Contents

 

                                                                                                                                                                                                

7            Land Contamination  7-1

7.1           Legislation, Standards and Guidelines  7-1

7.2           Description of the Environment 7-5

7.3           Assessment Methodology  7-6

7.4           Identification of Potentially Contaminated Sites  7-6

7.5           Conclusion  7-9

 

 

 

Figures

 

 

Appendices

Appendix 7.1        Historical Aerial Photos

Appendix 7.2        Correspondences with FSD and EPD

Appendix 7.3        Photo Records of Site Survey

Appendix 7.4        Site Walkover Checklist

 


7                                Land Contamination

7.1                         Legislation, Standards and Guidelines

7.1.1                    General

7.1.1.1                The relevant legislation, standards and guidelines applicable to the Study for the assessment of land contamination include:

·               Annex 19 of the Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO), Guidelines for Assessment of Impact On Sites of Cultural Heritage and Other Impacts (Section 3: Potential Contaminated Land Issues), Environmental Protection Department (EPD), 1997; 

·               Guidance Note for Contaminated Land Assessment and Remediation, EPD, 2007;

·               Guidance Manual for Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management, EPD, 2007; and

·               Practice Guide for Investigation and Remediation of Contaminated Land, EPD, 2011.

7.1.2                    Environmental Impact Assessment Ordinance (EIAO) (Cap. 499), Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO)

7.1.2.1                Under Annex 19 of the TM-EIAO, a number of potentially contaminating historical and present landuses should be considered, including oil installations, gas works, metal workshops, car repair and dismantling workshops, which have the potential to cause or have caused land contamination.  Nevertheless, any other potential contaminating activities/ installations/ facilities within the boundary of the Project should be identified and considered based on professional judgement.

7.1.3                    Guidance Note for Contamination Land Assessment and Remediation

7.1.3.1                In accordance with EPD’s Guidance Note for Contamination Land Assessment and Remediation, a contamination assessment evaluation should:

·              Provide a clear and detailed account of the present landuse and the relevant past land history, in relation to possible land contamination; 

·               Identify areas of potential contamination and associated impacts, risks or hazards; and

·               Submit a plan to evaluate the actual contamination conditions for soil and/or groundwater, if required.

7.1.4                    Guidance Manual for Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management

7.1.4.1                The Guidance Manual introduces the risk-based approach in land contamination assessment and presents instructions for comparison of soil and groundwater data to the RBRGs for 54 chemicals of concern commonly found in Hong Kong. The RBRGs were derived to suit Hong Kong conditions by following the international practice of adopting a risk-based methodology for contaminated land assessment and remediation and were designed to protect the health of people who could potentially be exposed to land impacted by chemicals under four broad post restoration landuse categories. The RBRGs also serve as the remediation targets if remediation is necessary. The RBRGs for soil and groundwater are given in Table 7.1 and Table 7.2 respectively.

Table 7.1 RBRGs for soil & soil saturation limit

Chemical

Risk-Based Remediation Goals (RBRGs) for Soil

Soil Saturation Limit (Csat)

(mg/kg)

Urban Residential

(mg/kg)

Rural Residential

(mg/kg)

Industrial

(mg/kg)

Public Park

(mg/kg)

VOCs

Acetone

9,590

4,260

10,000*

10,000*

***

Benzene

0.704

0.279

9.21

42.2

336

Bromodichloromethane

0.317

0.129

2.85

13.40

1,030

2-Butanone

10,000*

10,000*

10,000*

10,000*

***

Chloroform

0.132

0.0529

1.54

253

1,100

Ethylbenzene

709

298

8,240

10,000

138

Methyl tert-Butyl Ether

6.88

2.80

70.1

505

2,380

Methylene Chloride

1.30

0.529

13.9

128

921

Styrene

3,220

1,540

10,000*

10,000*

497

Tetrachloroethene

0.101

0.0444

0.777

1.84

97.1

Toluene

1,440

705

10,000*

10,000*

235

Trichloroethene

0.523

0.211

5.68

69.4

488

Xylenes (Total)

