4.2 Relevant Legislations, Standards
& Guidelines
4.3 Baseline Environmental
Conditions
4.4 Assessment Area and Noise
Sensitive Receivers
4.8 Residual Construction Noise Impacts
List of Figures
Noise Impact Assessment – Key Plan |
|
Location of Representative Noise Sensitive Receivers at
Sung Shan New Village |
|
Location of Representative Noise Sensitive Receivers at
Tai Wo |
|
Location of Representative Noise Sensitive Receivers at
Lin Fa Tei |
|
Location of Representative Noise Sensitive Receivers at
Ha Che |
|
Photographs of Representative Noise Sensitive Receivers
at Sung Shan New Village |
|
Photographs of Representative Noise Sensitive Receivers
at Tai Wo |
|
Photographs of Representative Noise Sensitive Receivers
at Lin Fa Tei (Sheet 1 of 2) |
|
Photographs of Representative Noise Sensitive Receivers
at Lin Fa Tei (Sheet 2 of 2) |
|
Photographs of Representative Noise Sensitive Receivers
at Ha Che |
List of Appendices
Appendix 4-1a-1d Locations
of Works Areas
Appendix 4-2a Plant
Inventory (Unmitigated Scenario)
Appendix 4-2b Predicted
Construction Noise Levels (Unmitigated Scenario)
Appendix 4-3a Plant
Inventory (Mitigated Scenario)
Appendix 4-3b Predicted
Construction Noise Levels (Mitigated Scenario)
Appendix 4-4 Potential
Overlapping Works Areas with Other Projectsv
Appendix 4-5 Typical Section Drawing of
Temporary/Movable Noise Barrier
4.
Noise Impact Assessment
4.1.1. This section presents the
assessment on the potential noise impacts that are likely to be generated
during the construction phase of the Project. Appropriate mitigation measures
have been identified to mitigate the potential noise impacts arising from
construction phase of the Project.
4.1.2. The Project will not
involve any fixed noisy plant and will not generate noise during the
operational phase. It also will only involve channel widening and new drainage
conduits and no pumping station will be constructed. As such, operational noise impact has not been
considered further.
4.1.3. This assessment has been
carried out based on the criteria and guidelines for evaluation and assessment
of noise impacts as stated in Annex 5 and 13 of EIAO-TM and has covered the
scope outlined in Section 3.4.2 of the EIA Study Brief.
4.2
Relevant
Legislations, Standards & Guidelines
4.2.1. The relevant legislation and associated guidance
applicable to the present study for the assessment of noise impacts include:
Noise Control Ordinance (NCO) (Cap.400);
Environmental Impact Assessment Ordinance (EIAO) (Cap.499);
Technical Memorandum on Noise from Construction Work other than
Percussive Piling (GW-TM).
Technical Memorandum on Environmental Impact Assessment Process
(EIAO-TM); and
EIAO Guidance Note – Preparation of Construction Noise Impact Assessment
under the Environmental Impact Assessment Ordinance (GN9/2010).
4.2.2. The NCO provides the
statutory framework for noise control in Hong Kong. Assessment procedures and
standards are set out in the respective TM promulgated under the NCO.
4.2.3. To ensure a better
environment, the EIAO-TM promulgated under the EIAO has imposed more stringent
criteria. There is no statutory limit on the noise from general construction
works during the non-restricted hours (i.e. the hours between 0700 and 1900 any
day not being a Sunday or general holiday) under the NCO and the related TMs.
Noise impact arising from general construction activities other than percussive
piling during the non-restricted hours are assessed against the noise criteria
as stipulated in Table 1B of Annex 5 of the EIAO-TM as shown in Table
4‑1.
Table 4‑1 Noise
Standards for Daytime Construction Activities
Noise Sensitive Uses |
Noise Standards, Leq (30min), dB(A) (1), (2) |
0700 to 1900 hours on any day not being a Sunday or general holiday |
|
All domestic
premises including temporary housing accommodation |
75 |
Hotels and hostels |
75 |
Educational
institutions including kindergartens, nurseries and all others where unaided
voice communication is required |
70 65 (During
examinations) |
Notes:
(1)
The above noise standards
apply to uses which rely on openable windows for ventilations.
(2)
The above standards should
be viewed as the maximum permissible noise levels assessed at 1m from the
external facade.
4.2.4. No percussive piling is anticipated for the
Project. Notwithstanding, should percussive piling be required, the
requirements in Technical Memorandum on Noise from Percussive Piling (PP-TM)
shall be followed.
4.3
Baseline
Environmental Conditions
4.3.1. The proposed works area
is located within Sung Shan New Village and Tong Tau Po Tsuen as shown in Figure
2.2. The surrounding land
uses comprise village houses, temporary structures, open storage areas, vehicle
repairing areas, offices and workshops. A soy sauce factory is located on the
northern side of the proposed works area. During the site visit in January
2019, the background noise environment was dominated by the traffic noise from
the village access road and Tai Shu Ha Road East and noise from industrial
activities.
