2.0....... PROJECT DESCRIPTION
2.1 Project Objectives
2.2
Project Location and Site History
2.3
Need of Project
2.4
Project Scope and Design
2.5 Encroachment of the Conservation Areas and Works adjacent to the Existing
Watercourses
2.6
Consideration of Alternative Options
2.7
Construction Method and Sequence
2.8
Construction Programme
2.9
Summary of Environmental Designs
Recommended and Environmentally Friendly Options
Considered
2.10 Collating and Addressing Public Views
2.11 Concurrent Projects
2.12 Operation Traffic Forecast
2.13 Cultural Heritage Implications
FIGURES
Figure 2.1 Location of Encroachment of the Project Area into Conservation
Area
Figure 2.2 Exploration
of Alternative Schemes
Figure
2.3 (Not
used)
Figure 2.4 General
Layout Plan
Figure 2.5 Proposed
Preliminary Works Stages
Figure 2.6 Location
of Concurrent Projects
Figure 2.7 Location
of Pat Heung Sheung Tsuen Site of Archaeological Interest
APPENDICES
Appendix 2.1 Traffic Flow Data of Year 2040
Appendix 2.2 Letter of Acceptance by the
Transport Department
Appendix 2.3 Tentative Construction Works
Programme
The remaining unimproved sections of Kam Tin Road and Lam
Kam Road are Kam Tin Road section between Tung Wui Road and Lam Kam Road; and
Lam Kam Road section between Kam Tin Road and Kadoorie Farm. These remaining
sections are single two-lane carriageway with substandard width. Road safety
problems are compounded by overtaken vehicular traffic, sharp bends, hidden
accesses, sub-standard gradients, inadequate lateral clearance, frequent usage
of heavy vehicles, insufficient pedestrian crossing facilities and insufficient
bus laybys.
The Project is to upgrade the remaining sections of Kam Tin
Road and Lam Kam Road to a standard single two-lane carriageway, with the
associated improvement of pedestrian facilities and provision of public
transport laybys.
The Project is located at Kam
Tin Road section between Tung Wui Road and Lam Kam Road; and Lam Kam Road
section between Kam Tin Road and Kadoorie Farm. Figure 1.1 shows the location of the
Project.
Kam Tin Road was constructed in
1964 and the surrounding areas were mainly occupied by farmland and village
housing. Lam Kam Road was
constructed in 1952 and mainly surrounded by undeveloped land. Based on review of historical aerial
photographs, there was no apparent change in the road alignment noted in the
period from 1991 to 1995. Village
houses, clinic, open storage areas, parks and barracks were developed around
the Project Boundary from 1991 to 2004.
Since then, there was no further change in road alignment / layout
within the Project Boundary by 2018.
The need to upgrade the
remaining sections of Kam Tin Road and Lam Kam Road was recognized in the
Project Definition Statement (PDS) issued by the Environment, Transport and
Works Bureau (ETWB) in January 2007.
According to the traffic survey under the traffic impact assessment
(TIA) conducted by Civil Engineering and Development Department (CEDD) in
November 2015 under Agreement No. CE 34/2014 (CE) ¡§Site Formation and
Infrastructure Works for the Initial Sites at Kam Tin South, Yuen Long ¡V
Investigation, Design and Construction¡¨, TD determined that there was a need to upgrade the road
section of Kam Tin Road between Tung Wui Road and Fan Kam Road to a 10.3m wide
carriageway and the road section of Kam Tin Road (between Fan Kam Road and Lam
Kam Road) and Lam Kam Road to a standard single two-lane carriageway of at
least 7.3m wide to cater for the future development. The entire alignment under this Project is currently
a single two-lane carriageway with sub-standard width. Road safety problems are compounded by overtaken
vehicular traffic, sharp bends, hidden accesses, sub-standard gradients,
inadequate lateral clearance, frequent usage of heavy vehicles, insufficient
pedestrian crossing facilities and lack of bus laybys.
Scenarios with and without the Project
is compared according to their benefits and disbenefits, as shown in Table 2.1.
Table 2.1 Comparison between scenarios with and
without the Project
|
Scenario with Project |
Scenario without Project |
Social Benefit |
l
The traffic from future development can be catered l
Associated improvement of pedestrian facilities, public transport
laybys, slope and drainage works, traffic aids and street lighting
modification and landscaping works l
Improved road safety in Operation Phase due to carriageway and
footpath improvement works |
l
Daily life of residents is not affected during construction phase |
Social Disbenefit |
l
Daily life of residents is affected during construction phase |
l
Kam Tin Road and Lam Kam Road will not be able to cater for the
number of vehicles after the development of Kam Tin South in 2031 |
Environmental Benefit |
l
Increased noise protection due to direct noise mitigation measures
such as noise barriers based on the findings from noise impact assessment.
