4.0      Hazard Assessment 4-1

4.1            Introduction. 4-1

4.2            Assessment Objectives. 4-1

4.3            Risk Criteria. 4-2

4.4            Project Description. 4-2

4.5            Overview of Hazard Assessment Methodology. 4-2

4.6            Hazard Review Study. 4-3

4.7            Quantitative Risk Assessment 4-8

4.8            Population Estimation. 4-15

4.9            Risk Summation. 4-20

4.10          Sensitivity Analysis. 4-21

4.11          Risk Mitigation Measure. 4-22

4.12          Conclusion. 4-22

4.13          References. 4-22

 

TABLES

Table 4.1         Distance between Hazardous Facilities and Helicopter Flight Paths

Table 4.2         Crash Rates for Hazardous Facilities

Table 4.3         Hazard Scenarios Considered in the previous Kai Tak QRA for LPG Filling Station

Table 4.4         Hazard Scenarios Considered in the previous Kai Tak QRA for KDGW

Table 4.5         Failure Event Frequencies for LPG Filing Station

Table 4.6         Event Frequencies for KDGW

Table 4.7         Consequences Data of Building Collapse Scenario for KDGW

Table 4.8         Consequences Data of Catastrophic Failure Scenario of a Storage Vessel for LPG Filling Station

Table 4.9         Wind Direction Frequencies

Table 4.10       Population Category Distributions

Table 4.11       Indoor and Outdoor Ratios

Table 4.12       Building Population Assumptions

Table 4.13       Core Station and Coverage Stations near Kai Tak Area

Table 4.14       Representative Time Periods for Road Population Surveys

 

FIGURES

Figure 4.1       Societal Risk Criteria in Hong Kong

Figure 4.2       Location of the Proposed Helipad at New Acute Hospital and Adjacent Hazardous Facilities

Figure 4.3       Distance from the Helipad to the LPG Filling Station and KDGW

Figure 4.4       Helicopter Flight Paths

Figure 4.5       QRA Methodology

Figure 4.6       Maximum Hazard Zones from KGDW and LPG Filing Station

Figure 4.7        Individual Risk Contours for the KDGW

Figure 4.8       Individual Risk Contours for LPG Filling Station
Figure 4.9       Cumulative Individual Risk Contours for LPG Filling Station and KDGW

Figure 4.10     Societal Risk Results for LPG Filling Station
Figure 4.11     Societal Risk Results for the KDGW
Figure 4.12     FN Curve for Sensitivity analysis for the LPG Filling Station
Figure 4.13     FN Curve for Sensitivity analysis for the KDGW
Figure 4.14     FN Curve for Population Sensitivity analysis for the LPG Filling Station
Figure 4.15     FN Curve for Population Sensitivity analysis for the KDGW

 

APPENDICES

Appendix 4A  Comparison of land use type assumed in Kai Tak QRA against the latest OZP

Appendix 4B   Population Estimation

Appendix 4C   LPG Filling Station Operation Data and Fault Tree Analysis (FTA)

Appendix 4D   PHAST RISK Input Parameters of LPG Station

Appendix 4E   Calculation details for Event Frequency Associated with Helicopter Crash

Appendix 4F   PHAST RISK Input Parameters of Kerry Dangerous Goods Warehouse



4.0              Hazard Assessment

 

4.1                Introduction

 

4.1.1.1       The New Acute Hospital (NAH) in Kai Tak Development Area will be the main acute hospital services provider in the central Kowloon region. As part of the acute hospital with trauma facilities, a helipad will be built at the rooftop of the Acute Block of the NAH, where the Accident & Emergency Department is located.

4.1.1.2       The helipad will be installed and operated at the west corner on the roof of the proposed Acute Block of NAH, there will be no fuelling facilities provided in the proposed rooftop helipad. The rooftop helipad design will meet the ¡¥ICAO Standards for Heliport Design¡¦ and ¡¥Government Flying Service Helicopter Landing Site Specification Guidelines¡¦.

4.1.1.3       The EIA requirements for the proposed helipad are detailed in EIA Study Brief No. ESB-311/2019[1]. As stated in Section 3.2.1 of the brief [1], the EIA study shall address potential hazard to life impact during the construction and operation of the helipad due to the potentially hazardous facilities, including in particular the Kerry Dangerous Goods Warehouse (Kowloon Bay) (KDGW) at 7 Kai Hing Road and the LPG Filling Station at Cheung Yip Street.

4.1.1.4       This chapter presents the methodology, results, and findings of the Hazard Assessment, including Quantitative Risk Assessment (QRA), as part of the EIA study for the proposed helipad project.

4.2                Assessment Objectives

 

4.2.1.1       The main objective of the Hazard Assessment has been to demonstrate that the risk criteria set out in Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO)[2] will be met during the construction and operational periods of the helipad, and to identify practical mitigation measures to reduce the risk, where required.

4.2.1.2       The detailed scope of hazard assessment includes the following:

¡P           Undertaking a review of the risks from the KDGW and the LPG Filling Station to the Project to determine if risk to life is a key issue with respect to the Risk Guidelines given in Annex 4 of the TM-EIAO [2];

¡P           Identification of hazardous scenarios associated with the LPG Filling Station and the KDGW during the construction and operational phases of the helipad;

¡P           Prepare a QRA to estimate the risks to the surrounding population in both individual and societal terms;

¡P           Compare Individual Risks (IR) and Societal Risks (SR) with the TM-EIAO Criteria to determine the acceptability of the Project in terms of risk; and

¡P           Identify and assess practicable and cost effective risk mitigation measures, to demonstrate compliance with the Risk Criteria (Figure 4.1), if the risk is determined to be not ¡¥Acceptable¡¦.

4.3                Risk Criteria

 

4.3.1.1       The risk guidelines are stipulated in the TM-EIAO Annex 4 to determine the risk acceptability. The risk guidelines and criteria comprise the following two components:

1.      Individual Risk: the maximum level of off-site individual risk should not exceed 1 ¡Ñ 10-5 / year, i.e. 1 in 100,000 per year; and

2.      Societal Risk: Societal risk is expressed in the form of an F-N curve, which represents the cumulative frequency (F) of all event outcomes leading to N or more fatalities. The F-N curve criteria are shown in Figure 4.1. The three different regions are defined as:

¡P         Unacceptable region: where risk is so high that they should usually be reduced regardless of the cost or else the hazardous activity should not proceed;

¡P         ALARP region: where risk is tolerable, provided that it has been reduced to a level As Low As Reasonably Practicable (ALARP); and

¡P         Acceptable region: where risk is broadly acceptable and does not require further risk reduction.

4.4                Project Description

 

4.4.1.1       The proposed helipad will be located on the rooftop of the Acute Block of the NAH, at the south of Kai Fuk Road and Kwun Tong Bypass, as shown in Figure 4.2. The LPG Filling Station, a dedicated filling station, is located at Cheung Yip Street, about 211m from the proposed helipad. The KDGW is located at 7 Kai Hing Road, about 265m from the proposed helipad. Both facilities are within the Kai Tak Development Area and their locations relative to the Project site shown as region 1 and 2 respectively in Figure 4.3.

4.4.1.2       The current zoning of the KDGW site is "Commercial" under the approved Kai Tak Outline Zoning Plan No. S/K22/6[3]. According to Planning Permission Case No. A/K22/27, a proposal for minor relaxation of plot ratio restriction has been applied and is under review at the time of the preparation of this EIA report, and the information or development programme of the existing KDGW site is also not confirmed at the time of preparing this EIA report. As detailed in Section 4.6, the tentative date for the commencement of operations of the helipad would be in 2025. However, as the timing for the KDGW redevelopment has not been confirmed to be before this date, this facility has been included in this assessment.