Tai Wo
4.3.2. The proposed works area is located within Cheung Po
and Tai Wo as shown in Figure
2.3. The surrounding land uses comprise village houses,
open car parking areas, playground and agricultural lands. MTR Corporation Pat
Heung Depot and Kam Ho Road (classified as a “rural road” according to the
Annual Average Daily Traffic (AADT) Census 2019) are in close proximity to the
proposed drainage improvement works alignment at Cheung Po. During the site
visit in January 2019, the major noise sources are contributed by traffic noise
from Kam Ho Road and railway noise from MTR Corporation Pat Heung Depot.
Lin Fa Tei
4.3.3. The proposed works area is located at Lin Fa Tei as shown in Figures 2.4A and 2.4B. The land uses in the vicinity of the proposed
works area at this village are low rise residential buildings, car parking
area, open storage areas and car scrapyard. Kam Sheung Road (classified as a
“rural road” according to the AADT Census 2019) runs to the northern portion of
the proposed works area. The noise climate of the proposed works area surroundings
is contributed by the traffic noise from Kam Sheung Road and Kam Shui South
Road and village access roads and noise from industrial activities. During the
site visits in April 2019, there were two or more clusters of low rise
buildings being constructed next to the proposed drainage improvement works
area near the junction of Kam Sheung Road and Kam Shui South Road.
Ha Che
4.3.4. The proposed works area is located within Sheung
Che Tsuen, Chuk Hang and A Kung Tin as shown in Figures 2.5A and 2.5B. The major land uses in the vicinity of the
proposed works area are low rise residential buildings, temporary structures,
open storage areas and workshops. Fan Kam Road (classified as a “rural road”
according to the AADT Census 2019) runs crossing the proposed works area. A
Fire Services Department Training School is located close to the proposed
drainage improvement works area at A Kung Tin. During the site visits in April
2019, the major noise sources are traffic noise from Fan Kam Road and noise
from industrial activities.
4.4
Assessment
Area and Noise Sensitive Receivers
4.4.1. The assessment area for noise impact assessment
covers all areas within 300 m from the proposed drainage improvement works site
boundary and is shown in Figure
4.1. Representative noise sensitive receivers (NSRs) within
300m assessment area have been identified according to the criteria set out in
Annex 13 of the EIAO-TM. These NSRs are identified based on the review of the
latest information from Planning Department (PlanD) and Lands Department
(LandsD) as well as the statutory Outline Zoning Plans (OZPs) including OZP No.
S/YL-TT/17 (Tai Tong), S/YL-KTS/15 (Kam Tin South), S/YL-SK/9 (Skek Kong) and
S/YL-PH/11 (Pat Heung) and information available in the Statutory Planning
Portal of Town Planning Board. Site visits were conducted in January and April
2019 to verify the identification of NSRs and update the status of the NSRs
following the desktop review. No planned nor committed representative NSRs were
identified.
4.4.2. Only the first layer of
NSRs located closest to the noise sources have been identified as the representative noise assessment points for assessment as they
would be worst affected and would also provide acoustic shielding to the
generally low rise village house type receivers at further distance behind. Other
NSRs further away from these representative NSRs are expected to be less
affected. The representative NSRs selected for the noise assessment are
presented in Table
4‑2. The locations of these
representative NSRs are shown in Figures 4.2 to 4.5 and the relevant
photographs are provided in Figures 4.6 to 4.9.
Table 4‑2 Representative Noise Sensitive
Receivers
Description of NSRs |
Nature of Use |
Approximate Horizontal Distance from the NSR
to Proposed Works Area (m) |
Approximate ground level of NSRs (mPD) |
No. of Storeys |
|
Sung Shan New Village |
|||||
SSNV1 |
#88A, Yau Cha Po |
Residential |
12 |
12.7 |
3 |
SSNV2 |
Village house next to
a nullah in Tong Tai Po Tsuen (near DD118 1720 S.A) |
Residential |
2 |
13.3 |
2 |
SSNV3 |
Village house near a
soy sauce factory in Sung Shan New Village (near DD118 1712) |
Residential |
2 |
12.7 |
1 |
SSNV4 |
#107, Yau Cha Po |
Residential |
15 |
19.5 |
2 |
SSNV5 |
#25, Sung Shan New
Village |
Residential |
30 |
14.4 |
1 |
SSNV6 |
#43, Sung Shan New
Village |
Residential |
19 |
14.4 |
1 |
SSNV7 |
Temporary structure
next to a track in Sung Shan New Village (DD118 Lot. 1767) |
Residential |
36 |
15.8 |
1 |
Tai Wo |
|||||
TW1 |
Temporary structure
near footbridge in Cheung Po (DD112 Lot.837
S.A.RP) |
Residential |
15 |
15.4 |
1 |
TW2 |
#200, Cheung Po |
Residential |
36 |
17.3 |
3 |
TW3 |
Kai Yip Garden, #3H,
Tai Wo |
Residential |
50 |
20.6 |
3 |
TW4 |
#40B, Tai Wo |
Residential |
37 |
21.8 |
3 |
