Contents

 

                                                                                                                                                                                                

4            Noise  4-1

4.1           Legislation, Standards and Guidelines  4-1

4.2           Description of the Environment 4-5

4.3           Assessment Area and Noise Sensitive Receivers  4-5

4.4           Construction Noise Impact Assessment 4-6

4.5           Operational Noise Impact Assessment 4-9

4.6           Conclusion  4-9

 

 

 

Figures

Figure 4.1              Locations of Representative Noise Sensitive Receivers

 

 

Appendices

Appendix 4.1        Photos of Representative Noise Sensitive Receivers

Appendix 4.2        Detailed Plant Inventory

Appendix 4.3        Locations of Workfronts

 

 

 


4                                Noise

4.1                         Legislation, Standards and Guidelines

4.1.1                    General

4.1.1.1                The relevant legislation and associated guidance applicable to this Study for the assessment of noise impact include:

·               Environmental Impact Assessment Ordinance (EIAO) (Cap. 499), including Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO), Annex 5 and Annex 13;

·               Noise Control Ordinance (NCO) (Cap. 400);

·               Technical Memorandum (TM) on Noise from Construction Work other than Percussive Piling (TM-GW);

·               TM on Noise from Percussive Piling (TM-PP);

·               TM on Noise on Construction Work in Designated Areas (TM-DA); and

·               TM on Noise from Places other than Domestic Premises, Public Places or Construction Sites (TM-Places).

4.1.2                    Construction Noise

Construction Noise during Normal Hours

4.1.2.1                NCO provides the statutory framework for noise control in Hong Kong. Assessment procedures and standards are set out in the respective TM promulgated under NCO.

4.1.2.2                To ensure a better environment, the TM-EIAO promulgated under the EIA Ordinance has imposed more stringent criteria. For construction, there is no statutory limit on daytime construction noise under NCO and related TMs. There is statutory control on construction noise during daytime on general holidays (including Sundays).  Nevertheless, the TM-EIAO stipulates criteria of 65-75dB(A) for daytime construction activities, as shown in Table 4.1.

Table 4.1         Noise standards for daytime construction activities

Uses

Noise Standards[1], [2], Leq (30 mins) dB(A)

0700 – 1900 hours on any day not being a Sunday or general holiday

All domestic premises including temporary housing accommodation

75

Hotel and hostels

75

Educational institutions including kindergartens, nurseries and all others where unaided voice communication is required

70

65 (During examination)

Notes:

[1]       The above standards apply to uses that rely on opened windows for ventilation.

[2]       The above standards should be viewed as the maximum permissible noise levels assessed at 1m from the external facade.

Construction Noise during Restricted Hours

4.1.2.3                NCO also provides statutory control on general construction works during restricted hours (i.e. 1900 to 0700 hours (of the next day) from Monday to Saturday and at any time on Sundays or public holidays).  The use of Powered Mechanical Equipment (PME) for construction works during restricted hours would require a Construction Noise Permit (CNP). The TM-GW details the procedures adopted by Environmental Protection Department (EPD) for assessing such application. The granting of a CNP is subject to conditions stated in the CNP and it may be revoked at any time for failure to comply with the permit conditions.

4.1.2.4                In addition to the general controls on the use of PME during restricted hours, the use of Specified Powered Mechanical Equipment (SPME) and the undertaking of Prescribed Construction Work (PCW) during the restricted hours in a designated area are controlled by the TM-DA. Construction plant or equipment classified as SPME under the TM-DA includes hand-held breakers, bulldozers, concrete lorry mixers, dump trucks and vibratory pokers. The PCW includes the erection or dismantling of formwork or scaffolding, hammering, loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material, and the disposal of rubble through plastic chutes.

4.1.2.5                The TM-DA details the procedures that should generally be adopted by the Noise Control Authority for assessing the use of SPME during restricted hours and for determining whether a CNP would be issued.