Existing traffic noise impact on the nearby sensitive receivers along Kam Tin
Road and Lam Kam Road can be alleviated as much as practicable l
Better visual impact in operation phase due to renewal of the
existing road surface and associated auxiliary facilities along Kam Tin Road
and Lam Kam Road, and aesthetic noise barrier l
New trees and plants will be planted along roadside |
l
No tree felling in construction phase l
No air quality, noise impact to nearby residents and natural habitat during
construction phase l
No landscape impact during construction phase |
Environmental Disbenefit |
l
Dust and noise will be generated during construction phase l
Impact or disturbance to natural habitat and wildlife during construction
phase l
Tree felling during construction phase l
Landscape impact during construction phase |
l
Existing traffic noise problem is not resolved |
From Table 2.1, it
is shown that for scenario without the Project, the only benefit is no
construction environmental impacts to the nearby sensitive receivers along Kam
Tin Road and Lam Kam Road. On the other hand, for scenario with the Project, it
will involve renewal of road surface, construction of associated auxiliary
facilities, and provision of noise mitigation measures such as noise barriers
based on the findings from noise impact assessment. The environmental benefits
of the Project include better visual view with the carriageway
improvement works and aesthetic noise barrier, and more mitigation for existing
traffic noise impact during operation phase of the Project. Despite the
upgrading works would be generating dust and noise impacts and causing
impacts or disturbance on nearby natural habitat and wildlife during
construction phase, most of the environmental demerits are considered as
short-term and can be minimised with proper on-site mitigation measures, while
the benefits of the Project are permanent, it is expected that the upgrading
works can improve the nearby environment.
The total length of the remaining sections of Kam Tin Road
and Lam Kam Road to be upgraded under this Project is approximately 5.3 km. The
scope of the Project includes the following:
(a) Upgrading of the remaining
unimproved sections of Kam Tin Road (between Fan Kam Road and Lam Kam Road) and Lam Kam
Road from a substandard single two-lane carriageway to a standard carriageway of
at least 7.3m wide;
(b) Upgrading of the road section of
Kam Tin Road (between Tung Wui Road and Fan Kam Road) to a 10.3m wide
carriageway;
(c) Provision of 2m wide footpaths
on both sides (if site conditions do not allow, 2m wide footpath on one side
will be acceptable) and associated improvement of pedestrian facilities, public
transport laybys and right-turning lanes at major junctions at Kam Tin Road
& Kam Tai Road and Kam Tin Road & Wang Toi Shan Shan Tsuen Road; and
(d) Associated slope and drainage
works, traffic aids and street lighting modification, landscaping works, etc.
under the Project.
The Project comprises the following works:
(a) Site Clearance & Utility
Diversion;
(b) Road Upgrading Works (Backfill
and reinstatement works);
(c) Street Furniture & Soft
Landscape Works;
(d) Excavation and Lateral Support
(ELS) Works (Sheet piling and excavation works);
(e) Foundation and Substructure
Works (Rebar fixing and concreting works);
(f) Geotechnical Works (Soil nail
works); and
(g)
Construction of
Superstructure Works (Noise mitigation works), if necessary.
The Project is a Designated Project (DP) since part of the
proposed upgrading works encroaches upon the Conservation Area (CA) zoning as
defined on relevant Outline Zoning Plans of Shek Kong (Plan no.: S/YL-SK/9) and
Pat Heung (Plan no.: S/YL-PH/11).
There are four encroachment areas which are shown in Figure
2.1, and described below:
CA at north of section between Chainage CHB
28+70 and CHB 30+10 of Kam
Tin Road (Figure 2.4j)
¡P
The proposed works
within CA are geotechnical works such as soil
nailing to upgrade the existing slope after cut-back and
reconstruction of existing footpath.
The concerned works are not arising from the change of road
alignment. The proposed
works are to upgrade the existing road side slope which is
assessed to be below the current safety standards. The shotcreted slope with vegetation on top would be cut-back
slightly to resume the least area for the proposed footpath and would not
affect the graves above the concerned slope. The
footpath reconstruction is required from maintenance viewpoint.
CA at south of section between Chainage CHB
44+30 to CHB 44+80 of Lam Kam Road (Figure 2.4o)
¡P
The proposed works
within CA are widening of existing carriageway, and reconstruction of existing
footpath and carriageway. The works area encroached into the CA zone are currently paved
footpath with carriageway and mixed woodland edge as inspected on site.
CA at south of section between Chainage CHB
49+00 to CHB 52+30 of Lam Kam Road (Figure 2.4p and 2.4q)
¡P
The area within CA zone is a shortcreted slope with trees.
