2.        PROJECT DESCRIPTION.. 16

2.1             Location and Description of the Project 16

2.2             Need for the Project 18

2.3             Scenarios With and Without the Project 18

2.4             Consideration of Alternative Design and Layout 19

2.5             Consideration of Alternative Construction Methods and Sequences of Work. 23

2.6             Project Implementation Programme. 24

2.7             Project Interface / Concurrent Projects. 25

2.8             Public Consultation to Date. 25

 

List of Figures

Figure 2.1          Site Location Plan

Figure 2.2         Proposed Drainage Improvement Works at Sung Shan New Village

Figure 2.3         Proposed Drainage Improvement Works at Tai Wo

Figure 2.4A       Proposed Drainage Improvement Works at Lin Fa Tei (Sheet 1 of 2)

Figure 2.4B       Proposed Drainage Improvement Works at Lin Fa Tei (Sheet 2 of 2)

Figure 2.5A       Proposed Drainage Improvement Works at Ha Che (Sheet 1 of 2)

Figure 2.5B     Proposed Drainage Improvement Works at Ha Che (Sheet 2 of 2)

 

 

List of Drawings

 

Drawing No.

Drawing Title

5124336-GLP-OE-0002

General Notes and Legends

5124336-GLP-OE-1031

Proposed Drainage Works at Sung Shan New Village – Option 1

5124336-GLP-OE-1032

Proposed Drainage Works at Sung Shan New Village – Option 2

5124336-GLP-OE-1033

Proposed Drainage Works at Sung Shan New Village – Option 3

5124336-GLP-OE-1041

Proposed Drainage Works at Tai Wo – Option 1

5124336-GLP-OE-1042

Proposed Drainage Works at Tai Wo – Option 2

5124336-GLP-OE-1043

Proposed Drainage Works at Tai Wo – Option 3

5124336-GLP-OE-1051

Proposed Drainage Works at Lin Fa Tei – Option 1 (Sheet 1 of 2)

5124336-GLP-OE-1052

Proposed Drainage Works at Lin Fa Tei – Option 1 (Sheet 2 of 2)

5124336-GLP-OE-1055

Proposed Drainage Works at Lin Fa Tei – Option 2 (Sheet 1 of 2)

5124336-GLP-OE-1056

Proposed Drainage Works at Lin Fa Tei – Option 2 (Sheet 2 of 2)

5124336-GLP-OE-1057

Proposed Drainage Works at Lin Fa Tei – Option 3 (Sheet 1 of 2)

5124336-GLP-OE-1058

Proposed Drainage Works at Lin Fa Tei – Option 3 (Sheet 2 of 2)

5124336-GLP-OE-1059

Proposed Drainage Works at Lin Fa Tei – Option 4 (Sheet 1 of 2)

5124336-GLP-OE-1060

Proposed Drainage Works at Lin Fa Tei – Option 4 (Sheet 2 of 2)

5124336-GLP-OE-1071

Proposed Drainage Works at Ha Che – Option 1 (Sheet 1 of 2)

5124336-GLP-OE-1072

Proposed Drainage Works at Ha Che – Option 1 (Sheet 2 of 2)

5124336-GLP-OE-1073

Proposed Drainage Works at Ha Che – Option 2 (Sheet 1 of 2)

5124336-GLP-OE-1074

Proposed Drainage Works at Ha Che – Option 2 (Sheet 2 of 2)

5124336-GLP-OE-1075

Proposed Drainage Works at Ha Che – Option 3 (Sheet 1 of 2)

5124336-GLP-OE-1076

Proposed Drainage Works at Ha Che – Option 3 (Sheet 2 of 2)

5124336-GLP-OE-1077

Proposed Drainage Works at Ha Che – Option 4 (Sheet 1 of 2)

5124336-GLP-OE-1078

Proposed Drainage Works at Ha Che – Option 4 (Sheet 2 of 2)

 

2.               PROJECT DESCRIPTION

2.1             Location and Description of the Project

2.1.1.       The works of this Project include investigation, design and construction of drainage improvement works to four villages: Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che, including landscaping, waterscaping, utilities diversion, temporary traffic arrangements and any other works incidental works. Site photos of the existing channels are shown below.