4.1.2.6                Maximum noise levels from construction activities during restricted hours at affected Noise Sensitive Receivers (NSRs) are controlled under the TMs and shall not exceed the specified Acceptable Noise Levels (ANLs). These ANLs are stipulated in accordance with the Area Sensitivity Ratings (ASRs) established for the NSRs. The ANLs for construction works in Designated Areas are more stringent than those given in the TM-GW and summarised in Table 4.2.

Table 4.2         ANLs for construction during restricted hours

Time Period

ANL, dB(A)

ASR A

ASR B

ASR C

All weekdays during the evening (1900 to 2300 hours), and general holidays (including Sundays) during the day-time and evening (0700 to 2300 hours)

60 (45)

65 (50)

70 (55)

All days during the night-time (2300 to 0700 hours)

45 (30)

50 (35)

55 (40)

Note:

[1]       Figures in brackets are ANLs for SPME construction work in designated areas.

4.1.2.7                As defined in Noise Control Designated Area Plan, the assessment area of the Project is not within the Designated Area.

4.1.2.8                Despite any description made in this EIA, there is no guarantee that a CNP will be issued for the project construction. The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant TMs issued under the NCO. The Noise Control Authority will take into account contemporary conditions / situations of adjoining land uses and any previous complaints against construction activities at the Project site before making a decision in granting a CNP. Nothing in this EIA report shall bind the Noise Control Authority in making a decision. If a CNP is to be issued, the Noise Control Authority shall include in it any conditions demand. Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution under the NCO. According to the proposed construction methodology for the Project, construction during night-time period and other time periods under restricted hours are not anticipated.

Percussive Piling

4.1.2.9                Under the TM-PP, CNPs are required for carrying out of percussive piling during 0700 - 1900 hours of the next day on normal weekdays, and carrying out of percussive piling is generally prohibited during general holidays including Sundays. This TM specifies the permitted hours and other conditions for percussive piling. Table 4.3 lists the acceptable percussive piling noise levels for various types of NSR.

Table 4.3         ANLs for percussive piling

NSR Window Type or Means of Ventilation

ANL, dB(A)

(i)      NSR (or part of NSR) with no window or other opening

100

(ii)     NSR with central air conditioning system

90

(iii)    NSR with windows or other openings but without central air conditioning system

85

4.1.2.10            Depending on the numbers and types of piling machines and pile types, and the separation from NSRs, percussive piling would be restricted to 12, 5 or 3 hours respectively during 07:00 - 1900 hours on normal weekdays. For NSRs that are particularly sensitive to noise, such as hospitals, medical clinics, educational institutions and courts of law, a further reduction of 10dB(A) shall be applied to the above ANLs. According to the proposed construction methodology for the Project, percussive piling is not anticipated.

4.1.3                    Operational Noise

4.1.3.1                The TM-EIAO (Annex 5 of TM) has stipulated the noise standards for various noise sources as shown in Table 4.4. It should, however, be noted that the following noise criteria are only applicable to uses that rely on opened windows for ventilation.

Table 4.4         Noise standards for operational phase

Common Uses

Noise Standards[1], [2]

Aircraft Noise (Noise Exposure Forecast: NEF)

Helicopter Noise

Lmax dB(A)

0700-1900 hours

Road Traffic Noise

L10 (1hour) dB(A)

Rail

Noise

Fixed Noise

Sources

All domestic premises including temporary housing accommodation

25

85

70

(a) The appropriate ANLs shown in Table 2 of the Technical Memorandum for the Assessment of Noise from Places Other than Domestic Premises, Public Places or Construction Sites and

(b) Lmax (2300-0700 hours)

= 85dB(A)

(a) 5dB(A) below the appropriate ANLs shown in Table 2 of the Technical Memorandum for the Assessment of Noise from Places Other than Domestic Premises, Public Places or Construction Sites, or

(b) the prevailing background noise levels (For quiet areas with level 5 dB(A) below the ANL)

Hotel and hostels

25

85

70

Offices

30

90

70

Educational institutions including kindergartens, nurseries and all others where unaided voice communication is required

25

85

65

Places of public Worship and courts of law

25

85

65

Hospitals, clinics, convalescences and homes for the aged, diagnostic rooms, wards

25

85

55

Notes:

[1]       The above standards apply to uses that rely on opened windows for ventilation.

