TABLE OF CONTENT
1.2 Project
Scope and Location
1.6 Structure
of the EM&A Manual
2.4 Laboratory
Measurement / Analysis
5 WASTE
MANAGEMENT Implication
8.1 Site
Inspection Requirements
8.2 Compliance
with Legal and Contractual Requirements
9.2 Baseline
Environmental Monitoring Report
9.4 Quarterly
EM&A Summary Report
9.7 Interim
Notifications of Environmental Quality Limit Exceedances
List of Drawings |
|
Location Plan of the Proposed Revised Austin Road Flyover |
|
Phasing of Construction Works |
|
Locations of Air Sensitive Receivers |
|
Locations of Air Quality Monitoring Stations |
|
Locations of Noise Sensitive Receivers |
|
Locations of Noise Monitoring Stations |
|
Locations of Water Sensitive Receivers |
List of Appendices
Tentative Construction Programme |
|
Project Organization Chat |
|
Implementation Schedule of the Proposed Mitigation Measures |
|
Sample Data Record Sheet |
|
Sample Template for Interim Notifications of Environmental Quality
Limits Exceedances |
List of Tables
Table 2.1 Proposed
Construction Dust Monitoring Stations for Baseline and Impact Monitoring
Table 2.2 Summary of
Construction Dust Monitoring Programme
Table 2.3 Action and Limit
Levels for Air Quality (Construction Dust)
Table 2.4 Event and Action
Plan for Air Quality (Construction Dust)
Table 3.1 Proposed Noise
Monitoring Stations for Baseline and Impact Monitoring
Table 3.2 Action and Limit
Levels for Construction Noise
Table 3.3 Event and Action
Plan for Construction Noise
Table 7.1 Event / Action Plan
for Landscape and Visual during Construction Stage
(i) Construction of a single 2-lane flyover of about 400m long across WHC toll plaza area;
(ii) Construction of a single 2-lane ramp of about 250m long from the western end of the Revised Austin Road Flyover to the WKCD;
(iii) Construction of a single-lane ramp of about 300m long from the western end of the Revised Austin Road Flyover towards the northbound service road of WHC; and
(iv) Modification of at-grade roads within the interface of WKCD road network to connect with the ramp stated in (ii).
¡P Phase 1: Construction of NER (within WKCD Area)
¡P Phase 2: Construction of NER (within WHC Area) and Construction of WHC Flyover (within WHC Area)
¡P Responsibilities of the Contractor, the Engineer or Engineer¡¦s Representative (ER), Environmental Team (ET) and Independent Environment Checker (IEC) with respect to the environmental monitoring and audit requirements during the course of the Project;
¡P Project organisation for the EM&A works;
¡P The basis for, and description of the broad approach underlying the EM&A programme;
¡P Details of the methodologies to be adopted, including all field laboratories and analytical procedures, and details on quality assurance and quality control programme;
¡P The rationale on which the environmental monitoring data will be evaluated and interpreted;
¡P Definition of Action and Limit levels;
¡P Establishment of Event and Action plans;
¡P Requirements for reviewing pollution sources and working procedures required in the event of non-compliance with the environmental criteria and complaints; and
¡P Requirements for presentation of environmental monitoring and audit data and appropriate reporting procedures; and
¡P Requirements for reviewing the EIA predictions and the effectiveness of the mitigation measures / environmental management systems and the EM&A programme.
The Contractor
¡P Work within the scope of the contract and other tender conditions with respect to environmental requirements;
¡P Operate and strictly adhere to the guidelines and requirements in this EM&A programme and contract specifications;
¡P Provide assistance to ET in carrying out monitoring and auditing;
¡P Participate in the site inspections undertaken by ET as required, and undertake correction actions;
¡P Provide information / advice to ET regarding works activities which may contribute, or be continuing to the generation of adverse environmental conditions;
¡P Submit proposals on mitigation measures in case of exceedance of Action and Limit levels in accordance with the Event / Action Plans;
¡P Implement measures to reduce impact where Action and Limit levels are exceeded; and
¡P Adhere to the procedures for carrying out complaint investigation.