Site photo at Sung Shan New Village

Site photo at Tai Wo

A close up of a tree

Description automatically generated

A large tree in a forest

Description automatically generated

Site photo at Lin Fa Tei

Site photo at Ha Che

 

2.1.2.       The area for the proposed widening and deepening of channels would be excavated.  Upon completion of excavation works, construction of proposed rectangular channels would be carried out on site by fixing of reinforcement bars and concreting works.

2.1.3.       The general location plan is shown in Figure 2.1. The site specific works for the four villages are described below and shown in Figures 2.2 to 2.5B:

Sung Shan New Village

2.1.4.       It is proposed to carry out upgrading works along 610m of the existing stream. The cross section of the proposed rectangular channel with width ranging from 7.5m to 8.0m varies in height (3m to 5m) along the stream to suit the existing site constraints by optimizing the hydraulic capacity but minimizing the land resumptions. Pedestrian crossings will be re-provided along the proposed works. The proposed works at Sung Shan New Village are shown in Figure 2.2.

Tai Wo

2.1.5.       It is proposed to provide a 290m long of rectangular channel with 1m wide of various height at Tai Wo to suit the existing site constraints by optimizing the hydraulic capacity but minimizing the land resumptions and discharging to the existing channel at the west. The proposed channel height ranges from 1.5m to 3.1m. The proposed works at Tai Wo are shown in Figure 2.3.

Lin Fa Tei

2.1.6.       A 150m long and 2m wide rectangular channel of height of approximately 1.7m is proposed to intercept part of the surface runoff from hillside and connect to the upstream of Shui Tsan Tin stream which will then be upgraded to a proposed rectangular channel with width ranging from 2.4m to 4.8m wide with total length of approximately 780m along the original alignment to suit the existing site constraints by optimizing the hydraulic capacity but minimizing the land resumptions. The proposed channel height at the south of Lin Fa Tei is approximately 3.7m. The 240m long 2m wide rectangular channel of various height downstream of Lin Fa Tei channel is proposed to be deepened along original alignment. Part of the flow will be diverted to the proposed 1650mm dia. storm drain underneath Kam Sheung Road. Pedestrian and vehicular crossings will be re-provided along the proposed works. The proposed works at Lin Fa Tei are shown in Figures 2.4A and 2.4B.

Ha Che

2.1.7.       Approximately 600m of the existing stream is proposed to be upgraded to a rectangular channel of various width and depth along the original alignment to suit the existing site constraints by optimizing the hydraulic capacity but minimizing the land resumptions. The proposed channel width is ranging from 3m to 6.5m, while the proposed channel height is ranging from 1.8m to 3.1m. For the bottleneck at Fan Kam Road, it will be improved by additional twin 1500mm dia. drains located to the south of the existing twin 1500mm dia. drains. A portion of stream of about 170m long (adjacent to Fu Hing Garden) will be upgraded to 3.5 to 4.5m wide rectangular channel of various height. Pedestrian and vehicular crossings will be re-provided along the proposed works. The proposed works at Ha Che are shown in Figures 2.5A and 2.5B.

2.1.8.       The following Table 2‑1 summarises the details of works.

Table 21        Scope of Proposed Project

Nature of Work

Details of Works

Drainage system

·     Construction of rectangular channel along existing stream in Sung Shan New Village.

·     Construction of rectangular channel in Tai Wo.

·     Construction of rectangular channel along existing stream in Lin Fa Tai.

·     Deepening of existing rectangular channel in Lin Fa Tai.

·     Construction of storm drain along Kam Sheung Road.

·     Construction of rectangular channel along existing stream in Ha Che.

·     Construction of storm drain across Fan Kam Road.

·     Re-provision of pedestrian and vehicular crossings.