¡P
For road section between chainage CHB 49+00 CHB 50+40, the existing
slopes would be cut back for widening of carriageway and construction of
footpath. The proposed works within CA zone are construction of footpath,
extension of box culvert at chainage CHB 49+20 (south), construction of a retaining
wall and geotechnical works such as soil nailing to upgrade the existing road
side slopes which are assessed to be below the current safety standards.
¡P
For road section between chainage CHB 50+40 CHB 51+20, the existing
slope would be cut back for the widening of carriageway and construction of
footpath. The proposed works within CA zone are construction of a retaining wall and
geotechnical works such as soil nailing to
upgrade the existing road side slopes which are assessed to be below the
current safety standards.
¡P
For road section between chainage CHB 51+20 CHB 52+30, the existing slope
shall be cut back for the widening of carriageway and reconstruction of
footpath. The proposed works within CA zone are construction of a retaining wall and geotechnical
works such as soil nailing to upgrade the existing road side slopes which
are assessed to be below the current safety standards.
¡P
To summarize the above, the proposed works
within CA are widening and reconstruction of carriageway and footpath,
extension of box culvert, soil nailing of existing slopes and construction of earth
retaining wall. The concerned works
are not arising from change of road alignment. The proposed soil nailing is to
upgrade the existing road side slopes which are assessed to be below the
current safety standards. The proposed retaining wall is a safety measure to
protect road users against the identified potential natural terrain hazards.
CA at north of section between Chainage CHB
50+20 to CHB 52+40 of Lam Kam Road (Figure 2.4 p and 2.4q)
¡P
The area within CA zone is an existing slope covered with herbaceous
plants and a few trees and shrubs.
¡P
For road section between CHB 50+20 to CHB 51+30, the existing topography
is downhill profile, the existing slope will be filled and the fill slope with
geotechnical works such as soil nailing is proposed to resume the additional area
for the widening of carriageway and reconstruction of footpath and meet the
current safety standards of slope.
¡P
For road section between
¡P
In conclusion, the proposed works
within CA are widening of existing footpath and carriageway, soil nailing of existing
slope, and filling of slope. The proposed soil nailing are to upgrade the existing
slopes, which are assessed to be below current safety standards.
There are nine road sections which are adjacent to or even
across the existing watercourses, the locations are shown in Figure
2.4 and 7.1 and described below:
Watercourse (channelized) at the western end of
the project site along Tung Wui Road (Figure 2.4a)
¡P
No works are proposed
to construct inside or in the proximity of the watercourse.
Watercourse (channelized) adjacent to north of
section at Chainage CHA 6+40 of Kam Tin Road (Figure 2.4c)
¡P
The proposed works
near to the channelized watercourse are widening of existing carriageway, and
reconstruction of existing footpath and carriageway. The existing
watercourse near the roadside would be partially decked over for road widening.
No encroachment into the existing watercourse shall be expected.
Watercourse (meander) adjacent to north of
section between Chainage CHA 8+00 to CHA 9+10 of Kam Tin Road (Figure 2.4d)
¡P
The proposed works
adjacent to meander are widening of existing carriageway, rehabilitation of
gabion wall, and reconstruction of existing footpath and carriageway. As
inspected on site, Shek Kong Barrack is situated on the south of section of Kam
Tin Road whereas the existing gabion wall is located on the north of
section of Kam Tin Road. For achieving the widening works, it is inevitable to shift the
boundary of the gabion walls and the existing slope toe at north towards the
meander side. During the particular seasons of construction stage, cofferdam
with silt curtain would be erected to separate the proposed works area (within the existing slope area)
from the existing meander. The existing gabion wall would then be removed
and will be rehabilitated
after
the completion of road widening and reconstruction of footpath and carriageway.
There will be no encroachment into the existing river bed of the meander.
Watercourse (channelized) adjacent to north of
section between Chainage CHA 14+30 to 14+40 of Kam Tin Road (Figure 2.4e)
¡P
The proposed works
near to the channelized watercourse are widening of existing carriageway, and
reconstruction of existing footpath and carriageway. The existing watercourse was
channelized under the project of The Hong Kong section of the
Guangzhou-Shenzhen-Hong Kong Express Rail Link (XRL) for the construction of Shek Kong Stabling Sidings. The proposed road widening works including reconstruction of
footpath and carriageway would be far from the channelized
watercourse and would not encroach into the
existing watercourse.
Watercourse (semi-natural) across road section
between Chainage CHB 33+70 (north) and CHB 33+90 (south) of Kam Tin Road
(Figure 2.4k)
¡P
The proposed works across
the semi-natural watercourse are upgrading of existing carriageway, and
reconstruction of existing footpath and carriageway. The existing Kam Tin Road
will be upgraded to a standard carriageway with minor increase of road width.
