TABLE OF CONTENT

 

6                  WASTE MANAGEMENT IMPLICATION. 6-1

6.1              Introduction. 6-1

6.2              Environmental Legislations, Standards and Guidelines. 6-1

6.3              Description of Environment 6-3

6.4              Identification of Waste Management Implications. 6-3

6.5              Assessment Methodology. 6-4

6.6              Prediction and Evaluation of Waste Management Implications. 6-5

6.7              Mitigation of Adverse Environmental Impacts. 6-9

6.8              Evaluation of Residual Impacts. 6-14

6.9              Environmental Monitoring and Audit Requirements. 6-14

6.10            Conclusion. 6-14

 

List of Drawings

 

Figure 6.1

Tentative Location of Stockpiling Area

 

List of Tables

Table 6.1                   Estimated Quantities of C&D Materials during Construction Phase. 6-5

Table 6.2                   C&D Materials Generated from Demolition of Existing Carriageways. 6-6

Table 6.3                   C&D Materials Generated from Site Clearance / Set-up / Plant Mobilization, Underground Utilities Protection and Diversion Works, Piling Works, Pile Cap / Pier / Abutment Construction  6-6

Table 6.4                   C&D Materials Generated from Falsework / Deck Construction. 6-7

Table 6.5                   C&D Materials Generated from Drainage and Pavement Construction. 6-7

Table 6.6                   Tentative Transportation Routings for Waste Disposal During Construction Phase. 6-9

Table 6.7                   Summary of Waste Generation, Waste Handling Procedures and Disposal Outlets. 6-13


6                      WASTE MANAGEMENT IMPLICATION

6.1                  Introduction

6.1.1.1           This section identifies the type of wastes that are likely to be generated from the construction activities of the Project, based on their sequence and duration, and evaluates the potential environmental impacts that may result from waste generated.  Mitigation measures and good site practices, including waste handling, storage and disposal, have been recommended with reference to applicable waste legislation and management guidelines.  It is expected that no waste will be generated during the operation phase of the Project.  As such, it is considered that there should be no adverse environmental impacts.

6.1.1.2           Mitigation measures and good site practices regarding the waste handling, storage, collection and disposal are recommended with reference to relevant waste legislation and guidelines. 

6.2                  Environmental Legislations, Standards and Guidelines

6.2.1              General

6.2.1.1           The criteria and guidelines for assessing waste management implications are outlined in Annex 7 and 15 respectively in the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

6.2.1.2           The following legislation relates to the handling, treatment and disposal of wastes in the Hong Kong Special Administrative Region (SAR):

¡P         Waste Disposal Ordinance (Cap. 354);

¡P         Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C);

¡P         Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N);

¡P         Land (Miscellaneous Provisions) Ordinance (Cap. 28); and

¡P         Public Health and Municipal Services Ordinance ¡V Public Cleansing and Prevention of Nuisances Regulation (Cap. 132BK)

Waste Disposal Ordinance (Cap. 354)

6.2.1.3           The Waste Disposal Ordinance (WDO) prohibits the unauthorized disposal of wastes.  Construction waste is defined under Cap. 354N of the WDO as any substance, matter or thing that is generated and abandoned from construction works regardless if it has been processed or stockpiled before being abandoned, excluding sludge, screenings or any matter removed or generated from desludging, desilting or dredging works.  Under WDO, waste can be disposed of only at designated waste disposal facilities licensed by the Environmental Protection Department (EPD).

Waste Disposal (Chemical Waste) (General) Regulation (Cap.354C)

6.2.1.4           Under the WDO, the Waste Disposal (Chemical Waste) (General) Regulation legislates controls over the management of chemical waste, and applies to the possession, storage, collection, transport and disposal of chemical waste. EPD has also issued A Guide to the Chemical Waste Control Scheme (2016), A Guide to the Registration of Chemical Waste Producers (2016) and Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), which provide guidance for complying with the requirements of the Waste Disposal (Chemical Waste) (General) Regulation on the packaging, labelling and storage of chemical waste.

Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N)

6.2.1.5           Under the Waste Disposal (Charges for Disposal of Construction Waste) Regulation enacted in January 2006, construction waste delivered to a landfill for disposal must not contain more than 50% by weight of inert material.  Construction waste delivered to a sorting facility for disposal must contain more than 50% by weight of inert material, and construction waste delivered to a Public Fill Reception Facility (PFRF) for disposal must consist entirely of inert material.