Operation phase

·     Regular desilting maintenance

 

 

2.2             Need for the Project

2.2.1.       Currently, the four villages are susceptible to flooding in the existing drainage system. Under the DMP Review Study commissioned by DSD in 2008, it was identified that some areas in Yuen Long District could not meet the required flood protection level according to the latest land use changes and future developments. This includes taking into account of various factors, including sedimentation at the downstream main channels, mangrove growth at river estuaries, updated extreme sea level statistics at Tsim Bei Tsui and projected Climate Change impacts in the hydraulic analysis. To account for the severity and extent of possible flooding, the DMP Review Study proposed drainage improvement works in the Yuen Long District. DSD carried out a further review on the proposed works under the Project and it was considered feasible to improve the existing drainage condition for the four villages in Yuen Long. The proposed drainage improvement works aim to alleviate the flooding spots in the villages.

2.2.2.       In addition to improving the flood situation in the villages, the proposed landscaping works of the channels will revitalize the channels in terms of visual and landscape treatment for public enjoyment and blending into the environment.

2.3             Scenarios With and Without the Project

Without the Project

2.3.1.       Areas of Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che will continue to expose the adverse risk of flooding.

With the Project

2.3.2.       After the improvement works, area of Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che will provide a protection level of 10 years and the flood situation will be significantly improved.

2.4             Consideration of Alternative Design and Layout

2.4.1.       Detailed review of the DMP Review Study, site conditions and public aspirations have been carried out. Alternatives of the original design scheme are discussed below:

Drainage Improvement Works at Sung Shan New Village

Option 1

2.4.2.       To improve the drainage condition, the existing stream is proposed to be upgraded to a consistent 5m wide trapezoidal channel before connecting to the existing nullah along Tai Shu Ha Road. The proposed alignment will be realigned to reduce the extent of meander at midstream with land resumption. Natural bedding will be constructed at the trapezoidal channel for provisioning of habitat in the existing stream. Pedestrian crossings will be re-provided along the proposed works. (Drawing No. 5124336-GLP-OE-1031 refers).

Option 2

2.4.3.       It is proposed to carry out upgrading works along the existing stream.  In order to optimize the hydraulic capacity, the cross sections will vary along the proposed channel to suit the existing site constraints as well as providing natural bedding and intermediate openings for natural bedding in various sections for provisioning of habitat in the existing stream. This option would also minimize land resumptions by avoiding encroaching into private land lots. Pedestrian crossings will be re-provided along the proposed works (Drawing No. 5124336-GLP-OE-1032 refers).

Option 3

2.4.4.       It is proposed to carry out upgrading works along 610m of the existing stream. The cross section of the proposed rectangular channel with width ranging from 7.5m to 8.0m varies in height (3m to 5m) along the stream to suit the existing site constraints by optimizing the hydraulic capacity but minimizing the land resumptions. Green channel with natural bedding is proposed as far as possible to maintain the naturalness of the existing stream. Pedestrian crossings will be re-provided along the proposed works (Drawing No. 5124336/GLP/OE/1033 refers).

Drainage Improvement Works at Tai Wo

Option 1

2.4.5.       A new 1350mm dia. pipe is proposed along the existing low-lying area at the south of Tai Wo, connecting to the existing channel in the west (Drawing No. 5124336/GLP/OE/1041 refers). The proposed underground drains would minimise the disturbance to the existing land, visual impact and habitats.

Option 2

2.4.6.       Considering the limited government land, trapezoidal channel design will not be considered. In order to optimise the drainage capacity but minimizing the land resumptions, it is proposed to provide a 1m (W) x 1.5m (H) open rectangular channel along the existing low-lying area at the southwest corner of Tai Wo connecting to the engineering channel at the west, which facilitates collection of surface runoff. A 900mm covered channel is proposed to collect the runoff within Tai Wo Village and divert the flow to proposed rectangular channel (Drawing No. 5124336/GLP/OE/1042 refers).

