TABLE OF CONTENT

 

1             INTRODUCTION. 1-1

1.1           Project Background. 1-1

1.2           Designated Projects under EIAO.. 1-1

1.3           Purpose of the EIA Study. 1-2

1.4           Objectives of this EIA Study. 1-2

1.5           Structure of the EIA Report 1-2

 

List of Drawings

 

Figure 1.1

Location Plan of the Proposed Revised Austin Road Flyover

Figure 1.2

Revision of Project Boundary

 

 


1                      INTRODUCTION

1.1                  Project Background

1.1.1.1           West Kowloon Cultural District (WKCD) is an arts and cultural facilities (ACF) building programme which aims to deliver new performance and visual arts venues, museums, open spaces, education resources, commercial and retail opportunities for the residents of Hong Kong and visitors from overseas.  The related works include a mainly 2-lane flyover (including approaching roads) across the toll plaza of Western Harbour Tunnel (Austin Road Flyover).

1.1.1.2           As raised by Members of District Council in the Yau Tsim Mong District Council Meeting in November 2014, traffic leaving WKCD to Austin Road West Roundabout and Nga Cheung Road Flyover would add significant burden on the capacity of these road networks, which are already congested with traffic at the moment.  As such, the Revised Austin Road Flyover from WKCD should be proposed to allow access to the section of Lin Cheung Road running in parallel to the West Kowloon Highway (Route 3) aiming to divert traffic from Nga Cheung Road Flyover and Austin Road West Roundabout.  The location plan of the Revised Austin Road Flyover is shown in Figure 1.1.

1.1.1.3           The Revised Austin Road Flyover (The Project) integrates the proposed exit road with the proposed Flyover.  The proposed exit road would connect the service road of West Kowloon Highway (Route 3 ¡V Western Harbour Crossing Tunnel Area).  Other than providing connection from WKCD to adjacent local roads, the Revised Flyover provides an additional single road way to alleviate the traffic from the WKCD to the West Kowloon Highway.

1.2                  Designated Projects under EIAO

1.2.1.1           A Project Profile (No. PP-580/2019) was submitted to the Environmental Protection Department (EPD) on 4 April 2019 for application for an Environmental Impact Assessment (EIA) Study Brief under section 5(1)(a) of the Environmental Impact Assessment Ordinance (EIAO) and the EIA Study Brief No. ESB-316/2019 for the Project was issued on 16 May 2019 under the EIAO.

1.2.1.2           During the course of the Project development, a refined ramp alignment for the Austin Road Flyover was developed which is slightly longer then the schematic design in the Project Profile, resulting in an enlargement of the Project Boundary (total area from approximately 34,000 m2 to 44,100 m2) as presented in Figure 1.2.  The existing scope of issues covered in the EIA Study Brief including air quality impact, noise impact, water quality impact, waste management implications, land contamination and landscape and visual impacts are considered sufficient to cover the potential environmental impacts due to the latest design of the Project.  In addition, the revised Project Boundary would not cover any manufacture, storage, use or transport of dangerous goods, cultural heritages, sites of conservation importance, or seabed, foreshores and fish ponds.  No additional issues such as hazard to life, cultural heritage, ecology and fisheries are anticipated under the revised Project Boundary.  Revision of Project Boundary was confirmed with EPD in accordance with Section 6.2 of EIA Study Brief and the confirmation letter is presented in Appendix 4.1.  

1.2.1.3           The Project is classified as a Designated Project (DP) under

Item

 

Description

Remarks

Item A.1, Part I, Schedule 2 of the EIAO

¡V

A road which is an expressway, trunk road, primary distributor road or district distributor road including new roads, and major extensions or improvements to existing roads

The proposed exit road is a district distributor.

Item A.8, Part I, Schedule 2 of the EIAO

¡V

A road or railway bridge more than 100 m in length between abutments

The distance between two abutments of the proposed exit road is about 400m.

 

 

 

 

1.3                  Purpose of the EIA Study

1.3.1.1           The purpose of the EIA Study is to provide information on the nature and extent of the environmental impacts arising from construction and operation of the Project and associated works that will take place concurrently.  This information will contribute to decisions on:

¡P               The overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project;

¡P               the conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences wherever practicable; and

¡P               the acceptability of residual impacts after the proposed mitigation measures are implemented.

1.4                  Objectives of this EIA Study

1.4.1.1           The objectives of the EIA study as stated in the EIA Study Brief are as follows:

(i)        to describe the Project and associated works together with the requirements and environmental benefits for carrying out the Project;

(ii)       to identify and describe the elements of the community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including both the natural and man-made environment and the associated environmental constraints;

(iii)      to identify and quantify emission sources and determine the significance of impacts on sensitive receivers and potential affected uses;

(iv)      to propose the provision of infrastructure or mitigation measures so as to minimise pollution, environmental disturbance and nuisance during construction and operation of the Project;

(v)       to investigate the feasibility, effectiveness and implications of the proposed mitigation measures;

(vi)      to identify, predict and evaluate the residual (i.e. after practicable mitigation) environmental impacts and the cumulative effects expected to arise during the construction and operational phases of the Project in relation to the sensitive receivers and potential affected uses;

(vii)     to identify, assess and specify methods, measures and standards, to be included in the detailed design, construction and operation of the Project which are necessary to mitigate these residual environmental impacts and cumulative effects and reduce them to acceptable levels;

(viii)    to design and specify the environmental monitoring and audit requirements;

(ix)      to identify any additional studies necessary to implement the mitigation measures or monitoring and proposals recommended in the ElA report

1.5                  Structure of the EIA Report

1.5.1.1           The background of the project, purpose and objectives of this Report are introduced in this section.  A description of the Project and details of options consideration are provided in Section 2.  Sections 3 to 8 detail the results of the environmental impact assessment of each key subject area, covering relevant legislation, environmental conditions, assessment criteria, methodology, and assessment findings.

1.5.1.2           Sections 3 to 8 are outlined as follows:

¡P               Section 3: Air Quality Impact

¡P               Section 4: Noise Impact

¡P               Section 5: Water Quality Impact

¡P               Section 6: Waste Management Implication

¡P               Section 7: Land Contamination

¡P               Section 8: Landscape and Visual Impact

1.5.1.3           An outline of the requirements for the Environmental Monitoring and Audit (EM&A) programme is presented in Section 9.  The EM&A programme is presented in detail in a separate EM&A Manual.  A detailed implementation schedule of the recommended mitigation measures is provided in Section 9.  A summary of environmental outcomes and conclusions is presented in Section 10.

1.5.1.4           This EIA Report consists of the following booklets:

¡P               Volume 1 of 3 ¡V Main Text (This booklet)

¡P               Volume 2 of 3 ¡V Figures

¡P               Volume 3 of 3 ¡V Appendices

1.5.1.5           An Executive Summary has been prepared as a separate document in both Chinese and English, which contains summaries of the key findings, recommendations and conclusions of the EIA Report.