Land (Miscellaneous Provisions) Ordinance (Cap. 28)

6.2.1.6           The inert portion of Construction and Demolition (C&D) materials (including rocks, soil, broken concrete, building debris etc.) may be taken to PFRFs.  PFRFs usually form part of land reclamation schemes and are operated by the Civil Engineering and Development Department (CEDD) and others.  The Land (Miscellaneous Provisions) Ordinance requires that individuals or companies who deliver public fill to the PFRFs are required to obtain Dumping Licences.  The licences are issued by CEDD under delegated authority from the Director of Lands.

Public Health and Municipal Services Ordinance ¡V Public Cleansing and Prevention of Nuisances Regulation (Cap. 132BK)

6.2.1.7           The Public Cleansing and Prevention of Nuisances Regulation provides control on illegal dumping of wastes on unauthorized / unlicensed sites.  The illegal dumping of wastes can lead to a fine and/or imprisonment.

6.2.2              Other Relevant Environmental Guidelines

6.2.2.1           Other environmental relevant circulars/guidelines applicable to waste management practices for this Project include:

¡P         Works Branch Technical Circular (WBTC) No. 2/93 Public Dumps;

¡P         WBTC No. 2/93B Public Filling Facilities;

¡P         WBTC No. 12/2000 Fill Management;

¡P         WBTC No. 19/2001 Metallic Site Hoardings and Signboards;

¡P         WBTC No. 12/2002 Specifications Facilitating the Use of Recycled Aggregates;

¡P         Environment, Transport and Works Bureau Technical Circular (Works) (ETWB TCW) No. 33/2002 Management of Construction and Demolition Material Including Rock;

¡P         ETWB TCW No. 19/2005 Environmental Management on Construction Sites;

¡P         Development Bureau Technical Circular (Works) (DevB TCW) No. 06/2010 Trip-ticket System for Disposal of Construction and Demolition Material;

¡P         DevB TCW No. 08/2010 Enhanced Specification for Site Cleanliness and Tidiness;

¡P         DevB TCW No. 09/2011 Enhanced Control measures for Management of Public Fill;

¡P         Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (EPD);

¡P         A Guide to the Chemical Waste Control Scheme (EPD);

¡P         Section 4.1.3 of Chapter 4 of the Project Administration Handbook (PAH) for Civil Engineering Works, Management of Construction/Demolition Materials including Rocks.

6.2.2.2           The WBTC No. 2/93 ¡¥Public Dumps¡¦ documents the current policy related to the disposal of C&D materials.  C&D materials that are wholly inert, i.e. public fill, should be taken to PFRFs for reuse instead of being disposed of at landfill.

6.2.2.3           Under DevB TCW No. 6/2010 ¡¥Trip Ticket System for Disposal of Construction and Demolition Materials¡¦, for all contracts that are expected to generate inert C&D materials requiring disposal from site, the project office shall write to the Public Fill Committee (PFC) through Secretary of the PFC to request a designated disposal ground for incorporation into the tender documents.  For contracts where the estimated amount of non-inert C&D materials requiring disposal at landfill facilities equals to or exceeds 50 m3, the project office shall seek confirmation from the Director of Environmental Protection (DEP) in terms of the availability of landfill facilities for disposal of such materials and the DEP will designate landfill facilities, if available, for the contracts.  For contracts where the estimated amount of non-inert C&D materials to be generated from the contract is less than 50 m3, the project office is not required to apply to DEP for designated landfill facilities but it should still specify in the tender documents of the appropriate landfill facilities for disposal.

6.2.2.4           Further measures have been introduced under Paragraph 4.1.3 of Chapter 4 of the PAH for Civil Engineering Works to enhance the management of C&D materials, and to minimize its generation at source.  The enhancement measures include:

¡P         Drawing up a Construction and Demolition Materials Management Plan (C&DMMP) at an early design stage to minimize C&D materials generation and to encourage proper management of such materials;

¡P         Vetting of the C&DMMP prior to upgrading of the project to Category A in the Public Works Programme; and

¡P         Providing the contractor with information from the C&DMMP in order to facilitate the preparation of Waste Management Plan (WMP) and to minimize C&D materials generation during construction.

6.2.2.5           The ETWB TCW No. 19/2005 Environmental Management on Construction Sites introduces additional measures to enhance waste management on construction sites.  The circular sets out the policies and procedures that require the contractors to prepare and implement an Environmental Management Plan (EMP), which includes the WMP to encourage on-site sorting of C&D materials and to minimize generation of C&D materials during the course of construction.

6.3                  Description of Environment

6.3.1.1           The Project site is situated within part of the WKCD area and across the toll plaza of the Western Harbour Crossing (WHC).  The western boundaries of the study area are at the side of the WKCD Waterfront Promenade to the west of the WHC toll plaza, while the eastern boundaries of the study area are at the side of the Austin Road West / Nga Cheung Road roundabout.  Part of the Project site encroaches existing at-grade carriageways including a section of Museum Drive and slip road of West Kowloon Highway, which would undergo demolition in the Project.