Option 3

2.4.7.       It is proposed to provide a 290m long of rectangular channel with 1m wide of various height at Tai Wo and discharging to the existing channel at the west. Due to land matters, the construction of proposed 900mm covered channel proposed in Option 2 requires obtaining HAD’s consent, hence it has been removed from this option. The proposed channel height ranges from 1.5m to 3.1m. (Drawing No. 5124336/GLP/OE/1043 refers).

Drainage Improvement Works at Lin Fa Tei

Option 1

2.4.8.       A 2m wide rectangular channel is proposed to intercept the runoff from upstream of Lin Fa Tei stream and convey into Shui Tsan Tin stream which will then be upgraded to a 4m wide trapezoidal channel with local straightening at bend. The proposed alignment will be realigned to reduce the extent of meander at midstream with land resumption. Portion of the Shui Tsan Tin stream will need to be in the form of rectangular shape due to the limited space between village houses. Natural bedding will be provided to various sections along the proposed channel. Pedestrian and vehicular crossings will be re-provided along the proposed works (Drawing Nos. 5124336/GLP/OE/1051 and 5124336/GLP/OE/1052 refer).

Option 2

2.4.9.       A 2m wide rectangular channel is proposed to intercept the runoff from upstream of Lin Fa Tei stream and convey into Shui Tsan Tin stream which will then be upgraded to trapezoidal channel or rectangular channel along the original alignment. The existing Lin Fa Tei stream is proposed to be upgraded to 1m wide rectangular channel along the original alignment to increase the drainage capacity. Natural bedding will be provided to various sections along the proposed channel. Pedestrian and vehicular crossings will be re-provided along the proposed works (Drawing Nos. 5124336/GLP/OE/1055 and 5124336/GLP/OE/1056 refer).

Option 3

2.4.10.    Shui Tsan Tin stream will be upgraded to rectangular channel along the original alignment as far as possible. Pedestrian and vehicular crossings will be re-provided along the proposed works. It is proposed to be a 2m wide rectangular intercepting channel, connecting to the upstream of Shui Tsan Tin stream to cut off part of surface runoff from the hill. At the downstream approximately 2m wide rectangular channel across the entrance of Lin Fa Tei village is proposed to be deepened along the original alignment, with part of the flow diverted to the proposed twin 1050mm dia. storm drains underneath Kam Sheung Road which will be connected to existing engineered nullah to increase the drainage capacity. Natural bedding will be provided to various sections along the proposed channel (Drawing Nos. 5124336/GLP/OE/1057 and 5124336/GLP/OE/1058 refer).

Option 4

2.4.11.    A 2m wide rectangular channel of height of approximately 1.7m is proposed to intercept part of the surface runoff from hillside and connect to the upstream of Shui Tsan Tin stream which will then be upgraded to a proposed rectangular channel with width ranging from 2.4m to 4.8m wide with total length of approximately 930m along the original alignment. The proposed channel height at the south of Lin Fa Tei is approximately 3.7m. Green channel with natural bedding is proposed to maintain the naturalness of the existing stream. The 240m long 2m wide rectangular channel of various height downstream of Lin Fa Tei channel is proposed to be deepened along original alignment. Part of the flow will be diverted to the proposed 1650mm dia. storm drain underneath Kam Sheung Road. Pedestrian and vehicular crossings will be re-provided along the proposed works (Drawing Nos. 5124336/GLP/OE/1059 and 5124336/GLP/OE/1060 refer).

Drainage Improvement Works at Ha Che

Option 1

2.4.12.    To improve the drainage capacity, it is recommended to upgrade the existing stream adjacent to the Fan Kam Road to a 6m wide rectangular channel at the upper stream and a 8m wide trapezoidal channel at mid-stream. Due to being close to the existing buildings, a portion of stream of about 200m long (adjacent to Fu Hing Garden) will be upgraded to a twin cell box culvert with 2.5m (H) ×2.5m (W) each. Natural bedding will be provided in the areas of Sections A and B Drawing No. 5124336/GLP/OE/1071. Natural bedding would not be required within proposed box culvert as shown in Section C of Drawing No. 5124336/GLP/OE/1072. Existing bottlenecks at crossings at the Fan Kam Road and at access road to Shui Kan Shek will be upgraded to a twin cell box culvert with 2.5m (H) ×2.5m (W) each. Pedestrian and vehicular crossings will be re-provided along the proposed works (Drawing Nos. 5124336/GLP/OE/1071 and 5124336/GLP/OE/1072 refer).

