Contents

 

                                                                                                                                                                                                

13          Summary of Environmental Outcomes  13-1

13.1         General 13-1

13.2         Environmental Friendly Options Considered and Incorporated to Avoid Environmental Impact 13-1

13.3         Environmental Designs Recommended to Minimise and Mitigate Environmental Impacts  13-2

13.4         Summary of Key Environmental Problems Avoided and Sensitive Areas Protected  13-4

13.5         Estimated Population Protected from Various Environmental Impacts  13-5

13.6         Environmental Benefits of Environmental Protection Measures Recommended  13-5

 

Appendix

 

5.      Do not delete this. This is for Table Number.

 


13                          Summary of Environmental Outcomes

13.1                    General

13.1.1.1            This section summarises the overall environmental outcomes due to the construction and operation of Lai Chi Wo (LCW) Pier in accordance with Section 3.6.1 of the Environmental Impact Assessment (EIA) Study Brief No.: ESB-305/2017. It can be seen in Section 1 and Section 2 that environmental considerations have been the key considerations throughout the development of the Project. Alternative options for designs and construction methodologies have been duly considered.  Besides, all the options considered have ensured that environmental impacts could be avoided or minimised where practicable and mitigated by implementation of suitable mitigation measures to fulfil all the statutory requirements. The technical assessments conducted (Section 3 to Section 11) have demonstrated that all the statutory requirements in the EIA Study Brief (ESB-305/2017) and Technical Memorandum of the Environmental Impact Assessment Ordinance (TM-EIAO) have been compiled with.

13.1.1.2            The following sections summarise the approaches that have been adopted to either avoid or minimise various environmental impacts throughout the design process, and the associated environmental enhancements.

13.2                    Environmentally Friendly Options Considered and Incorporated to Avoid Environmental Impact

13.2.1.1            Avoidance of environmental impacts has been one of the key considerations throughout the entire project development and design. The environmental impacts that have been avoided are listed and discussed below:

·               Avoidance of open sea dredging works;

·               Avoidance of wastewater / effluent discharge during both construction and operational phases; and

·               Avoidance of solid pier design.

13.2.2               Avoidance of Open Sea Dredging Works

13.2.2.1            As discussed in Section 8, the Project is located within the Yan Chau Tong Marine Park and next to the seagrass bed. The ecological surveys conducted have concluded that the ecological value of the seagrass bed is High (see Section 8.4.4 for the ecological evaluation). The seagrass bed is sensitive to any suspended solids that may be generated during the construction phase of the Project.

13.2.2.2            In order to avoid any adverse water quality impacts and hence ecological impacts on the seagrass bed in close proximity to the Project, the design has been very mindful on the configuration and design of the pier. According to the proposed design, open sea dredging works would be totally avoided during the construction phase. By avoiding open sea dredging works, any adverse water quality impacts and hence impacts on marine ecological resources during the construction phase would be minimised as much as practicable.

13.2.3               Avoidance of Wastewater / Effluent Discharge During both Construction and Operational Phases

13.2.3.1            Given that the Project is within the Yan Chau Tong Marine Park which is a Water Sensitive Receiver (see Section 5.3), it is important to implement all practicable measures to avoid any discharge of waste water / effluent discharge into Yan Chau Tong Marine Park during both the construction and operational phases.

13.2.3.2            During the construction phase, the potential impacts that would be generated by the construction team has been assessed in detail (see Section 5.4.2). The Contractor will be prohibited to discharge any wastewater and effluent into the Yan Chau Tong Marine Park. Any wastewater and effluent that would be generated during the construction activities would be transported away for proper treatment and disposal.

13.2.3.3            During the operational phase, the Project has been designed to avoid any need for using detergents/chemicals during routine maintenance (see Section 5.5). This would therefore avoid any potential water quality impacts on the Yan Chau Tong Marine Park.

13.2.4               Avoidance of Solid Pier Design

13.2.4.1            The Project is located at the eastern coastal area of Crooked Harbour near Lai Chi Wo. The cove is partly surrounded by the natural terrain with a wide coastal inlet of about 800m.

13.2.4.2            The existing pier is a straight solid concrete structure. In order to minimise any additional impacts caused by the proposed pier improvement works, the structure of the proposed pier would adopt concrete decks on top supported by piled foundation. The proposed pier is extending from the existing pier towards the area with deeper water region of about -2.4mPD to the east. The diameter of the foundation would be approximately 0.8m to 1m and the column-to-column spacing is approximately 5m to 8m. Such a configuration is typical for other similar piers in Hong Kong, for instance, Sai Kung Public Pier.