95.0

36.8

1,230

10,000*

150

SVOCs

Acenaphthene

3,510

3,280

10,000*

10,000*

60.2

Acenaphthylene

2,340

1,510

10,000*

10,000*

19.8

Anthracene

10,000*

10,000*

10,000*

10,000*

2.56

Benzo(a)anthracene

12.0

11.4

91.8

38.3

 

Benzo(a)pyrene

1.20

1.14

9.18

3.83

 

Benzo(b)fluoranthene

9.88

10.1

17.8

20.4

 

Benzo(g,h,i)perylene   

1,800

1,710

10,000*

5,740

 

Benzo(k)fluoranthene

120

114

918

383

 

Bis-(2-Ethylhexyl)phthalate

30.0

28.0

91.8

94.2

 

Chrysene

871

919

1,140

1,540

 

Dibenzo(a,h)anthracene

1.20

1.14

9.18

3.83

 

Fluoranthene

2,400

2,270

10,000*

7,620

 

Fluorene

2,380

2,250

10,000*

7,450

54.7

Hexachlorobenzene

0.243

0.220

0.582

0.713

 

Indeno(1,2,3-cd)pyrene

12.0

11.4

91.8

38.3

 

Naphthalene

182

85.6

453

914

125

Phenanthrene

10,000*

10,000*

10,000*

10,000*

28.0

Phenol

10,000*

10,000*

10,000*

10,000*

7,260

Pyrene

1,800

1,710

10,000*

5,720

 

Metals 

Antimony

29.5

29.1

261

97.9

 

Arsenic

22.1

21.8

196

73.5

 

Barium

10,000*

10,000*

10,000*

10,000*

 

Cadmium

73.8

72.8

653

245

 

Chromium III

10,000*

10,000*

10,000*

10,000*

 

Chromium VI   

221

218

1,960

735

 

Cobalt

1,480

1,460

10,000*

4,900

 

Copper

2,950

2,910

10,000*

9,790

 

Lead

258

255

2,290

857

 

Manganese

10,000*

10,000*

10,000*

10,000*

 

Mercury

11.0

6.52

38.4

45.6

 

Molybdenum

369

364

3,260

1,220

 

Nickel

1,480

1,460

10,000*

4,900

 

Tin

10,000*

10,000*

10,000*

10,000*

 

Zinc

10,000*

10,000*

10,000*

10,000*

 

Dioxins / PCBs

Dioxins (I-TEQ)

0.001

0.001

0.005

0.001

 

PCBs

0.236

0.226

0.748

0.756

 

Petroleum Carbon Ranges

C6 - C8

1,410

545

10,000*

10,000*

1,000

C9 - C16

2,240

1,330

10,000*

10,000*

3,000

C17 - C35

10,000*

10,000*

10,000*

10,000*

5,000

Other Inorganic Compounds

Cyanide, free

1,480

1,460

10,000*

4,900

 

Organometallics

TBTO

22.1

21.8

196

73.5

 

Notes:

[1]       For Dioxins, the clean-up levels in USEPA Office of Solid Waste and Emergency Response (OSWER) Directive of 1998 have been adopted. The OSWER Directive value of 1 ppb for residential use has been applied to the scenarios of "Urban Residential", "Rural Residential", and "Public Parks", while the low end of the range of values for industrial, 5 ppb, has been applied to the scenario of "industrial".

[2]       Soil saturation limits for petroleum carbon ranges taken from the Canada-Wide Standards for Petroleum Hydrocarbons in Soil, CCME 2000.

[3]       * indicates a 'ceiling limit' concentration.

[4]       *** indicates that the Csat value exceeds the 'ceiling limit' therefore the RBRG applies.