[2]       The above standards shall be viewed as the maximum permissible noise levels assessed at 1m from the external facade.

4.1.3.2                As mentioned in Section 2, the main objectives of the Project are to enhance pier facilities and provide adequate structural integrity for safe pier usage. There is neither planned increase in the existing Kaito services nor alteration of their routing. Therefore, the Project will not introduce any additional operational noise sources in Table 4.4.

4.2                         Description of the Environment

4.2.1                    Existing Environment

4.2.1.1                As discussed in Section 2, the works area of the Project is located at the shore of Lai Chi Wo, mostly within Yan Chau Tong Marine Park, and partly within Plover Cove Country Park. Part of the works area is currently occupied by Lai Chi Wo Pier of approximately 64m long and 2.5m wide which would be subject to pier improvement works under the Project. The adjacent area of the Project is generally rural in character with Lai Chi Wo village located to about 400m southwest of the Project. The Project and its adjacent area are currently not covered by any Outline Zoning Plan (OZP). The existing environment is relatively tranquil and quiet. No major noise sources are identified during the site visit.

4.3                         Assessment Area and Noise Sensitive Receivers

4.3.1                    Assessment Area

4.3.1.1                According to Clause 2.2.1(a) of Appendix C of the EIA Study Brief (ESB-305/2017), the assessment area for noise impact should generally include the area within 300m from the boundary of the Project and the works of the Project. A 300m assessment area from the works area of the Project has been adopted. Figure 4.1 shows the extent of the assessment area and the location of the Project.

4.3.2                    Noise Sensitive Receivers

4.3.2.1                With reference to Annex 13 of the TM-EIAO, NSRs shall include residential uses (all domestic premises including temporary housing), institutional uses (educational institutions including kindergartens and nurseries), hospitals, medical clinics, homes for the aged, convalescent homes, places of public worship, libraries, courts of law, performing arts centres, auditoria and amphitheatres, country parks and others.

4.3.2.2                All NSRs within the 300m assessment area from the boundary of the Project and the works of the Project have been identified with the representative NSRs selected as assessment points for assessment. These NSRs should include both the existing and committed and planned sensitive developments (if any) during both construction and operational phases.

4.3.2.3                The representative existing NSRs are identified by means of reviewing topographic maps, aerial photos, land status plans, relevant Outline Zoning Plans (OZP) (the Approved Lai Chi Wo, Siu Tan and Sam A Tsuen OZP No. S/NE-LCW/2), Development Permission Area Plans, Outline Development Plans, Layout Plans and other relevant published land use plans, including plans and drawings published by Lands Department and any land use and development applications approved by the Town Planning Board, and supplemented by site inspections. No committed/planned NSR was identified within the 300m assessment area from the boundary of the Project and the works of the Project. Photos of the representative existing NSRs are shown in Appendix 4.1.

4.3.2.4                The representative NSRs identified are summarised in Table 4.5 and their locations are shown in Figure 4.1.

Table 4.5         Identified representative NSRs

NSR[1]

Description

Uses [2]

Approx. Separation Distance

LCW-N1

Plover Cove Country Park[3]

CP

Partly within the proposed works area

Notes:

[1]       The nearest village house at Lai Chi Wo Village is located at more than 400m away from the Project.

[2]       CP – Country Park

[3]       Floor is not applicable for this NSR.

4.4                         Construction Noise Impact Assessment

4.4.1                    Identification of Construction Noise Impact

4.4.1.1                As discussed in Section 1, the major works items for the Project include the following:

·               Carrying out site investigation works for detailed design;

·               Provision of plants, equipment and materials on working barge(s) for implementation of the Project;

·               Provision of temporary berthing and mooring facilities (temporary pier) using working barge and/or steel structures supported by piles to maintain access to Lai Chi Wo throughout the construction stage;

·               Installation of piles for the new pier;

·               Modification of the existing pier and construction of new pier structures (e.g. installation of precast elements of the new pier structure etc.);

·               Construction of associated facilities on the new pier; and

·               Removal of temporary pier after completion of the improvement works on the existing pier.