4.5                Overview of Hazard Assessment Methodology

 

4.5.1.1       According to the Project EIA Study Brief [1], a review of the risks from the KDGW and the LPG Filling Station shall be conducted to examine whether the risk to life is a key issue with respect to Risk Guidelines given in Annex 4 of the TM.  A QRA is required if, and only if, risk to life is considered to be a key issue.

4.5.1.2       A hazard review study has been performed to determine if the risks associated with the proposed helipad are significant.  Consideration has been given to both the risks due to impact from the KDGW and the LPG Filling station on the proposed helipad, and vice versa.  If the increase in frequency of the hazardous events is anticipated to be above 1 ¡Ñ10-9 per year, which is the lower limit of the societal criteria of Hong Kong, then it is considered to be significant requiring further assessment using a detailed QRA approach (Section 4.7). With the frequency screening criterion of 10-9 per year, the individual risk would also be covered since the individual risk criterion of Hong Kong concerns only the risk level at 10-5 per year, which is in principle, not affected if the frequency increase, is below 10-9 per year.

4.5.1.3       If a QRA is considered to be necessary, it will be performed following the traditional QRA methodology, as outlined in Figure 4.5, which includes the following key steps:

¡P           Hazard Identification;

¡P           Consequence Analysis;

¡P           Frequency Analysis; and

¡P           Risk Summation and Assessment.

4.5.1.4       The QRA also presents an update of the previous QRA Study for the KDGW and the LPG Filling station carried out under the approved EIA report for Kai Tak Development (Kai Tak QRA)[4], including the additional consideration of the impact due to the proposed helipad. Where appropriate, the latest available information of the area including the population data (Section 4.8) has been considered in the QRA update.

4.5.1.5       The methodology and assumptions used in the QRA have made reference to the following three previously approved EIA studies:

¡P           Kai Tak Development Environmental Impact Assessment Report. Hong Kong, 2006 (AEIAR-130/2009)[4];

¡P           A Rooftop Helipad at the Proposed New Block at Queen Mary Hospital Environmental Impact Assessment. Hong Kong, 2017 (AEIAR-208/2017)[5]; and

¡P           Engineering Study for Police Facilities in Kong Nga Po ¡V Feasibility Study, Hong Kong, 2016 (AEIAR-201/2016)[6].

4.6                Hazard Review Study

 

4.6.1           Review of Impact from Proposed Helipad

4.6.1.1       During the construction and operational phases of the helipad, the impact on the two facilities of concern have been reviewed as follows:

¡P           Construction Phase: the construction phase of the helipad will introduce additional worker population to the area, which, albeit temporary, may lead to an increase in the societal risk levels associated with the operations of KDGW and the LPG filling station. Therefore, an assessment has been carried out to examine whether such an increase in risk is considered to be significant with respect to the societal risk criteria adopted in Section 4.3.

¡P           Operational Phase: a frequency assessment has been carried out to examine whether the operation of the proposed helipad will lead to any significant increase in risk, with respect to the Hong Kong Risk Criteria, to the hazardous facilities in the vicinity due to potential helicopter crash accidents. The frequency assessment for helicopter crashes makes reference to the methodology given in the report prepared by UK HSE[7] and is consistent with the previous EIA study in Hong Kong (AEIAR-130/2009)[4]. The individual risk has been evaluated based on the helicopter crashes rate. Besides that, the impact on societal risk associated with the additional population associated with the operational phase of the helipad has also been considered in the assessment.

Construction Phase Assessment

4.6.1.2       The impact from the helipad construction activities would be related to the increased population (i.e. construction workers) in the vicinity of the two sites of concern, which may in turn lead to an increase in the societal risk. As per the construction plan, the construction phase of the helipad will last over a period of 12 months, commencing towards the end of the construction for the NAH. The maximum number of workers involved in the helipad construction phase is anticipated to be about 20. However, given that the construction of the helipad will be undertaken partly in parallel to the construction of the NAH, this number of workers for helipad construction phase is not considered to be significant compared to the overall workforce that will be required. In addition, the construction of helipad would only involve line painting and supporting frame, landing platform, lighting system, fire services facilities, covered safety walkway and equipment in the final construction stage of the hospital, as majority of the helipad deck would be comprised of prefabricated steel work conducted at off-site premises. Hence, the increase in risk due to the helipad construction alone is not considered to be significant compared to the expected background risk level during the period of the overall hospital construction. Besides, the number of personnel during the construction phase is considered much less than the population during the operation phase. Nevertheless, the risk assessment for the KDGW and the LPG Filling station during the helipad construction phase is presented in Section 4.9 for completeness. 

Operational Phase Assessment

Impact on Overall Exposed Population

4.6.1.3       During the operational phase, the hospital staff will be responsible for the helipad operations with no additional dedicated staff solely responsible for the helipad. As advised by the Government Flying Service (GFS), the maximum capacity of the helicopter would be about 20 people. For the typical casualty evacuation (CASEVAC) event, there would be approximately 10 people including aircrew (i.e. Captain, Co-pilot, winch operator and winchman, air medical officer and air medical nurse officer and escort) and patient(s) in the helicopter.

4.6.1.4       In addition for a single CASEVAC event, one patient is expected normal, but in some rare instances up to several patients may be possible.

4.6.1.5       These staff members are regarded as transient populations, who will be presented only during helipad operations.  Also, this size of helicopter crew would not be significant as compared to the total population of the hospital.  Therefore, there is no significant increase in population during the operational phase of the proposed helipad, in addition to the hospital personnel.

 

Helicopter Crashes Scenarios

4.6.1.6       Considering the nature of the helipad, the key potential hazard has been identified as the potential impact on the KDGW and the LPG filling station in the case of a helicopter crash.

4.6.1.7       The probability of a helicopter crash for a given target near the helipad, and its associated flight paths, can be approximated using the methodology given by UK HSE[7], which is consistent with the previous Kai Tak QRA (AEIAR-130/2009)[4]. Based on this methodology, the total helicopter crash rate for a specific site comprises of 3 components, which are:

¡P           the background crash rate[7];

¡P           the helipad related crash rate, that is, landings and take-offs; and

¡P           the crash rate below flight paths, that is the flight paths.

4.6.1.8       As specific routes are known to be used on a regular basis, it is then possible to treat these routes as airways and crash rates for the routes can be calculated.(see Section 4.5 of AEA paper[7]). The methodology given by UK HSE [7] suggests that any facility lying under the flight paths associated with the helipad, or situated within a 200 m radius from the helipad, could be subjected to a potential increase in risk due to accidental helicopter crash. Beyond this range, the risk imposed by the helipad to other locations is generally considered to be not significant and can be regarded as the same as the baseline risk level elsewhere due to the background air traffic [7], that is, the background crash rate.

4.6.1.9       In Figure 4.3, both the KGDW and the LPG filling station are located beyond 200m from the centre of the helipad; hence, the risks associated with helipad related crashes are also considered to be negligible[7].  Therefore, only the risk relating to helicopter crashes below flight paths are relevant for assessment.

Helicopter Crash Frequency below Flight Paths

4.6.1.10     Based on the project information, the helicopter model to be used will be the Airbus H175, which is being operated by the GFS. The annual number of helicopter movements depends upon the requirement for emergency services which may vary from year to year, and the project also does not have any estimation on this figure. Currently, public hospitals under the Hospital Authority (HA) provided with helipad facilities include Pamela Youde Nethersole Eastern Hospital (PYNEH) and Tuen Mun Hospital (TMH). According to the usage data from PYNEH and TMH between 2007 to 2019, PYNEH has the highest number of helicopter operations; hence, the PYNEH figure has been used to provide a reasonably conservative estimation for the new helipad usage. It should also be noted that the data for PYNEH does not show any downward or upward trend in the number of helicopter movements over the years.