 

Table 7.2        RBRGs for groundwater and solubility limit

Chemical

Risk-Based Remediation Goals (RBRGs) for Groundwater

Solubility Limit

(mg/L)

Urban Residential

(mg/L)

Rural Residential

(mg/L)

Industrial

(mg/L)

VOCs

Acetone

10,000*

10,000*

10,000*

***

Benzene

3.86

1.49

54.0

1,750

Bromodichloromethane

2.22

0.871

26.2

6,740

2-Butanone

10,000*

10,000*

10,000*

***

Chloroform

0.956

0.382

11.3

7,920

Ethylbenzene

1,020

391

10,000*

169

Methyl tert-Butyl Ether

153

61.1

1,810

***

Methylene Chloride

19.0

7.59

224

***

Styrene

3,020

1,160

10,000*

310

Tetrachloroethene

0.250

0.0996

2.95

200

Toluene

5,110

1,970

10,000*

526

Trichloroethene

1.21

0.481

14.2

1,100

Xylenes (Total)

112

43.3

1,570

175

SVOCs

Acenaphthene

10,000

7,090

10,000*

4.24

Acenaphthylene

1,410

542

10,000*

3.93

Anthracene

10,000*

10,000*

10,000*

0.0434

Benzo(a)anthracene

 

 

 

 

Benzo(a)pyrene

 

 

 

 

Benzo(b)fluoranthene

0.539

0.203

7.53

0.0015

Benzo(g,h,i)perylene   

 

 

 

 

Benzo(k)fluoranthene

 

 

 

 

Bis-(2-Ethylhexyl)phthalate

 

 

 

 

Chrysene

58.1

21.9

812

0.0016

Dibenzo(a,h)anthracene

 

 

 

 

Fluoranthene

10,000*

10,000*

10,000*

0.206

Fluorene

10,000*

10,000*

10,000*

1.98

Hexachlorobenzene

0.0589

0.0234

0.695

6.20

Indeno(1,2,3-cd)pyrene

 

 

 

 

Naphthalene

61.7

23.7

862

31.0

Phenanthrene

10,000*

10,000*

10,000*

1.00

Phenol

 

 

 

 

Pyrene

10,000*

10,000*

10,000*

0.135

Metals

Antimony

 

 

 

 

Arsenic

 

 

 

 

Barium

 

 

 

 

Cadmium

 

 

 

 

Chromium III

 

 

 

 

Chromium VI   

 

 

 

 

Cobalt

 

 

 

 

Copper

 

 

 

 

Lead

 

 

 

 

Manganese

 

 

 

 

Mercury

0.486

0.184

6.79

 

Molybdenum

 

 

 

 

Nickel

 

 

 

 

Tin

 

 

 

 

Zinc

 

 

 

 

Dioxins / PCBs

Dioxins (I-TEQ)

 

 

 

 

PCBs

0.433

0.171

5.11

0.031

Petroleum Carbon Ranges

C6 - C8

82.2

31.7

1,150

5.23

C9 - C16

714

276

9,980

2.80

C17 - C35

12.8

4.93

178

2.80

Other Inorganic Compounds

Cyanide, free

 

 

 

 

Organometallics

TBTO

 

 

 

 

Notes:

[1]    Blank indicates that RBRG could not be calculated because the toxicity or physical/chemical values were unavailable, or the condition of Henry's Law Constant>0.00001 was not met for the inhalation pathway.

[2]    Water solubilities for Petroleum Carbon Range aliphatic C9-C16 and greater than C16 generally are considered to be effectively zero and therefore the aromatic solubility for C9-C16 is used.

[3]    * indicates a 'ceiling limit' concentration.

[4]    *** indicates that the solubility limit exceeds the 'ceiling limit' therefore the RBRG applies.

7.1.5                    Practice Guide for Investigation and Remediation of Contaminated Land

7.1.5.1                The EPD’s Practice Guide for Investigation and Remediation of Contaminated Land includes a summary of the general steps of a contamination assessment study, which include site appraisal, site investigation and remediation.