6.4                  Identification of Waste Management Implications

6.4.1              Construction Phase

6.4.1.1           The construction of the Project would be divided into Phase 1 (construction works of new exit road within WKCD area) and Phase 2 (construction works of new exit road within WHC area and construction works of WHC flyover within WHC area).  Phase 1 construction would be carried out from Q2 2022 to Q4 2024, and Phase 2 from Q1 2023 to Q3 2025 tentatively.  The phases of construction works are illustrated in Figure 2.8.  The construction activities to be carried out for the Project include demolition of the existing carriageways, site clearance / set-up / plant mobilization and underground utilities protection and diversion works, piling works, pile cap / pier / abutment construction, falsework and deck construction, and drainage and pavement construction.  All the construction activities would be conducted on site and no off-site works area within Hong Kong would be involved.  It is anticipated that no excavated/dredged sediment would arise from the Project during construction phases of the Project. The types of wastes associated with these activities include

¡P         C&D materials from demolition of the existing carriageways;

¡P         C&D materials from site clearance / set-up / plant mobilization and underground utilities protection and diversion works, piling works, pile cap / pier / abutment construction;

¡P         C&D materials from falsework and deck construction;

¡P         C&D materials from drainage and pavement construction;

¡P         Chemical waste; and

¡P         General refuse.

6.4.2              Operation Phase

6.4.2.1           No wastes are expected to be generated during the operation of the Project.

6.5                  Assessment Methodology

6.5.1.1           The assessment of the potential waste management implications during the construction and operation phases of the Project has been conducted in accordance with Annexes 7 and 15 of the EIAO-TM, including the following tasks:

¡P         Estimation of the types and quantities of the wastes generated;

¡P         Evaluation of opportunities for waste reduction and re-use;

¡P         Identification of disposal options for each type of wastes;

¡P         Assessment of potential environmental impacts arising from the waste management with respect of potential hazards, air and odour emissions, noise, wastewater discharge, and public transport; and

¡P         Assessment of impacts on the capacity of waste collection, transfer and disposal facilities.

6.5.1.2           Prior to considering the disposal options for various types of waste, opportunities for reducing waste generation, on-site or off-site reuse and recycling have been evaluated in Section 6.7.3.1.  Measures which can be taken in the planning and design phases (e.g. by modifying the design approach) and in the construction phase for maximizing waste reduction have been separately considered.  According to Section 2.8, the extent of excavation and therefore the waste generation was minimized during the planning and design phases.  According to Section 2.10, pre-cast construction method would be opted for as far as possible, resulting to less waste generation on site.   Practices to promote segregation of waste materials are additionally considered for advancing the waste management efficiency.

6.5.1.3           After considering all the opportunities for reducing waste generation and maximizing reuse, the types and quantities of the waste required to be disposed of have been estimated and the disposal options for each type of waste have been described.  The disposal method recommended for each type of waste has taken into account the result of the assessment.  The impacts caused by handling (including stockpiling, labelling, packaging and storage), collection and reuse / disposal of waste have been addressed and appropriate mitigation measures have been proposed.

6.6                  Prediction and Evaluation of Waste Management Implications

6.6.1              Construction Phase

6.6.1.1           C&D materials would be generated from the construction works of the Project such as demolition of the existing carriageways, site clearance/set-up/plant mobilization, underground utilities protection and diversion works, piling works, pile cap/pier/abutment construction, falsework/deck construction, and drainage and pavement construction.  The C&D materials would comprise both inert C&D materials (i.e. public fill including soil, rock, concrete, asphalt, bentonite slurry, etc.) and non-inert C&D materials (i.e. timber).  Improper handling, collection, transportation and reuse/disposal of C&D materials would give rise to adverse environmental impacts such as potential hazard, air and odour emissions, noise and wastewater discharge, and public transport impact.  During general layout design, devising construction method described in Section 2.8 and Section 2.10 and planning of construction programme, considerations have been given to minimize the generation of inert C&D materials and maximize the use of these generated inert C&D materials for other construction works. 

6.6.1.2           Based on the latest design information, it was estimated that the volume of C&D materials generated would be 9,550 m3 for Phase 1 (9,400 m3 inert materials and 150 m3 non-inert materials) and 4,750 m3 for Phase 2 (4,600 m3 inert materials and 150 m3 non-inert materials).  However, it should be noted that these quantities are initial estimates only and would need to be further reviewed and updated as the design progresses.

6.6.1.3           Around 3,600 m3 and 2,800 m3 of inert C&D materials from Phase 1 and Phase 2 respectively, mainly soft public fill and large rocks, could be reused on site as backfill materials.  Imported fill is not required for the Project works.  A summary of the C&D materials estimates during construction phase is shown in Table 6.1. 