The
existing paved areas are sufficient for road upgrading as inspected on site. No
encroachment into the existing watercourse shall be expected.
Watercourse (channelized) across road section
between Chainage CHB 36+20 (north) to CHB 35+90 (south) of Kam Tin Road (Figure
2.4l)
¡P
The proposed works across
the channelized watercourse are upgrading of existing carriageway, and
reconstruction of existing footpath and carriageway. The proposed works and
site condition are similar to the road section
between Chainage CHB 33+70 (north) and CHB 33+90 (south) of Kam Tin
Road. The
existing paved areas are sufficient for road upgrading as inspected on site. No
encroachment into the existing watercourse shall be involved.
Watercourse (semi-natural) across road section
between Chainage CHB 41+10 (north) to CHB 41+40 (south) of Lam Kam Road (Figure
2.4n)
¡P
The proposed works
encroaching into the semi-natural watercourse are upgrading of existing
carriageway, extension of existing box culvert, and reconstruction of existing
footpath and carriageway. Due to the upgrading and realignment of Lam Kam Road,
the
existing box culvert would be required to be extended along the existing watercourse
at north under the realigned Lam Kam Road. Cofferdam
with silt curtain would be adopted for the construction of box culvert to avoid
the existing watercourse from contamination during the construction stage. Construction of the box culvert would
also be carried out by traditional method such as precast units to minimize the
impacts to the watercourse. The
extension works would be carried out
during dry seasons in order to minimize the drainage and ecological impacts to
the existing watercourse. The adopted construction methods would depend on the
site constraints such as topography and geology during the construction stage.
During the construction stage, the Contractor would be required to provide
measures such as sediment tanks and septic tanks and obtain a discharge licence
from relevant authorities to ensure the surface runoff and sewage from
construction activities do not cause adverse impact to the water bodies.
Watercourse (semi-natural) at road section
between Chainage CHB 48+80 (north) to CHB 49+20 (south) of Lam Kam Road (Figure
2.4p)
¡P
The proposed works
encroaching into the semi-natural watercourse are upgrading of existing
carriageway, extension of existing box culvert, and reconstruction of existing
footpath and carriageway. Due to the upgrading and realignment of Lam Kam Road, geotechnical works such as soil nailing and construction of retaining wall
are proposed to upgrade two existing slopes at two sides of the road,
which are assessed to be below current safety standards. The
existing box culvert is thereof extended under the realigned Lam
Kam Road and existing slopes, the cofferdam with silt curtain would be one of the feasible schemes for the construction of box culvert to prevent
the existing watercourse from contamination during the construction stage.
Construction of the box culvert
would also be carried out by traditional method such as precast units to
minimize the impacts to the watercourse. The
extension works would be carried out
during dry seasons in order to minimize the drainage and ecological impacts to
the existing watercourse. The adopted construction methods would depend on the
site constraints such as topography and geology during the construction stage.
During the construction stage, the Contractor would be required to provide
measures such as sediment tanks and septic tanks and obtain a discharge licence
from relevant authorities to ensure the surface runoff and sewage from
construction activities do not cause adverse impact to the water bodies.
Watercourse (semi-natural) across road section
at Chainage CHB 53+20 (north) of Lam Kam Road (Figure 2.4q)
¡P
No works are proposed
to construct at the semi-natural watercourse which is outside the Project Boundary
but within the assessment area.
Alternative options have been considered in terms of the following
aspects:
¡P
Alignment;
¡P
Design;
¡P
Construction method;
and
¡P
Construction
sequence.
For alignment and design alternatives, the proposed work is aimed to
upgrade the existing sub-standard road to a standard road. The road sections of
Kam Tin Road and Lam Kam Road to be upgraded are rural roads which are serving
many existing roadside developments. To minimize the impacts to the existing
roadside developments, the proposed road alignment thus follows closely with
the existing alignment. The proposed alignment is designed according to the
principle of minimizing land resumption and environmental impacts. Constructing
a new road and/or off-line realigning road will not be one of optimum and
feasible options, especially constructing a new road, which would incur
additional land resumption and bring undesirable impacts to the environment
during and after the new road construction. Thus, it is considered that such
alternative alignment and design for the road sections of Kam Tin Road and Lam
Kam Road should not be pursued.