Lin Fa Tei |
|||||
LFT1 |
#2G, Lin Fa Tei |
Residential |
6 |
23.1 |
3 |
LFT2 |
Temporary building
next to a nullah in Lin Fa Tei |
Residential |
3 |
25.4 |
1 |
LFT3 |
#125, Lin Fa Tei |
Residential |
<1 |
19.4 |
2 |
LFT4 |
#156A, Lin Fa Tei |
Residential |
4 |
19.2 |
3 |
LFT5 |
#156B, Lin Fa Tei |
Residential |
4 |
19.2 |
3 |
LFT6 |
#47, Shui Tsan Tin |
Residential |
6 |
17.5 |
2 |
LFT7 |
Village house near
the nullah |
Residential |
2 |
17.5 |
3 |
LFT8 |
Village house near
the nullah |
Residential |
1 |
17.6 |
3 |
LFT9 |
Village house near
the nullah |
Residential |
1 |
18.6 |
3 |
LFT10 |
Moon Wo Grand Houses,
#510, Lin Fa Tei |
Residential |
14 |
19.5 |
4 |
LFT11 |
#210 Ngau Keng |
Residential |
4 |
20.1 |
3 |
LFT12 |
#297, Lin Fa Tei |
Residential |
3 |
19.8 |
3 |
LFT13 |
#290, Lin Fa Tei |
Residential |
2 |
19.3 |
3 |
LFT14 |
#231C, Lin Fa Tei |
Residential |
2 |
20.1 |
3 |
Ha Che |
|||||
HC1 |
#149, Chuk Hang |
Residential |
10 |
20.2 |
4 |
HC2 |
Block 29, Fu Hing
Garden, #88 Sheung Che |
Residential |
6 |
20.2 |
3 |
HC3 |
Block P, Fu Hing
Garden, #88 Sheung Che |
Residential |
4 |
21.5 |
3 |
HC4 |
Block N, Fu Hing
Garden, #88 Sheung Che |
Residential |
1 |
21.8 |
4 |
HC5 |
Block F, Fu Hing
Garden, #88 Sheung Che |
Residential |
1 |
22.3 |
4 |
HC6 |
#1C, Chuk Hang |
Residential |
1 |
23.2 |
3 |
HC7 |
#300, Sheung Che |
Residential |
3 |
22.5 |
3 |
HC8 |
The Arbutus House 12,
#52, Shui Kan Shek |
Residential |
4 |
27.1 |
3 |
4.5.1. The construction noise impact has been assessed
based on the following methodology:
· Determine extent of the 300 m assessment area from the proposed Project Site Boundary;
· Identify representative NSRs which would most likely be affected by noise from the proposed construction works;
· Obtain the construction method and works sequence for the construction period from the Engineer;
· Obtain the items of Powered Mechanical Equipment (PME) for each construction activity (including number of each type of plant and utilization rate) from Engineer;
· Determine the Sound Power Levels (SWLs) of plant items according to the information stated in the GW-TM or other recognized sources of reference. Where appropriate;
· Calculate the distance attenuation from notional noise source. Under the GW-TM, the distance attenuation will be determined by the following formula:
· Distance attenuation in dB(A) = 20 Log D + 8 [where D is distance in metre];
· Apply corrections in the calculations such as potential screening effect and acoustic reflection, if any;
· A +3 dB(A) façade correction has been applied to account for the facades effect at each NSR;
· Calculate the unmitigated Predicted Noise Levels at the identified NSRs;
· Consider accumulative noise impact from concurrent projects within 300m of the NSRs, if any;
· If necessary, selection of project-specific quiet PME and other types of mitigation measures (e.g. temporary/ movable noise barrier, enclosure, etc.) to address the predicted noise exceedance; and calculate the mitigated noise impact; and
· Calculate the mitigated predicted noise levels at the identified NSRs and compare with the noise standards to determine acceptability and the need for further mitigation/ environmental monitoring and audit.
4.5.2. As a conservative
approach for assessing the worst-case construction noise impacts, it was
assumed that all the proposed PMEs for each work stage are operating
concurrently. Various combination of works located close to the NSRs have been
considered and the maximum SWLs generated from the Project works was calculated
and applied in the calculation of cumulative worst-case construction noise
level at the NSRs.
4.5.3. For each proposed work
areas (Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che), the drainage
improvement works will be conducted by sections. The length of each section
will be approximately 30 m in Sung Shan New Village and Ha Che, 15m in Tai Wo and 25m in Lin Fa Tei, respectively.
4.5.4. For conducting the early
stage drainage improvement work i.e. excavation, it is expected that there will
only be one group of workers working beginning at the downstream. After this
early stage work, a maximum of two groups of workers will carry out concurrent
activities at two adjoining sections at any one time due to a limited number of
Powered Mechanical
equipment (PMEs)
and narrow working space. Therefore, the assessment has adopted the maximum
total SWLs of two works section areas (i.e. the nearest two adjoining
construction works areas to the representative NSRs and/or two adjoining
construction works areas with conducting specific works to affect the nearest
representative NSRs) under construction concurrently. The construction works
that are expected to affect works areas to the representative NSRs are shown in
Table
4‑3 and the locations of the respective works areas are
shown in Appendix 4-1a to 4-1d.
