1. INTRODUCTION.. 13
1.1 Project Background. 13
1.2 Objectives of this Report 14
1.3 Structure of the Report 14
1.1.1.
The
Drainage Master Plan Studies for the Yuen Long, Kam Tin, Ngau
Tam Mei and Tin Shui Wai Drainage Basin (YLDMP) were completed in 1998. The
majority of the improvement works in Yuen Long and Kam Tin recommended under
the YLDMP Study have been completed. Since completion of the DMP Studies, there
were changes in developments within the areas and new development proposals and
town planning studies were commissioned. In addition, some new flooding
complaints were received on the upstream areas of the drainage basins,
indicating that further improvement to the drainage systems was required.
1.1.2.
DSD
commissioned the "Review of Drainage Master Plans in Yuen Long and North
Districts - Feasibility Study" (DMP Review Study) in 2008 so that
the new development scenarios could be incorporated
and the effectiveness of the previously recommended works could also be
assessed. The DMP Review Study completed in end 2011 identified that some areas
in Yuen Long District could not meet the required flood protection level
according to the latest land use changes and future developments taking into
account various factors, including sedimentation at the downstream main
channels, mangrove growth at river estuaries, updated extreme sea level
statistics at Tsim Bei Tsui
and projected Climate Change impacts, in the hydraulic analysis. To account for
the severity and extent of possible flooding and the works implementation time,
the DMP Review Study proposed drainage improvement works in Yuen Long District.
1.1.3.
Atkins
China Ltd (ACL) was commissioned by Drainage Services Department (DSD) in
November 2013 to undertake an Investigation, Design and Construction
Consultancy entitled "Agreement No. CE 22/2013 (DS) Drainage Improvement
Works in Yuen Long, Stage 1 - Investigation, Design and Construction
(hereinafter called the Assignment). The Project comprises construction of
drainage improvement works to four villages (namely Sung Shan New Village, Tai
Wo, Lin Fa Tei, and Ha Che) including landscaping, waterscaping, utilities diversion, temporary traffic
arrangements and any other works incidental to the completion of the Project.
1.1.4.
The
Assignment is to carry out adoptive review, surveys, investigations, option
appraisals, impact assessments, public consultation, planning submissions,
architectural, landscaping and greening design, preliminary design, detailed
design, tendering, construction supervision and commissioning of the Project as
described in the Brief. Construction of the Project is tentatively scheduled to
commence in 2022 with a view to completing all the proposed works in 2025.
1.1.5.
Since
the completion of the DMP Review Study, the Project Management Division of DSD
carried out a further review on the proposed works under the Project. The
Project was considered feasible to improve the existing drainage condition in
Yuen Long for four villages, yet technical concern and public aspirations were
also identified that needed to be addressed properly.
1.1.6.
The
proposed drainage improvement works for consideration under this Report is
based on the preferred options evaluated under the Option Exploration and
Selection Report for this Assignment.
1.1.7.
The
Project with Project Profile (No. PP-515/2014) (hereinafter referred as the
"Project Profile") allocated with Environmental Impact Assessment
(EIA) Study Brief No. ESB-279/2014 for the Project.
1.1.8.
The Project is a designated
project under Item I.1(b) of Part I, Schedule 2 the EIAO, i.e. A drainage
channel or river training and diversion works which discharges or discharge
into an area which is less than 300m from the nearest boundary of an existing
or planned (i) site of special scientific interest;
(ii) site of cultural heritage; (iii) marine park or marine reserve; (iv) fish
culture zone; (v) wild animal protection area; (vi) coastal protection area; or
(vii) conservation area.
1.2.1.
The
objectives of the EIA study are as follows:
·
to describe the Project and
associated works together with the requirements and environmental benefits for
carrying out the Project;
·
to identify and describe the
elements of the community and environment likely to be affected by the Project
and/or likely to cause adverse impacts to the Project, including both the
natural and man-made environment and the associated environmental constraints;
·
to identify and quantify
emission sources and determine the significance of impacts on sensitive
receivers and potential affected uses;
·
to identify and quantify any
potential losses or damage to flora, fauna and wildlife habitats;
·
to identify any negative
impacts on sites of cultural heritage and to propose measures to mitigate these
impacts;
·
to identify and evaluate any
potential landscape and visual impacts and to propose measures to mitigate
these impacts;
·
to propose the provision of
infrastructure or mitigation measures to minimise
pollution, environmental disturbance and nuisance during the construction and
operation of the Project;
·
to investigate the feasibility,
effectiveness and implications of the proposed mitigation measures;
·
to identify, predict and
evaluate the residual (i.e. after practicable mitigation) environmental impacts
and the cumulative effects expected to arise during the construction and
operation phases of the Project in relation to the sensitive receivers and
potentially affected uses;
·
to identify, assess and specify
methods, measures and standards, to be included in the detailed design,
construction and operation of the Project which are necessary to mitigate these
residual environmental impacts and cumulative effects and reduce them to
acceptable levels;
·
to design and specify
environmental monitoring and audit requirements; and
·
to identify any additional
studies necessary to implement the mitigation measures or monitoring and
proposals recommended in the EIA report.
1.3.1.
The backgrounds, descriptions
and justifications of this Project are provided in Section 2. The assessment
results and recommended mitigation measures for each of the environmental
parameters that have been identified are presented in the following sections:
Section 3 – Air Quality
Section 4 – Noise
Section 5 – Ecology
Section 6 – Water Quality
Section 7 – Waste Management
Implication
Section 8 – Land Contamination
Section 9 – Landscape & Visual
Section 10 – Cultural Heritage
Section 11 – Environmental
Monitoring and Audit Requirements
Section 12 – Implementation Schedule
of Recommended Mitigation Measures
Section 13 – Summary of
Environmental Outcomes and Overall Conclusions
1.