5.0....... WATER QUALITY
IMPACT ASSESSMENT
5.1 Introduction
. 5-1
5.2 Environmental Legislation,
Standards and Guidelines
5.3 Description of the Environment
5.4 Assessment Methodologies
5.5 Identification and Evaluation
of Environmental Impacts
. 5-3
5.6 Potential Cumulative Impacts
from Concurrent Project
5.7 Mitigation of Environmental
Impacts
5.8 Environmental Monitoring and
Audit
5.9 Conclusion
FIGURES
Figure 5.1 Location
of Representative Water Sensitive Receivers
Figure 5.2 Schematic
Design of Perimeter Channel and Typical Design of Silt/Sand
Trap
APPENDICES
Appendix 5.1 Water Supplies Department (WSD)
Guidelines on Protection of Water Gathering Ground
This section presents an assessment of the potential water quality impacts
associated with the construction and operation phases of the Project.
Appropriate mitigation measures are proposed to minimize any potential water
quality impacts identified.
The water quality impact
assessment and evaluation have been conducted in accordance with the criteria
and guidelines as presented in Annexes 6 and 14 of the EIAO-TM respectively.
The following
legislation, Standards and Practice Notes are considered in the Project:
•
Water Pollution
Control Ordinance (Cap. 358): Water Quality Objectives (WQOs) for Deep Bay
Water Control Zone (WCZ);
•
Water Pollution
Control Ordinance (Cap. 358): WQOs for Tolo Harbour and Channel WCZ;
•
Water Pollution
Control Ordinance (Cap. 358): Technical Memorandum on Standards for Effluents
Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters;
•
EIAO (Cap. 499):
Annexes 6 and 14 of TM-EIAO; and
•
EPD¡¦s Practice Notes
for Professional Persons ProPECC PN 1/94 ¡§Construction Site Drainage¡¨
Water courses in the vicinity of
the Project comprise the channelized Kam Tin River and a number of natural
streams with unpolluted and polluted sections. The direction of flow is towards
the Kam Tin River and ultimately Inner Deep Bay to the northwest for those
water courses near Shek Kong Barracks and Wang Toi Shan Shan Tsuen, and the
towards Lam Tsuen River and ultimately Tolo Harbour to the east for those water
courses near Kadoorie Experimental Farm. Table
5.1 summarizes the WQOs for inland waters of
Deep Bay WCZ and Tolo Harbour and Channel WCZ.
Table 5.1 Water Quality Objectives for Inland
Waters of Deep
Bay WCZ and Tolo Harbour and Channel WCZ
Parameters |
Water Quality Objectives |
pH |
6.5 ¡V 8.5 |
Suspended solids (SS) |
Annual median 20mg/L |
Dissolved oxygen (DO) |
4 mg/L |
Chemical oxygen demand
(COD) |
15 mg/L |
5-day Biochemical Oxygen
Demand (BOD5) |
3 mg/L |
The latest EPD¡¦s water quality
index (WQI) indicates that Lam Tsuen River is classed as ¡§Excellent¡¨ but Kam
Tin River received WQI grading of ¡§Bad¡¨ in 2017.
Table 5.2 shows the water quality monitoring data at Lam Tsuen
River and Kam Tin River in 2017[1].
The data indicated that the water quality in Lam Tsuen River is still much
better than in Kam Tin River, with higher DO but lower SS, BOD5, COD, E. coli and NH3-N.
