11.0... SUMMARY
OF ENVIRONMENTAL OUTCOMES
11.1 Overview
. 11-1
11.2 Population and Environmental
Sensitive Areas Protected
11.3 Summary of Environmental
Designs Recommended, Environmentally Friendly Options
Considered and Incorporated in the Preferred Option
11.4 Key Environmental Problems
Avoided
11.5 Environmental Benefits of the
Project
. 11-4
11.6 Environmental Benefits of
Environmental Protection Measures Recommended
11.7 Summary of Alternative Measures
This chapter summarises the key
environmental outcomes arising from the EIA Study. Chapter 2 outlines the
analysis of alternative development options during the optioneering process,
which has taken account of public views.
Alternative options, designs and construction methodologies have been
duly considered. The technical assessments (Chapter 3 to 9) conducted have
demonstrated that all the statutory requirements in EIA Study Brief (EIA SB
No.: ESB-310/2018) and Technical Memorandum on Environmental Impact Assessment
Process (EIAO-TM) are complied with.
The following sections summarise
the approaches that have been adopted to either avoid or minimise various
environmental impacts throughout the design process, and the associated
environmental enhancements and compensation measures.
Air
Quality Impact
In construction phase, fugitive
dust may be generated from works activities including site clearance,
excavation, handling of construction materials, concrete breaking and from
minor wind erosion. Activities that may induce significant dust emissions such
as extensive site formation and blasting are not required for Project
development. The impact can be minimized with proper implementation of
mitigation measures stated in Section 3.5.3. The population protected by the
mitigation measures includes all air sensitive receivers (ASRs) within 500m
from Project Boundary. The protected ASRs includes residents, place for
worship, offices, parks and elderly centre along Kam Tin Road and Lam Kam Road.
In operation phase, cumulative
air quality impact arising from the vehicular emissions from the open roads
within the assessment area has been assessed at the worst-case-year. The assessment results conclude that the
concerned air pollutant concentrations at representative ASRs would comply with
the Air Quality Objectives.
Noise
Impact
In construction phase, all
representative NSRs identified within 300m from Project Boundary (total of 57
NSRs) can be protected with proper implementation of mitigation measures stated
in Section 4.5.4. The protected NSRs includes residents, place for worship and
elderly centre along Kam Tin Road and Lam Kam Road.
In operation phase, direct noise mitigation measures such as LNRS and vertical
noise barrier are evaluated to minimize the operation noise impact. LNRS with
total length of approximate 2.1km would be applied on several road sections of
Kam Tin Road. A total length of approximate 837m vertical noise barriers with
maximum height of 5.0m along Kam Tin Road and maximum height of 3.0m along Lam
Kam Road are recommended for the NSRs with exceedance in unmitigated scenario. 106
out of 648 affected dwellings are protected and 565 out of 648 affected
dwellings are benefited from the direct noise mitigation measures. The protected
and/or benefited dwellings includes residents and planned residential areas,
place for worship and elderly centre along Kam Tin Road and Lam Kam Road.
Water
Quality Impact
Potential water quality impact
might be arisen from the associated construction works of road widening and
improvement works such as retaining wall and geotechnical works, which can be
minimised with proper implementation of mitigation measures stated in Section 5.7.
The environmental sensitive areas protected by the implementation of the
mitigation measures include water gathering ground from the Project eastern
end, local streams near Kadoorie Experimental Farm, Ling Wan Monastery, Wong
Chuk Yuen, Sheung Tsuen and Kam Tin Bypass; nullah near Wang Toi Shan Hung Mo
Tam, Shek Kong Barracks and the channelized Kam Tin River.
Ecological
Impact
There will be disturbance from
construction activities to nearby habitats and site runoff during construction
phase which can be minimised with proper implementation of mitigation measures
stated in Section 7.8. Nearby sensitive areas such as nearby waterbodies and
habitats for wildlife are protected with proper implementation of mitigation
measures.
