation phase is not anticipated.
3.4
Water Quality Impact
3.4.1
Key Assessment Scope and Key Criteria
3.4.1.1
The water quality impact assessment was
conducted in accordance with the requirements in Annexes 6 and 14 of the
EIAO-TM and the requirements in Section 3.4.5 and Appendix C of the EIA Study
Brief. According to the EIA Study Brief, the study area for the water quality
impact assessment included areas within 500 m from the boundary of the Project
site and covered Victoria Harbour (Phase one) Water
Control Zone (WCZ), Junk Bay WCZ and Eastern Buffer WCZ under the Water
Pollution Control Ordinance (WPCO).
3.4.2
Construction Phase
3.4.2.1
During construction phase, the key issues
associated with the land-based construction activities would be the potential
release of construction site run-off from surface work areas, wastewater from
general construction activities, accidental spillage and sewage from
construction workforce. Minimization of water quality deterioration could be
achieved through implementing adequate mitigation measures such as minimising surface run-off and implementing measures to
abate pollutants at source. Regular
site inspections should be undertaken routinely to inspect the construction
activities and work areas in order to ensure the recommended mitigation
measures are properly implemented. No
unacceptable residual water quality impact is therefore anticipated.
3.4.2.2
For marine construction activity, the key source
of potential water quality impact is associated with dredging and filling
activities, which have potential to release contaminants and increase suspended
solid levels in marine water. The potential water quality impacts have been
quantitatively assessed using the Delft3D Model, which has identified that the
potential water quality impacts from suspended solids and sedimentation rate
elevation as well as the contaminants release would be confined within 100m of
the Project site. With the adoption of the recommended mitigation measures
including use of closed grab dredger, restriction of dredging production rate
(no more than 100m3 per hour) and deployment of silt curtains, no
unacceptable residual water quality impact would be resulted.
3.4.3
Operation Phase
3.4.3.1
The key source of potential water quality
impacts under the operation phase will be the change in hydrodynamic regime,
sewage effluent from the increased touristic and commercial activities, surface
run-off associated with the new paved areas and maintenance dredging. Since LYM
waterfront was predicted to maintain its good flushing ability, no adverse
water quality impact is thus attributed to the establishment of landing
facility and breakwater. It is expected that water quality would be improved
upon the completion of the concurrent project (i.e. Lei Yue Mun Village
Sewerage). For the potential impacts of surface run-off, with proper
implementation of the recommended mitigation measures such as proper drainage
system design, provision of pollution control devices and adoption of good
management practice, no unacceptable water quality impact is anticipated. During maintenance dredging, with
proper implementation of the recommended mitigation measures including use of closed grab dredger,
restriction of dredging production rate (no more than 100m3 per
hour) and deployment of silt curtains, no unacceptable water quality impact is anticipated.
3.5
Sewerage and Sewage
Treatment Implications
3.5.1
Key Assessment Scope and Key Criteria
3.5.1.1
The assessment for sewerage and sewage treatment
implications was conducted in accordance with Section 3.4.6 and Appendix D of
the EIA Study Brief and the criteria and guidelines for evaluating and
assessing impacts on the public sewerage, sewage treatment and disposal
facilities as stated in Annex 14 of the EIAO-TM.
3.5.2
Construction Phase
3.5.2.1
During the construction phase, impact on the existing
sewerage system arising from the Project is not anticipated.
3.5.3
Operation Phase
3.5.3.1
According to the latest construction programme, no programme gap is
envisaged between this Project and the Lei Yue Mun
Village Sewerage project to be undertaken by DSD. Hence, any sewerage plug-in and additional
sewage arising from the increase in visitors will be discharged into the newly
constructed sewerage system.
3.5.3.2
The
existing Kwun
Tong Preliminary Treatment Works has adequate treatment capacity to handle the
sewage flow generated from the visitors in Lei Yue Mun
after the completion of the waterfront enhancement works. Hence,
no adverse sewage impact arising from the operation of the Project is
anticipated.
3.6
Waste Management
Implications
3.6.1
Key Assessment Scope and Key Criteria
3.6.1.1
The waste management implications assessment was
conducted based on the criteria and guidelines in Annexes 7 and 15 of the
EIAO-TM and Section 3.4.7 and Appendix E-1 of the EIA Study Brief.
