7.0     WASTE MANAGEMENT.. 7-1

7.1         Introduction. 7-1

7.2         Mitigation Measures. 7-1

7.3         Audit Requirements. 7-4

 

 

 

 

 

 

 

 

 

 

 

 

                 

                 


7.0                        WASTE MANAGEMENT

7.1                        Introduction

7.1.1.1             Waste management during the construction phase will mainly be the responsibility of the Contractor, who shall implement the mitigation measures recommended in the EIA Report in order to minimise waste or resolve the issues associated with the management of wastes.  The Contractor shall also ensure that all wastes produced during the construction phase would be handled, stored and disposed of in accordance with good waste management practices, relevant legislation and waste management guidelines.  Wastes generated from the construction activities, such as the construction and demolition (C&D) materials, shall be audited at regular intervals to ensure that proper storage, transportation and disposal practices are undertaken.  Such audits would ensure that the wastes generated would be properly disposed of.

7.1.1.2             No significant wastes are expected to be generated from the operational phase of the Project and no adverse environmental impacts would arise with the implementation of good waste management practices.  Therefore, an audit programme for the operational phase will not be required.

7.2                        Mitigation Measures

7.2.1.1             With the proper handling, storage and disposal of wastes arising from the construction works as recommended in the EIA Report and summarised in the Environmental Mitigation Implementation Schedule (EMIS) in Appendix A of this EM&A Manual, the potential for adverse environmental impacts is minimised.  During weekly site inspections and audits, the Engineer and ET shall pay special attention to the issues relating to the waste management and check whether the Contractor has implemented the recommended good site practices and other mitigation measures on waste management. The following waste management measures shall be implemented by the Contractor:

¡P                The requirements as stipulated in the ETWB TC(W) No.19/2005 Environmental Management on Construction Sites and the other relevant guidelines should be included in the Particular Specification for the Contractor as appropriate.

 

¡P                The Contractor should submit a Waste Management Plan (WMP) as part of the Environmental Management Plan (EMP) to Architect/Engineer for approval prior to the commencement of construction work, in accordance with the ETWB TC(W) No.19/2005 so as to provide an overall framework of waste management and reduction.  The WMP should include:

 

-               Waste management policy;

-               Record of generated waste;

-               Waste reduction target;

-               Waste reduction programme;

-               Role and responsibility of waste management team;

-               Benefit of waste management;

-               Analysis of waste materials;

-               Reuse, recycling and disposal plans;

-               Transportation process of waste products; and

-               Monitoring and action plan.

¡P                The waste management hierarchy, which includes the following in descending preference, should be strictly followed:

 

-               Avoidance and reduction of waste generation;

-               Reuse of materials as far as practicable;

-               Recovery and recycling of residual materials where possible; and

-               Disposal according to relevant legislations, guidelines and good practices.

¡P                This hierarchy should be adopted to evaluate the waste management options in order to maximise the extent of waste reduction and cost reduction.  The records of quantities of waste generated, recycled and disposed (locations) should be properly documented.

 

¡P                A trip-ticket system should be established in accordance with DevB TC(W) No. 6/2010 and Waste Disposal (Charges for Disposal of Construction Waste) Regulation to monitor the disposal of inert C&D materials to public fill and solid wastes to landfills, and to control fly-tipping.  A trip-ticket system would be included as one of the contractual requirements for the Contractor to strictly implement.  The Engineer would also regularly audit the effectiveness of the system.

 

¡P                The Contractor should also provide proper training to workers regarding the appropriate concepts of site cleanliness and waste management procedures, e.g. waste reduction, reuse and recycling all the time.

 

¡P                The site and surroundings shall be kept tidy and litter free.

 

¡P                No waste shall be burnt on-site.

 

¡P                Prohibit the Contractor to dispose of inert C&D materials at any sensitive locations e.g. natural habitat, etc.  The Contractor should propose the final disposal sites in the EMP and WMP for the Architect/ Engineer¡¦s approval before implementation.

 

¡P                The Contractor should recycle as much of the non-inert C&D materials as possible on-site.  The non-inert C&D waste should be segregated and stored in separate containers or skips to facilitate the reuse or recycling of materials and proper disposal. 

 

¡P                The Contractor shall register as Chemical Waste Producers with the EPD.  Chemical waste should be handled in accordance with the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes as follows:

 

-               The containers used for storing chemical waste should be suitable for the substance to be held, resistant to corrosion, maintained in good conditions and securely closed;

-               The containers should have a capacity of <450L unless the specifications have been approved by the EPD;

-               The label on the containers should be clearly labelled in English and Chinese and comply with the requirements prescribed in Schedule 2 of Waste Disposal (Chemical Waste) (General) Regulation;

-               The storage area for the chemical waste should be used solely for the storage of chemical wastes;

-               The storage area should be enclosed on at least three sides by a wall, partition or fence with a height of not less than two metres or the total height of containers in stack, whichever is less;

-               Where containers of liquid chemical wastes are stored, the area should be designed with impermeable floor and provided with a bund with capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in the area, whichever is greatest;

-               Adequate ventilation should be allowed in the storage area by leaving some space between the top of the enclosure walls and the ceiling, or provision of louvers on the sides of the enclosure walls;

-               The storage area should be sufficiently covered to prevent rainfall entering (water collected within the bund must be tested and disposed of as chemical waste, if necessary); and

-               Separate containers should be used for packing different types of waste or waste arising from different sources and process to minimise mixing of incompatible materials.