4.6.1.11     The emergency helicopter operation records at the PYNEH indicate that the maximum number of helipad operations has been 295 per year between 2007 and 2019. In order to adopt a conservative approach, the annual number of helicopter movements for the proposed helipad has been assumed to be 330 for the purposes of this assessment. Note that the annual number of helicopter movements of 330 is applied to the base and future cases in Section 4.10.

4.6.1.12     Figure 4.4 presents the helicopter flight paths associated with the proposed helipad, as agreed with the GFS, and the distances from the concerned hazardous facilities to each flight path are summarised in Table 4.1. The Flight Path W is not considered relevant here, since the two facility sites are on the eastern side of the helipad while the flight path is on the western side, as indicated in Figure 4.4, and, thus, this flight path does not cross both the sites.

Table 4.1 Distance between Hazardous Facilities and Helicopter Flight Paths

Site

Distance/m

Flight Path NE

Flight Path SE

Flight path W

KDGW

116

116

N/A

LPG filling station

0.00

211

N/A

 

4.6.1.13     The rate of aircraft crashes below flight paths is given by the following equation [7]:

Where:

CA is in km-2yr-1,

NA is the annual number of helicopter movements on the flight path,

RA is the aircraft inflight reliability. The in-flight reliability is given according to the aircraft category[7]. For helicopters, the in-flight reliability is 1¡Ñ10-7 crashes per flight km [7] .

The area factor, afac, takes into account the mean flight path attitude and the minimum distance from flight path to the concerned sites.

For the purpose of this analysis, the altitude of the flight path, alt, has been assumed to be the same as the height of the helipad which is 119.15 mPD [1] or 117.85 m from Mean Sea Level[16]. This is considered to be a conservative assumption to account for the lower altitude operations of helicopter when it is approaching (or leaving) the helipad in the area.

4.6.1.14     As there are three flight paths associated with the helipad, the total annual number of helicopter movements is assumed to be equally distributed between the three flight paths, leading to 110 annual number of helicopter movements for each flight path. As will be seen in the later section of this report, a sensitivity analysis has been included in the QRA to evaluate the impact of this usage distribution on the overall risk level.

4.6.1.15     Based on the above equation, the crash rate below flight paths for each hazardous site has been calculated, as presented in Table 4.2 Since the estimated crash rates are not insignificant (>10-9 per year), the scenarios have been further assessed in the QRA (Section 4.7).

Table 4.2 Crash Rates for Hazardous Facilities

Site

Annual Crash Rate

(per unit area / km-2yr-1)

Area of the Target Site (km2)

Crash Rate

(per Year)

KDGW

4.56¡Ñ10-5

4.18¡Ñ10-3

1.91¡Ñ10-7

LPG Filling Station

4.52¡Ñ10-5

1.12¡Ñ10-3

5.05¡Ñ10-8

 

Consequence Assessment for Helicopter Crash

4.6.1.16     In the event of a helicopter crashing onto either the KDGW or the LPG Filling Station, the consequence is expected to be catastrophic. Similar catastrophic events have been assessed in the previous EIA study (AEIAR-130/2009)[4], and the worst-case scenarios are extracted as follows:

¡P           Major Warehouse Fire (building collapsed) for KDGW (Scenario ID D-WF-EX of Table 11.4.13 in (AEIAR-130/2009)[4]);

¡P           LPG Fire Loss Area (building collapsed) for KDGW (Scenario ID D-LF-EX of Table 11.4.13 in (AEIAR-130/2009)[4]);

¡P           Pentane Fire Loss Area (building collapsed) for KDGW (Scenario ID D-PF-EX of Table 11.4.13 in (AEIAR-130/2009)[4]);

¡P           Chlorine toxic release (building collapsed) for KDGW (Scenario ID DG-CT-W of Table 11.4.13 in (AEIAR-130/2009)[4]);

¡P           Ammonia toxic release (building collapsed) for KDGW (Scenario ID DG-AT-W of Table 11.4.13 in (AEIAR-130/2009)[4]);and

¡P           Catastrophic Failure of LPG Storage Vessel for LPG filling station (Scenario 1 of Table 11.5.6 in (AEIAR-130/2009)[4]).

4.6.1.17     The potential helicopter crash scenarios due to the proposal helipad are considered to increase the event frequency of these catastrophic events. According to the previous Kai Tak QRA[4], extreme events represent those accidents relating to extreme initialising events such as earthquake, which would lead to building collapse. The consequence of a helicopter crash on the KDGW would fall in this category. The results of the frequency calculation can be found in Section 4.7.4.

4.6.2           Review of Impact from KDGW and LPG Filling Station

4.6.2.1       As shown in Figure 4.4, the flight paths of the helicopter are close to the airspace above the LPG Filling station and the KDGW.  Adopting the method used in the EIA report for Operation of the Existing Tai Lam Explosives Magazine at Tai Shu Ha, Yuen Long for Liantang / Heung Yuen Wai boundary Control Point Project (AEIAR-193/2015)[15], the potential impact on the passing helicopter can be estimated.

4.6.2.2       With regard to the LPG Filling Station, according to paragraph 11.5.61 of the previous Kai Tak QRA[4], the maximum LPG cloud height calculated is 10m for all continuous release events using the dense gas dispersion models as per the previous EIA[4]. Therefore, only instantaneous releases, namely ¡¥Catastrophic Failure of a Storage Vessel¡¦ and ¡¥Catastrophic Failure of Road Tanker¡¦ are considered to be relevant, having the potential for impacting the passing helicopters.  The frequency of impact on any point along the flight paths can be calculated as the sum of the two event frequencies which is 2.36¡Ñ10-6 per year.

4.6.2.3       The maximum consequence distance of the concerned scenario is 259m based on the LPG filling station QRA. The total helicopter movements are 220 annually along Flight Path SE and Flight Path NE (Section 4.6.1.14). The approaching speed of the helicopter (Airbus H175) is conservatively assumed to be 60 km/h[a]. On this basis, the transit time of a helicopter along the concerned section of flight path has been approximated to be 31 seconds. The presence factor is, therefore, calculated as 2 ¡Ñ 110 ¡Ñ 31 / (365 ¡Ñ 24 ¡Ñ 3600) = 2.17¡Ñ10-4, which results in a probability of potential impact of 2.36¡Ñ10-6¡Ñ2.17¡Ñ10-4= 5.12¡Ñ10-10 per year.

4.6.2.4       A significant warehouse fire scenario at KDGW can result in a smoke plume impacting the passing helicopter, if the smoke plume encroaches upon the flight paths. A smoke plume generated from a fire follows the tilt angle of the flame initially and rises upward due to high buoyancy caused by high temperature. Plume Height (H) can be calculated as L ¡Ñ tan(90¢X - tilt angle), where L is horizontal distance from the fire size based on Section 11.4.129 of the previous EIA[4]. The tilt angle should be set as 60¢X to represent the worst case scenario. Using this equation, the smoke plume height is estimated as 67m, considering a distance of 116 m between KDGW and the flight paths. Since helicopters at this segment of the flight path are anticipated to remain above an altitude of 117.85 m from Mean Sea Level, smoke plume encroaching upon the flight paths is considered to be possible. However, in the event of a fire accident at KDGW, the resulting fire and smoke plume will be visible to the pilot, who can take necessary actions to avoid approaching near the smoke plume. Therefore, the impact of the smoke plume has not been considered further in this QRA. As per paragraph 11.4.132 of the Kai Tak EIA[4] ,a comprehensive study was done to compute the indoor fatality probability relative to the outdoor fatality probability. For the purpose of the assessment it was assumed that all commercial sites would be centrally air conditioned with fresh air change rates of 1 air change per hour. Furthermore, it is assumed that population inside the building can escape in 30 minutes. Hence, having taken these factors into account, it is concluded that the indoor fatality probability is 5% of the outdoor fatality probability.