4.4.1.2                The noise sources during the construction phase would be the use of Power Mechanical Equipment (PME) in different construction works. The key construction activities which have a bearing on construction noise impacts include:

·               Site investigation works for detailed design;

·               Mobilization, pre-drilling works and construction of the temporary pier;

·               Installation of piles for the new pier;

·               Construction of the new pier structures;

·               Construction of associated facilities on the pier; and

·               Demolition of the temporary pier and reinstatement work.


 

4.4.1.3                The PME inventories would generally include tug boat, derrick barge, rotary type drill rig, concrete saw/groover, generator and barge-mounted mobile crane, etc. Detailed plant inventory and anticipated utilisation rate provided and confirmed by the project engineer to be applicable can be referred to Appendix 4.2.

4.4.2                    Evaluation of Construction Noise Impact

4.4.2.1                As discussed in Section 2, site investigation works for detailed design of the Project are tentatively targeted to commence in mid-2021 for completion in end-2021.  The pier improvement works of the Project is tentatively targeted to commence in Year 2023 for completion in Year 2025. There are neither residential premises nor educational institutions within the 300m assessment area of the Project. Only the Plover Cove Country Park, with limited transient hikers, is identified as the NSR. Although the NSR is identified in accordance with Annex 13 of the TM-EIAO, the relevant legislation and guidelines including TM-EIAO and TM-GW do not provide a specific noise limit for Country Parks.

4.4.2.2                In view of the minor scale and low complexity of the Project, it is anticipated that construction works during the restricted hours (i.e. 19:00 to 07:00 on weekdays or any hours in general holidays including Sunday) can be avoided through a better scheduling of works. Moreover, as the site investigation, foundation works and demolition works of the Project are marine-based, only a limited air-borne construction noise would be generated. In addition, the construction works of above-water superstructure will mainly be implemented using prefabrication method as far as practicable. Prefabrication method could reduce the amount of above-water noisy operations on-site, and the number of PME items to be used would be limited. Therefore, no adverse construction noise impact is anticipated.

4.4.3                    Enhancement Measures of Construction Noise Impact

4.4.3.1                Although no adverse construction noise impact is anticipated, it is still recommended to minimise the construction noise impact as far as practical. As such, the following enhancement measures are recommended:

·               Good site practices to limit noise emissions at the source;

·               Use of quality powered mechanical equipment (QPME);

·               Use of temporary noise barriers to screen noise from relatively static PME; and

·               Alternative use of plant items within one worksite, wherever practicable.

4.4.3.2                The above enhancement measures would need to be implemented in worksites as good practices where appropriate. “Recommended Pollution Control Clauses for Construction Contracts” promulgated by EPD will be added to the Contract for future contractors to follow. Detailed descriptions of these enhancement measures are given in the following sections.

Good Site Management Practices

4.4.3.3                Good site practice and noise management techniques could considerably reduce the noise impact from construction site activities on nearby NSRs. The following measures should be practised during each phase of construction.

·               only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction programme;

·               machines and plant (such as crane and generator) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;

·               plant known to emit noise strongly in one direction, where possible, be orientated so that the noise is directed away from nearby NSRs;

·               silencers or mufflers on construction equipment should be properly fitted and maintained during the construction works;

·               mobile plant should be sited as far away from NSRs as possible and practicable; and

·               material stockpiles, site office and other structures should be effectively utilised, where practicable, to screen noise from on-site construction activities.

4.4.3.4                The benefits of these techniques can vary according to specific site conditions and operations. The environmental noise climate would certainly be improved with these control practices, although the improvement can only be quantified during implementation when specific site parameters are known.