Environmental
Team (ET)
¡P Monitor various environmental parameters as required in this EM&A Manual;
¡P Analyse the environmental monitoring and audit data and review the success of EM&A programme to cost-effectively confirm the adequacy of mitigation measures implemented and the validity of the EIA predictions and to identify any adverse environmental impacts arising;
¡P Carry out regular site inspection to investigate and audit the Contractors' site practice, equipment and work methodologies with respect to pollution control and environmental mitigation, and effect proactive action to pre-empt problems; carry out ad hoc site inspections if significant environmental problems are identified;
¡P Audit and prepare monitoring and audit reports on the environmental monitoring data and site environmental conditions;
¡P Report on the environmental monitoring and audit results to the Independent Environmental Checker, Contractor, the ER and EPD or its delegated representative;
¡P Recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit levels in accordance with the Event and Action Plans;
¡P Advice to the Contractor on environmental improvement, awareness, enhancement matters, etc. on site;
¡P Timely submission of the EM&A report to the Project Proponent and the EPD; and
¡P Adhere to the procedures for carrying out complaint investigation.
Engineer or
Engineer¡¦s Representative (ER)
¡P Supervise the Contractor¡¦s activities and ensure that the requirements in the EM&A Manual are fully complied with;
¡P Inform the Contractor when action is required to reduce impacts in accordance with the Event and Action Plans;
¡P Participate in joint site inspection undertaken by the ET; and
¡P Adhere to the procedures for carrying out complaint investigation
Independent
Environmental Checker (IEC)
¡P Review the EM&A works performed by the ET (at least at monthly intervals);
¡P Carry out random sample check and audit the monitoring activities and results (at least at monthly intervals);
¡P Conduct random site inspection;
¡P Review the EM&A reports submitted by the ET;
¡P Review the effectiveness of environmental mitigation measures and project environmental performance;
¡P Review the proposal on mitigation measures submitted by the Contractor in accordance with the Event and Action Plans;
¡P Check the mitigation measures that have been recommended in the EIA and this Manual, and ensure they are properly implemented in a timely manner, when necessary; and
¡P Adhere to the procedures for carrying out complaint investigation.
¡P Section 2 ¡V Sets out EM&A requirement for air quality;
¡P Section 3 ¡V Sets out EM&A requirement for noise;
¡P Section 4 ¡V Sets out EM&A requirement for water quality;
¡P Section 5 ¡V Sets out EM&A requirement for waste management;
¡P Section 6 ¡V Sets out EM&A requirement for land contamination;
¡P Section 7 ¡V Sets out EM&A requirement for landscape and visual impact;
¡P Section 8 ¡V Describes scope and frequency of environmental site audits and sets out the general requirements of the EM&A programme; and
¡P Section 9 ¡V Details the EM&A reporting requirements.
• 0.6 - 1.7 m3 per minute (20 - 60 standard cubic feet per minute) adjustable flow range;
• equipped with a timing / control device with ¡Ó 5 minutes accuracy for 24 hours operation;
• installed with elapsed-time meter with ¡Ó 2 minutes accuracy for 24 hours operation;
• capable of providing a minimum exposed area of 406 cm2;
• flow control accuracy: ¡Ó 2.5% deviation over 24-hour sampling period;
• equipped with a shelter to protect the filter and sampler;
• incorporated with an electronic mass flow rate controller or other equivalent devices;
• equipped with a flow recorder for continuous monitoring;
• provided with a peaked roof inlet;
• incorporated with a manometer;
• able to hold and seal the filter paper to the sampler housing at horizontal position;
• easy to change the filter; and
• capable of operating continuously for 24-hour period.
• The wind sensors shall be installed on masts at an elevated level 10m above ground so that they are clear of obstructions or turbulence caused by the buildings;
• The wind data shall be captured by a data logger. The data recorded in the data logger shall be downloaded periodically for analysis at least once a month;
• The wind data monitoring equipment shall be re-calibrated at least once every six months; and
• Wind direction should be divided into 16 sectors of 22.5 degrees each.