4.6.2.5       Also, based on consequence modelling, all other KDGW scenarios, such as chlorine, pentane and ammonia loss of containment, were found to have an impact height less the 117.85 m from Mean Sea Level (the maximum impact height was found to be lower than 50m considering all weather classes); therefore, the impact from these other scenarios on flight paths are also not considered further in the study.

4.6.2.6       Since helicopter crash frequencies due to the scenarios by the LPG Filling station and the KDGW are not considered to be significant, it is concluded that the impact of the hazard events to the helicopter operation is negligible.

4.7                Quantitative Risk Assessment

4.7.1           Introduction

 

4.7.1.1       Based on the hazard review study (Section 4.6), the risk associated with helicopter crashing into the KDGW and the LPG filling station was found to be significant requiring further assessment using the QRA approach. The QRA approach is outlined in Figure 4.5.

4.7.1.2       The NAH is one of the major projects in the Kai Tak Development Area, for which an EIA [4], including a QRA for the KDGW and the LPG filling, was approved in 2009.  As such, some of QRA aspects relating to the proposed helipad project, such as the construction population during the project construction phase, have been already assessed in the previous Kai Tak QRA[4]. Hence, this QRA has adopted the methodology, assumptions, and data used in the previous Kai Tak QRA[4].

4.7.1.3       The QRA has considered three population scenarios for societal risk assessment:

¡P         Base case in 2025 (the year in which the proposed helipad will begin operation); and

¡P         Future case in 2036 (a future case to account for population growth in the surrounding areas over the years).

¡P         Future case in 2036 (future case accounting for the population growth in the surrounding areas over the years, without the Project i.e., without the Rooftop Helipad and its Operation)

4.7.2           Hazard Identification

 

4.7.2.1       The hazard identification has comprised a review of the hazardous material scenarios studied in the previous Kai Tak QRA[4], with the objective of identifying potential hazards involved during the construction and operation phase of the helipad, and understanding the ways in which those hazards may be realised.

4.7.2.2       As noted in Section 4.6.1.2, the construction phase of the proposed helipad is not expected to pose any significant risk to the operation of KDGW and LPG filling station.

4.7.2.3       In the event of a helicopter loss of control when operating in the vicinity of the proposed helipad, the helicopter can potentially crash into the LPG filling station or KDGW, leading to damage to the facilities with subsequent fire, explosion or toxic release.  This has been identified as the key hazard associated with the proposed helipad during its operation phase.

4.7.2.4       For the LPG Filling Station, the LPG facilities have been verified and confirmed by site visit and interview that no significant modification has been undertaken as compared to those assumed in the previous Kai Tak QRA[4], while operational information such as LPG tanker delivery frequency has been updated. In terms of the risk, the flammability of LPG remains to be the key hazard of concern.  In line with similar LPG QRA studies in Hong Kong[4] [22], the following types of scenarios have been identified for assessment:

¡P           Failure of tank and road tanker;

¡P           Failure of pipe;

¡P           Failure of storage tank valve; and

¡P           Boiling Liquid Expanding Vapour Explosion (BLEVE) of road tanker.

4.7.2.5       For the KDGW, the following scenarios have been identified[4]:

¡P           Major warehouse fire;

¡P           Fire in single store and escalating toxic release;

¡P           LPG release;

¡P           Pentane fire;

¡P           Chlorine release; and

¡P           Ammonia release.

4.7.3           Hazard Scenarios

 

4.7.3.1       Based on the hazards described above, Table 4.3 and Table 4.4 present the hazard scenarios considered for the KDGW and the LPG filling station based on the previous Kai Tak QRA[4]. It is reasonable to assume that the consequence resulting from a helicopter crash would be catastrophic. For the LPG station, such an event was identified as ¡¥Catastrophic Failure of a Storage Vessel¡¦, which is associated with the maximum consequence distance among all failure scenarios based on the previous Kai Tak QRA[4]. For the KDGW, building collapse has been considered in the event of a helicopter crash. As per the previous Kai Tak QRA[4], building collapse was regarded as an extreme scenario, as a consequence of a major earthquake in Hong Kong.

4.7.3.2       Since the identified catastrophic events already involve the entire hazardous inventory of the respective site releasing in the most rigorous manner, these are considered to be the worst case scenarios even in the event of a helicopter crash. Therefore, no modification is, in principle, required for the consequence assessment, as given in the previous Kai Tak QRA[4]; however, the associated event frequencies should be updated to include the additional frequency contribution due to the potential helicopter crash scenario. 

4.7.3.3       Table 4.3 and Table 4.4 summarise the hazard scenarios which are affected by the proposed helipad for the LPG Filling Station and the KDGW, respectively.

Table 4.3 Hazard Scenarios Considered in the previous Kai Tak QRA[4] for LPG Filling Station

Hazard Scenarios

Event Frequencies to be Modified due to the Helipad

Catastrophic Failure of a Storage Vessel

Yes

Catastrophic Failure of a Road Tanker

No*

Partial Failure of a Storage Vessel

No

Partial Failure of a Road Tanker

No

Guillotine Failure of Liquid Filling Line to Storage Vessel

No

Guillotine Failure of Liquid Filling Line to Dispenser

No

Failure of Dispenser

No

Guillotine Failure of Hose during Unloading from Tanker to Storage Vessel, LPG Released from Tanker

No

Guillotine Failure of Hose during Unloading from Tanker to Storage Vessel, LPG Released from Vessel

No

Failure of Flexible Hose during Loading to LPG Vehicles, LPG Released from Dispenser

No

Failure of Flexible Hose during Loading to LPG Vehicles, LPG Released from Vehicle

No

Release from Storage Vessel Pump Flange

No

Release from Storage Vessel Drain Valve

No

Guillotine Failure of Vapour Return Line

No

Guillotine Failure of Liquid Line from Tanker to Loading Hose

No

BLEVE of Road Tanker

No

Notes*   Road tanker has the same consequence distances as storage tank rupture. However, since road tanker is present only intermittently at the filling station, the additional failure frequency due to helicopter impact is assigned to storage tank only for modelling purposes.

 

Table 4.4 Hazard Scenarios Considered in the previous Kai Tak QRA[4] for KDGW

Hazard Scenario

Event Frequencies to be Modified due to the Helipad

Major Warehouse Fire

No

Fire in Single Store

No

LPG Fire Loss area Internal (no offsite effect)

No

LPG Fire Loss cylinder Internal (no offsite effect)

No

LPG Fire Loss area External

No

LPG Fire Loss cylinder External (no offsite effect)

No

Pentane fire Loss Area Internal (no offsite effect)

No

Pentane fire Loss drum Internal (no offsite effect)

No

Pentane fire Loss Area External

No

Pentane fire Loss drum External (no offsite effect)

No

Chlorine toxic release (building collapsed)

Yes

Ammonia toxic release (building collapsed)

Yes

Chlorine¡VLoss of Area Internal

No

Chlorine¡VLoss of Cylinder Internal

No

Ammonia¡VLoss of Area Internal

No

Ammonia¡VLoss of Cylinder Internal

No

Chlorine¡VLoss of Area External

No

Chlorine¡VLoss of Cylinder External

No

Ammonia¡VLoss of Area External

No

Ammonia¡VLoss of Cylinder External

No

Major Warehouse Fire (building collapsed)

Yes

LPG Fire Loss Area (building collapsed)

Yes

Pentane fire Loss Area (building collapsed)

Yes

 

4.7.4           Frequency Assessment

 

4.7.4.1       For the LPG filling station, although most of the scenarios are not affected by the proposed project, the event frequency and consequence have been re-assessed for all scenarios in this study.  The failure frequencies of LPG facilities have been derived based on literature [20].  The current operation data of the LPG filling station has also been obtained [18]; it is noted that  LPG tankers will generally remain in the LPG station for about 90 minutes per delivery, in which the initial and final 5 minutes are spent on preparation, connection and disconnection of the transfer.  As such, inventories of the road tankers are assumed to be full for 5.6% of time, 50% for 88.8% of time and 0% for 5.6% of time.   Based on the above, Fault Tree Analysis (FTA) has been performed in this QRA to estimate the various failure event frequencies.  The latest operation data obtained and the FTA are detailed in Appendix 4C.  However, the data request sent to KDGW was not responded; therefore, all data and assumptions used in the Kai Tak QRA[4], which are deemed conservative, have been retained in this QRA.