Table 5.2 Summary of EPD
Water Quality Monitoring Data for Lam Tsuen River and Kam Tin River in 2017
Parameters |
TR12H (Lam Tsuen River) |
TR12D (Lam Tsuen River) |
KT2 (Kam Tin River) |
DO (mg/L) |
8.4 (7.9 ¡V 9.9) |
8.5 (7.9 ¡V 10.0) |
5.1 (2.7 ¡V
7.5) |
pH |
7.2 (6.7 - 7.7) |
7.1 (6.9 ¡V 8.0) |
7.5 (6.9 - 7.7) |
SS (mg/L) |
1.4 (0.6 ¡V 28.0) |
0.7 (<0.5 ¡V 1.5) |
17.0 (4.6 ¡V 74.0) |
BOD5 (mg/L) |
0.5 (0.1 ¡V 3.8) |
0.4 (0.1 ¡V 2.0) |
18.0 (4.9 ¡V 170.0) |
COD (mg/L) |
<2 (<2 - 12) |
<2 (<2 - 6) |
28 (11 - 180) |
E. coli (counts/100mL) |
1 200 (350 ¡V 22 000) |
370 (53 ¡V 16 000) |
140 000 (13 000 - 590
000) |
NH3-N (mg/L) |
0.079 (0.024 - 0.260) |
0.017 (0.008 - 0.026) |
6.900 (1.300 ¡V 19.000) |
Lam Tsuen River recorded a WQOs compliance rate of 95% in 2017. It is
due to the continuous enforcement for the WPCO and improved sewerage works for
village houses in the area. Domestic, commercial and industrial sewage are
directed to the government sewers and transferred to sewage treatment plant
before discharge.
For Kam Tin River, the overall compliance rate of the WQOs in 2017 was
60%. This main river was still impacted by discharges from livestock farms,
misconnections in old buildings and unsewered premises. However, with the
implementation of the Livestock Waste Control Scheme, continuous enforcement
for the WPCO, sewage treatment plants and improved sewerage system for village
houses, the water quality of the water course is likely to be further improved
in the coming years.
.
The assessment area for the water quality impact assessment covers all
areas within 500m from the Project Boundary in Deep Bay WCZ and Tolo Harbour
and Channel WCZ as designated under the WPCO.
The Water Sensitive Receivers (WSRs) that may be affected by the
Project have been identified. These include water gathering ground from
the project eastern end, local streams near Kadoorie Experimental Farm, Ling
Wan Monastery, Wong Chuk Yuen, Sheung Tsuen and Kam Tin Bypass; nullah near
Wang Toi Shan Hung Mo Tam, Shek Kong Barracks and the channelized Kam Tin
River. It is noted that there is an encroachment of about 60m of the
water gathering zone located at the eastern end of the Project. Locations of
the representative WSRs are shown in Figure 5.1.
Terrain in the
vicinity of the construction works area varies along the Project road. In
general, relatively gentle and plain slope is found at the western part of Kam
Tin Road from the road works section near Kam Tin Bypass to the section near
Wang Toi Shan Lo Uk Tsuen. The slope of Lam Kam Road inclines upwards towards
the east and the altitude of the road is higher than that of the nearby area
near Wong Chuk Yuen, and lower than the land on the side of Ling Wan Monastery. Construction
sites located at higher altitude may induce potential surface runoff flowing
towards the nearby lowland.
Potential sources of water quality impact that may arise during the
construction and operation phases of the Project are described as below. All
the identified sources of potential water quality impact are evaluated and the
impact significance is determined. Mitigation measures are recommended to reduce
any identified adverse impacts on water quality to acceptable levels and
prevent wastewater generated from construction works from entering Kam Tin
River within Deep Bay WCZ and Lam Tsuen River within Tolo Harbour and Channel
WCZ.
Potential water quality impact might be arisen from
the associated construction works of road widening and improvement works such
as retaining wall and geotechnical works. Key water pollution sources include:
• General construction activities
and site runoff from wash water from dust suppression measures, vehicle wheel
washing facilities and concrete casting;
• Surface runoff from rainfall and
wind erosion of exposed surface areas and material stockpiles;
• Spillage of chemicals,
lubrication oils, solvent and petroleum products;
• Sewage from the construction
workforce; and
• Construction works in close
proximity of nearby water bodies
General Construction Activities
General construction activities, including general
cleaning and polishing, wheel washing, dust suppression, concrete casting and
utility installation, may generate wastewater which would contain high
concentration of SS. Various construction works may also generate debris and
waste such as packaging, construction materials and general refuse.
Uncontrolled discharge of site effluents and waste generated from the
construction works would lead to deterioration in water quality. Adoption of
the guidelines and good site practices for handling and disposal of
construction discharges as specified in Section 5.7 would minimize the
potential impacts.