Table 4‑3 Works
Sites Affecting the Representative NSRs
NSR ID |
Description of NSRs |
Nature of Use |
Works Sites (Sections) That would affect the NSR during Construction
Phase |
Locations of Works Sites (Sections) |
Sung Shan New Village |
||||
SSNV1 |
#88A, Yau Cha Po |
Residential |
S102 & S103 |
Refer to Appendix 4-1a |
SSNV2 |
Village house next to a nullah in Tong Tai Po Tsuen (near DD118 1720
S.A) |
Residential |
S104 & S105 |
|
SSNV3 |
Village house near a soy sauce factory in Sung Shan New Village (near
DD118 1712) |
Residential |
S112 & S113 |
|
SSNV4 |
#107, Yau Cha Po |
Residential |
S113 & S114 |
|
SSNV5 |
#25, Sung Shan New Village |
Residential |
S115 & S116 S116 & S117 |
|
SSNV6 |
#43, Sung Shan New Village |
Residential |
S118 & S119 S119 & S120 |
|
SSNV7 |
Temporary structure next to a track in Sung Shan New Village |
Residential |
S119 & S120 |
|
Tai Wo |
||||
TW1 |
Temporary structure near footbridge in Cheung Po (DD113 Lot.1542) |
Residential |
S201 & S202 |
Refer to Appendix 4-1b |
TW2 |
#200, Cheung Po |
Residential |
S205 & S206 S206 & S207 |
|
TW3 |
Kai Yip Garden, #3H, Tai Wo |
Residential |
S217 & S218 |
|
TW4 |
#40B, Tai Wo |
Residential |
S217 & S218 |
|
Lin Fa Tei |
||||
LFT1 |
#2G, Lin Fa Tei |
Residential |
S332 & S333 |
Refer to Appendix 4-1c |
LFT2 |
Temporary building next to a nullah in Lin Fa Tei |
Residential |
S327 & S328 |
|
LFT3 |
#125, Lin Fa Tei |
Residential |
S316 & S317 |
|
LFT4 |
#156A, Lin Fa Tei |
Residential |
S311 & S312 S312 & S313 |
|
LFT5 |
#156B, Lin Fa Tei |
Residential |
S311 & S312 |
|
LFT6 |
#47, Shui Tsan Tin |
Residential |
S308 & S309 S309 & S310 |
|
LFT7 |
Village house near the nullah |
Residential |
S304 & S305 |
|
LFT8 |
Village house near the nullah |
Residential |
S301 & S302 |
|
LFT9 |
Village house near the nullah |
Residential |
S301 & S302 |
|
LFT10 |
Moon Wo Grand Houses, #510, Lin Fa Tei |
Residential |
S341 & S342 S342 & S343 |
|
LFT11 |
#210 Ngau Keng |
Residential |
S346 & S347 S347 & S348 |
|
LFT12 |
#297, Lin Fa Tei |
Residential |
S350 & S351 S351 & S352 |
|
LFT13 |
#290, Lin Fa Tei |
Residential |
S352 & S353 S353 & S354 |
|
LFT14 |
#231C, Lin Fa Tei |
Residential |
S353 & S354 |
|
Ha Che |
||||
HC1 |
#149, Chuk Hang |
Residential |
S401 & S402 |
Refer to Appendix 4-1d |
HC2 |
Block 29, Fu Hing Garden, #88 Sheung Che |
Residential |
S401 & S402 |
|
HC3 |
Block P, Fu Hing Garden, #88 Sheung Che |
Residential |
S402 & S403 |
|
HC4 |
Block N, Fu Hing Garden, #88 Sheung Che |
Residential |
S404 & S405 |
|
HC5 |
Block F, Fu Hing Garden, #88 Sheung Che |
Residential |
S405 & S406 |
|
HC6 |
#1C, Chuk Hang |
Residential |
S409 & S410 |
|
HC7 |
#300, Sheung Che |
Residential |
S409 & S410 S410 & S411 |
|
HC8 |
The Arbutus House 12, #52, Shui Kan Shek |
Residential |
S423 & S424 |
Identification of Potential Noise
Impacts
4.6.1. The potential source of noise impact during construction
phase of the Project would be the use of PMEs for various construction
activities. There are four major construction works types to be carried out
which are relevant to the construction noise assessment as follows:
Works Type 1 – Widening of the existing drainage channel at Sung Shan
New Village;
Works Type 2 – Construction of drainage channel at Tai Wo;
Works Type 3 – Widening of the existing drainage channel and
construction of a new drainage pipe at Lin Fa Tei; and
Works Type 4 – Widening of the existing drainage channel and
construction of a new drainage pipe at Ha Che.
4.6.2. All the works types will be conducted in stages and
implemented concurrently. With consideration that the separation distance
between drainage improvement works at each village are more than 300m,
cumulative noise impact is not expected between each work type. Estimated
durations of the construction work are provided in Table 4-4. The
proposed works will be conducted during non-restricted hours only, i.e. between
07:00 and 19:00 hours on any day except Sunday and general holiday.