4.7.5.1       As assessed in Section 4.6.1, the frequency of helicopter crashing into the LPG filling station and KDGW has been found as 5.05¡Ñ10-8 per year and 1.91¡Ñ10-7 per year, respectively. These crash frequencies have been added to the catastrophic scenarios, as identified in Table 4.3 and Table 4.4.  A summary of the updated frequency data used in this QRA is provided in Table 4.5 and Table 4.6. The calculation details can be found in Appendix 4E Table 4E1 and 4E2.

Table 4.5 Failure Event Frequencies for LPG Filing Station[4]

Scenario

Event Frequency

(per Year)

Catastrophic Failure of Storage Vessel (full)*

5.05 ¡Ñ 10-7

Catastrophic Failure of Road Tanker (full)

2.53 ¡Ñ 10-7

Catastrophic Failure of Road Tanker (50%)

4.02 ¡Ñ 10-6

Pump Flange Leak

4.36 ¡Ñ 10-4

Partial failure of storage vessel

1.02 ¡Ñ 10-5

Partial failure/leak road tanker

3.33 ¡Ñ 10-4

Guillotine failure of filling line to storage vessel

1.72 ¡Ñ 10-10

BLEVE of Road Tanker

9.02 ¡Ñ 10-9

Failure of Liquid Supply Line to Dispenser

6.64 ¡Ñ 10-7

Failure of Dispenser

5.71 ¡Ñ 10-3

Failure of Flexible Hose during Loading to Vessel

1.06 ¡Ñ 10-5

Release from Storage Vessel Drain Valve

4.80 ¡Ñ 10-4

Failure of Vapour Return Line

1.65 ¡Ñ 10-7

* Scenario affected by helicopter crash

 

Table 4.6 Event Frequencies for KDGW[4]

Scenario

Event Frequency

(per Year)

Major Warehouse Fire

1.68 ¡Ñ 10-4

LPG Fire Loss area External

1.16 ¡Ñ 10-9

Chlorine toxic release(building collapsed)*

3.26 ¡Ñ 10-10

Ammonia toxic release(building collapsed)*

3.26 ¡Ñ 10-10

Chlorine-Loss of Area Internal

1.97 ¡Ñ 10-8

Ammonia-Loss of Area Internal

1.97 ¡Ñ 10-7

Chlorine-Loss of Area External

9.71 ¡Ñ 10-9

Ammonia-Loss of Area External

9.71 ¡Ñ 10-8

Pentane fire Loss Area (building collapsed)*

1.19 ¡Ñ 10-6

Chlorine-Loss of Cylinder External

8.74 ¡Ñ 10-8

Ammonia-Loss of Cylinder External

9.32 ¡Ñ 10-9

LPG Fire Loss Area(building collapsed)*

<<1.00 ¡Ñ 10-9

Major Warehouse Fire(building collapsed)*

1.19 ¡Ñ 10-6

Fire in Single store

1.12 ¡Ñ 10-4

Chlorine-Loss of Cylinder Internal

3.50 ¡Ñ 10-6

Ammonia-Loss of Cylinder Internal

3.73 ¡Ñ 10-6

Pentane fire-Loss of Area External

1.40 ¡Ñ 10-3

* Scenario affected by helicopter crash

 

4.7.4.2       For the LPG filling station, the main ignition sources have been identified as the traffic on the adjacent roads.  By using PHAST Risk and its built-in risk / event tree modelling program, MPACT, the road traffic was modelled as ignition sources, whereby the various fire event frequencies could be determined. The detailed parameters used in PHAST Risk are attached in Appendix 4D.  As for KDGW, no further ignition probability or event tree modeling is necessary, as the derived frequencies as given in Table 4.6 already represent the ultimate undesired event (e.g. fires and toxic dispersion) frequencies.

4.7.5           Consequence Assessment

 

4.7.5.1       Consequence modeling has been performed using PHAST for the LPG filling station, based on the LPG storage and road tanker information obtained, as detailed in Table 4C1 and 4C2 in Appendix 4C.  The following physical effects have been considered in the event of LPG loss of containment.

¡P           Flash Fire: flash fire results from delayed ignition of a flammable vapour cloud, generated either through vaporisation directly from the release, or from vaporising pools. The main hazards of a flash fire being direct flame contact. The area of possible direct flame contact effects is determined as the distance to the lower flammability limit (LFL) of the vapour cloud. Due to the extreme short duration of a flash fire, radiation effects are negligible. Flash fire was considered for delayed ignition of flammable gases.

¡P           Jet Fire: A jet fire results from immediate ignition of the flammable material (i.e. LPG) from a pressurised release. In the context of the LPG station, jet fires are relevant to continuous leak from pipework and storage vessel which are under pressure.  The main hazards from a jet fire are direct flame contact and radiation, both of which are modelled using default parameters in PHAST Risk.

¡P           Fireball: Spontaneous rupture (e.g. cold rupture) of LPG vessels or road tankers can give rise fireballs in case of immediate ignition. A fireball is characterized by its high thermal radiation intensity and short duration time. The principal hazard of fireball arises from thermal radiation, which is not significantly influenced by weather, wind direction or source of ignition. A BLEVE is similar to a fireball except that it is caused by integrity failure from fire impingement and therefore occurs as fire escalation events. The physical effects are calculated in the same way as fireballs.

¡P           Vapour Cloud Explosion (VCE): When a flammable vapour cloud forms, disperses and accumulates in areas with high congestion or confinement, and is then ignited, a Vapour Cloud Explosion (VCE) may result. The VCE effects were modelled using TNO multi-energy model in PHAST.

4.7.5.2       For all the physical effects above, the associated fatality probabilities was estimated using Probit equations, the Tsao and Perry Correlation, as given in PHAST Risk. A protection factor of 0.1 was assumed for indoor population.

4.7.5.3       The consequence results for KDGW have been extracted directly from the previous Kai Tak QRA[4]. It is noted that consequence results are not reported in the Kai Tak QRA for some of the scenarios, such as the Chlorine and Ammonia releases (Building Collapse). It is also noted that the consequence results reported in the Kai Tak QRA for KDGW include only 3E and 4C weather conditions. Nevertheless all scenarios that are reported in Table 11.4.13 of Kai Tak QRA, except for those with no offsite effect, have been modeled using PHAST for all weather conditions. A check was done to identify hazard distances from Appendix 11.4.4 that are greater than those obtained from modeling in PHAST. These were used alongside those from modeling in PHAST to allow for a conservative approach. The consequence distances for the representative cases of the LPG filling station and the KDGW are summarised in Table 4.7 and Table 4.8, respectively.

 

 

Table 4.7 Consequences Data of Building Collapse Scenarios and other representative cases for KDGW[4].