Surface Runoff from Rainfall and
Wind Erosion
In particular, surface runoff into receiving water
courses during and immediate after rainstorm events is of major concern. During
rainstorms, site runoff would wash away the soil particles on unpaved lands and
areas with exposed topsoil. Sediment lade runoff and wind-blown dust would
result in deteriorating water quality with increase of SS levels and turbidity and
may result in induced effects on aquatic ecological resources. It is important
that proper site practice and good site management (as specified in the ProPECC
PN 1/94 ¡§Construction Site Drainage¡¨) to be followed to prevent site runoff
with high level of SS from entering the surrounding waters. With the
implementation of appropriate measures to control runoff and drainage from the
construction site, disturbance of water bodies would be avoided and
deterioration in water quality would be minimal.
Spillage of Chemicals
Accidental spillage and the storage of chemicals used
on-site, such as petroleum products, surplus adhesives, spent lubrication oil,
grease and mineral oil, spent acid and alkaline solutions/solvent and other
chemicals, may contaminate the surface soils. The contaminated soil particles
may be washed away by construction site runoff or stormwater drainage and
eventually may affect nearby water bodies.
The potential impacts could
however be mitigated by practical mitigation measures and good site practices
as given in Section 5.7.
Sewage from the Construction
Workforce
Sewage effluents will arise from the sanitary
facilities provided for the on-site construction workforce. The characteristics
of sewage would include high levels of BOD5, Ammonia and E. coli counts.
This temporary sewage can be
handled by providing adequate portable chemical toilets. Provided that sewage
is not discharged directly into storm drains or inland waters adjacent to the
construction site, and temporary sanitary facilities are used and properly
maintained, it is unlikely that sewage generated from the sites would have a
significant water quality impact.
Construction Works in Close
Proximity of Nearby Water Bodies
As the Project Boundary fall within about 60m of the
water gathering ground located at the eastern end of the Project, some sections of road works would be at close proximity of
nearby water bodies. Potential water quality
impacts associated with construction works of the Project may be arisen.
There
are nine road sections which are adjacent to or even across the existing
watercourses, the locations are shown in Figure 2.4.
Details of construction works at the road sections can be referred to Section
2.5 of Chapter 2.
Construction activities within or in close vicinity
to nearby water bodies may affect the water quality due to potential release of
wastewater which is generally with high concentration of SS and elevated pH.
Mitigation measures shall be implemented to control the release of wastewater
into the adjacent water environment. With proper implementation of appropriate
construction runoff control practices as referred to ProPECC PN 1/94
¡§Construction Site Drainage¡¨ and the provision of mitigation measures as
described in the ETWB TC (Works) No. 5/2005 ¡§Protection of natural
streams/rivers from adverse impacts arising from construction works¡¨, it is
anticipated that no unacceptable water quality impacts would be arising from
the construction works nearby the water bodies.
Potential water quality impacts
during the operation phase is the road surface runoff. Runoff from paved road surface may be arisen from storm
water carrying dissolved and particulate materials including dust, debris, heavy metals and vehicle
oil, which are generated from the degradation of the road
surface and tyres, corrosion of metal body parts and leakage of fuel, oil,
fluid and fine solids of passing vehicles. Materials deposited and accumulated on road surface
will be washed from the carriageway during rainfall events into surface water
drainage system and discharged to storm drains. In
addition, there will be no sewage
generation during the operation phase of the Project.
The
drainage system along Kam Tin Road and Lam Kam Road will be upgraded to cater
for the highway discharge with increased capacity after road widening. The road
drainage system will be properly planned to receive road surface runoff
at the planning and design stages.
With adequate capacity to collect all surface water and implementation of good management measures as
described in Section 5.7.2 below, no adverse impacts associated with the discharge of runoff
are anticipated during the operation phase.
Further to Chapter 2 of this Report, there will be
four concurrent projects identified in the vicinity (within 500m from the
Project site) during construction phase of the Project.