Table
4‑4 Tentative
Construction Activities Schedule
Works Stage |
Construction Activities |
Estimated Duration per Section |
Works Type 1 – Widening
of the existing drainage channel at Sung Shan New Village (1) (2) |
||
Stage 1 |
Excavation |
5 weeks |
Stage 2 |
Formwork and Reinforcement |
|
Works Type 2-
Construction of drainage channel at Tai Wo (1) (2) |
||
Stage 1 |
Excavation |
4 weeks |
Stage 2 |
Formwork and Reinforcement |
|
Works Type 3 –
Widening of the existing drainage channel and construction of new drainage
pipes at Lin Fa Tei (1) (2) |
||
Stage 1 |
Excavation |
4 weeks |
Stage 2 |
Formwork and Reinforcement |
|
Works Type 4 –
Widening of the existing drainage channel and construction of new drainage
pipes at Ha Che (1) (2) |
||
Stage 1 |
Excavation |
3 weeks |
Stage 2 |
Formwork and Reinforcement |
Notes:
(1) Only one set of PME of stage 1 and stage 2 will be undertaken concurrently
for each works type; and
(2)
Note that works programme is subject to variables such as weather, conflict
with utilities etc. and is variable upon these conditions
4.6.3. An inventory of project specific PMEs required for
the proposed drainage improvement works is detailed in Appendix 4-2a. A summary of the
predicted maximum SWLs of the different works types are provided in Table
4‑5. Whilst it is possible that the future appointed
Contractor may adopt a different plant inventory, this
assessment has been undertaken based on the plant inventory detailed in Appendix 4-2a to allow early
identification of any potential noise issues and to ensure there are
practicable and sufficient noise mitigation measures that can be implemented to
alleviate adverse noise impacts. The Contractor will be required to provide and
implement sufficient direct noise mitigation measures based on the
recommendation in this assessment to achieve acceptable noise levels on the
nearby NSRs. The Contractor would also use the plant with SWL equivalent to or lower
than that in the plant inventory for carrying out the proposed construction
activities.
Table 4‑5 Summary
of Maximum SWLs of the Different Works Types
Works Stage |
Construction Activities |
SWL, dB(A) |
Works Type 1 –
Widening of the existing drainage channel at Sung Shan New Village |
||
Stage 1 |
Excavation |
115 |
Stage 2 |
Formwork and Reinforcement |
110 |
Works Type 2-
Construction of drainage channel at Tai Wo |
||
Stage 1 |
Excavation |
115 |
Stage 2 |
Formwork and Reinforcement |
110 |
Works Type 3 –
Widening of the existing drainage channel and construction of new drainage
pipes at Lin Fa Tei |
||
Stage 1 |
Excavation |
115 |
Stage 2 |
Formwork and Reinforcement |
110 |
Works Type 4 – Widening
of the existing drainage channel and construction of new drainage pipes at Ha
Che |
||
Stage 1 |
Excavation |
115 |
Stage 2 |
Formwork and Reinforcement |
110 |
Note:
Only
one set of PME of stage 1 and stage 2 will be undertaken concurrently for each
works type;
Detailed
construction plant inventory is shown in Appendix 4-2a.
Prediction of Construction Noise
Impacts – Unmitigated Scenario
4.6.4. The predicted noise levels at the representative
NSRs due to the proposed drainage improvement works at Sung Shan New Village,
Tai Wo, Lin Fa Tei and Ha Che are summarized in Table
4‑6. Detailed calculations are provided in Appendix 4-2b.
Table 4‑6 Predicted Noise Levels at the Representative
NSRs Affected by the Proposed Project Works – Unmitigated Scenario
NSR ID |
Description of NSRs |
No. of Storeys |
Predicted Maximum Noise Level, dB(A) |
EIAO-TM Noise Standard, dB(A). |
Noise Exceedance, dB(A) |
Sung Shan New Village |
|||||
SSNV1 |
#88A, Yau Cha Po |
3 |
87 |
75 |
12 |
SSNV2 |
Village house next to a nullah in Tong Tai Po Tsuen (near DD118 1720
S.A) |
2 |
91 |
75 |
16 |
SSNV3 |
Village house near a soy sauce factory in Sung Shan New Village (near
DD118 1712) |
1 |
91 |
75 |
16 |
SSNV4 |
#107, Yau Cha Po |
1 |
85 |
75 |
10 |
SSNV5 |
#25, Sung Shan New Village |
1 |
81 |
75 |
6 |
SSNV6 |
#43, Sung Shan New Village |
1 |
84 |
75 |
9 |
SSNV7 |