7.2                         Description of the Environment

7.2.1.1                As discussed in Section 2, the works area of the Project is located at the shore of Lai Chi Wo, mostly within Yan Chau Tong Marine Park, and partly within Plover Cove Country Park. Part of the works area is currently occupied by Lai Chi Wo Pier of approximately 64m long and 2.5m wide which would be subject to pier improvement works under the Project. The adjacent area of the Project is generally rural in character with Lai Chi Wo village located to about 400m southwest of the Project. The Project and its adjacent area are currently not covered by any Outline Zoning Plan (OZP). Figure 1.3 shows the works area of the Project.

7.3                         Assessment Methodology

7.3.1                    Overview

7.3.1.1                A land contamination assessment has been conducted according to the following procedures. The procedures listed below are further discussed in the following sections.

·               Identification of potentially contaminated sites;

·               Identification of potential for future land contamination; and

·               Recommending necessary mitigation measures, if necessary.

7.4                         Identification of Potentially Contaminated Sites

7.4.1                    General

7.4.1.1                To minimise the work areas and potential environmental impacts, the total area of the proposed site boundary/works area has been reduced 0.4ha from 1.93ha in the Project Profile to 1.53ha in the EIA Report. Within the latest works area, a desktop review of historical aerial photos, activities and relevant incidents in the works area was conducted to identify any potentially contaminated sites. After the desktop review had been completed, site walkover surveys were conducted to ground truth the findings. A summary of the key procedures to identify potentially contaminated sites is given below.

·               Review of aerial photographs;

·               Review of other relevant information; and

·               Site surveys.

7.4.2                    Aerial Photographs and Historical Land Uses

7.4.2.1                The aerial photos from Year 1945 to Year 2018 were reviewed to identify any historical land uses with potential of land contamination within the works area.  The review indicated that the works area comprises mainly natural terrain with village houses located to the northwestern and outside the works area.

7.4.2.2                The findings from reviewing the aerial photographs between 1945 and 2018 showing the works area of the Project are summarized in Table 7.3 and the aerial photographs are given in Appendix 7.1.

Table 7.3            Historical land use of the Project

Year

Description

1945

·             The first aerial photograph recorded the works area of the Project

·             The works area is rural in nature, only consisting of undeveloped land and sea

·             Neither pier nor other structures were identified within the works area.

1954

·             The last aerial photograph before a pier was built.

·             No significant change in land uses within the works area was observed as compared with those in Year 1945.

1956

·             The earliest aerial photograph recorded the presence of a pier.

·             A pier, which is shorter than the existing pier, was built at the location of the existing pier.

1963

·             No significant change in land uses within the works area was observed as compared with those in Year 1956.

·             Village settlements were observed to the northwest outside the works area. 

1978

·             No significant change in land uses within the works area was observed as compared with those in Year 1963.

·             The pier was lengthened when compared with the pier in 1963.

·             Plover Cove Country Park was designated in 1978. Lai Chi Wo was also partly included in the Country Park.

1986

·             No significant change in land uses within the works area was observed as compared with those in Year 1978.

2007

·             No significant change in land uses within the works area was observed as compared with those in Year 1986.

·             Part of the woodland to the west outside the works area was lost.

2018

·             The recent aerial photograph recorded the works area.

·             No significant change in land uses within the works area was observed as compared with those in Year 2007.

7.4.3                    Other Relevant Information

Fire Services Department

7.4.3.1                Fire Services Department (FSD) was contacted in August 2019 for:

·               The records of Dangerous Goods License(s); and

·               The reported accidents of spillage/leakage within the boundary of the Project.

7.4.3.2                Based on the latest information provided by FSD in September 2019, no record of dangerous goods licence was issued but six incident records were found at Lai Chi Wo in the past three years. The six incident records included four records of vegetation fire occurred at Lai Chi Wo, one record of rubbish fire on the Pier and one record of mountain rescue at Lai Chi Wo. None of the records were incidents of spillage/ leakage of dangerous goods within the boundary of the Project. Copy of FSD’s correspondence is provided in Appendix 7.2.

