3          PROJECT ORGANISATION.. 3-1

3.1            Background. 3-1

3.2            The Project Proponent 3-1

3.3            The Engineer or EngineerĄŠs Representative (ER) 3-1

3.4            Contractor 3-2

3.5            Environmental Team (ET) 3-2

3.6            Independent Environmental Checker (IEC) 3-3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                       

                                       

 

 

           

           


3                       PROJECT ORGANISATION

3.1                             Background

3.1.1.1                  The Project organisation is defined below. 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


3.1.1.2                  The roles and responsibilities of various parties involved in the EM&A process and the organisational structure of the parties responsible for implementing the EM&A programme are outlined in the sections below. 

3.2                             The Project Proponent

3.2.1.1                  The Project Proponent initiates the Project and is responsible for overseeing the construction works and ensuring the works to be undertaken by the Engineer and Contractor in accordance with the specifications and contractual requirements.  The Project Proponent will cooperate with the Engineer in various issues with respect to the EM&A programme include:

ĄP          To oversee the Engineer and ContractorĄŠs activities and ensure the requirements in the EM&A Manual to be fully complied with;

ĄP          To discuss with the Engineer when action is required to reduce the environmental impacts in accordance with the Event and Action Plans;

ĄP          To liaise with relevant parties if complaints on environmental issues are received; and

ĄP          To cooperate with the Engineer and Contractor to ensure smooth implementation of the environmental mitigation measures.

3.3                             The Engineer or EngineerĄŠs Representative (ER)

3.3.1.1                  The Engineer is responsible for overseeing the construction works and ensuring the works to be undertaken by the Contractor in accordance with the specifications and contractual requirements.  The duties and responsibilities of the Engineer with respect to the EM&A programme include:

ĄP          To supervise the ContractorĄŠs activities and ensure the requirements in the EM&A Manual to be fully complied with;

ĄP          To inform the Contractor when action is required to reduce the environmental impacts in accordance with the Event and Action Plans;

ĄP          To lead the regular site inspections and audits attended by the Contractor and ET/ETL;

ĄP          To adhere to the procedures for carrying out the complaint investigation; and

ĄP          To ensure a qualified IEC is employed as required under the relevant requirements under the EIAO.

3.4                             Contractor

3.4.1.1                  The Contractor shall report to the Engineer.  The duties and responsibilities of the Contractor are:

ĄP          To implement the recommendations and requirements of the EM&A Manual;

ĄP          To provide assistance to the ET in carrying out the relevant environmental inspection and audit;

ĄP          To submit the proposals of mitigation measures in case of adverse environmental impact identified ;

ĄP          To implement the mitigation measures to reduce the environmental impacts;  and

ĄP          To adhere to the procedures for carrying out the complaint investigation as required in the EM&A Manual. 

3.5                             Environmental Team (ET)

3.5.1.1                  The ET will conduct the EM&A programme to ensure the ContractorĄŠs compliance with the ProjectĄŠs environmental requirements during the construction phase. 

3.5.1.2                  The ET shall be led and managed by an Environmental Team Leader (ETL), who shall possess at least 7 years of experience in EM&A.  The ET shall monitor the mitigation measures implemented by the Contractor on a regular basis to ensure the compliance with the intended aims of the mitigation measures.  The duties and responsibilities of the ET are:

ĄP          To monitor various environmental parameters as required in the EM&A Manual;

ĄP          To carry out site inspections to investigate and audit the ContractorĄŠs site practices, equipment and work methodologies with respect to the pollution control and environmental mitigation, and anticipate the environmental issues for the proactive and practicable action before problems arising;

ĄP          To analyse the EM&A results, review the success of EM&A programme to confirm the adequacy of mitigation measures implemented, and to identify any adverse environmental impacts arising and report the EM&A results to the IEC, Contractor, and Engineer;

ĄP          To prepare the reports of site inspection and site environmental conditions; and

ĄP          To review the proposals of mitigation measures by the Contractor in case of adverse environmental impact identified.

3.6                             Independent Environmental Checker (IEC)

3.6.1.1                  The IEC shall advise the Engineer on the environmental issues related to the Project.  The IEC shall possess at least 7 years of experience in EM&A.  The duties and responsibilities of the IEC are:

ĄP          To review and audit in an independent, objective and professional manner in all aspects of the EM&A programme;

ĄP          To review the EM&A Manual prior to the commencement of the works, and provide comments for the ET to update as required before submitting to EPD;

ĄP          To conduct random site inspections during construction;

ĄP          To audit the recommendations and requirements of the EIA against the status of the implementation of environmental protection measures on-site;

ĄP          To review the effectiveness of the environmental mitigation measures and environmental performance of the Project;

ĄP          On as-needed basis, to verify and certify the environmental acceptability of ContractorĄŠs construction methodology (both temporary and permanent works), including relevant design plans and submissions;

ĄP          To verify the investigation results of the environmental complaints and the effectiveness of corrective measures;

ĄP          To verify the EM&A reports that have been certified by the ETL; and

ĄP          To provide feedback of the audit results to the ET/Project Proponent according to the requirements in the EM&A manual.