As all the concurrent projects would be land-based
and provided that proper mitigation measures would be proposed in EIA
Study/environmental assessments and implemented in future construction phase,
only local-scale impacts arising from the construction activities of these
projects are anticipated.
Table 5.3 below
summarises the potential concurrent projects that would contribute to the
cumulative impacts on water quality during construction and/or operation phase.
Table
5.3 Potential
Cumulative Water Quality Impacts from Concurrent Project
Concurrent Projects |
Project Proponent |
Designated Project |
Construction Programme |
Potential Cumulative Impacts |
|
Construction Phase |
Operation Phase |
||||
Development of Organic Resources Recovery Centre (ORRC)
(Phase 3) |
EPD |
Yes |
Tentatively scheduled to commence in 2023 and complete by
2026 |
Potential water quality impact arisen from site surface
runoff from general construction activities and sewage effluent from
construction workforce is anticipated. However, the cumulative impact is not able to be taken
into account in this study as no detail information, construction methods and
activities can be provided from the concurrent project. Nevertheless, according to EIAO, an
EIA study of this concurrent project will be conducted, and the cumulative
impact will be addressed in the study. |
Potential water quality impact of this concurrent project
may be arisen from the discharge of stormwater gathered from rainfall events
and effluents from operation processes to the drainage and sewerage system. Yet, with the provision of appropriate treatment
facilities and re-circulation of process water as recommended in Project
Profile (No. PP-552/2017)[2], no
cumulative water quality impact is anticipated during operation phase of this
concurrent project. |
Site Formation and Infrastructure Works for Developments
at Kam Tin South, Yuen Long - Advance Works |
CEDD |
No |
Commenced in 2018 and tentatively scheduled to complete
by 2021 |
No cumulative water quality impact as only a works area
of minor road junction improvement works located around 300m away from the
Project. |
Potential water quality impact of this concurrent project
would be the surface runoff during rainfall events, which contains vehicle
dust, fallen leaves, particles and litter etc. Given that the Best Management Practices (BMPs) and
mitigation measures suggested in the Preliminary Environmental Review (PER)[3] is
implemented, the potential water quality impacts associated with the storm
water discharge would be avoided as far as possible. No cumulative water quality impact is
anticipated during operation phase of this concurrent project. |
Improvement to Fan Kam Road |
HyD |
No |
The project is still under investigation stage and thus
no construction programme is consolidated. |
Potential water quality impact arisen from site surface
runoff from general construction activities and sewage effluent from construction
workforce is anticipated. However, the cumulative impact is not able to be taken
into account as no detail information such as design, construction and
operation details can be provided from the concurrent project. |
Potential water quality impact of this concurrent project
would be the surface runoff during rainfall events, which contains vehicle
dust, fallen leaves, particles and litter etc. Given that the mitigation measures suggested in the PER[4] is
implemented, the potential water quality impacts associated with the storm
water discharge would be avoided as far as possible. No cumulative water quality impact is
anticipated during operation phase of this concurrent project. |
Kam Tin ¡V Pat Heung Sports Centre |
LCSD |
No |
No Construction Programme available as LCSD has not
engaged any parties to carry out the investigation for the project. |
Potential water quality impact arisen from site surface
runoff from general construction activities and sewage effluent from
construction workforce is anticipated. However, the cumulative impact is not able to be taken
into account as no detail information such as design, construction and
operation details can be provided from the concurrent project. Nevertheless, according to ETWB TCW No.
13/2003, a PER study of this concurrent project will be conducted, and the
cumulative impact will be addressed in the study. |
Potential water quality impact arisen from stormwater and
sewage discharge is anticipated. However, the cumulative impact is not able to be taken
into account as no detail information such as design, construction and
operation details can be provided from the concurrent project. Nevertheless, according to ETWB TCW No.
13/2003, a PER study of this concurrent project will be conducted, and the
cumulative impact will be assessed in the study. |
Dust Suppression
Water used in dust suppression should as far as
practicable be re-circulated after sedimentation. When there is a need for
final disposal, the wastewater should be leaded to silt removal facilities
before being discharged to the storm drain.
