TABLE OF CONTENT
10 SUMMARY
OF ENVIRONMENTAL OUTCOMES
10.2 Environmental
Benefits of the Project
10.3 Incorporation
of Environmentally Friendly Options
10.4 Environmental
Design Recommended
10.5 Key
Environmental Problems Avoided and Environmentally Sensitive Areas Protected
10.6 Environmental
Protection Measures Recommended
10.7 Estimation
of Population Protected
List
of Tables
Table 10.1 Summary of Key Environmental Problems Avoided and
Sensitive Areas Protected
Table 10.2 Key Recommended
Mitigation Measures
¡P Adoption of environmentally friendly construction method;
¡P Implementation of trip-ticket system; and
¡P Implementation of environmental monitoring and auditing system.
Adoption of Environmentally Friendly Construction
Method
Implementation of Trip-Ticket System
Implementation of Environmental Monitoring and
Auditing System
Table 10.1 Summary of Key Environmental Problems
Avoided and Sensitive Areas Protected
Design Approach |
Environmental
Problems Avoided and Sensitive Areas Protected |
Avoidance of encroachment of the project road alignment into
potentially contaminated area (New Yau Ma Tei
PCWA) (Section 10.3.1.2) |
¡P
Avoid construction works in
potentially contaminated area to minimize land contamination impacts. |
Adoption of environmentally friendly construction method (Section 10.4.1.2) |
|
Implementation of trip-ticket system (Section 10.4.1.3) |
¡P Implementation of trip-ticket system to monitor, document and verify the disposal of C&D materials and control fly tipping. |
Implementation of Environmental Monitoring and Auditing System (Section 10.4.1.4) |
¡P Ensure all the recommended measures are properly in place and their effectiveness. |
Table 10.2 Key Recommended
Mitigation Measures
Environmental Aspect |
Mitigation Measure and any Associated Benefit |
Air Quality Impact |
¡P The approved non-road mobile machinery (NRMMs) under NRMM Regulation (excluding exempted NRMMs) would be used on site and NRMMs supplied with mains electricity instead of diesel-powered should be adopted as far as possible to minimize the potential emission from NRMMs. ¡P Implementation of dust suppression measures as required in the Air Pollution Control (Construction Dust) Regulation to minimize construction dust impact. ¡P Although unacceptable air quality impact is not anticipated due to the Project during the operation phase, some mitigation measures such as relocation of fresh air intakes at elevated levels with AQO compliance and provision of air purification filters have been considered due to the high background level of NO2. For the existing ASRs, planned ASRs under construction and planned ASRs with detailed design, these mitigation measures were considered not feasible in time as the designs have already been completed or in some cases even physical buildings have been completed. For the planned ASRs without detailed design, the future WKCD project owner(s) within the Study Area would be notified of the findings under this air quality impact assessment in EIA of Revised Austin Road Flyover for consideration so that the relevant mitigation measures could be implemented as far as practicable. |
Noise Impact |
¡P Implementation of good site practice to minimize construction noise impact. |
Water Quality Impact |
¡P Implementation of site practices as outlined in ProPECC Note PN 1/94 to control and minimize site runoff and drainage. ¡P Minimum distances of 100m should be maintained between the discharge points of construction site effluent and no effluent shall be discharged into the typhoon shelter. ¡P Adoption of proper site management and good housekeeping practices to minimize the potential water quality impact due to spillage events. ¡P Provision of silt trap for road drainage for removal of pollutants from storm water. ¡P Collection and conveyance of sewage effluent from the proposed toilets to the existing sewerage system. |
Waste Management Implications |
¡P Implementation of good site practices and waste reduction measures (e.g. reuse of construction and demolition (C&D) materials before off-site disposal or develop a materials recovery and recycling programme during construction and operation). ¡P Implementation of proper storage, collection and transportation of waste. ¡P Preparation of a Waste Management Plan (WMP), as part of the Environmental Management Plan (EMP). ¡P Implementation of trip-ticket system for each works contract in accordance with DevB TC(W) No. 6/2010 to ensure that the disposal of C&D materials is properly documented and verified. |
Land Contamination |
¡P No land contamination impacts would be anticipated from the Project, therefore, no mitigation measures are required. |
Landscape and Visual Impacts |
¡P Implementation of landscape and visual mitigation measures for construction phase and operation phase. |