13.2.4.3            Due to small footprint of the new supportive piles, changes in the flow regime and hydrodynamic in the eastern coastal area of Crooked Harbour are limited. The proposed pier improvement works have minimised any impacts on hydrodynamics as much as practicable. Details are provided in Section 5.5.

13.3                    Environmental Designs Recommended to Minimise and Mitigate Environmental Impacts

13.3.1.1            Other than initiatives to avoid environmental impacts as summarised in Section 13.2, efforts have been exercised to minimise those inevitable impacts. The need for any environmental designs required to mitigate the associated impacts have also been identified and will be implemented as appropriate. A summary of these approaches is given below.

·              Minimisation of works in Country Park;

·              Minimisation of waste generation during construction phase; and

·              Minimisation of construction vessels during construction phase.

13.3.2               Minimisation of Works in Country Park

13.3.2.1            As discussed in Section 1.2, the Plover Cove Country Park is located immediately next to Yan Chau Tong Marine Park at Lai Chi Wo. The existing connecting walkway between the pier and the footpath to Lai Chi Wo falls within the Country Park.

13.3.2.2            Due to the pier improvement works, the connecting walkway made of concrete will be inevitably constructed between the proposed LCW pier and the existing footpath to Lai Chi Wo due to the level difference in between. The connecting walkway partly falls within the intertidal shore of Plover Cove Country Park (PCCP) (occupied around 0.0054 ha) as illustrated in Figure 1.3.

13.3.2.3            During the pier improvement works, depending on the construction method to be proposed by the Contractor, it might not be possible for the vessels to berth the existing pier, and hence a temporary pier will then be constructed or provided to maintain the pier operation during construction works. A temporary connecting walkway will also need to be constructed to connect the temporary pier and the existing footpath to Lai Chi Wo and located within the intertidal shore near the boundary of PCCP (occupied around 0.0026 ha).

13.3.2.4            The proposed works area for two connecting walkways has been limited (e.g. only 2m wide on each side of both walkways would be occupied) and part of the connecting walkways falls within the PCCP (occupied around 0.0061 ha).

13.3.2.5            Based on the ecological survey results, the ecological values within the occupied area of intertidal shore at the boundary of the PCCP are ranked as Low to Moderate.

13.3.2.6            The woodlands in PCCP are important land-based ecological resources.  According to the proposed pier improvement work, all the land-based construction activities would be limited to within 7m from the exiting coastline. Only small and/or manual handling equipment shall be deployed to construct the walkway, hence would totally avoid disturbance to the woodlands and natural slope in the PCCP. Adverse ecological impact on the natural habitats in the PCCP is not anticipated.

13.3.3               Minimisation of Waste Generation During Construction Phase

13.3.3.1            The pier improvement works for LCW Pier endeavour to minimise the waste generation in relation to integrate the structures of the existing pier to the new pier structures. It therefore minimises the generation of over 400m3 construction and demolition (C&D) materials disposed of to the landfills/public fill banks if the whole pier was demolished and reconstructed.

13.3.3.2            The Project will limit works on land and avoids tree felling during the construction of pier. Hence, it minimises vessel trips required for the delivery of C&D materials and waste from the remoted Project site to the disposal sites. As such, disturbance from the marine vessels to the marine park can be minimised.

13.3.3.3            Section 6.3 has assessed all the practicable approaches to minimise the waste generation during the construction phase. Amongst the approaches adopted, the most effective approach is to adopt pre-cast elements for the deck as much as practicable. By adopting this approach, most of the elements for the deck would be pre-cast off-site and then transported to the site for final assembly.

13.3.4               Minimisation of Construction Vessels During Construction Phase

13.3.4.1            As open sea marine dredging would be avoided and pre-cast elements would be adopted as much as practicable, the number of construction vessels during the construction phase would also be minimised.  Since the Project is located within the Yan Chau Tong Marine Park, it is inevitable that the construction vessels will travel within the marine park.  Hence, by minimising the number of construction vessels required, any indirect impacts caused by those vessels on the marine park would also be minimised as well.  Nevertheless, appropriate good practices would be adopted by the Contractor to operate the construction vessels.