Table 2.1 Proposed
Construction Dust Monitoring Stations for Baseline and Impact Monitoring
Air Quality Monitoring
Station |
Air Quality Assessment
Point ID in EIA |
Location |
AM1 |
CUL1 |
The
Cullinan I |
AM2 |
ICC |
International
Commerce Centre |
AM3 |
P46Aa |
Parcel 46A - Hong Kong Palace Museum |
(i) at the site boundary or such locations close to the major dust emission source;
(ii) close to the air sensitive receivers as defined in the EIAO-TM;
(iii) proper position/sitting and orientation of the monitoring equipment; and
(iv) take into account the prevailing meteorological conditions.
(i) a horizontal platform with appropriate support to secure the samplers against gusty wind shall be provided;
(ii) two samplers shall be placed less than 2 metres apart;
(iii) the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
(iv) a minimum of 2 metres of separation from walls, parapets and penthouses is required for rooftop samplers;
(v) a minimum of 2 metres of separation from any supporting structure, measured horizontally is required;
(vi) no furnace or incinerator flue is nearby;
(vii) airflow around the sampler is unrestricted;
(viii) the sampler is more than 20 metres from the dripline;
(ix) any wire fence and gate, to protect the sampler, shall not cause any obstruction during monitoring;
(x) permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
(xi) a secured supply of electricity is needed to operate the samplers.
Table 2.2 Summary
of Construction Dust Monitoring Programme
Monitoring Period |
Duration |
Sampling Parameter |
Frequency |
Baseline Monitoring |
Consecutive days of at least 2 weeks before commencement of major construction works |
1-hour TSP |
3 times per day |
Impact Monitoring |
Throughout the construction phase |
1-hour TSP |
Table 2.3 Action
and Limit Levels for Air Quality (Construction Dust)
Parameter |
Action Level [1] |
Limit Level |
TSP (1-hour average) |
BL <= 384 µgm-3, AL = (BL * 1.3 + LL)/2 BL > 384 µgm-3, AL = LL |
500 µgm-3 |
Note:
[1] BL = Baseline level, AL = Action level, LL = Limit level
Table 2.4 Event
and Action Plan for Air Quality (Construction Dust)
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action level being exceeded by one sampling |
1. Identify source, investigate the causes of
complaint and propose remedial measures; 2. Inform Contractor, IEC and ER; 3. Repeat measurement to confirm finding; and 4. Increase monitoring frequency to daily. |
1. Check monitoring data submitted by ET; 2. Check Contractor¡¦s working method; and 3. Review and advise the ET and ER on the
effectiveness of the proposed remedial measures. |
1. Notify Contractor. |
1. Identify source(s), investigate the causes
of exceedance and propose remedial measures; 2. Implement remedial measures; and 3. Amend working methods agreed with the ER
as appropriate. |
Action level being exceeded by two or more consecutive sampling |
1. Identify source; 2. Inform Contractor, IEC and ER; 3. Advise the Contractor and ER on the
effectiveness of the proposed remedial measures; 4. Repeat measurements to confirm findings; 5. Increase monitoring frequency to daily; 6. Discuss with IEC and Contractor on
remedial actions required; 7. If exceedance continues, arrange meeting
with Contractor, IEC and ER; and 8. If exceedance stops, cease additional
monitoring. |
1. Check monitoring data submitted by ET; 2. Check Contractor¡¦s working method; 3. Discuss with ET, ER and Contractor on possible
remedial measures; 4. Advise the ET and ER on the effectiveness
of the proposed remedial measures; and 5. Supervise Implementation of remedial
measures. |
1. Confirm receipt of notification of
exceedance in writing; 2. Notify Contractor; 3. Ensure remedial measures properly
implemented. |
1. Identify source and investigate the causes
of exceedance; 2. Submit proposals for remedial measures to