Table 6.1          Estimated Quantities of C&D Materials during Construction Phase

Type of Construction

Inert C&D Materials (m3)

Non-inert C&D Materials (m3)

Total C&D Materials (m3)

Inert C&D Materials to be Reused

Inert C&D Materials to be Disposed of

Phase 1

Demolition of existing carriageways

0

800

0

800

Site clearance / set-up / plant mobilization, underground utilities protection and diversion works, piling works, pile cap / pier / abutment construction

3,600

4,700

70

8,370

Falsework / deck construction

0

0

80

80

Drainage and pavement construction

0

300

0

300

Total (Phase 1)

3,600

5,800

150

9,550

Phase 2

Site clearance / set-up / plant mobilization, underground utilities protection and diversion works, piling works, pile cap/pier/abutment construction

2,800

1,600

60

4,460

Falsework / deck construction

0

0

90

90

Drainage and pavement construction

0

200

0

200

Total (Phase 2)

2,800

1,800

150

4,750

Total

(Phase 1 + Phase 2)

6,400

7,600

300

14,300

Note:

[1]    All in-situ volume

 

Demolition of Existing Carriageways

6.6.1.4           To facilitate the construction of the Project, the existing carriageways would be demolished in Phase 1 of construction.  It was assumed that the wearing course, base course and road base of the road would be demolished.  The demolition works would generate inert C&D materials, which are mainly asphalt, as summarized in Table 6.2

Table 6.2          C&D Materials Generated from Demolition of Existing Carriageways

Phase of Construction

Inert C&D Materials (m3)

Non-inert C&D Materials (m3)

Asphalt and Bentonite Slurry

Others Excluding Asphalt and Bentonite Slurry

Phase 1

800

0

0

 

Site Clearance/Set-up/Plant Mobilization, Underground Utilities Protection and Diversion Works, Piling Works, Pile Cap/Pier/Abutment Construction

6.6.1.5           Site clearance / set-up / plant mobilization, underground utilities protection and diversion works, piling works, pile cap/pier/abutment construction in Phase 1 and Phase 2 of construction would generate inert C&D materials, which are mainly soft public fill and large rock, and non-inert C&D materials, which are mainly timber formwork for pile cap/pier/abutment construction.  In addition, grouting would be involved mainly during the pile foundation and underground utilities protection.  The waste generated is summarized in Table 6.3.

Table 6.3          C&D Materials Generated from Site Clearance / Set-up / Plant Mobilization, Underground Utilities Protection and Diversion Works, Piling Works, Pile Cap / Pier / Abutment Construction

Phase of Construction

Inert C&D Materials (m3)

Non-inert C&D Materials (m3)

Asphalt and Bentonite Slurry

Others Excluding Asphalt and Bentonite Slurry

Phase 1

400

7,900

70

Phase 2

250

4,150

60

 

6.6.1.6           Backfilling of soil would be required. Around 3,600 m3 and 2,800 m3 of inert C&D materials generated from Phase 1 and Phase 2 respectively would be reused on site as backfill materials.

Falsework / Deck Construction

6.6.1.7           The falsework and construction of the new exit road bridge and WHC flyover would generate non-inert C&D materials, which are mainly timber formwork for bridge deck construction, as summarized in Table 6.4.

Table 6.4          C&D Materials Generated from Falsework / Deck Construction

Phase of Construction

Inert C&D Materials (m3)

Non-inert C&D Materials (m3)

Asphalt and Bentonite Slurry

Others Excluding Asphalt and Bentonite Slurry

Phase 1

0

0

80

Phase 2

0

0

90

 

Drainage and Pavement Construction

6.6.1.8           The drainage and pavement construction works would generate inert C&D materials, which are mainly asphalt and bentonite slurry generated during the road paving activity. The amount of waste generated is summarized in Table 6.5.

Table 6.5          C&D Materials Generated from Drainage and Pavement Construction

Phase of Construction

Inert C&D Materials (m3)

Non-inert C&D Materials (m3)

Asphalt and Bentonite Slurry

Others Excluding Asphalt and Bentonite Slurry

Phase 1

300

0

0

Phase 2

200

0

0

 

6.6.1.9           For inert C&D materials, they would be reused on-site as far as practicable subject to the review of detailed design stage before exported off site for reuse at other concurrent projects or delivered to PFRF for beneficial use in other projects.  For non-inert C&D materials, upon exhaustion of reuse/ recycling effort, they would be delivered to landfills.  A stockpiling area should be assigned to facilitate the sorting of inert and non-inert C&D materials and store the inert C&D materials for subsequent backfilling.  Subject to actual on-site condition, the tentative stockpiling area is located at the existing pet park next to New Yau Ma Tei Public Cargo Working Area, as shown in Figure 6.1. 