Scenario

Consequence

Maximum Hazard Distance from Release Source (m)

Major Warehouse Fire

Toxic cloud (3% probability of fatality)

223a

Major Warehouse Fire (building collapsed)

Toxic cloud (3% probability of fatality)

426a,b

LPG Fire Loss Area (building collapsed)

Fireball

23

Flash fire (0.85 LFL)

96a

Pentane Fire Loss Area (building collapsed)

Thermal radiation (3% probability of fatality)

86

Ammonia¡VLoss of Area External

Toxic cloud (3% probability of fatality)

218a

Chlorine¡VLoss of Area External

Toxic cloud (3% probability of fatality)

344

Chlorine release ¡V loss of warehouse

Toxic cloud (3% probability of fatality)

900a,b

Ammonia release ¡V loss of warehouse

Toxic cloud (3% probability of fatality)

630a,b

Note a: Scenarios having larger hazard distances upon remodeling using PHAST, compared to hazard distances reported in Appendix 11.4.4 of EIA report for Kai Tak Development no. AEIAR-130/2009.

Note b: Frequencies associated with these hazard distances have been taken into account the occurrence probabilities of the specific wind conditions.  

 

Table 4.8 Consequences Data of Catastrophic Failure Scenario of a Storage Vessel for LPG Filling Station[4]

Mass of LPG (tonnes)

Fireball Radius (m)

Fireball Duration (s)

Max. Dispersion Distance to LFL (m)

6.58 [4]

57

8

105

 

4.7.5.4       The latest weather data (recent five years) has been obtained from the Hong Kong Observatory in the QRA update and presented in Table 4.9 below.

Table 4.9 Wind Direction Frequencies 

Day Time

Direction

Weather Class

Total

1F

3E

1D

3B

4C

7D

0 - 30

0.42

0.39

0.32

0.57

0.97

0.05

2.72

30 - 60

0.23

0.70

0.18

0.74

1.99

0.14

3.98

60 - 90

0.16

0.40

0.14

0.73

3.15

1.18

5.76

90 - 120

0.26

1.47

0.26

1.39

15.57

8.04

26.99

120 - 150

1.11

2.30

0.97

4.46

16.73

1.23

26.80

150 - 180

0.60

0.32

0.59

1.92

1.78

0.05

5.26

180 - 210

0.19

0.16

0.38

1.31

1.50

0.04

3.58

210 - 240

0.29

0.29

0.44

2.92

3.03

0.17

7.14

240 - 270

0.30

0.27

0.34

1.70

3.45

0.67

6.73

270 - 300

0.42

0.33

0.34

0.70

1.41

0.19

3.39

300 - 330

0.37

0.48

0.26

0.69

2.24

0.34

4.38

330 - 360

0.28

0.38

0.25

0.73

1.51

0.12

3.27

All

4.63

7.49

4.47

17.86

53.33

12.22

100.00

 

 

Night Time

Direction

Weather Class

Total

1B

3E

1F

4D

7D

1D

0-30

0.00

1.48

2.12

0.38

0.01

0.04

4.03

30 - 60

0.00

2.86

1.04

0.85

0.03

0.09

4.87

60 - 90

0.00

2.47

0.78

1.73

0.94

0.05

5.97

90 - 120

0.00

10.26

1.51

11.98

6.05

0.05

29.85

120 - 150

0.00

11.64

6.54

4.27

0.35

0.05

22.85

150 - 180

0.00

2.08

3.91

0.36

0.00

0.08

6.43

180 - 210

0.06

1.40

1.91

0.20

0.01

0.02

3.60

210 - 240

0.00

2.51

1.95

0.52

0.06

0.03

5.07

240 - 270

0.00

2.39

2.07

0.95

0.15

0.05

5.61

270 - 300

0.00

1.34

1.62

0.53

0.13

0.07

3.69

300 - 330

0.00

1.96

1.10

1.08

0.18

0.09

4.41

330 - 360

0.00

1.50

1.25

0.63

0.17

0.07

3.62

All

0.06

41.89

25.80

23.48

8.08

0.69

100.00

 

 

4.8                Population Estimation

4.8.1           Approach

4.8.1.1       Overall, the approach adopted in the previous Kai Tak QRA[4] has been adopted to estimate the population to be considered in the helipad QRA. Based on the Kai Tak QRA, the population that can be potentially impacted can be classified as:

¡P           Building Population (residential and employment), and

¡P           Traffic Population (marine and road)

4.8.1.2       For the LPG Filling Station and KWDG, the study areas have been determined based on the maximum hazard radius of the worst case scenarios. The determination of the maximum hazard radius is further explained in Section 4.7.5.3.

4.8.1.3       An average annual population growth rate of 1% for the effective regions is calculated by considering the population data given by the Planning Department [14].

4.8.2           Time Period and Occupancy

4.8.2.1       Four time periods have been considered, namely weekday and weekend at day and night time. Following the assumptions used in AEIAR-130/2009[4], the percentages of the population (occupancy) at different times of the day/ night are presented in Table 4.10, and the indoor/ outdoor fraction for different population groups is presented in Table 4.11.

 Table 4.10 Population Category Distributions

Population Category

Weekday

Weekend

Day

Night

Day

Night

Car Park

100%

10%

40%

5%

Hospital

100%

100%

100%

100%

Industrial Building

100%

10%

40%

5%

Commercial Building

100%

10%

40%

5%

Petrol Station

50%

1%

50%

1%

Police Station

100%

30%

65%

30%

Station

100%

10%

55%

10%

Leisure

100%

10%

100%

10%

 

Table 4.11 Indoor and Outdoor Ratios

Population Category

Indoor (Outdoor) Ratio

Residential

0.95 (0.05)

School

0.95 (0.05)

Park

0.00 (1.00)

Road

0.00 (1.00)

Railway/ Bus Station

0.00 (1.00)

Marine

0.00 (1.00)

 

4.8.3           Building Population

4.8.3.1       As stated in the previous Kai Tak QRA[4], the permanent population (i.e. residential and commercial population) in the Kai Tak Development (KTD) was estimated based on the Kai Tak Engineering Study [8]. The previous Kai Tak QRA has also made reference to the Outline Zoning Plan (OZP) zoning and the Planning Vision and Strategy (PVS)[4] zones for estimating the indoor / outdoor population ratios and the areas of the zones.

4.8.3.2       For consistency, the building population data as reported in the previous Kai Tak QRA[4] has been used as much as practicable.  Nevertheless, an update of the population has been performed for the followings:

¡P           Recently developed sites where more detailed population data is available. 

¡P           Sites reserved for future development where the land use type as per latest PVS[3] has been modified as compared to that assumed in the Kai Tak QRA[4]. The modified sites are identified in Appendix 4A.

4.8.3.3       For building population update, a detailed estimation method has been implemented using the following sources of reference, for which the approach is similar to the previous EIA[9]:

¡P         Census Statistics Report 2016[10]

¡P         Unit floor plans from Centadata[11]; and

¡P         Specific websites for different building category.

Population for each building has been estimated based on the type of building (i.e. residential, commercial, etc.), number of floors and number of units per floor. Buildings are assigned to the appropriate building usage categories using information from property developers¡¦ websites and site visits. The specific population assumptions utilised are summarised in Table 4.12[9].

Table 4.12 Building Population Assumptions

Category

Building Size*

Assumptions

Total

Bus Terminus

Based on the building area

Carpark

 

The car park population was adjusted based on the parking level.

 

Parking Level

Parking Spaces

People/ Parking Space

H

5

40

0.2

40

L

1

20

0.2

4

Clinic

Clinics with higher no. of floors were scaled up proportionally.