Wheel Washing Water
All vehicles and plant should be cleaned before they
leave a construction site to minimize the deposition of earth, mud, debris on
roads. A wheel washing facility should be provided at every site exit if
practicable and wheel-wash overflow shall be directed to silt removal
facilities before being discharged to the storm drain. The site boundary
between the wheel washing facility and the public road should be placed with
sand bunds to prevent wheel-wash overflow from entering public road drains.
Wastewater from Concrete Casting
Wastewater generated from the washing down of mixing
trucks and drum mixers and similar equipment should whenever practicable be
recycled. The discharge of wastewater should be kept to a minimum. To prevent
pollution from wastewater overflow, the pump sump of any water
recycling system should be provided with an on-line standby pump of adequate
capacity and with automatic alternating devices. Under normal circumstances,
surplus wastewater may be discharged into foul sewers after treatment in silt
removal.
Rubbish and Litter
Good site practices should be adopted to remove
rubbish and litter from construction sites so as to prevent the rubbish and
litter from spreading from the works area. It is recommended to clean the
construction sites on a regular basis. Adequate refuse collection points shall
be provided on-site.
Construction Site Runoff
The site practices outlined in ProPECC PN 1/94
¡§Construction Site Drainage¡¨ should be followed as far as practicable to
minimise surface runoff and the chance of erosion. It is expected that the
following measures recommended will effectively control runoff from the works
sites and avoid water pollution downstream and shall be implemented during
construction phase. A schematic diagram illustrating the general drainage
design for a work front is given in Figure 5.2.
Surface runoff from construction sites should be
discharged into storm drains via sand/silt removal facilities such as
sedimentation basin/tank. Earth bunds or waterfilled barriers with geotextile
sheet should be provided on site boundaries to intercept surface runoff from
outside the site so that it will not wash across the site and to prevent
surface runoff flowing out of the site. Bunds or sandbags should also be used
within the site to direct surface runoff into the silt removal facilities.
Stagnant surface runoff should be pumped to the silt removal facilities before discharged
into storm drains.
Manholes (including newly constructed ones) should
always be adequately covered and temporarily sealed so as to prevent silt,
construction materials or debris from getting into the drainage system without
having previously passed through sedimentation tank, and to prevent storm
runoff from getting into foul sewers. Discharge of surface runoff into foul
sewers must always be prevented in order not to unduly overload the foul
sewerage system.
Silt removal facilities and manholes should be
maintained and the deposited silt and grit should be removed regularly, at the
onset of and after each rainstorm to prevent local flooding.
Surface excavation should be carefully programmed to
avoid wet-season operation. If it is unavoidable, any exposed top soils should
be covered with a tarpaulin or other means. For the purpose of preventing soil
erosion, temporary exposed slope surfaces should be covered e.g. by tarpaulin,
as excavation proceeds. Earthworks final surfaces should be well compacted and
the subsequent permanent work or surface protection should be carried out
immediately after the final surfaces are formed to prevent erosion caused by
rainstorms.
Open stockpiles (e.g. aggregates, sand and fill
material) should also be covered with a tarpaulin to avoid erosion during
rainstorms. The washing of material from the stockpiles directly into the storm
drains should be prevented by passing the runoff through sedimentation tank.
Arrangements should always be in place in such a way that adequate surface
protection measures can be safely carried out well before the arrival of a
rainstorm.
Spillage of Chemicals
Chemical waste, as defined under the Waste Disposal
(Chemical Waste) (General) Regulation, includes any substance being scrap material,
or unwanted substances specified under Schedule 1 of the Regulation. Substances
likely to be generated by construction activities arise from the maintenance of
construction plant and equipment of the Project. These include, but not limited
to the following:
•
Lubricating oil and waste fuel (diesel) from construction plant with
improper maintenance; and
•
Spent solvents from equipment cleaning activities.
Due to the scale of an active work front of the
Project, it is anticipated that no maintenance shop for construction plant and
equipment would be operated on-site and storage fuel on-site is minimal. Drainage
traps such as grease traps and petrol interceptors will be installed at each of
the drainage outlets to filter out chemical pollutants from surface runoff.