6.6.1.10        The non-inert C&D materials would be disposed of at the South East New Territories (SENT) Landfill while surplus inert C&D materials (general fill) would be transported to Chai Wan Public Fill Barging Point (CWBP) and surplus inert C&D materials (asphalt and bentonite slurry) to Tseung Kwan O Area 137 Fill Bank (TKOFB) or other construction sites with potential fill demand.  The Contractor should liaise with CEDD on the arrangement of and obtain all necessary permits on disposal at the fill bank and enquire with the EPD on the availability of landfill and acceptability of the waste.  Considering that the total quantity of C&D materials generated are relatively small, the amount of C&D materials to be generated daily is anticipated to be small, and the collection, transfer and disposal facilities would be able to cater for the C&D materials to be disposed of.  Construction works would be carried out in different phases and no more than 1 type of construction waste would be generated per day.  Therefore, the disposal of C&D materials would require about 2 trucks per day.  With the implementation of measures recommended in Section 6.7.5, no adverse environmental impacts (including potential hazard, air and odour emissions, noise and wastewater discharge) and public transport impact caused by handling, collection, transportation and reuse/disposal of C&D materials are expected.  In addition, the total quantity of C&D materials generated is relatively small, the amount of C&D materials to be generated daily is anticipated to be small, and the collection, transfer and disposal facilities would be able to cater for the C&D materials to be disposed.

Chemical Waste

6.6.1.11        The maintenance and servicing of construction plant and equipment may generate a negligibly small amount of chemical wastes including:

¡P         Used paint, engine oils, hydraulic fluids and waste fuel from plant operation;

¡P         Spent mineral oils / cleaning fluids from plant maintenance; and

¡P         Spent solvents / solutions, from equipment maintenance.

6.6.1.12        Chemical waste may pose serious environmental, health and safety hazards if not stored and disposed of in an appropriate manner as outlined in the Waste Disposal (Chemical Waste) (General) Regulation and the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes, i.e. posing adverse effects on air, water and land upon spilling and creating fire hazards.

6.6.1.13        It is difficult to quantify the amount of chemical waste that would arise from the construction activities since it would depend on the Contractor¡¦s on-site maintenance requirements and the amount of plant utilized.  However, it is anticipated that the quantity of chemical waste, such as lubrication oil and solvent produced from plant maintenance, would be small to in the order of a few hundred litres per month.  The amount of chemical waste to be generated would be quantified in the WMP, as a part of the EMP, to be prepared by the Contractors.

6.6.1.14        With the incorporation of suitable arrangements for storage, handling, transportation and disposal of chemical wastes in accordance with the requirements stated in the Waste Disposal (Chemical Waste) (General) Regulation and the Code of Practice on the Packaging,  Labelling and Storage of Chemical Wastes, adverse environmental (including potential hazard, air and odour emissions, noise and wastewater discharge) and public transport impact will be negligible.  In addition, since the amount of chemical waste generated is relatively small, the collection, transfer and disposal facilities would be able to cater for the chemical waste to be disposed.

General Refuse

6.6.1.15        General refuse comprising general site wastes, such as food scraps, waste paper, empty containers etc. would be generated by workforce during the construction phase.  Improper collection and removal of general refuse would give rise to hygiene problems and adverse environmental impacts to local residents, e.g. odour impacts, and contamination of the nearby watercourses.

6.6.1.16        The maximum number of construction workers to be working on site at any one time was estimated to be about 60.  Based on a generation rate of 0.65 kg per worker per day, approximately 39 kg of general refuse would be generated daily during the construction period.  It is expected that the general refuse from construction sites would be disposed of separately from the non-inert C&D materials at West New Territories (WENT) landfill.  Given the quantity of general refuse to be disposed of at landfill would be small, no adverse impact on the operation of landfill would be anticipated.

6.6.1.17        In order to minimize the final disposal quantities of general refuse, provision of sufficient number of recycling bins for the collection of different types of recyclable waste (including paper, aluminium cans, plastic and glass bottles) and sufficient number of general refuse bins for the collection of non-recyclable waste is recommended.  The Contractor should implement an education programme for worker relating to avoiding, reducing, reusing and recycling of general refuse.