Floors

Unit

People/ Unit

H

3

20

3

180

M

2

10

2

40

L

1

1

10

10

Commercial Building

Floors

Unit

People/ Unit

H

10

20

2

400

M

5

20

2

200

L

2

10

2

40

Fire Station & Ambulance Depots

About 10240 uniformed staff are employed in Hong Kong. It is assumed that the members of fire and ambulance streams are evenly distributed in 81 fire stations and 39 ambulance depots respectively. It is also assumed that members fire stream will roster on 24 hours (on-duty) and 48 hours (off-duty) and members of ambulance stream will roster on 12 hours, 2 shifts each day.

32

Industrial Building

The Industrial building population was scaled proportionally with the number of floors.

Floors

Unit

People/ Unit

H

25

8

8

1600

M

15

6

8

720

L

8

6

6

288

Leisure

H

200 people for leisure facility with large size.

200

M

100 people for leisure facility with medium size.

100

L

50 people for leisure facility with small size.

50

LL

10 people for leisure facility with very small size.

10

Petrol Station

It is assumed that there are 2 staff stationed in the convenience shop, 4 stationed in the fuel area for filling and 4 vehicles each with 3 people, parked into the Petrol Station for petrol filling.

18

Police Station

About 29400 policemen are employed in Hong Kong. It is assumed that they are distributed evenly among 55 branches. It is also assumed that they will roster on 2 shifts each day and about 50% will be out for patrol.

149

Station

H

5 people in Refuse disposal and Mortuaries

5

M

2 people in Traffic Control Stations

2

L

No people will stay in Sewage treatment works, Toilet, Electric substations or pump house

0

Temple/ Church

H

100 people for temple/ church with large size

100

M

50 people for temple/ church with medium size

50

L

10 people for temple/ church with small size

10

*Legend for Building Height/Size

        - H for Tall/Large,

        - M for Medium,

        - L for Low/Small

        - LL for Very Low/Very Small

 

4.8.3.4       Other than the above building types, the population in residential buildings was estimated based on site survey and other publicly available sources, e.g. floor plan of public housing estates from the Hong Kong Housing Authority, properly developers¡¦ websites, and property agencies websites. 

4.8.3.5       For the acute block of the hospital, a total population of 10,000 was assumed in the QRA for 2019. The assumed population has taken into consideration the number of hospital employees and patients as given by the Sewerage Impact Assessment report (Section 4.2.2)[13], with additional people to account for the transient population, such as visitors and contractors.

4.8.3.6       For areas reserved for future development, the data available from the public domain has been referenced for estimation. The population data used in the QRA for year 2025 and 2036 has been estimated by extrapolating the data from Projection of Population Distribution 2019-2028 [14]. 

4.8.3.7       Site visits have also been carried out with the objective of confirming any latest development of commercial or residential buildings over the past few years, which may not have been captured in the published PVS (2016)[10]. The site visits also supplemented and verified the estimate of the building information such as number of floors as given by the various sources previously mentioned[4]. Appendix 4B presents the buildings identified in each OZP and the population data.

4.8.4           Traffic Populations

Marine Population

4.8.4.1       For updating the marine population density, site surveys have been conducted to estimate the latest marine traffic population in the vicinity of the Kwun Tong Typhoon Shelter. The maximum survey radius has been determined with respect to the maximum radius of the 1E-09 per year individual risk contour of the Kai Tak QRA[4] and the current QRA, as shown in Figure 4.6.

4.8.4.2       The survey used the same technique as adopted in the previous Kai Tak QRA[4]. At the survey location, the surveyor took 3 snapshots at the survey location. The survey was conducted at different periods of the day (i.e. day and night) covering both weekday and weekend. Records of the surveys and estimation of the marine population are detailed in Appendix 4B. The marine population was calculated by the following equation:

4.8.4.3       It was observed during the site surveys that the majority of the marine vessels berthed within the Typhoon Shelter were unoccupied. Therefore, a presence factor of 0.1 was applied in estimating the marine population based on the number of marine vessels counted. On this basis, the marine population density for the Kwun Tong Typhoon Shelter has been estimated as 1.44 x 10-5 people / m2 , assuming 10 occupants per boat, as per the approach in the previous Kai Tak QRA [4]  

Road Population

4.8.4.4         Road population has been updated mainly based on the information from Annual Traffic Census (ATC) [12]. Specifically, the data from the following core stations and coverage stations, as detailed in Table 4.13 below, have been used in the analysis.

Table 4.13  Core Station and Coverage Stations near Kai Tak Area

Station No.

Station Name

From

To

Core Station

3012

Kwun Tong Road

Ngau Tau Kok Road

Kwun Tong Road

3020

Wai Yip Street

Lai Yip Street

Hoi Yuen Road

3023

Kwun Tong Bypass <K77>

Wai Yip Street

Cheung Yip Street

Coverage Stations

3833

Kwun Tong Road

Kai Fuk Road FO <K58> Eastern

Hong Ning Road

3870

Ngau Tau Kok Road

Hong Ning Road

Elegance Road

3873

Lai Yip Street

Wai Yip Street

Kwun Tong Road

4075

Sheung Yee Road

Wai Yip Street

Wang Chiu Road

 

4.8.4.5       ATC provides traffic density information in the form of Annual Average Daily Traffic (AADT)[12], which is considered a suitable representation for normal traffic flows.

The parameters used in the above equation are the same as those given in the previous Kai Tak QRA AEIAR-130/2009[4].

4.8.4.6       By analysing the AADT trend, a population growth rate can be derived for each road, assuming that the road population increases proportionally each year. If the population is expected to decrease in the future, then the population data reflecting the current status has been used, without any adjustment for growth or reduction, as a conservative approach.

4.8.4.7       Population data for the following roads within the maximum hazard zones of KDGW and LPG filling station[4] is, however, not provided by the published ATC[12]

¡P         Kai Hing Road

¡P         Hoi Bun Road

¡P         Wang Hoi Road

4.8.4.8       Therefore, site surveys have been conducted for the above roads in order to estimate the road population. In the survey, a count of the various types of vehicles has been made and recorded. The surveys were conducted at different periods of the day/night, in line with the representative periods considered in Table 4.14. Using the survey data, the number of vehicle per day for each road was calculated, based on which the road population can be estimated using the equation in Section 4.8.4.5.

  Table 4.14   Representative Time Periods for Road Population Surveys

Representative Time Period

Start Time

End Time

1

8:00 am

8:15 am

2

2:00 pm

2:15 pm

3

6:00 pm

6:15 pm

4

10:00pm

10:15 pm

 

4.8.4.9       Appendix 4B shows the updated traffic population. For Kai Hing Road and Hoi Bun Road, the population projection for year 2025 and 2036 has been made based on ATC[12].

4.9                Risk Summation

4.9.1.1       Risk summation combines the estimates of likelihood and consequence for the hazardous events to produce the risk results, which are expressed in terms of individual risk and societal risk, as per the TM-EIAO.  For the LPG filling station, consequence analysis and risk modelling were performed using PHAST Risk to give the individual risk and societal risk results.  For KDGW, risk summation of the remodeled consequence and updated frequency data (updated with potential helicopter impact frequency) as given in the previous Kai Tak QRA [4] was carried out using IRESC risk summation tool.

4.9.2           Individual Risk

 

4.9.2.1       The individual risk contours for KDGW and LPG Filling Station are presented in Figure 4.7 and Figure 4.8, respectively. The cumulative individual risk contours for the two facilities are presented in Figure 4.9.

4.9.2.2       Despite the additional impact due to the proposal helipad, the individual risk associated with KDGW and the LPG filling station has been found to be acceptable with respective to the Individual Risk Criterion that the off-site individual risk does not exceed 1 ¡Ñ 10-5 / year.