Option 2

2.4.13.    The existing stream is proposed to be upgraded to a 3m (W) x 2m (H) rectangular channel along the original alignment to suit the existing site constraints by optimizing the hydraulic capacity but minimizing the land resumptions. For underground drainage pipes, it would be impracticable to provide natural bedding due to risk of blockage and flooding. For the bottleneck at Fan Kam Road, addition of two 1500mm dia. drains will be proposed by pipe jacking method. A portion of stream of about 200m long (adjacent to Fu Hing Garden) will be upgraded to 4.5m (W) x 3m (H) rectangular channel.   Pedestrian and vehicular crossings will be re-provided along the proposed works (Drawing Nos. 5124336/GLP/OE/1073 and 5124336/GLP/OE/1074 refer).

Option 3

2.4.14.    The existing stream is proposed to be upgraded to a 3m (W) x 2m (H) rectangular channel along the original alignment to suit the existing site constraints by optimizing the hydraulic capacity but minimizing the land resumptions. For the section upstream close to Shui Kan Shek, it is proposed to construct a new 2m (W) x 1.5m (H) rectangular channel and maintain the existing channel due to space constraint in the area. For the other existing bottleneck at access road to Shui Kan Shek, two 1200mm dia. pipes will be provided to improve the cross-section area. For another bottleneck at Fan Kam Road, addition of two 1500mm dia. drains will be proposed by pipe jacking method. A portion of stream of about 200m long (adjacent to Fu Hing Garden) will be upgraded to 4.5m (W) x 3m (H) rectangular channel. Pedestrian and vehicular crossings will be re-provided along the proposed works (Drawing Nos. 5124336/GLP/OE/1075 and 5124336/GLP/OE/1076 refer).

Option 4

2.4.15.    By optimizing the hydraulic capacity but minimizing the land resumptions, approximately 600m of the existing stream is proposed to be upgraded to a rectangular channel of various width and depth along the original alignment to suit the existing site constraints. The proposed channel width is ranging from 3m to 6.5m, while the proposed channel height is ranging from 1.8m to 3.1m. For the bottleneck at Fan Kam Road, it will be improved by additional twin 1500mm dia. drains located to the south of the existing twin 1500mm dia. drains. A portion of stream of about 170m long (adjacent to Fu Hing Garden) will be upgraded to 3.5 to 4.5m wide rectangular channel of various height. Green channel with natural bedding is proposed to maintain the naturalness of the existing stream. Pedestrian and vehicular crossings will be re-provided along the proposed works. (Drawing Nos. 5124336/GLP/OE/1077 and 5124336/GLP/OE/1078 refer).

Preferred Options of Drainage Improvement Works

2.4.16.    Considering the options of drainage improvement works as described in para. 2.4.2 to 2.4.15 and the corresponding drawings, the preferred option is presented as follows:

Sung Shan New Village

2.4.17.    The trapezoidal channel design considered in Option 1 would have a larger footprint of the proposed channel, which would encroach into a number of private land lots and clearance of the existing structures is inevitably required. The trapezoidal channel design will likely arose strong public objection. Full width opening at channel bed in Option 3 is more preferable over the provisions of intermediate openings in Option 2 in environmental point of view. Thus, the preferred option is Option 3. It is proposed to provide a 7.5m – 8.0m (W) x 3m – 5m (H) rectangular sections with vertical wall to optimize the use of government land by minimizing land resumption to suit the existing site constraints while meeting the requirements for hydraulic performance. The Aquilaria Sinensis (seedling) in Sung Shan New Village will be protected and retained during construction. Green channel with natural bedding will be provided along the proposed channel as far as possible. The preferred option is presented in Figure 2.2.