For construction methods and sequence of construction works alternatives,
the existing Kam Tin Road and Lam Kam Road are the main roads to Yuen Long,
Fanling and Tai Po for the residents in Kam Tin. In order to minimize the
traffic impact during implementation of Temporary Traffic Arrangement (TTA),
the upgrading of at-grade road sections is a straight forward construction
process that will not involve complicated construction sequences. Typical work
fronts of maximum 50m in length would be implemented at minimum 600m separation
simultaneously along Kam Tin Road and Lam Kam Road in stages, i.e. lane by
lane. Conventional construction method of open-cut excavation should be adopted
on the upgrading works of existing rural roads in Kam Tin area.
In
view of the existing heavy traffic and potential traffic congestion during peak
hours, using this construction method, although involves a longer construction
period, less complicated scheme of traffic diversion and less disturbance to
the existing roadside developments would be expected. In addition, the number
of trees to be affected and temporary land resumption required facilitating the
temporary traffic diversion could be minimized using this construction method.
In conclusion, the above proposed construction method and sequence of works are
considered to be the most cost effective causing least adverse impact to the
traffic and public.
In addition, the following measures have also been taken to minimise the
environmental impacts.
Road section between
Chainage CHB 43+90 and CHB 49+30 of Lam Kam Road
¡P
Option A is to widen the carriageway northwards to minimize
encroachment of two CA zones while Option B is to widen southwards. The
sections forming the two alternative options are reviewed and made a detailed
comparison, Option A is adopted as the preferred option. A brief summary of the
assessment findings is described below:
i.
The preferred option reduced the encroachment of CA
zones, resulting in only slight encroachment of the two CA zones at south of
section from CHB 44+30 to CHB 44+80 and CHB 49+00 to CHB 49+30 of Lam Kam Road.
However, the concerned CA zones are at the woodland edge and partly shotcreted
respectively, and hence the potential impact to habitat loss/vegetation
clearance is considered to be low. Detailed ecological impact assessment is in
Section 7 of EIA study report.
ii.
Apart from less CA encroachment, another advantage
of the preferred option is the need to resume relatively small area of private
land.
Road section between
Chainage CHB 48+00 and CHB 48+80 of South of Lam
Kam Road (Figure 9.11p)
¡P
The southern footway is proposed to be cut back in
order to preserve the existing road side trees thereat.
Road section between
Chainage CHB 49+10 and CHB 50+20 of Lam Kam Road
¡P
The preferred option upgrades the carriageway and
the footway, but the carriageway shall not follow
the existing alignment and shift northwards. Such arrangement is to minimize
the extent of CA encroachment at south of section between CHB 49+10 and CHB
50+20 of Lam Kam Road. Besides, considering that extensive geotechnical works
will be required for providing the concerned southern
footway, such
arrangement can reduce waste, noise, air quality, landscape and visual impacts.
The sections of Kam Tin Road and Lam Kam Road to be upgraded are rural
roads serving many road side residence and developments. Hence, the proposed
road alignment follows closely with the existing alignment as far as practical.
In addition, the proposed road alignment is designed based on the principle of
minimising land resumption and environmental impacts. Two options have been proposed
for the upgrading works. The layouts of Option A and Option B are attached in Figure 2.2 respectively. Below Table 2.2 summarises the comparison of
Option A and Option B based on their environmental benefits and dis-benefits:
Table 2.2 ¡V Comparison of Option A and Option B
|
Option A (Selected) |
Option B |
Environmental
Benefit |
l Less encroachment
on CA zone l Avoid affecting the
existing slopes |
l Comparatively
further away from air and noise sensitive receivers |
Environmental
Disbenefit |
l Closer to air and
noise sensitive receivers |
l Slight encroachment
on CA l Require larger land
resumption |
Among the two options
proposed, Option A is selected as it will cause less impact on local community,
and involve in smaller scale construction works, which leads to smaller
environmental impact during construction phase. Although Option A will slightly
encroach on CA, the concerned area is a paved footway with isolated trees, and
hence the potential impact to habitat loss/vegetation clearance is considered
to be low.
The proposed land use
of this Project is rural road. The land taken by the Project, including that
for associated access arrangements and auxiliary facilities, is shown in Figure 2.4.
The upgrading works are to be carried out by
conventional method of open-cut excavation to minimize impact and ensure road
safety to the existing traffic as concerned by the relevant authorities. The
construction sequence is to shift in stages with two-way traffic maintained
throughout the construction period. The construction method and sequence to be
adopted for the Project are based on engineering, site constraints and environmental
considerations. Details of the construction methods are presented in below Table 2.3.