6.6.1.18        The general refuse would be collected on site on a regular basis, separately from C&D materials by an appropriate waste collector to be employed by the Contractor.  Prior to disposal off site, such refuse will be temporarily put in suitably covered storage areas / bins where they will have to be regularly cleaned and maintained to avoid attracting vermin and pests.  With proper on-site handling and storage as well as regular disposal of the wastes, no unacceptable hygiene problems and environmental impacts (e.g. odour impacts and contamination of the nearby watercourses) would be anticipated.  In addition, since the amount of general refuse generated is relatively small, the collection, transfer and disposal facilities would be able to cater for the general refuse to be disposed.  Recommendations of mitigation measures for managing general refuse are presented in Section 6.7.7.

Transportation Arrangement for Waste Disposal during Construction Phase

6.6.1.19        Land transport should be used to deliver and dispose of the waste generated from the Project area to the designated disposal outlets.  Referring to Section 6.6.1.10, it is expected there will be about 2 trucks per day for transporting waste during the construction phase of the Project.  The tentative transportation routings for the disposal of various types of wastes generated during the construction phase of the Project are shown in Table 6.6.  No barging points or conveyor systems would be established in the Project area.  The transportation routings may change subject to the actual traffic conditions of the roads.  Nevertheless, with the implementation of appropriate mitigation measures (e.g. using water-tight containers and covered trucks), no adverse environmental impacts are expected due to the transportation of waste.

Table 6.6          Tentative Transportation Routings for Waste Disposal During Construction Phase

Disposal Outlet

Type of Waste

Tentative Transportation Routing

South East New Territories Landfill

Non-inert C&D Materials

Via Lin Cheung Road, West Kowloon Highway, Ching Cheung Road, Kwun Tong Road, TKO Tunnel Road, Wan Po Road

West New Territories Landfill

General Refuse

Via Lin Cheung Road, West Kowloon Highway, Tsing Kwai Highway, Tuen Mun Road, Lung Fu Road, Lung Mun Road, Nim Wan Road

Chai Wan Public Fill Barging Point

Inert C&D Materials (excluding asphalt and bentonite slurry)

Via Lin Cheung Road, West Harbour Crossing tunnel and Central Wanchai Bypass, Island Eastern Corridor, Wing Tai Road

Tseung Kwan O Area 137 Fill Bank

Inert C&D Materials (Asphalt and bentonite slurry)

Via Lin Cheung Road, West Kowloon Highway, Ching Cheung Road, Kwun Tong Road, TKO Tunnel Road, Wan Po Road

Chemical Waste Treatment Facility

Chemical Waste

Via Lin Cheung Road, West Kowloon Highway, Tsing Kwai Highway, Kwai Tsing Road, Tsing Yi Road

 

6.6.2              Operation Phase

6.6.2.1           It is expected that no waste will be generated during the operation phase of the Project.  As such, it is considered that there should be no adverse environmental impacts.

6.7                  Mitigation of Adverse Environmental Impacts

6.7.1              Waste Management Hierarchy

6.7.1.1           The waste management hierarchy has been applied in the assessment and development of mitigation measures for waste which aims at evaluating the desirability of waste management methods and includes the followings in descending preference:

¡P         Avoidance and reduction of waste generation;

¡P         Reuse of materials as far as practicable;

¡P         Recovery and recycling of residual materials where possible; and

¡P         Treatment and disposal according to relevant laws, guidelines and good practices.

6.7.1.2           Based on the waste management hierarchy, waste reduction measures are recommended as follows to reduce impacts and costs arisen from the Project.  Recommendations of good site practices and waste reduction measures would be stated in order to achieve avoidance and minimization of waste generation in the hierarchy.  EMP and trip-ticket system are recommended for monitoring management of waste.

6.7.2              Good Site Practices

6.7.2.1           It is anticipated that adverse impacts would not arise on the construction site, provided that good site practices are strictly followed.  Recommendations for good site practices during the construction phase include:

¡P         Nomination of approved personnel, such as a site manager, to be responsible for good site practices, and making arrangements for collection of all wastes generated at the site and effective disposal to an appropriate facility;

¡P         Training of site personnel in proper waste management and chemical waste handling procedures;

¡P         Provision of sufficient waste reception/ disposal points, and regular collection of waste;

¡P         Adoption of appropriate measures to minimize windblown litter and dust during transportation of waste by either covering trucks or by transporting wastes in enclosed containers;

¡P         Provision of regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors;

¡P         Adoption of a recording system for the amount of wastes generated, recycled and disposed (including the disposal sites); and

¡P         Preparation of a WMP, as a part of the EMP, in accordance with ETWB TCW No. 19/2005 and submit to the Project Engineer / Architect for approval.