-                   Drip tray should be provided to chemical waste containers. The drip tray should be clean up regularly. Clean up should be done before foreseeable inclement weather such as typhoon or heavy rain.

¡P                Waste oils, chemicals or solvents shall not be disposed of to drain.

 

¡P                General refuse arising on-site should be stored in enclosed bins or compaction units separately from C&D materials/ wastes and chemical wastes.  Sufficient bins shall be provided for storage of general refuse as required under the Public Cleansing and Prevention of Nuisances Regulation.  In addition, general refuse shall be cleared daily and shall be disposed of to the nearest landfill or refuse transfer station.  Burning of refuse on construction sites is prohibited. Disposal of general refuse is recommended before foreseeable inclement weather such as typhoon or heavy rain.

 

¡P                All waste containers shall be in a secure area on hardstanding.

 

¡P                Segregation and storage of different types of waste should be promoted to facilitate the reuse and recycling of the materials. Separately labelled bins for the deposition of aluminum cans, paper and plastic bottles etc. should be provided as far as practicable. Participation in a local collection scheme by the Contractor should be advocated.

 

7.3                        Audit Requirements

7.3.1.1             Weekly site inspections and audits shall be carried out by the ET, as detailed in Table 6.1, to ensure that the recommended good site practices and other mitigation measures are implemented by the Contractor.  The inspections and audits shall look at all aspects of on-site waste management practices including the waste generation, storage, recycling, transport and disposal. Documents including licenses, permits, disposal and recycling records shall be reviewed and audited for the compliance with the legislation and contract requirements. 

 


Table 7.1    Waste Management Checklist

Activities

Timing

Audit/ Inspection Frequency

If non-compliance, Action Required

All necessary waste disposal permits or licences have been obtained

Before commencement of works

Once

Apply for the necessary permits/ licences prior to disposal of the waste.  The ET shall ensure that corrective action has been taken.

Only licensed waste haulers are used for waste collection.

Throughout the works

Weekly

The ET shall inform the ER and IEC of the non-compliance.  The ER shall instruct the Contractor to use a licensed waste hauler.  The Contractor shall temporarily suspend waste collection of that particular waste until a licensed waste hauler is used.  Corrective action shall be undertaken within 48 hours.

Records of quantities of wastes generated, recycled and disposed are properly kept.  For demolition material/waste, the number of loads for each day shall be recorded (quantity of waste can then be estimated based on average truck load.  Should landfill charging be implemented, the receipts of the charge could be used for estimating the quantity).

Throughout the works

Weekly

The Contractor shall estimate the missing data based on previous records and the activities carried out.  The ET shall audit the results and forward to the ER and IEC for approval.

Wastes are removed from site in a timely manner.  General refuse is collected on a daily basis.

Throughout the works

Weekly

The ET shall inform the ER and IEC of the non-compliance.  The ER shall instruct the Contractor to remove waste accordingly.

Waste storage areas are properly cleaned and do not cause windblown litter and dust nuisance.

Throughout the works

Weekly

The ET shall inform the ER and IEC of the non-compliance.  The ER shall instruct the Contractor to clean the storage area and/or cover the waste.

Different types of waste are segregated in different containers or skip to enhance recycling of material and proper disposal of waste.

Throughout the works

Weekly

The ET shall inform the ER and IEC of the non-compliance.  The ER shall instruct the Contractor to provide separate skips/ containers.  The Contractor shall ensure the workers place the waste in the appropriate containers.

Chemical wastes are stored, handled and disposed of in accordance with the Code of Practice on the Packaging, Handling and Storage of Chemical Wastes, published by the EPD.

Throughout the works

Weekly

The ET shall inform the ER and IEC of the non-compliance.  The ER shall instruct the Contractor to rectify the problems immediately.  Warning shall be given to the Contractor if corrective actions are not taken within 24 hrs and the Regional Office of EPD shall be notified.

Demolition material/waste in dump trucks are properly covered before leaving the site.

Throughout the works

Weekly

The ET shall inform the ER and IEC of the non-compliance.  The ER shall instruct the Contractor to comply.  The Contractor shall prevent trucks from leaving the site until the waste are properly covered.

Wastes are disposal of at licensed sites.

Throughout the works

Weekly

The ET shall inform the ER and IEC of the non-compliance.  The ER shall warn the Contractor and instruct the Contractor to ensure the wastes are disposed of at the licensed sites.  Should it involve chemical waste, the Regional Office of EPD shall be notified.

Note:  ET ¡V Environmental Team, IEC ¡V Independent Environmental Checker, ER ¡V Engineer¡¦s Representative