Mitigation such as providing drip tray/proper storage
of chemical containers will be strictly implemented during the construction
works. In case of any leakage on
bare ground, oil and grease decontamination kit will be available on-site for
clean-up of oil leakage. Any fuels should be stored in bunded areas such that
spillage can be easily collected. The contractor shall prepare an oil /
chemical clean-up plan in the Waste Management
Plan before the commencement of
construction works. It should ensure that leakages or spillages are contained
and cleaned up immediately. Once spillage is identified on-site, the clean-up
procedures should be carried out as below:
• Contact the site agent and/or
foreman immediately and report the spillage;
• Identify the source of spillage
and determine nature of the material;
• Stop leakage immediately where
possible;
• Identify all current and
potential affected areas according to the flow of spillage and stop the spillage from
flowing to other works areas;
• Contain the surface runoff of
spillage by using bunds made from available materials;
• After the surface runoff of
spillage is contained, remove the materials (including contaminated soil where
necessary) using pumps and/or absorbent materials; and
• Dispose of the materials,
including the contaminated soil, as chemical waste
Waste oil should be collected and stored for
recycling or disposal, in accordance with the Waste Disposal Ordinance (Cap.
354). The contractor must register as a chemical waste producer if chemical
wastes would be produced from the construction activities. The Waste Disposal
Ordinance (Cap. 354) and its subsidiary regulations in particular the Waste
Disposal (Chemical Waste) (General) Regulation, should be observed and complied
with for disposal of chemical wastes. The Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes published under the Waste Disposal
Ordinance (Cap. 354) details the requirements to deal with chemical wastes.
General requirements are given as follows:
• Suitable containers should be used to hold the chemical
wastes to avoid leakage or spillage during storage, handling and transport;
•
Chemical waste
containers should be suitably labelled, to notify and warn the personnel who
are handling the wastes, to avoid accidents; and
•
Storage area should
be selected at a safe location on site and adequate space should be allocated
to the storage area
Sewage Effluent from
Construction Workforce
Portable chemical toilets would be provided for
handling the sewage effluent generated by the workforce. The number of the
chemical toilets required for the construction sites would be subject to later
detailed design, the capacity of the chemical toilets, and contractor¡¦s site
practices. A licensed contractor would be employed to provide appropriate and
adequate portable toilets and be responsible for appropriate disposal and
maintenance.
Domestic sewage generated by the construction
workforce should be appropriately managed to avoid potential adverse impacts of
uncontrolled sewage discharge into nearby water courses. Portable chemical
toilets shall be appropriately located on-site in proximity to all major works
areas where they shall remain and be maintained in good working order for the
convenience of the workforce during the construction phase.
The provision of temporary toilet facilities within
the water gathering ground, if any, is subject to approval of the Director of
Water Supplies. As a minimum requirement, temporary toilet
facilities must be located more than 30m from any watercourse.
Notices would be posted at conspicuous locations to
remind the workers not to discharge any sewage or wastewater into the nearby
environment during the construction phase of the Project. Regular environmental
audit on the construction site would be conducted in order to provide an
effective control of any malpractices and achieve continual improvement of
environmental performance on site.
Construction Works in Close
Proximity of Nearby Water Bodies
The practices outlined in ETWB TC (Works) No. 5/2005
¡§Protection of natural streams/rivers from adverse impacts arising from
construction works¡¨ should also be adopted where applicable to minimize the
water quality impacts upon any natural streams or surface water systems.
Relevant mitigation measures from the ETWB TC (Works) No. 5/2005 are listed
below:
• Construction works close to the inland waters should be
carried out in dry season as far as practicable where the flow in the surface
channel or stream is low.
•
The use of less or
smaller construction plants may be specified in areas close to the water
courses to reduce the disturbance to the surface water.
•
Temporary storage of
materials (e.g. equipment, chemicals and fuel) and temporary stockpile of
construction materials should be located well away from any water courses
during carrying out of the construction works.