Temporary structure next to a track in Sung Shan New Village (DD118
Lot. 1767) |
1 |
77 |
75 |
2 |
Tai Wo |
|||||
TW1 |
Temporary structure near footbridge in Cheung Po (DD112 Lot.837 S.A.RP) |
1 |
84 |
75 |
9 |
TW2 |
#200, Cheung Po |
3 |
81 |
75 |
6 |
TW3 |
Kai Yip Garden, #3H, Tai Wo |
3 |
78 |
75 |
3 |
TW4 |
#40B, Tai Wo |
3 |
79 |
75 |
4 |
Lin Fa Tei |
|||||
LFT1 |
#2G, Lin Fa Tei |
3 |
91 |
75 |
16 |
LFT2 |
Temporary building next to a nullah in Lin Fa Tei |
1 |
93 |
75 |
18 |
LFT3 |
#125, Lin Fa Tei |
2 |
96 |
75 |
21 |
LFT4 |
#156A, Lin Fa Tei |
3 |
95 |
75 |
20 |
LFT5 |
#156B, Lin Fa Tei |
3 |
92 |
75 |
17 |
LFT6 |
#47, Shui Tsan Tin |
2 |
92 |
75 |
17 |
LFT7 |
Village house near the nullah |
3 |
92 |
75 |
17 |
LFT8 |
Village house near the nullah |
3 |
93 |
75 |
18 |
LFT9 |
Village house near the nullah |
3 |
95 |
75 |
20 |
LFT10 |
Moon Wo Grand Houses, #510, Lin Fa Tei |
4 |
87 |
75 |
12 |
LFT11 |
#210 Ngau Keng |
3 |
94 |
75 |
19 |
LFT12 |
#297, Lin Fa Tei |
3 |
93 |
75 |
18 |
LFT13 |
#290, Lin Fa Tei |
3 |
94 |
75 |
19 |
LFT14 |
#231C, Lin Fa Tei |
3 |
91 |
75 |
16 |
Ha Che |
|||||
HC1 |
#149, Chuk Hang |
4 |
88 |
75 |
13 |
HC2 |
Block 29, Fu Hing Garden, #88 Sheung Che |
3 |
92 |
75 |
17 |
HC3 |
Block P, Fu Hing Garden, #88 Sheung Che |
3 |
91 |
75 |
16 |
HC4 |
Block N, Fu Hing Garden, #88 Sheung Che |
4 |
93 |
75 |
18 |
HC5 |
Block F, Fu Hing Garden, #88 Sheung Che |
4 |
94 |
75 |
19 |
HC6 |
#1C, Chuk Hang |
4 |
92 |
75 |
17 |
HC7 |
#300, Sheung Che |
3 |
91 |
75 |
16 |
HC8 |
The Arbutus House 12, #52, Shui Kan Shek |
3 |
92 |
75 |
17 |
Notes:
Underlined
bold value indicates an exceedance of the 75dB(A) noise criteria.
4.6.5. The predicted noise
levels at the representative NSRs range from 77 dB(A) to 96 dB(A). As shown in Table
4‑6, the maximum level of
exceedance predicted would be about 21 dB(A). Mitigation
measures would be considered necessary in order to reduce the construction
noise impact.
Prediction of Construction Noise
Impacts – Mitigated Scenario
4.6.6. To mitigate the construction noise impacts on the
affected NSRs during the construction phase, quiet PMEs and smaller sized of
PMEs have been proposed as practicable.
4.6.7. The use of quiet PMEs associated with the
construction works is made reference to the PME listed in the Quality Powered
Mechanical Equipment (QPME), “Sound Power Levels of Other Commonly Used PME”
listed in EPD website. It is generally known that particular models of
construction equipment are quieter than standard types given in GW-TM. It also
should be noted that various type of quiet plant can be available in the
market. The SWLs for quiet PMEs adopted for assessment are detailed in Table
4‑7.
Table 4‑7
Recommended PMEs and the SWLs
Description of PME |
QPME ID Code |
Model No. |
SWL, dB(A) |
Excavator, wheeled/tracked |
EPD-07033 [1] |
YANMAR |
91 |
Generator |
EPD-06600 [1] |
DENYO |
90 |
Crane, mobile |
EPD-06243 [1] |
Kobelco |
92 |
Notes:
[1]
Quality Powered Mechanical Equipment (QPME) ID Code by EPD (https://www.epd.gov.hk/cgi-bin/npg/qpme/search_gen.pl)
4.6.8. Asides from QPMEs, additional noise mitigation
measures in terms of temporary noise barriers are proposed to shield
construction plants from NSRs. According to EIAO Guidance Note No. 9/2010, with
provision of noise barriers, a 5dB(A) noise reduction for movable plant, 10dB(A)
for stationary plant and 15dB(a) for enclosed ones are assumed. With reference
to ”A Practical Guide for the Reduction of Noise from Construction Works”,
temporary noise barrier and enclosure material’s surface mass in excess of 7
kg/m2 and have no openings or gaps is recommended. The Contractor should be
responsible for the design of temporary/ movable noise barriers with
consideration of the size of PME and the requirements of intercepting the line
of sight between the noise sensitive receivers and PME. Typical section drawing
of the temporary/movable noise barrier is provided in Appendix 4-5. Table
4‑8 summarizes the assumed noise reduction achieved by
the temporary noise barrier/enclosure for certain PMEs.