the ER with a copy to ET and IEC within three working days of notification; 3. Implement the agreed proposals; and 4. Amend proposal as appropriate. |
Limit level being exceeded by one sampling |
1. Identify source, investigate the causes of
exceedance and propose remedial measures; 2. Inform Contractor, IEC, ER, and EPD; 3. Repeat measurement to confirm finding; 4. Increase monitoring frequency to daily;
and 5. Assess effectiveness of Contractor¡¦s
remedial actions and keep IEC, EPD and ER informed of the results. |
1. Check monitoring data submitted by ET; 2. Check Contractor¡¦s working method; 3. Discuss with ET and Contractor on possible
remedial measures; 4. Advise the ER on the effectiveness of the
proposed remedial measures; and 5. Supervise implementation of remedial
measures. |
1. Confirm receipt of notification of
exceedance in writing; 2. Notify Contractor; 3. Ensure remedial measures properly
implemented. |
1. Identify source(s) and investigate the
causes of exceedance; 2. Take immediate action to avoid further
exceedance; 3. Submit proposals for remedial measures to
ER with a copy to ET and IEC within three working days of notification; 4. Implement the agreed proposals; and 5. Amend proposal if appropriate. |
Limit level being exceeded by two or more consecutive sampling |
1. Notify IEC, ER, Contractor and EPD; 2. Identify source; 3. Repeat measurement to confirm findings; 4. Increase monitoring frequency to daily; 5. Carry out analysis of Contractor¡¦s working
procedures to determine possible mitigation to be implemented; 6. Arrange meeting with IEC and ER to discuss
the remedial actions to be taken; 7. Assess effectiveness of Contractor¡¦s
remedial actions and keep IEC, EPD and ER informed of the results; and 8. If exceedance stops, cease additional
monitoring. |
1. Check monitoring data submitted by the ET; 2. Discuss amongst ER, ET, and Contractor on
the potential remedial actions; 3. Review Contractor¡¦s remedial actions
whenever necessary to assure their effectiveness and advise the ER
accordingly; and 4. Supervise the implementation of remedial
measures. |
1. Confirm receipt of notification of
exceedance in writing; 2. In consultation with the ET and IEC, agree
with the Contractor on the remedial measures to be implemented; 3. Supervise the implementation of remedial
measures; and 4. If exceedance continues, consider what
portion of the work is responsible and instruct the Contractor to stop that
portion of work until the exceedance is abated. |
1. Identify source(s) and investigate the
causes of exceedance; 2. Take immediate action to avoid further
exceedance; 3. Submit proposals for remedial measures to
the ER with a copy to the IEC and ET within three working days of
notification; 4. Implement the agreed proposals; 5. Revise and resubmit proposals if problem
still not under control; and 6. Stop the relevant portion of works as
determined by the ER until the exceedance is abated. |
(i) locate close to the major site activities which are likely to have noise impacts;
(ii) locate close to the most affected existing NSRs; and
(iii) take into account the possibility of minimizing disturbance to occupants at the NSRs during monitoring.
Table 3.1 Proposed
Noise Monitoring Stations for Baseline and Impact Monitoring
Noise Monitoring Station |
Noise Assessment Point ID in EIA |
Location |
NM1 |
CUL1 |
The
Cullinan I |
NM2 |
CUL2 |
The Cullinan
II |
NM3 |
HT |
The
Harbourside ¡V Tower 3 |
NM4 |
SRT |
Sorrento
¡V Tower 1 |
Table 3.2 Action and Limit Levels for Construction Noise
Time
Period |
Action
Level |
Limit
Level |
0700 ¡V 1900 hours on normal weekdays |
When
one documented complaint is received |
75 dB(A) |
Note:
[1]
If works are to be carried out during restricted hours, the
monitoring requirements and the conditions stipulated in the Construction Noise
Permit (CNP) issued by the Noise Control Authority have to be followed.