3.6.2
Construction Phase
3.6.2.1
During
the construction phase, the major waste types generated from the Project
include marine sediment, construction and demolition (C&D) materials, general refuse from
workforce and chemical waste from the maintenance of construction plant and
equipment.
3.6.2.2
The
total volume of dredged sediment generated from the dredging works is estimated
to be approximately 10,875 m3. Based on the results of the chemical
and biological screening, approximately 9,740 m3 of sediment is
suitable for Type 1 – Open Sea Disposal and 1,135 m3 of sediment
requires Type 2 – Confined Marine Disposal with reference to ETWB TCW No.
34/2002. With the implementation of the
recommended mitigation measures such as avoidance of stockpiling of
contaminated sediments as far as possible, covering the dredged sediment on
trucks or barges, equipping barge transporting sediments with tight fitting
seals, and off-site disposal of dredged sediment in accordance with the
requirements of ETWB TCW No. 34/2002, no adverse waste impacts would be
expected from dredging, transportation and disposal of marine sediment.
3.6.2.3
The total quantity of C&D materials
generated from the Project is estimated to be approximately 3,360 m3,
of which approximately 2,890 m3 would be inert materials and
approximately 470 m3 would be non-inert materials. It is also
expected that chemical waste (a few hundred litres
per month)
and general refuse (approximately 52 kg per day) would be generated from the Project as well
as floating refuse (approximately 2.7 m3 per year) would be collected
from the newly constructed seawall during the construction phase. These
identified wastes would be properly handled, transported and disposed of using
the recommended methods and in accordance with the relevant legislations and
guidelines, and good site practices would be followed. Hence, adverse waste impacts would not be
expected.
3.6.3
Operation Phase
3.6.3.1
During operation phase, recreational activities
from visitors would generate about 107 kg of general refuse per day. With the
provision of sufficient quantity of recycling bins and
general refuse bins and
proper handling, no adverse
waste impact would be expected.
3.6.3.2
Approximately
3,056 m3 marine sediment would be dredged under maintenance dredging
at about every 5 to 10 years. The maintenance dredging would require
sediment sampling and
testing in accordance with the requirements of ETWB TCW No. 34/2002 for proper disposal
of the dredged sediment. With implementation of the recommended mitigation
measures such as avoidance of stockpiling of contaminated sediments as far as
possible, covering the dredged sediment on trucks or barges, equipping barge
transporting sediments with tight fitting seals, and off-site disposal of
dredged sediment in accordance with the requirements of ETWB TCW No. 34/2002,
no adverse waste impact would be anticipated.
3.7.1
Key Assessment Scope and Key Criteria
3.7.1.1
The land contamination assessment was conducted
following the criteria and guidelines in sections 3.1 and 3.2 of Annex 19 of
the EIAO-TM and the requirements in Section 3.4.8 and Appendix E-2 of the EIA
Study Brief.
3.7.2
Construction and Operation Phases
3.7.2.1
Based on the findings of site appraisal (i.e.
desktop study and site inspection) within the site boundaries of construction
works, no potentially contaminating activities were identified. Therefore,
adverse land contamination impact arising from the Project would not be
anticipated.
3.8.1
Key Assessment Scope and Key Criteria
3.8.1.1
The ecological impact assessment was conducted
following the criteria and guidelines in Annexes 8 and 16 of the EIAO-TM and
the requirements in Section 3.4.9 and Appendix F of the EIA Study Brief.
Habitat evaluation and impact assessment followed the requirements stated in
EIAO Guidance Notes 6/2010, 7/2010, 10/2010, 11/2010 and other relevant
legislations and guidelines. According to the EIA Study Brief, the study area
included areas within 500m from the boundary of the Project site and any other
areas likely to be impacted by the Project.
3.8.2
Construction and Operation Phases
3.8.2.1
Literature review and ecological field surveys
have been conducted. Eight terrestrial habitats were identified within the
study area including mixed woodland, plantation, shrubland,
grassland, developed area, natural watercourse, intertidal habitat and drainage
channel. Marine habitats within the study area include subtidal hard substrate
and soft bottom habitats, and intertidal habitats (i.e. rocky shore, sandy
shore and artificial seawall). The ecological values of the identified habitats
are rated as low or low to moderate. No sites of conservation importance would
be directly affected.