Tai Wo

2.4.18.    Considering the limited government land, trapezoidal channel design will not be considered. The drainage capacity of the rectangular channel design in Option 3 is more preferable as compared to Option 2. Thus, the preferred option is Option 3. It is proposed to provide a 1m (W) x 1.5m 3.1m (H) open rectangular channel along the sloping ground at the southwest corner of Tai Wo connecting to the engineering channel at the west. The width of the channel was limited to avoid land resumption, hence to fulfil the requirements of hydraulic performance. Green channel with natural bedding will be provided along the proposed channel. The width and depth of the proposed channel also limits the maintenance works to be carried within the channel. The preferred option is presented in Figure 2.3.

Lin Fa Tei

2.4.19.    The trapezoidal channel design considered in Options 1 and 2 would have a larger footprint of the proposed channel, which would encroach into a number of private land lots and clearance of the existing structures is inevitably required. The trapezoidal channel design will likely arose strong public objection. Full width opening at channel bed in Option 4 is more preferable over the provisions of intermediate openings in Options 2 and 3 in environmental point of view. Thus, the preferred option is Option 4. Shui Tsan Tin stream (the southern proposed works) will be upgraded to a rectangular channel along the original alignment as far as possible as green channel with natural bedding to maintain the naturalness of the existing stream. It is proposed to upgrade the existing rectangular intercepting channel, connecting to the upstream of Shui Tsan Tin stream, to a proposed rectangular channel ranging from 2.4m to 4.8m wide and 3.7m high along the original alignment to cut off part of surface runoff from the hill which will then be upgraded. At the northern proposed works, an approximately 240m long 2m wide rectangular concrete channel adjacent to the entrance of Lin Fa Tei village is proposed to be deepened along the original alignment with natural bedding, with part of the flow diverted to the proposed 1650mm dia. storm drains underneath Kam Sheung Road which will be connected to existing engineered nullah to increase the drainage capacity. Green channel with natural bedding or natural bedding will be provided at various sections along the proposed channel subject to the hydraulic performance at particular locations. Pedestrian and vehicular crossings will be re-provided along the proposed works. The preferred option is presented in Figures 2.4A and 2.4B.

Ha Che

2.4.20.    The trapezoidal channel design considered in Option 1 would have a larger footprint of the proposed channel, which would encroach into a number of private land lots and clearance of the existing structures is inevitably required. The trapezoidal channel design will likely arose strong public objection. Full width opening at channel bed in Option 4 is more preferable over the provisions of intermediate openings in Options 2 and 3 in environmental point of view. Thus, the preferred option is Option 4. It is proposed to upgrade the existing stream to a 3m – 6.5m (W) x 1.8m – 3.1m (H) rectangular channel along the original alignment to suit the existing site constraints by optimizing the hydraulic capacity but minimizing the land resumptions. For the bottleneck at Fan Kam Road, it will be improved by additional twin 1500mm dia. drains located to the south of the existing twin 1500mm dia. drains by pipe jacking method. A portion of stream of about 170m long (adjacent to Fu Hing Garden) will be upgraded to 3.5m to 4.5m wide rectangular channel of various height. Pedestrian and vehicular crossings will be re-provided along the proposed works. Green channel with natural bedding will be provided along the proposed channel. The preferred option is presented in Figures 2.5A and 2.5B.

2.5             Consideration of Alternative Construction Methods and Sequences of Work

Proposed Underground Drainage Pipes

2.5.1.       The proposed works for underground drainage pipes would be implemented by open cut method as far as practicable, due to its cost effectiveness in the improvement in proposed drainage works. The proposed works would be carried out on a section-by-section basis to minimize period of nuisance to the nearby sensitive receivers during construction.