6.7.3              Waste Reduction Measures

6.7.3.1           Good management and control of construction site activities / processes can minimize the generation of waste.  Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices.  Recommendations to achieve waste reduction include:

¡P         Segregate and store different types of construction related waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal;

¡P         Provide separate labelled bins to segregate recyclable waste such as aluminium cans from other general refuse generated by the work force, and to encourage collection by individual waste collectors;

¡P         Recycle any unused chemicals or those with remaining functional capacity;

¡P         Maximize the use of reusable steel formwork to reduce the amount of C&D material;

¡P         Adopt proper storage and site practices to minimize the potential for damage to, or contamination of, construction materials;

¡P         Plan the delivery and stock of construction materials carefully to minimize the amount of waste generated;

¡P         Adopt pre-cast construction method instead of cast-in-situ method for construction of concrete structures as much as possible; and

¡P         Minimize over ordering and wastage through careful planning during purchasing of construction materials.

6.7.3.2           In addition to the above measures, other specific mitigation measures are recommended below to minimize environmental impacts during handling, transportation and disposal of wastes.

6.7.4              Storage, Collection and Transportation of Waste

6.7.4.1           Storage of materials on site may induce adverse environmental impacts if not properly managed.  The following recommendations should be implemented to minimize the impacts:

¡P         Handle and store waste and excavated materials, such as soil well to ensure secure containment to minimize the potential of pollution;

¡P         Maintain and clean storage areas routinely;

¡P         Provide stockpiling area with covers and water spraying system to prevent materials from wind-blown or being washed away; and

¡P         Designate different locations for stockpiling each material to enhance reuse.

6.7.4.2           Waste collectors should be employed for the collection and transportation of C&D materials, chemical waste (licensed waste collectors required) and general refuse generated. The following recommendations should be implemented to minimize the impacts:

¡P         Remove waste in timely manner;

¡P         Employ the trucks with cover or enclosed containers for waste transportation;

¡P         Obtain relevant waste disposal permits from the appropriate authorities; and

¡P         Dispose of waste at licensed waste disposal facilities.

6.7.5              C&D Materials

6.7.5.1           In order to monitor, document and verify the disposal of C&D materials at landfills and public fill reception facilities, as appropriate, and to control fly tipping, a trip-ticket system in accordance with DevB TCW No. 6/2010 Trip Ticket System for Disposal of Construction and Demolition Materials should be implemented.

6.7.5.2           The C&D materials generated should be sorted on-site into inert C&D materials (excluding asphalt and bentonite slurry), inert C&D materials (asphalt and bentonite slurry) and non-inert C&D materials.  To minimize the impact resulting from collection and transportation of C&D materials as far as practicable, C&D materials, such as wood, plastic, steel and other metals should be reused or recycled and, as a last resort, disposed to landfill.  A suitable area should be designated within the site for temporary stockpiling of C&D materials and to facilitate the sorting process.  Within the stockpiling area, the following measures should be taken to control potential environmental impacts or nuisance:

¡P         Proper handling and storage of excavated materials such as soil by means of covers and/or water spraying system to minimize the potential environmental impact and to prevent materials from wind-blown or being washed away;

¡P         Covering materials during heavy rainfall;

¡P         Locating stockpiles to minimize potential visual impacts; and

¡P         Minimizing land intake of stockpile areas as far as possible.

6.7.6              Chemical Waste

6.7.6.1           As chemical waste is produced at the construction site, the Contractor will be required to register with EPD as a chemical waste producer and to follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes.  Suitable containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately.  Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc.  The Contractor shall employ a licensed waste collector to transport and dispose of the chemical wastes, to the licensed Chemical Waste Treatment Centre (CWTC), or other licensed facilities, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

6.7.7              General Refuse

6.7.7.1           General refuse should be stored in enclosed bins or compaction units separately from C&D materials.  A reputable waste collector should be employed by the contractor to remove general refuse from the site, separately from C&D materials.  An enclosed and covered area is preferred to reduce the occurrence of wind-blown light materials.

6.7.7.2           The recyclable component of general refuse, such as aluminium cans, paper and cleansed plastic containers shall be separated from other wastes.  Provision and collection of recycling bins for different types of recyclable waste shall be set up by the Contractor.  The Contractor shall also be responsible for arranging recycling companies to collect these materials.

6.7.7.3           The Contractor shall carry out an education programme for workers in avoiding, reducing, reusing and recycling of general refuse.  Posters and leaflets advising on the use of the bins shall also be provided in the sites as reminders.

6.7.7.4           Table 6.7 provides a summary of the various waste types likely to be generated during the construction works and operation of the Project, together with the recommended handling and disposal methods.


Table 6.7          Summary of Waste Generation, Waste Handling Procedures and Disposal Outlets

Waste Material Type

Generated From

Materials Generated

Total Quantity Generated (Approx.)