Table 4‑8 Noise Mitigation Measures for Certain
PME
Description of PME |
Proposed Mitigation Measures |
Assumed Noise Reduction, dB(A) |
References |
Excavator, wheeled/tracked |
Movable noise barrier |
-5 |
[1] |
Dump Truck (5.5 tonne < Gross vehicle weight <= 38 tonne) |
Fixed Temporary noise barrier |
-5 |
[1] |
Lorry (5.5 tonne < Gross vehicle weight <= 38 tonne) |
Fixed Temporary noise barrier |
-5 |
[1] |
Bar bender and cutter (electric) |
Movable noise barrier |
-10 |
[1] |
Jig-saw, hand-held, wood (electric) |
Movable noise barrier |
-10 |
[1], [2] |
Generator |
Movable noise barrier |
-10 |
[1] |
Crane, mobile |
Movable noise barrier and Fixed temporary boundary noise barrier |
-5 |
[1] |
Notes:
[1]
With reference to the approved EIA report (Residential cum Passive Recreational
Development within REC Zone and R (C) Zone at Various Lots in DD 104, Yuen
Long. N.T.(AEIAR-182/2014)), the proposed mitigation measures have been
recommended to reduce the noise impacts from specific PMEs.
[2]
Jig-saw, hand-held, wood (electric) has been proposed to replace the use of
Saw, circular, wood.
4.6.9. With adoption of quiet PMEs and temporary/movable
barrier, the maximum predicted noise levels at the representative NSRs due to
the proposed drainage improvement works are summarized in Table
4‑9. Detailed calculations are provided in Appendix 4-3a and Appendix 4-3b.
Table 4‑9 Predicted Noise Levels at the
Representative NSRs Affected by the Proposed Project Works – Mitigated Scenario
NSR ID |
Description of NSRs |
No. of Storeys |
Predicted Maximum Noise Level, dB(A) |
EIAO-TM Noise Standard, dB(A). |
Noise Exceedance, dB(A) |
Sung Shan New Village |
|||||
SSNV1 |
#88A, Yau Cha Po |
3 |
66 |
75 |
- |
SSNV2 |
Village house next to a nullah in Tong Tai Po Tsuen (near DD118 1720
S.A) |
2 |
70 |
75 |
- |
SSNV3 |
Village house near a soybean sauce factory in Sung Shan New Village
(near DD118 1712) |
1 |
70 |
75 |
- |
SSNV4 |
#107, Yau Cha Po |
1 |
65 |
75 |
- |
SSNV5 |
#25, Sung Shan New Village |
1 |
60 |
75 |
- |
SSNV6 |
#43, Sung Shan New Village |
1 |
63 |
75 |
- |
SSNV7 |
Temporary structure next to a track in Sung Shan New Village (DD118
Lot. 1767) |
1 |
56 |
75 |
- |
Tai Wo |
|||||
TW1 |
Temporary structure near footbridge in Cheung Po |
1 |
63 |
75 |
- |
TW2 |
#200, Cheung Po |
3 |
60 |
75 |
- |
TW3 |
Kai Yip Garden, #3H, Tai Wo |
3 |
57 |
75 |
- |
TW4 |
#40B, Tai Wo |
3 |
58 |
75 |
- |
Lin Fa Tei |
|||||
LFT1 |
#2G, Lin Fa Tei |
3 |
70 |
75 |
- |
LFT2 |
Temporary building next to a nullah in Lin Fa Tei |
1 |
72 |
75 |
- |
LFT3 |
#125, Lin Fa Tei |
2 |
75 |
75 |
- |
LFT4 |
#156A, Lin Fa Tei |
3 |
74 |
75 |
- |
LFT5 |
#156B, Lin Fa Tei |
3 |
71 |
75 |
- |
LFT6 |
#47, Shui Tsan Tin |
2 |
71 |
75 |
- |
LFT7 |
Village house near the nullah |
3 |
71 |
75 |
- |
LFT8 |
Village house near the nullah |
3 |
72 |
75 |
- |
LFT9 |
Village house near the nullah |
3 |
74 |
75 |
- |
LFT10 |
Moon Wo Grand Houses, #510, Lin Fa Tei |
4 |
66 |
75 |
- |
LFT11 |
#210 Ngau Keng |
3 |
73 |
75 |
- |
LFT12 |
#297, Lin Fa Tei |
3 |
72 |
75 |
- |
LFT13 |
#290, Lin Fa Tei |
3 |
73 |
75 |
- |
LFT14 |
#231C, Lin Fa Tei |
3 |
70 |
75 |
- |
Ha Che |
|||||
HC1 |
#149, Chuk Hang |
4 |
67 |
75 |
- |
HC2 |
Block 29, Fu Hing Garden, #88 Sheung Che |
3 |
71 |
75 |
- |
HC3 |
Block P, Fu Hing Garden, #88 Sheung Che |
3 |
70 |
75 |
- |
HC4 |
Block N, Fu Hing Garden, #88 Sheung Che |
4 |
72 |
75 |
- |
HC5 |
Block F, Fu Hing Garden, #88 Sheung Che |
4 |
73 |
75 |
- |
HC6 |
#1C, Chuk Hang |
4 |
71 |
75 |
- |
HC7 |
#300, Sheung Che |
3 |
70 |
75 |
- |
HC8 |
The Arbutus House 12, #52, Shui Kan Shek |
3 |
71 |
75 |
- |
4.6.10. With adoption of quiet PMEs and temporary / movable
barrier stated above, the predicted construction noise levels at the
representative NSRs range 56 dB(A) to 75 dB(A). No construction noise
exceedance has been predicted. All predicted construction noise levels at the
representative NSRs will fully comply with the relevant noise standard.