4.9.3           Societal Risk

 

4.9.3.1       The societal risk modelling for the LPG filling station was carried out using PHASTRISK (with default parameters, except otherwise specified), with the following assumptions on people¡¦s exposure to hazard: the exposed building population was limited to the maximum height of the hazards[4]; a shielding factor of 0.5[17] was considered for assessing the risks to people located inside buildings which are within or partly within the fireball diameter; and the road population immediately next to the firewall of the LPG filling station was assumed to be protected from the fire scenarios.

4.9.3.2       The societal risk calculation for KDGW simply combined the frequency, consequence data (note that some scenarios were remodelled using PHAST) and population data, as reported in the previous sections of this report, without further adjustment or processing of data.

4.9.3.3       As discussed in Section 4.6.1.2, the construction of the helipad does not involve any heavy duty construction activities, and operations of the two concerned hazard sources are not expected to be affected. Thus, the risk impact associated with the construction phase is related to only the additional population of about 20 workers who will be located outdoors and exposed to the two hazard sources.

4.9.3.4       The total population at NAH site is assumed to be 15,547, of which 777 is considered to be outdoors, in the maximum NAH capacity case (refer to Section 4.10.1.3 and Appendix 4B for details). This number of people outdoors is 185 more than that considered in the year 2036 Case (Figure 4.10 and 4.11), and is much higher than that expected during helipad construction phase. As the 20 workers during construction phase is considered to be well within the assumed population for the maximum NAH capacity case, the risk level of the maximum NAH capacity case can be taken as representative for construction phase, though conservative. Even with this increase in the outdoor population, Figure 4.14 and Figure 4.15 show that the risk level is still within the acceptable limit of Risk Guidelines given in Annex 4 of the TM-EIAO. Hence, the risk associated with the construction phase is deemed acceptable.

4.9.3.5       The societal risk is presented in the form of FN Curves for comparison against societal risk criteria. It can be seen in Figure 4.10 and Figure 4.11 that the FN curves for both the assessed years, namely 2025 and 2036, lie within the Acceptable Region of the risk criteria. Figure 4.10 and Figure 4.11 also include an FN curve for a case without the Project (i.e. without the Helipad Operation), in order to assess the incremental risk due to the Project. In terms of Potential Loss of Life (PLL), the helicopter crash scenario contributes to only 1.5% of the total PLL of 2.01¡Ñ10-5 per year for the LPG filling station. For KDGW, the helicopter crash scenario contributes to about 6.1% of the total of 6.82 ¡Ñ10-6 per year.

4.10             Sensitivity Analysis

4.10.1.1     As described in Section 4.6.1.14, there are three helicopter flight paths associated with the helipad.  The previous base case assessment has assumed that the total annual number of helicopter movement is equally distributed among the three paths. To ensure the robustness of the base case assessment, a sensitivity check has been performed, assuming that all helicopter movements will be via only the flight path closest to the LPG filling station or KDGW, and accordingly the maximum crash rates for KDGW and LPG Filling Station have been estimated as 2.60¡Ñ10-7 per year and 1.14¡Ñ10-7per year, respectively.  Given that the crash frequency is still within the order of 10-7 per year, the 1¡Ñ10-5 per year individual risk contour is not affected due to the change and hence not assessed further.

4.10.1.2     The FN curves comparing the base case and sensitivity case for year 2036 are illustrated in Figure 4.12 and Figure 4.13 for the LPG filling station and KDGW, respectively.  While the risk is observed to have notably increased in the sensitivity case for both the facilities, it still remains within the acceptable region of the risk criteria.

4.10.1.3     To assess the effect on NAH population, another sensitivity case was performed applying the maximum design population capacity within hospital[1]. The risk associated with both facilities remains within the acceptable region of the risk criteria, with an increased in fatalities. The FN curves comparing the base case and the maximum population case for year 2036 are shown in Figure 4.14 and Figure 4.15 for the LPG filling station and KDGW, respectively.

4.11             Risk Mitigation Measure

4.11.1.1     Professional trainings and guidelines should be provided to the helicopter pilots in order to ensure the pilots be familiar with the procedures to avoid approaching near the smoke plume in event of a major fire accident at KDGW.

4.11.1.2     Since both individual risk and societal risk posed by the proposed helipad at Acute Hospital meet the criteria of Hong Kong Risk Guidelines, no further mitigation measures are required.

4.12             Conclusion

4.12.1.1     A QRA was conducted to evaluate the risk associated with the proposed helipad at the Acute Hospital. The risk, both in terms of individual risk and societal risk, has been found to be in compliance with the risk criteria stipulated in Section 2 of Annex 4 of the TM-EIAO.

4.13             References

[1]           EIA Study Brief No. ESB-311/2019, Feb 2019

[2]           Technical Memorandum of Environmental Impact Assessment Process (TM-EIAO)

[3]           Town Planning Board, Kai Tak Outline Zoning Plan (S/K22/6)

[4]           Kai Tak Development Environmental Impact Assessment Report. Hong Kong, AEIAR-130/2009, 2006

[5]           A Rooftop Helipad at the Proposed New Block at Queen Mary Hospital Environmental Impact Assessment Report. Hong Kong, (AEIAR-208/2017), 2017

[6]           Engineering Study for Police Facilities in Kong Nga Po ¡V Feasibility Study. Hong Kong, (AEIAR-201/2016), 2016

[7]           Byrne, J. P. The calculation of aircraft crash risk in the UK. Cheshire: AEA Technology plc, 1997

[8]           Kai Tak Development Engineering Study cum Design and Construction  of  Advance Works ¡V Investigation, Design and Construction, Agreement No: CE 35/2006 (CE)

[9]           Kwun Tong Line Extension (KTE): Hazard to Life Assessment for the Transport Storage and Use of Explosives, AEIAR-154/2010, 2010

[10]        Census and Statistics Department, Hong Kong 2016 Population By-Census

[11]        Centadata Website, http:// www.centamap.com/gc/home/aspx

[12]        Hong Kong Transport Department, Annual Traffic Census 2018

[13]        New Acute Hospital at Kai Tak Development Area Sewerage Impact Assessment Report, Drainage Services Department, 2019

[14]        Planning Department, Projection of Population Distribution 2019-2028

[15]        Operation of the Existing Tai Lam Explosives Magazine at Tai Shu Ha, Yuen Long for Liantang / Heung Yuen Wai Boundary Control Point Project, Hong Kong, AEIAR-193/2015, 2015

[16]        Survey and Mapping Office, Lands Department, Explanatory Notes on Geodetic Datums in Hong Kong, 2018.

[17]        Allied Environmental Consultants Limited, Environmental Impact Assessment Report for Chai Wan Government Complex and Vehicle Depot, AEIAR- 230/2015, 2015

[18]        Phone Interview on 17th September 2019

[19]        Meinhardt. Schedules, Site Coverage and Plot Ratio Calculations. Drawing No. NAH-A/WTP/AR/GBP-125, Rev. 0, Jan 2019

[20]        Reeves, A.B., Minah, F.CC. and Chow, V.H.K., ¡§Quantitative Risk Assessment Methodology for LPG Installations¡¨, Conference on Risk & Safety Management in the Gas Industry, EMSD & HKIE, Hong Kong. (1996)

[21]        Workbook on the dispersion of dense gases, Britter and MacQuaid, 1988

[22]        Proposed Join User Complex and Wholesale Fish Market at Area 44 Tuen Mun, Hong Kong, AEIAR-070/2003, 2003

 



[a] Typical approaching speed is 60 knot (111.2 km/h) based on GFS experience. A factor of 0.5 is applied for conservative reason.