Land
Contamination
Site re-appraisal is required for
the identified potentially contaminated sites as well as other areas within the
Project Boundary to address any change in land use that may give rise to
potential land contamination issues as soon as the sites become accessible and
a supplementary CAP should be submitted and endorsed by EPD before site
investigation. A CAR which includes the site investigation sampling and testing
results will be prepared for EPD's agreement upon completion of the site
investigation. If contamination is identified, RAP shall be also prepared and
submitted to EPD for agreement prior to the commencement of the remediation
works. Upon completion of the remediation, a RR shall be submitted to EPD for
agreement. No construction works of site should be carried out prior to the
agreement of the RR.
Landscape
and Visual Impact
Based on the tree survey
conducted, it is estimated that 756 trees will be felled, 1250 trees will be retained, and 43 trees will be
transplanted. The design of the proposed engineering works has been carefully
considered to retain as many of the existing trees as possible. The tree loss
will be compensated through the planting and growth to maturity of not less
than 756 heavy standard trees (with a DBH not less than 100mm) would be
required for compensation in 1:1 ratio.
Avoidance of environmental
impacts has been one of the key considerations throughout the entire project
development and design. For those impacts that could not be avoided, due
consideration has been given to minimise those impacts as much as practicable.
A summary of these approaches is
given below:
¡P Minimisation of impacts to
Conservation Area;
¡P
Preservation of habitats with ecological value;
¡P
Avoidance of impacts to sensitive receivers along Kam Tin Road and Lam Kam
Road;
¡P
Avoidance of impacts to natural watercourses; and
¡P
Provide compensation planting
Minimisation
of impacts to Conservation Area
The preferred option reduced the
encroachment of CA zones, resulting in only slight encroachment of the four CA
zones at north of section between Chainage CHB 28+70 and CHB 30+10 of Kam Tin
Road, south of section from CHB
44+30 to CHB 44+80 and CHB 49+00 to CHB 52+30 of Lam Kam Road as well as north of section between Chainage CHB 50+20
to CHB 52+40 of Lam Kam Road. However, the concerned CA zones are at the
shotcreted slopes with common roadside tress, mixed woodland edge and slopes
covered with herbaceous plants with a few common trees and shrubs, and hence
the potential impact to habitat loss/vegetation clearance is considered to be minor.
Detailed ecological impact assessment is in Section 7 of EIA study report.
Preservation
of habitats with ecological value
To minimize habitat loss to the nearby habitats and
associated wildlife, the following mitigation measures will be implemented:
¡P
Confining the works within the Project
Boundary;
¡P
Controlling access of site staff
to avoid damage to the vegetation in surrounding areas
¡P
Placement of equipment or
stockpile in the existing disturbed / urbanized area within the Project Boundary
of the Project to minimize disturbance to vegetated areas
Avoidance
of impacts to sensitive receivers along Kam Tin Road and Lam Kam Road
In order to minimise the impacts to sensitive
receivers along Kam Tin Road and Lam Kam Road, environmental assessment on air
quality, noise, water, waste, ecology, land contamination and visual and
landscape has been conducted. Relative mitigation measures have been proposed
in Chapter 3 to Chapter 9.
In addition, road works will be carried out section
by section and each active construction work front will be limited to occupy
about 50m x 10m work area at any one time, and with a separation distance of more
than 600m between two concurrent work areas, to reduce concurrent environmental
impacts to sensitive receivers.
Avoidance
of impacts to natural watercourses
During the construction phase, site runoff would
need to pass through sand/silt removal facilities to reduce the concentration
of suspended solid. In accordance
with the Practice Note for Professional Persons on Construction Site Drainage,
Environmental Protection Department, 1994 (ProPECC PN 1/94), best management
practices should be implemented on site as far as practicable to control site
runoff and drainage at all work sites during construction phase, so that the
treated runoff will be discharged to public drainage system in compliance with
the WPCO. Construction effluent,
site run-off and sewage should be properly collected and/or treated. Wastewater from a construction site
should be managed. Proper locations
for discharge outlets of wastewater treatment facilities well away from the
natural watercourses should be identified.