4.6.11. The proposed temporary noise barrier will only be
in place when the associated PME is in use on the construction work area and
this is anticipated to only be for short duration of time. Therefore, there are
no side effect predicted associated with the use of the proposed mitigation
measure.
4.7.1. Apart from the proposed mitigation measures, good
site practices as listed below are recommended to alleviate the noise impacts
on the identified NSRs.
· The Contractor shall adopt the Code of Practice on Good Management Practice to Prevent Violation of the NCO (Cap. 400) (for Construction Industry) published by the EPD;
· The Contractor shall observe and comply with the statutory and non-statutory requirements and guidelines;
· Before commencing any work, the Contractor shall submit to the Environmental Review for approval the method of working, equipment and noise mitigation measures intended to be used at the site;
· The Contractor shall devise and execute working methods to minimise the noise impact on the identified surrounding sensitive uses, and provide experienced personnel with suitable training to ensure that those methods are implemented;
· Noisy equipment and noisy activities should be located as far away from the NSRs as is practical;
· Machines and plant (such as dump truck, vibratory compactor, lorry, cranes) that may be intermitted use should be shut down between work periods or should be throttled down to a minimum. Additionally, the combined use of noisy equipment/machines should be avoided, when possible;
· Only well-maintained plant should be operated on-site and plants should be serviced regularly during the construction programme;
· Silencers, mufflers or acoustic treatment mats on construction equipment should be utilised and properly maintained during the construction duration;
· Plants known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs; and
· Material stockpiles and other structures should be effectively utilised as noise barriers, where practicable.
4.7.2. The Contractor shall, from time to time, be aware
of the noise impacts on the surrounding NSRs through adequate noise monitoring
during the works so that adjustments can be made to the number of plants used
for any construction activity and the corresponding plant positioning. These requirements shall be incorporated into
the Project works contract.
4.8
Residual Construction Noise
Impacts
4.8.1. No exceedance of the construction noise criteria
has been predicted at the NSRs with implementation of noise mitigation measures
as described in Sections 4.6 and 4.7.
4.8.2. With adopting quiet PMEs, temporary noise barriers
and implementing good site practices, adverse residual noise impacts are not
anticipated.
4.9.1. As mentioned in Section 2, the construction of
drainage improvement works is scheduled from Year 2022 to Year 2025. One
project has been identified within proximity of the subject works site. The
potential cumulative construction noise impacts are discussed below.
Table
4‑10 Identified
Potential Interface Projects within Proximity of the Project
Project |
Name of Project |
Remarks |
No.1 |
Agreement No. CE
61/2012 (HY) - Improvement to Fan Kam Road – Investigation (2021 to 2025) |
The project is
still at investigation stage, the exact schedule of works is uncertain and
subject to the findings on detail design stage. The project may overlap with
the construction of this Project. The potential overlapping area identified
in Ha Che Section was shown in Appendix 4-4. |
Project 1: Agreement No. CE
61/2012(HY) – Improvement to Fan Kam Road – Investigation
4.9.2. Under Agreement No. CE
61/2012 (HY), a road improvement work is proposed to be constructed along Fan
Kam Road and the certain sections will be within the 300m assessment area of
the Project. Based on information from the project consultant, the project is
still undergoing the investigation stage. The tentative schedule of
construction works will be from 2021 to 2025. Since the project is still at
investigation stage, the exact schedule of works is uncertain and subject to
the findings on detail design stage. With reference to Agreement No. CE 61/2012
(HY), the alignment of the road improvement has potentially interfaced with the
proposed drainage improvement works (nearest works under Ha Che section) in the
same section for 1 months. The Contractor
is recommended to coordinate and liaise with the detail design consultant
and/or contractor of the Fan Kam Road improvement project. Construction works
schedule should be arranged in order to minimize concurrent works at interface.
With this arrangement in place and implementation of mitigation measure,
adverse cumulative noise impact due to the improvement works on Fan Kam Road
and the drainage improvement works can be avoided.
4.10.1. The potential noise impacts due to the proposed drainage
improvement works at Sung Shan New Village, Tai Wo, Lin Fa Tei and Ha Che have
been evaluated. Whilst the Contractor may prefer to use different construction
methods, types and numbers of PMEs, the assumed tentative construction schedule
and plant inventory are representative and provide a conservative noise
assessment of reference value.
4.10.2. With adopting the quiet PMEs, temporary noise
barrier and good site practices as stipulated in the Code of Practice on Good
Management Practice to Prevent Violation of the NCO (Cap. 400) (for
Construction Industry) to minimize the
construction noise impacts, construction noise levels at the representative
NSRs will fully comply with the relevant noise criteria.