•
Stockpiling of
construction materials and dusty materials should be covered and located away
from any water courses.
•
Construction debris
and spoil should be covered up and/or disposed of as soon as possible to avoid
being washed into the nearby water receivers.
•
Proper shoring may
need to be erected in order to prevent soil or mud from slipping into the
watercourses.
•
Fencing should be
erected on the sides facing the nearest stream course to trap all wind-blown
litters such as paper, plastic bags, bottles and boxes within the site from
entering the nearby water bodies.
•
The proposed works
site inside or in the proximity of natural rivers and streams should be
temporarily isolated, such as by placing of cofferdam with silt curtain with
lead edge at bottom and properly supported props, to prevent adverse impacts on
the stream water qualities. Other protective measures should also be taken to
ensure that no pollution or siltation occurs to the water gathering grounds of
the work site.
•
The natural bottom
and existing flow in the river should be preserved as much as possible to avoid
disturbance to the river habitats. If temporary access track on riverbed is
unavoidable, this should be kept to the minimum width and length. Temporary
river crossings should be supported on stilts above the riverbed.
The contractor shall also comply with the ¡§Condition
of Working within Water Gathering Ground¡¨ during Project construction. The
guideline is attached in Appendix 5.1. Any effluent discharged from
the proposed development at points within gathering grounds should comply fully
at all times with standards for effluents stipulated in Table 2 and paragraph
8.4 of the ¡§Technical Memorandum on Effluent Standards¡¨ issued under section 21
of the WPCO.
Road gullies should be provided to direct and collect
all surface runoff to the drainage system. The capacity should be properly
designed to cater for all surface water.
Road gullies with standard design should be
incorporated during the detailed design to remove particles present in
stormwater runoff. Screening facility such as standard gully grating, with
spacing which is capable of screening off large substances such as fallen
leaves and rubbish should be provided at the inlet of drainage system.
Road drains should be properly maintained and cleaned
regularly to ensure good service condition. Good management measures such as
regular cleaning of road gullies and sweeping of road surface should be carried
out prior to occurrence of rainstorm.
There will be construction works in close proximity
of nearby water bodies: watercourse (meander) adjacent to north of section
between Chainage CHA 8+00 to CHA 9+10 of Kam Tin Road, watercourse across road
section between Chainage CHB 41+10 to CHB 41+30 of Lam Kam Road, and
watercourse across road section between Chainage CHB 48+85 to CHB 49+15 of Lam
Kam Road. Yet, no significant water quality impacts are expected during the
construction and operation phases given that the proposed mitigation measures
are properly implemented. Water quality monitoring is not considered necessary,
however, regular site inspections are recommended to be conducted during
construction phase in order to ensure the mitigation measures are implemented
properly. Any effluent discharges from the site would be required to comply
with the terms and conditions of a discharge license to be applied as necessary
under the WPCO.
Given both magnitude and duration of works and with
the implementation of the mitigation measures during the construction phase, no
significant water quality impacts are anticipated for the Project. The
implementation of the mitigation measures shall be included to the works
contracts. Regular site inspections are recommended during construction phase to
ensure the measures are implemented properly.
During the operation phase, the stormwater from the
surface runoff is the key identified environmental impact and there will be no
sewage generation during Project operation. Road drainage system along Kam Tin
Road and Lam Kam Road will be properly planned and upgraded to cater for the
road surface runoff from highway with increased capacity after road widening.
With the mitigation measures mentioned in Section 5.7.2 in place, residual
adverse water quality impacts are not anticipated.
[1] River Water Quality in Hong Kong in 2017, published by EPD.
[2] Project Profile
of Development of Organic Resources Recovery Centre (Phase 3) (No. PP-552/2017)
[3] Preliminary
Environmental Review Report (Final) for Agreement No. CE 34/2014 (CE) Site
Formation and Infrastructural Works for the Initial Sites at Kam Tin South,
Yuen Long ¡V Investigation, Design and Construction
[4] Report on Preliminary Environmental Review (Final) for Agreement No. CE 61/2012 (HY) Improvement to Fan Kam Road ¡V Investigation