2.5.2.       A proposed drainage section will be located across Fan Kam Road in Ha Che. In order to minimise traffic impact on the existing roads, trenchless method is proposed for pipe installation. The proposed drainage section located underneath Kam Sheung Road in Lin Fa Tei would be constructed by open trench method.

2.5.3.       Table 2‑2 provides the comparisons on environmental benefits and dis-benefits of open-cut and trenchless method.

Table 22        Environmental Benefits and Dis-Benefits of Alternative Construction Methods

Options

Environmental Benefits

Environmental Dis-Benefits

Open-Cut Method

· Faster construction progress and hence the period of environmental disturbance is reduced.

· Construction nuisances including dust and noise will affect all sensitive receivers along entire works alignment.

Trenchless Method

· Excavation is only required at launching and receiving pit locations. Hence localized construction nuisances are limited to the sensitive receivers near the working pits only.

· Comparatively less excavated materials will be generated.

· Longer period of environmental disturbance due to slow construction progress.

2.5.4.       For open-cut method, temporary traffic management will be carried out on a section-by-section basis to minimize period of nuisance to the village traffic.  Upon the completion of utility survey and inspection pits to ensure no existing utilities would clash with the proposed works, ground excavation will take place between the time periods 7am and 7pm. No construction noise permit would be required. For excavation greater than 1.2m, sheetpiles with struts and wales will be constructed as temporary support adjacent to the slope. Underground pipes would be laid after the completion of pipe bedding and then backfilled with soil.

2.5.5.       For trenchless method, the jacking pit and receiving pit would be constructed for the trenchless pipe sections. The pipes would be carried out by segmental pipe jacking method. After the completion of tunnel between the two pits, the proposed underground pipe would be laid.

2.6             Project Implementation Programme

2.6.1.       The proposed drainage improvement works in four villages are planned to commence in 2022 and completion in 2025. The tentative construction programme is provided in the Table 2‑3 below. The proposed rectangular channels at the 4 villages will be constructed during dry seasons. The proposed pipe works at Lin Fa Tei will be constructed during wet seasons as the construction of new drainage pipes will not be constrained by any existing flow.

Table 23           Tentative Construction Programme

Legends:

For construction works of rectangular channels

For construction works of pipe works

2.7             Project Interface / Concurrent Projects

2.7.1.       The major potential interfacing projects identified at this stage are listed as below. Summary of the potential interfacing projects of four villages is shown in Table 2‑4.

·                 Agreement No. CE 61/2012 (HY) Improvement to Fan Kam Road by Highways Department – Investigation.

Table 24           Summary of the Potential Interfacing Projects

Location

Potential Interfacing Projects

Cumulative Impact

 

 

Construction Phase

Operation Phase

Ha Che

Agreement No. CE 61/2012 (HY) Improvement to Fan Kam Road

(Tentative Schedule of Construction: 2021 to 2025)

Cumulative dust and air-borne noise impact near Fan Kam Road

Not anticipated

2.8             Public Consultation to Date

2.8.1.       The process of Continuous Public Involvement (CPI) for the proposed Project through meetings and public consultation are summarized below in Table 2‑5. The Rural Committees of Pat Heung, Shap Pat Heung and Ping Shan and Green Groups were also consulted through letters or emails.

Table 25           Summary of Continuous Public Involvement

Date

Concerned Parties

18 December 2015

Sheung Che Tsuen and Chuk Hang Tsuen Village Representatives

21 December 2015

Lin Fa Tei and Tai Wo Tsuen Village Representatives

07 April 2016

Sung Shan New Village Village Representatives

08 April 2016

Shui Tsan Tin Tsuen and Ngau Keng Village Representatives

10 May 2016

Ha Che Tsuen Village Representatives

16 May 2016

Ha Che Tsuen Village Representatives

25 May 2016

Lin Fa Tei Village Representatives

17 September 2018

Yuen Long District Council

24 April 2020

Green Groups

14 September 2020

Yuen Long District Council - Environment, Climate Change, Agriculture and Fisheries Committee