3.8.2.2
No plant species of conservation importance were
recorded within the study area and no direct impact on terrestrial species of
conservation importance would be anticipated. The proposed land-based works
would only affect developed area near the seafront. The proposed marine-based
works would directly affect marine habitats, including subtidal hard substrate
habitats (0.05 ha), rocky shore (0.03 ha), sandy shore (0.02 ha) and artificial
seawall (40 m); as well as causing temporary loss of subtidal soft bottom
habitat (0.32 ha) and artificial seawall (85 m). All temporarily affected
habitats would be reinstated. Given the small sizes and low
ecological values of the affected habitats, the direct impacts to habitats are
anticipated to be minor.
3.8.2.3
Direct impact to coral colonies of low abundance which are dominated by
locally common octocoral species is anticipated.
Translocation and/or other best practicable mitigation measures would be
implemented to minimize the direct impact of affected coral colonies. A detailed Coral Mitigation Plan, including description of the methodology of coral translocation and/ or other best
practicable mitigation measures identified with reference
to recently approved EIA project, would be submitted to the AFCD for comment
before commencement of project construction. Ecological
features such as seawall enhanced with rough texture and irregular pattern
would be incorporated into the design of vertical seawall as far as practicable
to increase the surface complexity of the seawall to provide shades and refuge
for organisms. A submission on the detailed design of the ecological features
to be adopted will be prepared subject to comment by the AFCD prior
to the installation of the ecological features. During operation phase, maintenance dredging
would be required at about every 5 to 10 years to maintain sufficient water
depth for safe navigation of vessels.
During both capital and maintenance dredging operations, mitigation
measures to control water quality impact are recommended (e.g. use of close
grab dredger, restriction of dredging rate to no more than 100m3 per
hour and deployment of silt curtain) to confine the sediment plume within the
proposed dredging area and to minimise indirect impact to the nearby intertidal
and subtidal flora and fauna. With implementation of the recommended mitigation measures, the residual
direct impact to coral is considered acceptable. During operation phase, it is
recommended to carry out coral survey to review and update the conditions of
corals in the dredging area and its vicinity prior to each maintenance
dredging. Subject to the findings of the coral survey, the impact on corals due
to maintenance dredging will be reviewed and mitigation measures will be
proposed as necessary.
3.8.2.4
Construction site runoff, noise, deteriorated water
quality and other disturbance impacts resulting from the proposed marine-based
and land-based works would have potential indirect impact to the nearby natural
habitats (e.g. intertidal and subtidal habitats, mixed woodland and shrubland, etc.), wildlife, as well as fauna species of
conservation importance. With the proper implementation of mitigation measures
such as good site practice and water quality impact control measures, no
adverse indirect ecological impact to nearby natural habitats, wildlife, and
fauna species of conservation importance would be expected from the Project.
3.9
Fisheries Impact
3.9.1
Key Assessment Scope and Key Criteria
3.9.1.1
The fisheries impact assessment was conducted
following the criteria and guidelines in Annexes 9 and 17 of the EIAO-TM and
the requirements in Section 3.4.10 and Appendix G of the EIA Study Brief. As
per the EIA Study Brief, the study area for fisheries impact assessment
included areas within 500m from the boundary of the Project and associated
works.
3.9.2
Construction and Operation Phase
3.9.2.1
The
potential fisheries impacts due to the construction and operation of the
Project are considered minor in view of the small scale of the works. About 0.05 ha permanent loss and 0.6ha
temporary loss of fishing ground would be resulted due to construction
of the project. Indirect impact on fisheries due to elevation in suspended
solids level, depletion of dissolved oxygen and release of contaminants would
be temporary. With the implementation of the recommended mitigation measures
such as adoption of silt curtain, reduced dredging rate, and use of closed grab
dredger, adverse impact on water quality and fisheries is not anticipated.
3.10
Landscape and Visual
Impacts
3.10.1
Key Assessment Scope and Key Criteria
3.10.1.1
The landscape and visual impact assessment was
conducted based on the criteria and guidelines in Annexes 10 and 18 of the EIAO-TM,
the EIAO Guidance Note No. 8/2010 and Section 3.4.11 and Appendix H of the EIA
Study Brief. According to the EIA Study Brief, the study area for the landscape
impact assessment included areas within 500m from the boundary of the Project
site, while the assessment area for the visual impact assessment shall be
defined by the visual envelope of the Project.