The best practices are detailed in the Water Quality Impact Assessment
(Chapter 5). The following
precautionary measures as referred in ETWB TC (W) No. 5/2005 to avoid any possible
impacts on natural stream courses and/ or nearby vegetation during construction
phase shall be implemented:
¡P
Construction works close to the inland waters should be carried out in
dry season as far as practicable where the flow in the surface channel or
stream is low.
¡P
The use of less or smaller construction plants may be specified in
areas close to the water courses to reduce the disturbance to the surface
water.
¡P
Temporary storage of materials (e.g. equipment, chemicals and fuel) and
temporary stockpile of construction materials should be located well away from
any water courses during carrying out of the construction works.
¡P
Stockpiling of construction materials and dusty materials should be
covered and located away from any water courses.
¡P
Construction debris and spoil should be covered up and/or disposed of
as soon as possible to avoid being washed into the nearby water receivers.
¡P
Proper shoring may need to be erected in order to prevent soil or mud
from slipping into the watercourses.
¡P
Fencing should be erected on the sides facing the nearest stream course
to trap all wind-blown litters such as paper, plastic bags, bottles and boxes
within the site from entering the nearby water bodies.
¡P
The proposed works site
inside or in the proximity of natural rivers and streams should be temporarily
isolated, such as by placing of cofferdam with silt curtain with lead edge at
bottom and properly supported props, to prevent adverse impacts on the stream
water qualities. Other protective measures should also be taken to ensure that
no pollution or siltation occurs to the water gathering grounds of the work
site.
¡P
The natural bottom and
existing flow in the river should be preserved as much as possible to avoid
disturbance to the river habitats. If temporary access track on riverbed is
unavoidable, this should be kept to the minimum width and length. Temporary
river crossings should be supported on stilts above the riverbed.
Provide
compensation planting
Compensatory planting proposals
have been recommended in the Landscape and Visual Impact Assessment (Chapter
9). The roadside of the upgraded roads has been proposed for tree compensation.
The locations can be referred to Figure 9.11.
In addition, as discussed in
Chapter 2, alternative options have been considered in terms of alignment,
design alternative, construction method and construction sequence. It is
proposed to implement several typical work fronts of maximum 50m in length at
minimum 600m separation simultaneously along Kam Tin Road and Lam Kam Road to
minimize the environmental impact to nearby sensitive receivers.
The key environmental problems
involve ecological and noise impacts during the construction phase and
operation phase. Minor impacts on air quality, waste, water quality, visual and
landscape are expected.
The EIA study has critically
assessed the overall acceptability of environmental impacts which are likely to
arise as a result of the construction of the Project. Where necessary and
practicable, the EIA study has specified the conditions and requirements for
the detailed design and construction of the Project in order to mitigate
environmental impacts to an acceptable level.
In order to avoid or minimize the
environmental impacts of the Project, a number of mitigation measures have been
recommended in the EIA report. The key environmental measures and problems
avoided are highlighted below.
¡P
With the implementation of quiet plant, temporary noise barriers and good
site practices, construction noise from construction activities will be
minimised;
¡P
With the implementation of vertical noise barriers and low noise road
surfaces, traffic noise in operation phase will be minimised;
¡P
During construction phase, several typical work fronts of maximum 50m in
length would be implemented at minimum 600m separation simultaneously along Kam
Tin Road and Lam Kam Road to avoid cumulative impacts;
¡P
Encroachment on Conservation Area (s) / Ecologically Sensitive Areas have
been avoided and/or minimized as far as practicable and possible during the
initial design stage;
¡P
Mitigation measures such as confining the works within the Project
Boundary, controlling access of site staff to avoid damage to the vegetation in
surrounding areas and placement of equipment or stockpile in the existing
disturbed / urbanized area within the Project Boundary of the Project to
minimize disturbance to vegetated areas have been adopted to minimize habitat
loss to the nearby habitats and associated wildlife.