Table 3.3 Event
and Action Plan for Construction Noise
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action Level |
1. Notify IEC, ER and Contractor; 2. Carry out investigation; 3. Report the results of investigation to the IEC, ER and Contractor; 4. Discuss with the Contractor and formulate remedial measures; and 5. Increase monitoring frequency to check mitigation effectiveness. |
1. Review the analysed results submitted by the ET; 2. Review the proposed remedial measures by the Contractor and advise the ER accordingly; and 3. Supervise the implementation of remedial measures. |
1. Confirm receipt of notification of failure in writing; 2. Notify Contractor; 3. Require Contractor to propose remedial measures for the analysed noise problem; and 4. Ensure remedial measures are properly implemented. |
1. Submit noise mitigation proposals to IEC, ET and ER; and 2. Implement noise mitigation proposals |
Limit Level |
1. Identify source; 2. Inform IEC, ER, EPD and Contractor; 3. Repeat measurements to confirm findings; 4. Increase monitoring frequency; 5. Carry out analysis of Contractor¡¦s working procedures to determine possible mitigation to be implemented; 6. Inform IEC, ER and EPD the causes and actions taken for the exceedances; 7. Assess effectiveness of Contractor¡¦s remedial actions and keep IEC, EPD and ER informed of the results; and 8. If exceedance stops, cease additional monitoring. |
1. Discuss amongst ER, ET, and Contractor on the potential remedial actions; 2. Review Contractors remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly; and 3. Supervise the implementation of remedial measures. |
1. Confirm receipt of notification of failure in writing; 2. Notify Contractor; 3. Require Contractor to propose remedial measures for the analysed noise problem; 4. Ensure remedial measures properly implemented; and 5. If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated. |
1. Take immediate action to avoid further exceedance; 2. Submit proposals for remedial actions to IEC within 3 working days of notification; 3. Implement the agreed proposals; 4. Resubmit proposals if problem still not under control; and 5. Stop the relevant portion of works as determined by the ER until the exceedance is abated |
Table 7.1 Event / Action Plan
for Landscape and Visual during Construction Stage
Action Level |
ET |
IEC |
ER |
Contractor |
Non- |
1.
Inform
the Contractor, the IEC and the ER; 2. Discuss remedial actions with the IEC, the
ER and the Contractor; and 3. Monitor the remedial actions until
rectification has been completed. |
1.
Check
the inspection report; 2.
Check
the Contractor's working method; 3.
Discuss
with the ET, ER and the Contractor on possible remedial measures; and 4.
Advise
the ER on effectiveness of proposed remedial measures |
1.
Confirm
receipt of notification of nonconformity in writing; 2.
Review
and agree on the remedial measures proposed by the Contractor; and 3.
Supervise
implementation of remedial measures. |
1.
Identify
Source and investigate the nonconformity; 2.
Implement
remedial measures; 3.
Amend
working methods agreed with the ER as appropriate; and 4.
Rectify
damage and undertake any necessary replacement. |
Repeated Non- |
1.
Identify
source; 2.
Inform
the Contractor, the IEC and the ER; 3.
Increase
inspection frequency; 4.
Discuss
remedial actions with the IEC, the ER and the Contractor; 5.
Monitor
remedial actions until rectification has been completed; and 6.
If
nonconformity stops, cease additional monitoring. |
1.
Check
inspection report; 2.
Check
the Contractor's working method; 3.
Discuss
with the ET and the Contractor on possible remedial measures; and 4.
Advise
the ER on effectiveness of proposed remedial measures. |
1.
Notify
the Contractor; 2.
In
consultation with the ET and IEC, agree with the Contractor on the remedial
measures to be implemented; and 3.
Supervise
implementation of remedial measures. |
1.
Identify
Source and investigate the nonconformity; 2.
Implement
remedial measures; 3.
Amend
working methods agreed with the ER as appropriate; and 4.