Table 2.3 Construction Methods of the Proposed Upgrading Works
Construction Activities |
Construction Methodology |
1. Site Clearance & Utility Diversion |
The proposed site clearance and utilities
works include temporary road, drainage systems and utility diversion to be
carried out in advance of road upgrading works. |
2. Road Upgrading Works (Backfill and
reinstatement works) |
Road works will be carried out section by
section and the length of each active section of the construction site is
maximum 50m; and based on preliminary design arrangement by the Project
Engineer (the Consultant appointed by Highways Department to carry out the
design of the Project), the minimum separation of each active section of the
construction site is 600m. The works involve earthworks, utilities laying,
backfilling, laying of sub-base materials and reinstatement of bituminous or
concrete pavement with low-noise road surfacing as applicable. |
3. Street Furniture & Soft Landscape Works |
Street furniture and landscape works at roadside and
slopes will be provided after road upgrading works. These will mainly involve
planting and pedestrian crossing facilities. |
4. ELS Works (Sheet piling and excavation works) |
The excavation and lateral support (ELS) is to be carried
out by layers. Part of the inert Construction & Demolition material would
be reused within the Project as far as practicable. Conventional earthwork
cut and fill machineries will be used for the proposed fill slopes. |
5. Foundation and Substructure Works (Rebar
fixing and concreting works) |
The retaining wall and substructures of the noise barrier
will be in form of reinforced concrete (RC) stem walls and base slabs founded
on grade. Traditional method such as precast unit would
be adopted for the extension of box culvert. Cofferdam with silt
curtain would be erected to limit the works footprint and avoid the existing
watercourse from contamination during the construction stage. The construction will have to be carried out during dry seasons
with less disturbance to the watercourses. Temporary drainage arrangement
will also be developed during the construction stage to avoid impact to the
watercourse. |
6. Geotechnical Works (Soil nail works) |
Near the hillside, considerably large scale soil nail is required
to meet the current safety standard. |
7. Construction of Superstructure Works (Noise mitigation
works) |
Regarding the superstructure, given the long total length
of noise barriers and limited working space, prefabricated frames and panels will
be usually adopted and erected on site with appropriate temporary traffic
arrangement. The superstructure will be in form of typical steel
structures. |
The Project construction works are anticipated to commence
in 2021 for completion by 2025. Each active construction activity location shall be at one
lane of the road alignment at any one time since long road closure on one lane
for single carriageway is not allowed under TTA.
Road works will be carried
out section by section and the length of each work front of the construction
site is maximum 50m; and based on preliminary design arrangement by the Project
Engineer, the minimum separation of each work front of the construction site is
600m. Construction sequence at each
section of the Project road is shown in Figure 2.5. Tentative
construction works programme is given in Appendix 2.3.
Avoidance of environmental impacts has been one of the key
considerations throughout the entire project development and design. For those
impacts that could not be avoided, due consideration has been given to minimise
those impacts as much as practicable.
A summary of these approaches
for minimising the environmental impacts is given below:
l Minimisation of impacts to Conservation Area;
l Preservation of habitats with ecological value;
l Avoidance of impacts to sensitive receivers along Kam Tin
Road and Lam Kam Road;
l Avoidance of impacts to natural watercourses; and
l Provide compensation planting for mitigating landscape and
visual impact.
Details of
environmental designs can be referred to Chapter 11 of this Report.
Comments Received During the EIA
Process
During the course of the EIA study, comments obtained from
consultations with the public had been duly revisited and were incorporated in
the design and construction of the Project where appropriate. The following table summarises all these
comments and how the Project Proponent has addressed them suitably.
Table
2.4 Summary of key comments and approaches adopted to address comments
collated
Issue |
Comments |
Responses
& Approaches Adopted |
Water Quality |
The layout/footprint of the development should avoid
watercourses and there should be buffer zones along
these watercourses to prevent the encroachment of the development. Under the
TM-EIAO, avoidance is considered to be the best solution to reduce impacts
caused by a development. We (the public) hope that the HyD, as the proponent
of this Project, can play a leading role to demonstrate this to the public.
We (the public) would also like to remind you (HyD) that these watercourses
eventually drain into the Deep Bay Area and there is a ¡§Zero Discharge
Policy¡¨ in the area. |
For any construction works in close proximity of nearby
water bodies, the practices outlined in ETWB TC (Works) No. 5/2005
¡§Protection of natural streams/rivers from adverse impacts arising from
construction works¡¨ will also be adopted where applicable to minimize the
water quality impacts upon any natural streams or surface water systems.