3.10.2
Construction Phase
3.10.2.1
During the construction phase, the key sources
of landscape and visual impacts would include construction of the public landing
facility, dredging works, enhancement works of sitting out area and footpath
and foundation work at lookout points. All existing trees within the proposed
works boundary would be preserved as far as possible. The work areas for the Project are generally
at ground level. The visual experience of the visual sensitive receivers (VSRs)
would not be significantly changed. With the implementation of mitigation
measures including preservation of existing trees, control of night-time
lighting glare, erection of decorative screen hoarding, careful management of
construction activities and facilities, provision of buffer zone (a minimum
distance of about 10m) between the CPA and dredging works boundary, deployment
of silt curtains and close supervision of dredging works, no unacceptable
residual landscape and visual impacts from construction of the Project would be
anticipated.
3.10.3
Operation Phase
3.10.3.1 During
the operation phase, the aboveground/above-sea-level structures/hardscape
features such as the pavilion, the breakwater and the promenade with public
landing facility, and maintenance dredging works would be the key sources of
landscape and visual impacts. Nevertheless, the height of all the proposed
aboveground/above-sea-level structures/hardscape features would not be
prominent (not higher than 5m) and the maintenance dredging works would be
limited scale and infrequent (interval
of about every 5 to 10 years). With the recommended mitigation measures including provision of buffer
zone between the CPA and dredging works boundary, deployment of silt curtains
and close supervision of dredging works, adoption of aesthetic design for the aboveground/above-sea-level structures/hardscape features,
provision of buffer and amenity planting to fit into the local landscape
and visual context, and reinstatement of temporarily disturbed landscape areas,
the overall landscape and visual impacts of the Project would be beneficial.
4
Environmental Monitoring and Audit
4.1.1.1
Environmental Monitoring and Audit (EM&A) requirements
for air quality, noise, water quality, sewerage and sewage treatment, waste
management, land contamination, ecology, fisheries, and landscape and visual
impacts were identified and recommended, which are detailed in the EM&A
Manual and summarized in Table 4.1 below.
On-site monitoring and auditing is recommended to check against the
implementation of recommended mitigation measures in the construction and
operation phases.
Table 4.1 Summary of
EM&A Requirements
Environmental Aspect
|
Environmental
Monitoring and Audit
|
Construction Phase
|
Operation Phase
|
Air Quality
|
✓
|
✗
|
Noise
|
✓
|
✗
|
Water Quality
|
✓
|
✓ (1)
|
Sewerage
and Sewage Treatment
|
✗
|
✗
|
Waste
Management
|
✓
|
✗
|
Land Contamination
|
✗
|
✗
|
Ecology
|
✓
|
✓ (1)
|
Fisheries
|
✗
|
✗
|
Landscape
and Visual
|
✓
|
✗
|
Note:
(1) EM&A
to be conducted during maintenance dredging operation.
4.2.1.1
With
the implementation of dust suppression measures stipulated in Air Pollution
Control (Construction Dust) Regulation, good site practice and proposed
mitigation measures, no adverse dust and odour impact
arisen from the construction works would be expected at the ASRs in the
vicinity of the site. No air quality monitoring is therefore considered
necessary. Weekly site audit is recommended to be
conducted during construction phase in order to ensure the proposed mitigation
measures are implemented in an appropriate manner and are effective.
4.2.1.2
Since
no adverse air quality impact is anticipated during the operation phase of the
Project, monitoring and audit is deemed unnecessary.
4.3.1.1
Noise
monitoring is recommended for the construction phase of the Project to ensure
compliance with the daytime construction noise criterion. The implementation of the recommended
mitigation measures for daytime construction activities should also be audited
weekly as part of the EM&A programme.
Construction noise levels will be measured in terms of the 30-minute
A-weighted equivalent continuous sound pressure level (Leq)
for the time period between 0700 and 1900hours before and during the
construction period.