Environmental Protection Department

7.4.3.3                EPD was contacted in August 2019 for:

·               The records of Chemical Waste Producers Registration; and

·               The reported accidents of spillage/leakage within the boundary of the Project.

7.4.3.4                Based on the information provided by EPD in August 2019, there are neither registered Chemical Waste Producers and nor chemical spillage/ leakage records within the boundary of the Project. Copy of EPD’s correspondence is provided in Appendix 7.2.

7.4.4                    Site Survey

7.4.4.1                Site walkover surveys were conducted in August 2018, September 2018 and May 2019 to ground truth the findings of the desktop research and to identify any other potentially contaminated areas. Possible contaminants, if any, would be identified in accordance with EPD’s Practice Guide for Investigation and Remediation of Contaminated Land.

7.4.4.2                Photo records of the site walkover surveys are shown in Appendix 7.3 and descriptions are provided in Table 7.4 below. The site walkover checklist is given in Appendix 7.4.

Table 7.4            Descriptions of site photos

Photo ID

Description

Photo 1

The photo shows the existing pier with a navigation light and landing steps from the sea. By site observation, there were neither oil stains nor land contaminating activities. No signs of land contamination were observed.

Photo 2

The photo shows the natural muddy shore to the southwest of the pier. By site observation, there were neither oil stains nor land contaminating activities. No signs of land contamination were observed.

Photo 3

The photo shows the natural sandy shore with patches of grasslands from the north of the pier. On the right is the natural slope of Plover Cove Country Park. By site observation, there were neither oil stains, stressed vegetation nor land contaminating activities. No signs of land contamination were observed.

Photo 4

The photo shows the concrete-paved pier walkway from the landside towards the seaside. By site observation, there were neither oil stains nor land contaminating activities. No signs of land contamination were observed.

Photo 5

The photo shows the concrete-paved pier walkway from the seaside towards the landside. By site observation, there were neither oil stains nor land contaminating activities. No signs of land contamination were observed.

Photo 6

The photo shows the signage next to the hiking trails. By site observation, there were neither oil stains, stressed vegetation nor land contaminating activities. No signs of land contamination were observed.

Photo 7

The photo shows the pier to the southwest of the pier. By site observation, there were neither oil stains nor land contaminating activities. No signs of land contamination were observed.

Photo 8

The photo shows the natural slope to the west of the pier. Wood pallets were also found right next to the hiking trail.  By site observation, there were neither oil stains, chemical containers, stressed vegetation nor land contaminating activities. No signs of land contamination were observed.

Photo 9

The photo shows the wood pallets right next to the hiking trail. By site observation, there were neither oil stains, chemical containers, stressed vegetation nor land contaminating activities. No signs of land contamination were observed.

Photo 10

The photo shows the natural sandy shore with patches of grasslands from the north of the pier. By site observation, there were neither oil stains, stressed vegetation nor land contaminating activities. No signs of land contamination were observed.

7.4.4.3                The existing pier is a straight solid concrete finger pier of about 64m long and 2.5m wide. A navigation light is at the head of the pier and two bollards are located on each side of the pier. Two sets of 1m high galvanised steel tubular railing are along the southwestern edge of the existing pier. According to FSD’s latest information, there was a rubbish fire occurred on the pier on 12 November 2018. During the site walkover survey conducted in May 2019 after the incident of the rubbish fire, neither oil stains, stressed vegetation, chemical containers nor land contaminating activities were identified at the existing pier or the proposed works area at the landside. As such, no potential land contamination issue is anticipated in the Project site.

7.4.5                    Summary

7.4.5.1                Based on the review of the aerial photos, the information from EPD and FSD and the findings from ground-truthing, no potentially contaminated areas have been identified in the Project Site.

7.5                         Conclusion

7.5.1.1                This land contamination assessment has examined the potential contaminative land uses within the boundary of the Project. Based on the desktop review findings of the aerial photos, the information collected during site surveys as well as the information provided by EPD and FSD, no potential land contamination issue is identified within the boundary of the Project. Further site investigation or mitigation measures are therefore not required.