Rectify
damage and undertake any necessary replacement. Stop relevant portion of
works as determined by the ER until the non-conformity is abated. |
• The EIA and EM&A recommendations on environmental protection and pollution control mitigation measures;
• The requirements of the EM&A Manual and conditions of the Environmental Permit;
• Works progress and programme;
• On-going results of the EM&A programme;
• Individual works methodology proposals (which shall include proposal on associated pollution control measures);
• Contract specifications on environmental protection and pollution prevention control;
• Relevant environmental protection and pollution control laws; and
• Previous site inspection/audit results undertaken by the ET and others.
• The ET Leader to log complaint and date of receipt onto the complaint database and inform the IEC and WKCDA immediately;
• The ET Leader to investigate the complaint to determine its validity, and to assess whether the source of the problem is due to works activities;
• The ET Leader to identify remedial measures in consultation with the IEC and WKCDA if a complaint is valid and due to construction works of Project;
• The Contractor to implement the remedial measures as identified by ET Leader and agreed with IEC and WKCDA. Any additional monitoring frequency and stations, where necessary, for checking the effectiveness of the remedial measures should be proposed by ET Leader and agreed with IEC and WKCDA;
• The ET and IEC to review the effectiveness of the Contractor¡¦s remedial measures and the updated situation;
• The ET/Contractor to undertake additional monitoring and audit to verify the situation if necessary, and oversee that circumstance leading to the complaint do not recur;
• If the complaint is a referral from EPD, the ET Leader to prepare interim report on status of the complaint investigation and follow-up action stipulated above, including the details of the remedial measures and additional monitoring identified or already taken, after endorsement by IEC and WKCDA, for submission to EPD within the time frame assigned by EPD;
• The ET report the investigation results and the subsequent actions to the source of complaint for responding to complainant (If the source of complain is a referral from EPD, the result should be reported within the time frame assigned by the EPD); and
• The ET record the details of the complaint, results of the investigation, subsequent actions taken to address the complaint and updated situation including the effectiveness of the remedial measures, supported by regular and additional monitoring results in the monthly EM&A reports.
(i) Up to half a page of executive summary:
(ii) Brief description of project background information;
(iii) Drawings showing locations of the baseline monitoring stations;
(iv) Monitoring results (in both hard and soft copies) together with the following information:
¡P Monitoring methodology
¡P Name of laboratory and types of equipment used and calibration details
¡P Parameters monitored
¡P Monitoring locations (and depth)
¡P Monitoring date, time, frequency and duration
¡P Quality assurance (QA) / quality control (QC) results and detection limits
(v) Details of influencing factor, including:
¡P Major activities, if any, being carried out on the Project site during the period
¡P Weather conditions during the period
¡P Other factors which might affect the monitoring results
(vi) Determination of the Action and Limit Levels (AL levels) for each monitoring parameter and statistical analysis of the baseline data;
(vii) Revisions for inclusion in the EM&A Manual; and
(viii) Comments and conclusions.
(i) 1-2 pages executive summary:
¡P Breaches of Action and Limit levels;
¡P Compliant log;
¡P Notifications of any summons and successful prosecutions;
¡P Reporting changes; and
¡P Future key issues.
(ii) Basic project information:
¡P Project organization including key personnel contact names and telephone numbers;
¡P Construction programme;
¡P Management structure; and
¡P Works undertaken during the reporting month.
(iii) Environmental status:
¡P Advice on the status of statutory environmental compliance such as the status of compliance with the EP conditions under the EIAO, submission status under the EP and implementation status of mitigation measures;
¡P Works undertaken during the reporting month with illustrations (such as location of works, etc.); and
¡P Drawings showing the Project area, any environmental sensitive receivers and the locations of the monitoring and control stations.
(iv) Summary of EM&A requirement:
¡P All monitoring parameters;
¡P Environmental quality performance limits (Action and Limit Levels);
¡P Event and Action Plan;
¡P Environmental mitigation measures as recommended in the EIA Report; and
¡P Environmental requirements in contract documents.
(v) Implementation Status:
¡P Advice on the implementation status of environmental protection and pollution control/mitigation measures, as recommended in the EIA Report, summarized in the updated implementation schedule.