Handling Methods / Reuse

Disposal Outlet

C&D Materials

Demolition of the existing carriageways, site clearance/set-up/plant mobilization, underground utilities protection and diversion works, piling works, pile cap/pier/abutment construction, falsework/deck construction, and drainage and pavement construction

Inert C&D materials ¡V soft public fill, rock, concrete, asphalt, bentonite slurry, etc.

14,000 m3

Reuse: 6,400 m3

Disposal: 7,600 m3

¡P         Segregation of inert C&D materials (except asphalt and bentonite slurry), inert C&D materials (asphalt and bentonite slurry) and non-inert C&D materials

¡P         Reusable materials should be separated and recycled as far as practicable

¡P         Stockpile area (if required) should be well managed with covers and water spraying system

¡P         Other potential projects / disposal outlets continue to be explored throughout the project to maximize the quantity of the recycled C&D materials

¡P         Chai Wan Public Fill Barging Point (inert C&D materials except asphalt and bentonite slurry)

¡P         Tseung Kwan O Area 137 Fill Bank (asphalt and bentonite slurry)

Non-inert C&D materials ¡V timber

300 m3

¡P         Segregation from inert C&D materials

¡P         Reusable materials should be separated and recycled as far as practicable

¡P         SENT Landfill

Chemical Waste

Plant operation and maintenance

Paint, oils, hydraulic fluids, waste fuel, cleaning fluids, solvents, etc.

Small quantity in the order of a few hundred litres per month

¡P         Store in compatible containers in designated area on site

¡P         To be collected by licensed waste collectors

¡P         Chemical Waste Treatment Centre at Tsing Yi

¡P         Other reception facility that is licensed to receive chemical waste

General Refuse

Construction works, on-site staff and workers

Food waste, plastic, aluminium cans, waste papers, etc.

Around 39 kg/day

¡P         Provide on-site collection points together with recycling bins

¡P         To be collected by waste collectors

¡P         WENT Landfill

 


6.8                  Evaluation of Residual Impacts

6.8.1.1           With the implementation of the recommended mitigation measures for the handling, transportation and disposal of the identified waste arising, no adverse residual impact would be anticipated.

6.9                  Environmental Monitoring and Audit Requirements

6.9.1.1           It would be the contractor¡¦s responsibility to ensure that any wastes produced during the construction and demolition works are handled, stored and disposed of in accordance with good waste management practices and relevant regulations and other legislative requirements.

6.9.1.2           It is recommended that the waste generated during the construction activities should be audited regularly by the Environmental Team (ET) to determine if wastes are being managed in accordance with approved procedures.  The audits should look at all aspects of on-site waste management practices including waste generation, storage, recycling, transport and disposal.  Apart from weekly site inspections, documents including licenses, permits, disposal and recycling records should be reviewed and audited for compliance with the legislation of the recommended good site practice and other waste management mitigation measures.

6.9.1.3           A WMP, as a part of the EMP, should be prepared in accordance with ETWB TCW No. 19/2005 and submitted to the Project Engineer / Architect for approval.  The recommended mitigation measures should form the basis of the WMP.  The monitoring and auditing requirement stated in ETWB TCW No. 19/2005 should be followed with regard to the management of C&D materials.

6.10                Conclusion

6.10.1            Construction Phase

6.10.1.1        The main waste types generated during the construction of the Project would be C&D materials (from demolition of existing carriageways, site clearance/set-up/plant mobilization, underground utilities protection and diversion works, piling works, pile cap/pier/abutment construction, falsework/deck construction, and drainage and pavement construction), chemical waste from plant operation and maintenance and general refuse from workforce.  Provided that these wastes are handled, transported and disposed of using approved methods and that the recommended good site practices are strictly followed, no adverse environmental impacts would be anticipated.

6.10.1.2        During the construction of the Project, it is estimated 14,300 m3 of C&D materials (including 14,000m3 inert C&D materials and 300 m3 non-inert C&D materials) would be generated.  6,400 m3 of inert C&D materials would be reused on site as backfill materials and the remaining 7,600 m3 would be delivered to CWBP (for inert C&D materials except asphalt and bentonite slurry) and TKOFB (for asphalt and bentonite slurry).  The 300m3 of non-inert C&D materials, upon exhaustion of reuse/ recycling effort, would be delivered to SENT landfill.  Minimal (in the order of a few hundred litres per month) of chemical waste and 39 kg of general refuse would be generated daily.  Chemical waste would be transported and disposed of at CWTC by a licensed waste collector or other licensed facilities, while general refuse would be disposed of at WENT landfill.

6.10.2            Operation Phase

6.10.2.1        It is expected that no waste will be generated during the operation phase of the Project.  As such, it is considered that there should be no adverse environmental impacts.