A comprehensive EM&A
programme will be setup to ensure effective implementation of mitigation
measures recommended in the EIA report, to assess the effectiveness of the
mitigation measures, and to identify any further need for additional measures
or remedial actions.
The development of the Project
could result in the following local and strategic benefits:
l
Increased noise protection due to direct
noise mitigation measures such as noise barriers based on the findings from
noise impact assessment. Existing traffic noise impact on the nearby sensitive
receivers along Kam Tin Road and Lam Kam Road can be reduced as much as
practicable
l
Better visual impact in Operation Phase due
to renewal of the existing road surface and associated auxiliary facilities
along Kam Tin Road and Lam Kam Road, and aesthetic noise barrier
l
New trees and plants will be planted along
roadside
Mitigation measures have been
recommended to further reduce the environmental impacts due to construction and
operation of the Project. Key recommended mitigation measures and their
associated benefits are summarised in Table
11.1 below.
Table 11.1 Key
recommended mitigation measures and their associated benefits
Aspect |
Key recommended mitigation measures and their
associated benefits |
Air Quality |
¡P
Limitation of each active construction work front to occupy about 50m x
10m work area at any one time, and with a separation distance of more than
600m between two concurrent work areas to reduce concurrent dust emission
impacts; ¡P
Works area for site clearance shall be sprayed with water before,
during and after the construction works so as to maintain the entire surface
wet to reduce dust emission; ¡P
Hoarding of not less than 2.4 m above ground shall be provided, as far
as practicable, along the Project Boundary which is next to the public areas
to prevent dust emission leaving Project Boundary; ¡P
Any stockpile of dusty materials shall be covered entirely by
impervious sheeting; and/ or placed in an
area sheltered on the top and 4 sides to reduce dust emission; and ¡P
Immediately before leaving a construction site, all vehicles shall be
washed to remove any dusty materials
from its body and wheels to reduce dust emission |
Noise |
¡P
Good site practices to limit noise emissions at the source; ¡P
Use of quality powered mechanical equipment (QPME); ¡P
Use of temporary noise barriers, enclosure and/or noise insulation
fabric to screen noise from relatively static PMEs; ¡P
Alternative quiet construction method; and ¡P
Vertical noise barrier and Low Noise Road Surface to reduce noise level
at NSR in operation phase |
Water Quality |
¡P
Good site practices to minimize site runoff; ¡P
Surface runoff from construction sites should be discharged into storm
drains via sand/silt removal facilities such as sedimentation basin/tank.
Earth bunds or sand bag barriers with tarpaulin sheet should be provided on Project
Boundary to intercept surface runoff from outside the site; ¡P
Silt removal facilities and manholes should be maintained and the
deposited silt and grit should be removed regularly to maintain water quality
at discharge; ¡P
Open stockpiles should be covered with a tarpaulin to avoid erosion
during rainstorms to minimize site runoff; ¡P
Drainage traps such as grease traps and petrol interceptors will be
installed at each of the drainage outlets to filter out chemical pollutants
from surface runoff; ¡P
Contractor must register as a chemical waste producer if chemical
wastes would be produced from the construction activities; ¡P
The practices outlined in ETWB TC (W) No. 5/2005 ¡§Protection of natural
streams/rivers from adverse impacts arising from construction works¡¨ would be
adopted where applicable to prevent impact to natural streams/rivers; and ¡P
Road gullies would be provided to direct and collect all surface runoff
to the drainage system to minimize site runoff. ¡P
The proposed works site inside or in the proximity of natural rivers
and streams should be temporarily isolated, such as by placing of cofferdam
with silt curtain with lead edge at bottom and properly supported props, to
prevent adverse impacts on the stream water qualities. Other protective
measures should also be taken to ensure that no pollution or siltation occurs
to the water gathering grounds of the work site. ¡P
The natural bottom and existing flow in the river should be preserved
as much as possible to avoid disturbance to the river habitats. If temporary
access track on riverbed is unavoidable, this should be kept to the minimum
width and length. Temporary river crossings should be supported on stilts
above the riverbed. |
Waste Management |
¡P
An on-site environmental co-ordinator should be identified at the
outset of the works. The
co-ordinator shall prepare an Environmental Management Plan (EMP)
incorporating waste management in accordance with the requirements set out in
the ETWB TC(W) No. 19/2005, Environmental Management on Construction Sites.