(vi) Monitoring results (in both hard and electronic copies) together the following information:
¡P Monitoring methodology;
¡P Name of laboratory and types of equipment used and calibration details;
¡P Monitoring parameters;
¡P Monitoring locations (and depth); and
¡P Monitoring date, time, frequency and duration.
(vii) Graphical plots of monitored trends over the past four reporting periods and the following information:
¡P Major activities being carried out on site during the period;
¡P Weather condition during the period; and
¡P Other factor which might affect the monitoring results.
(viii)
Report on
non-compliance, complaints, and notifications of summons and successful
prosecutions:
¡P Record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
¡P Record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
¡P Record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;
¡P Review of the reasons for and the implications of non-compliances, complaints, summons and prosecutions including review of pollution sources and working procedures; and
¡P Description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.
(ix)
Others
¡P An account of the future key issues as reviewed from the works programme and work method statements;
¡P Advice on the solid and liquid waste management status;
¡P A forecast of the works programme, impact predictions and monitoring schedule for the next three months;
¡P Record of any project changes from the originally proposed as described in the EIA Report (e.g. construction methods, mitigation proposals, design changes, etc.); and
¡P Comments (for example, effectiveness and efficiency of the mitigation measures), recommendations (for examples, any improvement in the EM&A programme) and conclusions.
(i) 1-2 pages executive summary;
¡P Breaches of Action / Limit Levels;
¡P Complaint log;
¡P Notifications of any summons and successful prosecutions;
¡P Reporting changes; and
¡P Future key issues.
(ii) Basic project information:
¡P Project organisation including key personnel contact names and telephone numbers;
¡P Programme;
¡P Management structure;
¡P Works undertaken during the month; and
¡P Any updates as needed to the scope of works and construction methodologies.
(iii) Environmental Status
¡P Advice on the status of statutory environmental compliance such as the status of compliance with the EP conditions under the EIAO, submission status under the EP and implementation status of mitigation measures;
¡P Works undertaken during the month with illustrations (such as location of works, etc.); and
¡P Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations.
(iv) Implementation status
¡P Advice on the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the project EIA Report, summarized in the updated implementation schedule.
(v) Monitoring results (in both hard and soft copies) together with the following information:
¡P Monitoring methodology;
¡P Name of laboratory and types of equipment used and calibration details;
¡P Monitoring parameters;
¡P Monitoring locations (and depth);
¡P Monitoring date, time, frequency, and duration;
¡P Weather conditions during the period;
¡P Any other factors which might affect the monitoring results; and
¡P QA / QC results and detection limits.
(vi) Graphical plots of monitored trends over the past four reporting periods and the following information:
¡P Major activities being carried out on site during the period;
¡P Weather condition during the period; and
¡P Other factor which might affect the monitoring results.
(vii) Report on non-compliance, complaints, and notifications of summons and successful prosecutions:
¡P Record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
¡P record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;
¡P Record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;
¡P Review of the reasons for and the implications of non-compliances, complaints, summons and prosecutions including review of pollution sources and working procedures; and
¡P Description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.
(viii) Others
¡P An account of the future key issues as reviewed from the works programme and work method statements;
¡P Advice on the solid and liquid waste management status;
¡P A forecast of the works programme, impact predictions and monitoring schedule for the next three months;
¡P Record of any project changes from the originally proposed as described in the EIA (e.g. construction methods, mitigation proposals, design changes, etc.); and
¡P Comments (for examples, effectiveness and efficiency of the mitigation measures), recommendations (for examples, any improvement in the EM&A programme) and conclusions.
(ix) Appendices
¡P Action and Limit levels;
¡P Graphical plots of trends of the monitoring parameters at key stations over the past four reporting periods for representative monitoring stations annotated against the following:
(a) Major activities being carried out on site during the period;
(b) Weather conditions during the period; and
(c) Any other factors that might affect the monitoring results.
¡P Monitoring schedule for the present and next reporting period;
¡P Cumulative statistics on complaints, notifications of summons and successful prosecutions; and
¡P Outstanding issues and deficiencies.