Use of Quality Powered Mechanical Equipment (QPME)

4.4.3.5                The use of quiet plant associated with the construction works is made reference to the PME listed in the QPME system and other commonly used PME listed in EPD web pages as far as possible. It is generally known (supported by field measurement) that particular models of construction equipment are quieter than standard types given in the TM-GW. Whilst it is generally considered too restrictive to specify that the Contractor has to use specific models or items of plant, it is reasonable and practicable to set plant noise performance specifications for specific PME so that some flexibility in selection of plant is allowed. A pragmatic approach would be to request that the Contractor independently verifies the noise level of the plant proposed to be used and demonstrates through furnishing of these results, that the plant proposed to be used on the Project site meets the requirements.

Use of Temporary Noise Barriers to Screen Noise from Relatively Static PME

4.4.3.6                Movable temporary noise barriers that can be located close to noisy plant and be moved concurrently with the plant along a worksite can be very effective for screening noise from NSRs. A typical design which has been used locally is a wooden framed barrier with a small-cantilevered upper portion of superficial density no less than 7kg/m2 on a skid footing with 25mm thick internal sound absorptive lining. This measure is particularly effective for low level zone of NSRs.

4.4.3.7                Movable temporary noise barriers will be used for some PME items (e.g. generator). It is anticipated that suitably designed barriers could achieve at least 5dB(A) reduction for movable plant. Acoustic mat would be used for other plant items such as piling rig and a 5 dB(A) noise reduction is anticipated.

Alternative Use of Plant Items within One Worksite

4.4.3.8                In practice, some plant items will operate sequentially within the same worksite, and certain reduction of the predicted noise impacts could be achieved. However, any additional control on the sequencing of plant will impose a restrictive constraint to the Contractor on the operation and planning of plant items, and the implementation of the requirement would be difficult to be monitored.

4.4.3.9                The feasibility, practicability, programming and effectiveness of the above enhancement measures have been reviewed by engineer.

4.4.4                    Cumulative Impact with Concurrent Project

4.4.4.1                As discussed in Section 2, there is only one concurrent project namely “Improvement of Trails and Provision of Facilities in Sha Tau Kok” during the construction phase of the Project. However, only minor replacement, renovation and conservation works will be carried out for this project. Noise impact from this project is expected to be minimal. In addition, the works of this concurrent project near the Project have all been completed. Therefore, no adverse construction noise impact from the concurrent project is anticipated.

4.4.5                    Evaluation of Residual Construction Noise Impact

4.4.5.1                With the recommended construction design and enhancement measures in place, no residual construction noise impact is anticipated.

4.5                         Operational Noise Impact Assessment

4.5.1.1                During the operational phase, the improved pier will not have any planned fixed noise sources. In addition, there would be no planned increase in the licensed Kaito services after the pier improvement works. Conversely, the main objectives of the Project are to enhance pier facilities and provide adequate structural integrity for safe pier usage. No loudspeakers, wind turbines or other fixed noise sources are proposed in the improved pier.

4.5.1.2                The representative NSRs, as summarised in Table 4.5 are located to the west of the Project site. As the pier length will increase from 64m to approximately 155m with the landing steps shifted seawards, the proposed berthing locations associated with the marine traffic noise sources will be farther away from the coast and the NSRs as compared with the current condition without pier improvement. Therefore, no operational noise impact is anticipated.

4.6                         Conclusion

4.6.1                    Construction Phase

4.6.1.1                Only the Plover Cove Country Park is identified as a NSR, partly encroaching the proposed works area. However, the relevant legislation and guidelines including TM-EIAO, TM-GW, etc. do not provide a specific noise limit for Country Parks.

4.6.1.2                Construction noise impact is anticipated to be limited in view of the small scale and low complexity of the Project. Furthermore, no construction works will be carried out during the restricted hours, and the prefabrication method for the superstructure construction will be adopted as far as practicable. In addition, a number of noise enhancement measures including good site practices, the use of QPME, and the use of temporary noise barriers, etc. have been proposed in Section 4.4.3 to further reduce the construction noise impact. Therefore, no adverse construction noise impact is anticipated.

4.6.2                    Operational Phase

4.6.2.1                During the operational phase, the improved pier will not have any planned fixed noise sources. In addition, there would be no planned increase in the licensed Kaito services after the pier improvement works. Therefore, no operational noise impact is anticipated.