Details can be referred to Chapter 5 of this Report. |
While the Project proponent mandates the Contractors to
set up ¡§vehicle wheel and body washing facilities at site exits¡¨ which will
generate murky and probably toxic wastewater, no corresponding clauses are
provided to incorporate in the contract to prohibit the Contractors to
discharge such wastewater to water channels. |
For wheel washing water, wheel-wash overflow will be
directed to silt removal facilities before being discharged to the storm
drain. The site boundary between the wheel washing facility and the public
road should be placed with sand bunds to prevent wheel-wash overflow from
entering public road drains. Details can be referred to Chapter 5 of this
Report. |
|
More concrete measures and surveillance plans should be
proposed to prevent construction site runoff, debris, refuse, liquid spillage
and sewage effluent from discharging into river channel directly, through
stormwater drains or surface runoff. |
For rubbish and litter, good site practices will be
adopted to remove rubbish and litter from construction sites so as to prevent
them from spreading from the site area. Surface run-off from construction
sites will be discharged into storm drains via sand/silt removal facilities
such as sedimentation basin/tank. Earth bunds or sand bag barriers with
tarpaulin sheet should be provided on site boundaries to intercept surface run-off
from outside the site. Details can be referred to Chapter 5 of this Report. |
|
Waste |
More concrete measures and surveillance plans should be
proposed to prevent construction and demolition waste and other wastes
generated from the Project from dumping improperly. |
In order to monitor, document and verify the disposal of
C&D materials at landfills and public fill reception facilities, as
appropriate, and to control fly tipping, a trip-ticket system in accordance
with DEVB TC(W) No. 6/2010 Trip Ticket System for Disposal of Construction
and Demolition Materials should be implemented. Details can be referred to
Chapter 6 of this Report. |
Ecology |
There are watercourses that may be affected by the
proposed works. These watercourses may provide habitats for the globally
endangered Platysternon megacephalum (Big-Head Turtle) |
9-month ecological survey (September 2018 to May 2019)
has been conducted covering both wet and dry seasons. No Platysternon megacephalum had been recorded in both the area
within Project Boundary and Assessment Area. Some works including rehabilitation of gabion wall, and
extension of existing box culvert will be conducted near semi-natural
watercourses within the Project Boundary. The direct impact due to habitat
loss for the semi-natural watercourse is considered minor. Construction works
at and close to the water body should be carried out in dry season as far as
practicable; the works inside or in the proximity of watercourse should be
temporarily isolated by placing of cofferdam with silt curtains to prevent
adverse ecological and water quality impacts. Details can be referred to Chapter 7 of this Report. |
Although mitigation measures proposed will make reference
to the ecological survey results, neither the survey results nor the mitigation
measures are disclosed in this Project Profile. The survey period has also
not been mentioned. |
9-month ecological survey (September 2018 to May 2019)
has been conducted covering both wet and dry seasons and mitigation measures
have been proposed based on the survey findings. Details can be referred to
Chapter 7 of this Report. |
|
Landscape |
Whether any trees will be affected by the Project and any
tree survey has been conducted. |
A tree survey was undertaken. After due considerations of
the latest condition of the tree including both size, health, form, amenity
value, as well as chance of survival after transplanting, 43 number of trees
are considered to be suitable for transplanting and 756 number of trees would
require felling for the implementation of the Project with proper mitigation
measures. Details can be referred to Chapter 9 of this Report. |
Comments Received from Traffic
& Transportation Committee and Rural Committee
Meetings presenting the Project were
held with the Rural Committee (RC) of Kam Tin and Pat Heung on 18, 24 April and
7 May 2019 respectively. The Project was also presented during the meetings
held with Traffic & Transportation Committee (T&TC) of Yuen Long District
Council and Tai Po District Council on 11 and 12 July 2019 respectively. The RC
and T&TC members supported the Project.
Views from both T&TC and RC
were taken to culminate into the current proposed design of the Project. The
Project is thus recommended as it is considered best meeting the aspirations of
the residents and road users in Kam Tin and Pat Heung while maintaining
technical feasibility with incorporation of environmental considerations.
The other existing, committed and
planned projects which are in interaction or in interface with the Project are
considered as having potential cumulative environmental impact with the Project
that may have a bearing on the environmental acceptability of the Project.
There will be four concurrent projects identified in the vicinity (within 500m
from the Project Boundary) of the Project.
As all the concurrent projects
would be land-based and provided that proper mitigation measures would be
proposed in environmental assessments and implemented in future construction
and operation phases, only local-scale impacts arising from these projects are
anticipated.
Table 2.5 and Figure 2.6
summarise the potential concurrent projects that would contribute to the
cumulative environmental impacts during construction and/or operation phase.
Table
2.5 Potential Concurrent Project
Concurrent Projects |
Project Proponent |
Designated Project |
Construction Programme |
Potential Cumulative
Impacts |
|
Construction Phase |
Operation Phase |
||||
Development of Organic Resources Recovery Centre (ORRC)
(Phase 3) |
EPD |
Yes |
Tentatively scheduled to commence in 2023 and complete by
2026 |
Potential cumulative construction dust, construction
noise, water quality, ecological and landscape impacts are anticipated. However, the cumulative impacts are not able to be taken
into account in this study as no detail information, construction methods,
activities and plant inventory can be provided from the concurrent project.
