1.1 Project Background
1.2
Propose of the EIA Study
1.3
Objects of the EIA Study
1.4
Report Structure
FIGURES
Figure 1.1 Indicative Layout of Proposed Scheme
Figure 1.2 Location of Conservation Area
In 2007, Transport Department (TD) and Highways Department
(HyD) proposed to upgrade the remaining sections of Kam Tin Road and Lam Kam
Road to 7.3m (¡§Original Scheme¡¨), which did not cover the upgrading of the road
section of Kam Tin Road between Tung Wui Road and Fan
Kam Road to 10.3m wide.
An Environmental Impact Assessment (EIA) study brief (No.
ESB-170/2007) was issued in October 2007 by the Director of Environmental
Protection under the Environmental Impact Assessment Ordinance.
Assessment on environmental impacts for the ¡§Original
Scheme¡¨ had been carried out. The EIA Report was approved by Environmental
Protection Department (EPD) on 26 June 2009. HyD then applied for Environmental
Permit (EP) on 10 April 2012 and the EP (EP No. EP-439/2012) was granted by EPD
on 7 May 2012. No upgrading works has been carried out after the issuance of EP
in 2012.
According to the traffic survey under the traffic impact
assessment (TIA) conducted by Civil Engineering and Development Department
(CEDD) in November 2015 under Agreement No. CE 34/2014 (CE) ¡§Site Formation and
Infrastructure Works for the Initial Sites at Kam Tin South, Yuen Long ¡V
Investigation, Design and Construction¡¨, the volume to capacity (v/c) ratio of
the road section of Kam Tin Road between Tung Wui
Road and Fan Kam Road has exceeded 1.2. Taking into account the TIA findings by
CEDD, TD considers if the ¡§Original Scheme¡¨ is to be implemented (i.e.
upgrading the concerned road section of Kam Tin Road to a standard 7.3m wide
carriageway), the v/c ratio would still be very close to 1.2 having regard to
full population intake of the Kam Tin South Development in 2031. Therefore, TD
determined that there was a need to upgrade the road section of Kam Tin Road
between Tung Wui Road and Fan Kam Road to 10.3m wide
(¡§New Scheme¡¨) to bring down the v/c ratio below 1.0 to cater for the planned
development.
The scope of the ¡§New Scheme¡¨ which involves the upgrading of the
existing road sections and footpaths on both sides of Kam Tin Road and Lam Kam
Road are as follows:
(b) upgrading of the road section of
Kam Tin Road (between Tung Wui Road and Fan Kam Road)
to a 10.3m wide carriageway;
(c) provision of 2m wide footpaths on
both sides (if site conditions do not allow, 2m wide footpath on one side will
be acceptable) and associated improvement of pedestrian facilities, public transport
laybys and right-turning lanes at major junctions at Kam Tin Road & Kam Tai
Road and Kam Tin Road & Wang Toi Shan Shan Tsuen
Road; and
(d) Associated slope and drainage
works, traffic aids and street lighting modification, landscaping works, etc.
under the project.
The proposed upgrading works do not include any
expressway, trunk road, primary distributor road or district distributor road,
road or railway tunnel more than 800m in length between portals, and road or
railway bridge more than 100m in length between abutments. As such, the project does not constitute
Designated Project (DP) under Schedule 2 Part 1 Categories A1, A7 and A8 of the
Environmental Impact Assessment Ordinance (EIAO) (Cap. 499). However, the proposed upgrading works
encroach upon existing conservation areas. Hence, the upgrading of remaining
sections of Kam Tin Road and Lam Kam Road (which is hereafter referred to as
the ¡§Project¡¨), is classified as Designated Project under Schedule 2 Part 1
Category Q.1 of the EIAO and it requires an environmental permit before works
commencement.
The Project location is shown in Figure 1.1 and Conservation Area near the Project
area is shown in Figure 1.2.
The construction
works are anticipated to commence in early 2021 with completion of the Project in
mid-2025. However, the actual programme is subject to review depending on the
progress of the Project.
Project profile of the Project
(Register No. PP-571/2018) was submitted on 11 October 2018 for application for
an EIA Study Brief. Subsequently, a
Study Brief (Register No. ESB-310/2018) was issued by EPD on
22 November 2018.
The purpose of the EIA Study is
to provide information on the nature and extent of environmental impacts
arising from the construction and operation phases of the Project and the
recommended mitigation, and related activities from the interface projects that
take place concurrently. This information will contribute to decisions on:
¡P
the overall acceptability of any adverse environmental consequences that
are likely to arise as a result of the Project;
¡P
the conditions and requirements for the detailed design, construction and
operation of the Project to mitigate against adverse environmental consequences
wherever practicable; and
¡P
the acceptability of residual impacts after the proposed mitigation measures
are implemented.
The EIA Study has been conducted
and completed in accordance with the requirements of the EIA Study Brief under
the EIAO and the guidelines on assessment methodologies provided in the
Technical Memorandum on Environmental Impact Assessment Process (hereinafter
referred to as the EIAO-TM). The
EIA Report has been prepared:
i.
to describe the Project and associated works together with the
requirements and environmental benefits for carrying out the Project;
ii.
to identify and describe elements of the community and the environment
likely to be affected by the Project and/or likely to cause adverse impacts to
the Project, including natural and man-made environment and the associated
environmental constraints;
iii.
to identify and quantify emission sources and determine the significance
of impacts on sensitive receivers and potential affected uses;
iv.
to identify and quantify contaminated land within any project area for
development works, and to propose measures to avoid disposal in the first
instance.
v.
to identify and quantify any potential losses or damage to flora, fauna
and natural habitats;
vi.
to identify and evaluate any potential landscape and visual impacts and
to propose measures to mitigate these impacts;
vii.
to propose measures/actions to avoid or minimise potential archaeological
impact if any archaeological remains are identified during construction phase of
the Project;
viii.
to propose the provision of infrastructure or mitigation measures so as
to minimize pollution, environmental disturbance and nuisance during construction
and operation phases of the Project;
ix.
to investigate the feasibility, effectiveness and implications of the
proposed mitigation measures;
x.
to identify, predict and evaluate the residual environmental impacts (i.e.
after practicable mitigation) and the cumulative effects expected to arise
during the construction and operation phases of the Project in relation to the
sensitive receivers and potential affected uses;
xi.
to identify, assess and specify methods, measures and standards, to be
included in the detailed design, construction and operation of the Project
which are necessary to mitigate these residual environmental impacts and
cumulative effects and reduce them to acceptable levels;
xii.
to design and specify environmental monitoring and audit (EM&A) requirements;
and
xiii.
to identify any additional studies necessary to implement the mitigation
measures or monitoring and proposals recommended in the EIA report.
This EIA Report is
organised as follows:
Section 1 ¡V Introduction
Section 2 ¡V Project
Description
Section 3 ¡V Air Quality
Impact
Section 4 ¡V Noise Impact
Section 5 ¡V Water Quality
Impact
Section 6 ¡V Waste
Management Implication
Section 7 ¡V Ecological
Impact
Section 8 ¡V Land
Contamination
Section 9 ¡V Landscape and
Visual Impact
Section 10 ¡V Environmental
Monitoring and Audit (EM&A) Requirements
Section 11 ¡V Summary of Environmental
Outcomes
Section 12 ¡V Implementation
Schedule of Recommended Mitigation Measures
Section 13 ¡V Conclusions