4.3.1.2
Baseline
monitoring will be conducted to determine the existing noise level prior to
commencement of construction works. Construction noise monitoring will be
carried out weekly at representative noise monitoring stations (residential
uses). Action Level or Limit Level for the monitoring is considered to be
triggered in case of the receipt of a noise complaint or an exceedance of the noise
criteria stipulated in the EIAO-TM. If noise exceedance is recorded, additional
noise monitoring will be conducted in accordance with the Event and Action
Plan. The monitoring shall be considered complete if the exceedance has been
rectified or proved to be from sources other than the Project construction
works.
4.4
Water Quality Impact
4.5.1.1
Since
adverse sewerage impact from the Project would not be anticipated, no
monitoring or audit is considered necessary.
4.6
Waste Management
Implications
4.6.1.1
The
contractor will formulate waste management measures on waste minimization,
storage, handling and disposal in a Waste Management Plan as part of
Environmental Management Plan in accordance with the Environment, Transport and
Works Bureau Technical Circular (Works) No. 19/2005. Weekly site audit should
be carried out to check the implementation status of the recommended waste
management measures throughout construction period.
4.6.1.2
During
the operational phase of the Project, with proper implementation of the
proposed mitigation measures, adverse waste impact arising from the Project is
not expected. No monitoring or audit is required.
4.7
Land Contamination
4.7.1.1
No
land contamination impact would be anticipated from the Project, therefore, no
monitoring or audit is required.
4.8.1.1
Implementation
of the recommended mitigation measures will be audited monthly throughout
the construction phase.
4.8.1.2
Prior to the marine-based construction works, a
detailed coral mapping is recommended to identify the exact number of coral
colonies (both movable and non-movable) within the affected area. Surveys of
finding a suitable recipient site are also recommended. The coral mitigation is
recommended to be undertaken during the winter season (November-March) in order
to avoid disturbance to the spawning period (i.e. July to October) of the
affected coral colonies. A detailed
Coral Mitigation Plan, including description of methodology for coral
translocation (e.g. pre-translocation survey, identification / proposal of
coral recipient site) and/or other best practicable mitigation measures, and
post-mitigation monitoring programme, should be prepared with reference to
recently approved EIA and submit to the AFCD for comment before commencement of
the project construction. All the coral mitigation exercises should be
conducted by experienced marine ecologist(s) with at least 5 years relevant
experience prior to commencement of coral mitigation. During operation phase, it is recommended to carry
out coral survey to review and update the conditions of corals in the dredging
area and its vicinity prior to each maintenance dredging. Subject to the
findings of the coral survey, the impact on corals due to maintenance dredging
will be reviewed and mitigation measures will be proposed as necessary.
4.9.1.1
Since
no unacceptable fisheries impact would be anticipated during the construction
and operation phases of the Project, no specific monitoring or audit for
fisheries is considered necessary.
4.10.1.1 The design, implementation and
maintenance of the proposed landscape and visual mitigation measures should be
checked to ensure that they are incorporated in the detailed design.
Implementation of the applicable recommended mitigation measures should be
checked at least once every two weeks through the site audit programme during the construction phase. No
specific monitoring or audit for landscape and visual is considered necessary
during operation phase.
5.1.1.1
The
Lei Yue Mun Waterfront Enhancement Project, which includes construction
of a public landing facility and improvement works to existing lookout points
and viewing platform, as well as development of a waterfront promenade and
related improvement works, aims primarily at providing more convenient
access and better supporting facilities for tourists visiting LYM with a view
to enriching their experience.
The Project would not only enhance LYM’s attractiveness for tourism but also
improve the general environment for the local residents.
5.1.1.2
The EIA Report provides information on the
nature and extent of the potential environmental impacts including air quality,
noise, water quality, sewerage and sewage treatment, waste management, land
contamination, ecology, fisheries, landscape and visual, that may arise during
the construction and operation of Lei Yue Mun Waterfront
Enhancement Project. Mitigation measures have been proposed, where necessary
and appropriate, to ensure full compliance with environmental legislation and
standards.
5.1.1.3
The EIA Report has concluded that the Project
would be environmentally acceptable with no unacceptable residual impacts on
the nearby environmental sensitive receivers with the implementation of the
proposed mitigation measures during its construction and operation. The
schedule of mitigation measures recommended to be implemented has been provided
in the EIA Report and an EM&A programme has been
recommended to check the proper implementation of these measures and monitor
environmental compliance of the Project.