11.0  REPORTING.. 11-1

11.1          Introduction. 11-1

11.2          Deliverables. 11-1

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                                                             


11.0                    REPORTING

11.1                    Introduction

11.1.1.1         The following reporting requirement are based upon a paper-documented approach.  However, the same information shall be provided in an electronic medium upon agreeing the format with the ER and EPD.

11.2                    Deliverables

 

11.2.1               First Monthly EM&A Report

11.2.1.1         The First Monthly EM&A Report shall include at least, but not be limited to, the following information:

¡P               Executive Summary (1-2 pages):

-         Complaint log;

-         Notification of any summons and successful prosecutions;

-         Reporting changes; and

-         Future key issues.

¡P          Basic project information:

-         The project organisation including key personnel contact names and telephone numbers;

-         The construction programme;

-         The management structure; and

-         Works undertaken during the reporting month.

¡P               Environmental status:

-         Advice on the status of statutory environmental compliance, such as the  status of compliance with the environmental permit (EP) conditions under the EIAO, schedule and progress of any submissions as required under the EP application of Construction Noise Permit (CNP), Waste Water Discharge License in accordance to Water Pollution Control Ordinance (WPCO), C&D Waste Disposal, Chemical Waste Disposal License, etc;

-         Advice on the status of the implementation of mitigation measures, etc.;

-         Works undertaken during the reporting month with illustrations (e.g. location of works, etc); and

-         Drawings showing the project area, environmental sensitive receivers.

¡P               Implementation status:

-         Advice on the implementation status of environmental protection and pollution control/mitigation measures as recommended in the EIA Report, summarised in the updated implementation schedule.

¡P               The report on the non-compliances, complaints, notifications of summons and status of prosecutions:

-         Records of all complaints received (written or verbal), including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

-         Records of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;

-         The review of the reasons for and implications of non-compliances, complaints, summons and prosecutions including the review of pollution sources and working procedures; and

-         Descriptions of the actions taken in the event of non-compliances and deficiency reporting and any follow-up procedures related to the earlier non-compliances.

¡P               Summary of Site Audit/ Inspection:

-         Records the dates and time of the site audit/ inspection, and any environmental problems observed;

-         Record the details of personnel involved; and

-         Descriptions of the mitigation measures/ action plans taken if environmental problems are identified during the audit/ inspection.

¡P               Others:

-         An account of the future key issues as reviewed from the works programme and work method statements;

-         Advice on the solid and liquid waste management status; and

-         Comments (e.g. the effectiveness and efficiency of mitigation measures), recommendations (e.g. any improvement in the EM&A programme) and conclusions.

11.2.2               Subsequent Monthly EM&A Reports

11.2.2.1         The subsequent monthly EM&A Reports during the construction phase shall include the following information:

¡P               Executive Summary (1-2 pages):

-         Complaint log;

-         Notifications of any summons and successful prosecutions;

-         Reporting changes; and

-         Future key issues.

¡P               Basic project information:

-         The project organisation including key personnel contact names and telephone numbers;

-         The construction programme;

-         The management structure; and

-         Works undertaken during the reporting month.

¡P               Environmental status:

-         Advice on the status of statutory environmental compliance, including the status of compliance with the environmental permit (EP) conditions under the EIAO, schedule and progress of any submissions as required under the EP application of Construction Noise Permit (CNP), Waste Water Discharge License in accordance to Water Pollution Control Ordinance (WPCO), C&D Waste Disposal, Chemical Waste Disposal License etc;

-         Works undertaken during the reporting month with illustrations (such as location of works, etc); and

-         Drawing showing the project area, environmental sensitive receivers.

¡P               Implementation status:

-         Advice on the implementation status of environmental protection and pollution control / mitigation measures as recommended in the EIA Report, summarised in the updated implementation schedule.

¡P               The report on non-compliances, complaints, notifications of summons and status of prosecutions:

-         Records of all complaints received (written or verbal), including the locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

-         Records of all notification of summons and successful prosecutions for breaches of current environmental protection/pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;

-         The review of the reasons for and implications of non-compliances, complaints, summons and prosecutions including review of pollution sources and working procedures; and

-         Descriptions of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to the earlier non-compliances.

¡P               Summary of Site Audit/ Inspection:

-         Records the dates and time of the site audit/ inspection, and any environmental problems observed;

-         Record the details of personnel involved; and

-         Descriptions of the mitigation measures/ action plans taken if environmental problems are identified during the audit/ inspection.

¡P               Others:

-         An account of the future key issues as reviewed from the works programme and work method statements;

-         Advice on the solid and liquid waste management status;

-         Comments (e.g. the effectiveness and efficiency of the mitigation measures), recommendations (e.g. any improvement in the EM&A programme) and conclusions;

-         Ad-hoc audits carried out.

¡P               Appendices:

-         Cumulative statistics on complaints, notifications of summons and successful prosecutions; and

-         Outstanding issues and deficiencies.

11.2.3               Final EM&A Review Report

11.2.3.1         The EM&A programme shall be terminated upon the completion of the construction activities that have the potential to cause significant environmental impacts.

11.2.3.2         Prior to the proposed termination, it may be advisable to consult the relevant local communities.  The proposed termination shall only be implemented after the proposal has been endorsed by the IEC, Engineer/ER and Project Proponent, followed by the approval from the Director of Environmental Protection. The following factors also need to be considered before the termination of the EM&A Programme:

¡P               Completion of construction activities and insignificant environmental impacts of the remaining outstanding construction works; and

¡P               No outstanding environmental complaint and prosecution involved.

11.2.3.3     The ET shall prepare and submit the Final EM&A Report within 14 working days after approval of termination of EM&A programme has been granted. The completion of the construction activities that have the potential to cause significant environmental impacts.  The Final EM&A Report shall contain at least the following information:

¡P               Executive summary (1 - 2 pages);

¡P               Drawings showing the project area, environmental sensitive receivers;

¡P               The basic project information including a synopsis of the project organisation, contacts of key management, and a synopsis of works undertaken during the course of the project or past twelve months;

¡P               A brief summary of EM&A requirements including:

-         Environmental mitigation measures implemented as recommended in the EIA Report; and

-         Environmental impact hypotheses tested.

¡P               A summary of the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the EIA Report, summarised in the updated environmental mitigation implementation schedule;

¡P               A summary of the site audit/inspection carried out, including a summary of observations and follow up actions taken;

¡P               A review of the reasons for and implications of non-compliances including the review of pollution sources and working procedures as appropriate;

¡P               A description of the action taken in the event of non-compliances;

¡P               A summary record of all complaints received (written or verbal), liaison and consultation undertaken, action and follow-up procedures taken;

¡P               A summary record of the notifications of summons and successful prosecutions for breaches of the current environmental protection / pollution control legislation, locations and nature of the breaches, follow-up investigation taken and results;

¡P               Comments (e.g. a review of the effectiveness and efficiency of the mitigation measures and of the performance of the environmental management system, i.e., of the overall EM&A programme); and

¡P               Recommendations and conclusions (e.g. a review of the success of the overall EM&A programme to cost-effectively identify deterioration and to initiate prompt effective mitigation action when necessary).