(i) 1-2 pages executive summary;
(ii) Basic project information including a synopsis of the project organisation, programme, contacts of key management, and a synopsis of works undertaken during the quarter;
(iii) A brief summary of EM&A requirements including:
¡P Monitoring parameters;
¡P Environmental quality performance limits (Action and Limit levels);
¡P Environmental mitigation measures for construction stage, as recommended in the project EIA Report
(iv) Advice on the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the project EIA Report, summarized in the updated implementation schedule;
(v) Drawings showing the project area, any environmental sensitive receivers and the locations of the monitoring and control stations;
(vi) Graphical plots of the trends of monitored parameters over the course of the project, including the post-project monitoring for all monitoring stations annotated against:
¡P Major activities being carried out on site during the period;
¡P Weather condition during the period; and
¡P Other factor which might affect the monitoring results.
(vii) Advice on the solid and liquid waste management status;
(viii) A summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);
(ix) A brief review of the reasons for and the implications of any non-compliance, including a review of pollution sources and working procedures;
(x)
A summary description
of the actions taken in the event of non-compliance and any follow-up procedures related to earlier non-compliance;
(xi)
A summary
record of all complaints received (written or verbal) for each media, liaison
and consultation undertaken, actions and follow-up procedures taken;
(xii)
A summary record of
notifications of summons and successful prosecutions for breaches of the
current environmental protection/pollution control legislations, locations and
nature of breaches, investigation, follow-up actions taken and results;
(xiii) Comments (for examples, a review of the effectiveness and efficiency of the mitigation measures and the performance of the environmental management system, that is, of the overall EM&A programme); recommendations (for example, any improvement in the EM&A programme) and conclusions for the quarter; and
(xiv)
Proponents' contacts and any
hotline telephone number for the public to make enquiries.
(i)
Executive summary (1-2 pages);
(ii)
Drawings showing the project area, any environmental sensitive receivers and the
locations of the monitoring and control stations;
(iii)
Basic
project information including a synopsis of the project organization,
contacts of key management, and a synopsis of work undertaken during the course
of the project or past twelve months;
(iv)
A brief
summary of EM&A requirements including:
¡P Monitoring parameters;
¡P Environmental quality performance limits (Action and Limit levels);
¡P Environmental mitigation measures for construction stage, as recommended in the project EIA Report; and
¡P Event and Action Plan.
(v)
A summary
of the implementation status of environmental protection and pollution control
/ mitigation measures, as recommended in the EIA Report, summarized in the updated implementation
schedule;
(vi)
Graphical
plots and the statistical analysis of the trends of monitoring parameters over
the course of the Project, including the post-project monitoring for all
monitoring stations annotated against:
¡P The major activities being carried out on site during the reporting period;
¡P Weather conditions during the reporting period; and
¡P Any other factors which might affect the monitoring results.
(vii)
A brief summary
of non-compliance (exceedances) of the environmental quality performance limits
(Action and Limit levels);
(viii)
A review of
the reasons for and the implications of non-compliance including review of
pollution sources and working procedures as appropriate;
(ix)
A summary description
of the actions taken in the event of non-compliance and any follow-up procedures related to earlier non-compliance;
(x)
A summary
record of all complaints received (written or verbal) for each media, including
locations and nature of complaints, liaison and consultation undertaken,
actions and follow-up procedures taken;
(xi)
A summary record of
notifications of summons and successful prosecutions for breaches of the
current environmental protection/pollution control legislations, locations and
nature of breaches, investigation, follow-up actions taken and results;
(xii)
A review of
the validity of EIA predictions and identification of shortcomings of the
recommendations proposed in EIA Report;
(xiii)
Comments
(for example, a review of the effectiveness and efficiency of the mitigation
measures, the performance of the environmental management system, and the
overall EM&A programme); and
(xiv)
Recommendations
and conclusions (for example, a review of success of the overall EM&A programme to cost-effectively identify
deterioration and to initiate prompt effective mitigation action
when necessary).