The EMP shall include monthly and yearly Waste Flow Tables (WFT) that
indicate the amounts of waste generated, recycled and disposed of (including
final disposal site), and which should be regularly updated to ensure waste
mitigation measures are properly implemented; ¡P
Good site practices shall be adopted from the commencement of works to
avoid the generation of waste, reduce cross contamination of waste and to
promote waste minimisation; and ¡P
Under the Waste Disposal (Chemical Waste) (General) Regulation, the
Contractor shall register as a Chemical Waste Producer if chemical wastes
such as spent lubricants and paints are generated on site. Only licensed
chemical waste collectors shall be employed to collect any chemical waste
generated at site. The handling, storage, transportation and disposal of
chemical wastes shall be conducted in accordance with the Code of Practice on
the Packaging, Labelling and Storage of Chemical Wastes and A Guide to the
Chemical Waste Control Scheme both published by EPD |
Ecology |
¡P
The Project Boundary is designed to avoid encroachment of the Lam Tsuen
Country Park and the FSW; ¡P
A detailed vegetation survey will be conducted within the proposed
works areas as well as the Conservation Area before construction to identify
any plant species of conservation importance before construction activities
to be carried out; ¡P
Confining the works within the Project Boundary to avoid disturbance; ¡P
Controlling access of site staff to avoid damage to the vegetation in
surrounding areas; ¡P
Placement of equipment or stockpile in the existing disturbed /
urbanized area within the site boundary
of the Project to minimize disturbance to vegetated areas; ¡P Reinstatement
and enhancement of temporarily affected habitats; ¡P Controlling
of site runoff to prevent impact to natural streams/rivers; and ¡P Reducing Glare / Lighting to minimize disturbance ¡P To reduce collision from birds, the design of noise
barrier will avoid / minimise the use of transparent / reflective materials
or adopt bird-friendly design on the surfaces. |
Land Contamination |
¡P The
Project Proponent shall engage a competent and experienced professional to
prepare a supplementary CAP for EPD's approval when the sites become
accessible; ¡P A CAR which includes the site investigation
sampling and testing results will be prepared for EPD's agreement upon
completion of the site investigation; ¡P If contamination was identified, RAP shall
be also prepared and submitted to EPD for agreement prior to the commencement
of the remediation works; ¡P Upon completion of the remediation, a RR
shall be submitted to EPD for agreement. |
Landscape and Visual |
¡P
Preservation of existing vegetation to minimize landscape impact; ¡P
The landscape of these works areas should be restored to its original
status or new amenity area following the completion of the construction phase
to minimize landscape impact; ¡P
Replanting of disturbed vegetation should be undertaken at the earliest
possible stage during the construction phase to minimize landscape impact; ¡P
The alignment and structures associated with the widened road should
integrate, as far as technically feasible, with existing roadside structures
and the landscape context to reduce the potential cumulative impact of the
proposed works; ¡P
In accordance with DEVB TC(W) No. 7/2015, the compensatory planting
proposal should have the basic primary objective of planting compensatory
trees in a ratio not less than 1:1 in terms of quantity as far as practicable; ¡P
Treatment of retaining walls and slopes to minimize visual and
landscape impact; and ¡P
Provision of visually pleasing aesthetic treatment on noise barriers. |
Alternative options have
been considered in terms of the following aspects:
• Alignment;
• Design alternative;
• Construction method; and
• Construction sequence
For
alignment and design alternatives, the proposed work is aim to upgrading the
existing sub-standard road to a standard road. The road sections of Kam Tin
Road and Lam Kam Road to be upgraded are rural roads which are serving many
existing road side developments, the proposed road alignment thus follows
closely with the existing alignment. The proposed alignment is designed according
to the principle of minimizing land resumption and environmental impacts.