13.4                    Summary of Key Environmental Problems Avoided and Sensitive Areas Protected

13.4.1.1            Section 13.2 and Section 13.3 have summarised the key approaches adopted in the current proposed layout to avoid, minimise and mitigate environmental impacts. Some of these approaches have contributed to avoid a number of environmental issues and to protect a number of environmentally sensitive areas. Table 13.1 presents the key environmental problems that have been avoided and any sensitive areas protected by these approaches.

Table 13.1            Key Environmental Problems Avoided and Sensitive Areas Protected

Design Approach

Key Environmental Problems Avoided, Sensitive Areas Protected & Environmental Outcomes Achieved

Avoidance of open sea dredging works

·         Adverse impacts on water quality and ecology would be avoided.

Avoidance of wastewater / effluent discharge during both construction and operational phases

·         Adverse impacts on water quality would be avoided.

Avoidance of solid pier design

·         Adverse impacts on water quality would be avoided.

Minimisation of works in Country Park

·         Adverse impacts on ecology would be minimised.

Minimisation of waste generation during construction phase

·         Generation of waste during construction phase would be minimised.

Minimisation of construction vessels during construction phase

·         Adverse impacts on air quality and noise would be minimised.

13.5                    Estimated Population Protected from Various Environmental Impacts

13.5.1.1            The Project has been carefully designed to protect the populations from various environmental impacts. The protected populations include the following:

·               Existing sensitive receivers of Lai Chi Wo Village would be protected from air quality impact by implementation of mitigation measures during construction phase of the Project.

13.6                    Environmental Benefits of Environmental Protection Measures Recommended

13.6.1.1            In addition, mitigation measures/good site practices/ enhancement measures have been recommended to further reduce the environmental impacts due to construction and operation of the Project. Key recommended mitigation measures/good site practices/ enhancement measures and their associated benefits are summarised in Table 13.2 below.

Table 13.2    Key Recommended Mitigation Measures/Good Site Practices/Enhancement Measures and their Associated Benefits

Aspect

Key recommended mitigation measures/good site practices/enhancement measures

Associated Benefits

Air Quality

·         Routing of barges used for delivery of goods should be as far away from the identified ASRs as practicable.

·         The number of boat trips should be minimised as far as practicable by appropriate planning.

·         Protect air sensitive receivers by reducing fugitive dust emission

Noise

·         Use of Quality Powered Mechanical Equipment (QPME).

·         Use of temporary noise barriers to screen noise from relatively static Powered Mechanical Equipment (PME).

·         Alternative use of plant items within one worksite, wherever practicable.

·         Protect noise sensitive receivers by reducing construction noise impact

Water Quality

·         Water quality monitoring.

·         Adoption of good site practices for foundation works, such as use of silt curtains and pile casings, to avoid and minimise water quality impacts.

·         Excavation should only be conducted inside pile casing. Only one grab should be used at the same time.

·         Only 1-2 piles to be constructed at the same time.

·         Prefabrication construction method should be adopted as far as practicable.

·         Contractor to prepare Emergency Spillage Plan for accidental spillage of chemicals.

·         Protect the neighbouring water sensitive receivers such as coral, seagrass and mangrove

Waste Management

·         Good waste management and control practices to avoid generation of excessive amount of waste materials.

·         Employ waste collectors for disposal of general refuse to prevent potential nuisance caused by mistreating general refuse, such as windblown, vermin, water pollution and visual impact.

·         Good management practices for handling and disposal of marine sediments at dedicated marine disposal sites.

·         Minimise waste generation

·         Ensure proper handling of chemical waste

Land Contamination

·         No mitigation measures would be required.

·         No land contamination anticipated

Ecology

·         Seagrass monitoring

·         Pre-construction dive survey to verify the conditions of small coral colonies on the existing LCW pier before construction works

·         Avoidance of encroaching the trees in particular within the country park.

·         Priority using eco-tiles or eco-concrete for the surface of the foundation to promote seamless integration of biodiversity into the pier design.

·         Minimise the impact to coral, seagrass bed and mangrove stand in proximity to the Project

·         Protect trees in country park

·         Enhance biodiversity of the site

Landscape and Visual

·         Sensitive design and disposition of the pier structures to minimise visual intrusion to VSRs as far as practicable.

·         Enhance the visual appearance for the operational phase

Fisheries

·         Avoidance of mariculture site and waters of high fisheries production

·         Adoption of good site practices for water quality in marine works to ensure no adverse fisheries impact would be anticipated.

·         Protect fisheries resources

Cultural Heritage

·         No mitigation measures would be required.

·         No impact of cultural heritage anticipated