Nevertheless, according to EIAO, an EIA study will be conducted under this
concurrent project, and the cumulative impact will be assessed in the study. |
Potential cumulative air quality and ecological impacts from
road traffic and increased human activities are anticipated. Yet, due to the nature of existing usage of Kam Tin Road
and Lam Kam Road, further road widening works of the Project would not cause
significant impacts to the fauna during operation phase. However, the cumulative impacts are not able to be taken
into account in this study as no detail information such as design and
operation details can be provided from the concurrent project. Nevertheless,
according to EIAO, an EIA study will be conducted under this concurrent
project, and the cumulative impact will be assessed in the study. |
Site Formation and Infrastructure Works for Developments
at Kam Tin South, Yuen Long - Advance Works |
CEDD |
No |
Commenced in 2018 and tentatively scheduled to complete
by 2021 |
No cumulative impact as only a works area of minor road
junction improvement works located within 500m from the project, but the
distance is around 300m away from the project. |
Potential cumulative ecological impacts from road traffic
and increased human activities are anticipated. Yet,
due to the nature of existing usage of Kam Tin Road and Lam Kam Road, further
road widening works of the Project would not cause significant impacts to the
ecology during operation phase. |
Improvement to Fan Kam Road |
HyD |
No |
The project is still under investigation stage and thus
no construction programme is consolidated. |
Potential cumulative construction dust, construction
noise, water quality and ecological impacts are anticipated. However, the cumulative impacts are not able to be taken
into account as no detail information such as design, construction and
operation details can be provided from the concurrent project. |
Potential cumulative ecological impacts from road traffic
and increased human disturbance are anticipated. However, the cumulative impacts are not able to be taken
into account as no detail information such as design, construction and
operation details can be provided from the concurrent project. |
Kam Tin ¡V Pat Heung Sports Centre |
LCSD |
No |
No Construction Programme available as LCSD has not
engaged any parties to carry out the investigation for the project. |
Potential cumulative construction dust, construction
noise and water quality impacts are anticipated. However, the cumulative impacts are not able to be taken
into account as no detail information such as design, construction and
operation details can be provided from the concurrent project. Nevertheless,
according to ETWB TCW No. 13/2003, a Preliminary Environmental Review (PER) will
be conducted under this concurrent project, and the cumulative impact will be
assessed in the study. |
Potential cumulative water quality and ecological impacts
from road traffic and
increased human activities are anticipated. However, the cumulative water quality impacts are not
able to be taken into account as no detail information such as design,
construction and operation details can be provided from the concurrent
project. Nevertheless, according to ETWB TCW No. 13/2003, a PER of this
concurrent project will be conducted, and the cumulative impact will be
assessed in the study. Yet, due to the nature of existing usage of Kam Tin Road
and Lam Kam Road, further road widening works of the Project would not cause
significant impacts to the ecology during operation phase. |
Traffic flow predictions for the years 2021, 2025, 2030,
2035 and 2040 (i.e. 15-year after Project commencement) have been adopted to
support the operation air quality and noise impact assessment studies as detailed
in Sections 3 and 4 of this report, respectively, as appropriate. Full details
of the adopted traffic forecast data accepted by the Transport Department is
presented in Appendix 2.1. The letter of acceptance by the
Transport Department is provided in Appendix 2.2.
The Project is in close vicinity of one of the sites of
archaeological interest, the Pat Heung Sheung Tsuen Site of Archaeological
Interest (AM04-2022). The location
of Pat Heung Sheung Tsuen Site of Archaeological Interest is shown in Figure 2.7. As the proposed upgrading works of Kam
Tin Road (between Fan Kam Road and Lam Kam Road) to 7.3m wide do not encroach
within AM04-2022 and the work areas are limited to immediately adjacent areas
next to the existing road, it is unlikely to have undisturbed archaeological
deposits to be present under the existing underground utilities and road
works. It is anticipated that there
will be no adverse archaeological and built heritage impact. Indeed, the existing underground
utilities and road works would also limit the archaeological findings,
therefore no further investigation and mitigation measures are recommended. In
addition, no built heritage items are located within 100m from the Project
boundary. As such, no adverse
impact will be anticipated and no mitigation measures would be required.
Nevertheless, if antiquity or supposed antiquity is
discovered during the course of any excavation works undertaken by the Contractor,
the Project Proponent shall report the discovery to the Antiquities and
Monuments Office (AMO) immediately and shall take all reasonable measures to
protect it as required in Antiquities and Monuments Ordinance (Cap. 53). If there are works nearby any built
heritage in future, precaution measures shall be proposed and implemented by
the Contractor.