Constructing a new road and/or off-line realigning road will not be one of
optimum and feasible option, especially constructing a new road, which would
incur additional land resumption and bring undesirable impacts to the
environment during and after implementation of these options. Thus, it is
sensible not to adopt such alternative alignment and design for the road
sections of Kam Tin Road and Lam Kam Road and no alternative option would be
expected.
For
construction methods and sequence of construction works alternatives, the
existing Kam Tin Road and Lam Kam Road is the main road to Yuen Long, Fanling
and Tai Po for the residents in Kam Tin. In order to minimize the traffic
impact during implementation of Temporary Traffic Arrangement (TTA), the
upgrading of at-grade road sections is a straight forward construction process
that will not involve complicated construction sequences, the typical work
fronts of maximum 50m in length would be implemented at minimum 600m separation
simultaneously along Kam Tin Road and Lam Kam Road in stages, i.e. bound by
bound. Conventional construction method of open-cut excavation should be
adopted on the upgrading works of existing rural roads in Kam Tin area.
In
view of the existing heavy traffic and potential traffic congestion during peak
hours, under this construction method, although the construction period is
longer, less complicated scheme of traffic diversion and less disturbance to the
existing road side developments would be expected. In addition, the no. of tree
to be affected and temporary land resumption for facilitating the temporary
traffic diversion could be minimized under this construction method. In
conclusion, the above proposed construction method and sequence of works would
be the only one option that is the most cost effective and least adverse impact
to the traffic and public.
In addition, the following measures have also been taken to minimise the
environmental impacts.
Road section between Chainage CHB 43+90 and CHB 49+30 of Lam Kam Road
¡P
Option
A is to widen the carriageway northwards to minimize encroachment of two CA zones
while Option B is to widen southwards. The sections forming the two alternative
options are reviewed and made a detailed comparison, Option A is adopted as the
preferred option. A brief summary of the assessment findings is described
below:
i.
The preferred option reduced the encroachment of CA
zones, resulting in only slight encroachment of the two CA zones at south of
section from CHB 44+30 to CHB 44+80 and CHB 49+00 to CHB 49+30 of Lam Kam Road.
However, the concerned CA zones are at the woodland edge and partly shotcreted respectively,
and hence the potential impact to habitat loss/vegetation clearance is
considered to be low. Detailed ecological impact assessment is in Section 7 of
EIA study report.
ii.
Apart from less CA encroachment, another advantage
of the preferred option is the need to resume relatively small area of private
land.
Road section between Chainage CHB 48+00 and CHB 48+80 of South of Lam
Kam Road
¡P
The southern footway is proposed to be cut back in
order to preserve the existing road side trees thereat.
Road section between Chainage CHB 49+10 and CHB 50+20 of Lam Kam Road
¡P
The preferred option upgrades the carriageway and
the footway, but the carriageway shall not follow
the existing alignment and shift northwards. Such arrangement is to minimize
the extent of CA encroachment at south of section between CHB 49+10 and CHB
50+20 of Lam Kam Road. Besides, considering that extensive geotechnical works will
be required for providing the concerned southern
footway, such
arrangement can reduce waste, noise, air quality, landscape and visual impacts.
The sections of Kam Tin Road and Lam Kam Road to be upgraded are rural
roads serving many road side residence and developments. Hence, the proposed
road alignment follows closely with the existing alignment as far as practical.
In addition, the proposed road alignment is designed based on the principle of
minimising land resumption and environmental impacts. Two options have been proposed
for the upgrading works. The layouts of Option A and Option B are attached in Figure 2.2 respectively. Summary of the
comparison of Option A and Option B based on their environmental benefits and
dis-benefits can be referred to Table 2.2.
Among the two options proposed,
Option A is selected as it will cause less impact on local community, and
involve in smaller scale construction works, which leads to smaller environmental
impact during construction phase. Although Option
A will slightly encroach on CA, the concerned area is a paved footway with
isolated trees, and hence the potential impact to habitat loss/vegetation
clearance is considered to be low.