4.2 Monitoring
Requirements and Equipment
4.3 Noise
Monitoring Methodology
4.4 Noise
Monitoring Locations
List of Appendices
Appendix
1 Implementation Schedule of
Recommended Mitigation Measures
Appendix
2 Sample Data Record Sheet for
Noise Measurement
List of Figures
Figure
4.1 Noise Impact Assessment – Key
Plan
Figure
4.2 Location of Representative
Noise Sensitive Receivers at Sung Shan New Village
Figure
4.3 Location of Representative
Noise Sensitive Receivers at Tai Wo
Figure
4.4 Location of Representative
Noise Sensitive Receivers at Lin Fei Tei
Figure
4.5 Location of Representative
Noise Sensitive Receivers at Ha Che
Figure
4.6 Location of Noise
Monitoring Station at Sung Shan New Village
Figure
4.7 Location of Noise
Monitoring Station at Tai Wo
Figure
4.8 Location of Noise
Monitoring Station at Lin Fa Tei
Figure
4.9 Location of Noise
Monitoring Station at Ha Che
4.2.2 Sound level meters and calibrators
shall comply with the International Electrotechnical Commission (IEC)
Publication 651:1979 (Type 1) and 804:1985 (Type 1) specification as referred
to in the Technical Memorandum (TM) issued under the Noise Control
Ordinance. The sound level meters shall
be supplied and used with the manufacturer recommended weather shield as appropriate.
4.2.3 Sound level meters shall be
calibrated using a portable calibrator prior to and following each noise
measurement. The calibration levels
shall be noted with the measurement results and where the difference between
the calibration levels is greater than 1.0 dB(A), the measurement shall be
repeated. Calibrated hand-held
anemometers shall also be supplied for the measurement of wind speeds during
noise monitoring periods.
4.2.4 The equipment shall be kept in a
good state of repair in accordance with the manufacturer’s recommendations and
maintained in proper working order with sufficient spare equipment available in
the event of breakdown to maintain the planned monitoring programme.
4.2.5 Noise measurements will not be made
in the presence of fog, rain, wind with a steady speed exceeding 5m/s or wind
with gusts exceeding 10m/s. The wind
speed shall be checked with the hand-held anemometers capable of measuring the
wind speed in m/s.
4.3.1 Weatherproof logging sound level
meters shall be installed at the monitoring locations during baseline
monitoring. Continuous baseline noise
for the A-weighted levels Leq, L10 and L90
shall be measured over a two week period, and sampling period of 5 minutes will
be used throughout the monitoring.
Average, by sound power, of six consecutive Leq (5 min)
reading is used to provide Leq (30 min) for the non-restricted
period and three consecutive Leq (5 min) reading is used to provide
Leq (15 min) for the restricted period during the impact stage.
Table 4.4.1 Noise
Monitoring Locations
ID No. |
Location |
Nature of Uses |
SSNV_M2 |
Village
house next to a nallah in Tong Tai Po Tsuen (near DD118 1720 S.A) |
Residential |
SSNV_M3 |
Village
house near a soybean sauce factory in Sung Shan New Village (near DD118 1712) |
Residential |
SSNV_M6 |
#43,
Sung Shan New Village |
Residential |
TW_M2 |
#200,
Cheung Po |
Residential |
TW_M3 |
Kai Yip
Garden, #3H, Tai Wo |
Residential |
LFT_M1 |
#2G,
Lin Fa Tei |
Residential |
LFT_M3 |
#125, Lin Fa Tei |
Residential |
LFT_M5 |
#156B, Lin Fa Tei |
Residential |
LFT_M7 |
Village house near the nullah (DD112 699 S.E) |
Residential |
LFT_M13 |
#290, Lin Fa Tei |
Residential |
HC_M3 |
Block F, Fu Hing
Garden, #88 Sheung Che |
Residential |
HC_M4 |
#1C, Chuk Hang |
Residential |
HC_M6 |
The
Arbutus House 12, #52, Shui Kan Shek |
Residential |
4.4.2 When alternative monitoring
locations are proposed, the monitoring locations shall be chosen based on the
following criteria:
(i)
The locations shall be close to the site
activities which are likely to have significant noise impacts;
(ii)
The locations shall be close to the noise sensitive
receivers (NSRs) (NB. For the purpose of this section, any domestic premises,
hotel, hostel, temporary housing accommodation, hospital, medical clinic,
educational institution, place of public worship, library, court of law,
performing art centre shall be considered as NSR);
(iii)
Care shall be taken to cause minimal
disturbance to the occupants of sensitive receivers; and
(iv)
The proposed alternative monitoring
locations should be agreed by ER and IEC.
4.5.1 To obtain fully satisfactory
baseline results, weatherproof logging sound level meter shall be used. Continuous baseline noise for the A-weighted
levels Leq, L10 and L90 shall be measured over
a period of two consecutive weeks and sampling period of 5 minutes will be used
throughout the monitoring. Average, by
sound power, of six consecutive Leq (5 min) reading is used to
provide Leq (30 min) for the non-restricted period and three consecutive
Leq (5 min) reading is used to provide Leq (15 min) for
the restricted period. The monitoring period shall be selected prior to the
commencement of any construction activities and so as to avoid other typical
noise sources. Measurements shall be recorded
to the nearest 0.1 dB. Major noise sources observed, both on-site and off-site,
at each location will be recorded. A
schedule on the baseline monitoring shall be submitted to the IEC for approval
before the monitoring.
4.6.1 Provided that the construction works
will be in small scale, noise monitoring shall be undertaken at each designated
monitoring stations when there are construction works nearby (within 100m of
the monitoring stations). The following is an initial
guide on the regular monitoring frequency for each station on a per week basis
when construction activities are undertaken:
(i)
one set of Leq (30 min) noise
level as six consecutive Leq (5 min) between 07:00-19:00 hours on
normal weekdays
4.6.2 Major noise sources observed, both
on-site and off-site, at each location shall be recorded.
Table 4.4.2 Action and
Limit Levels for Construction Noise
Time Period |
Action |
Limit |
07:00-19:00
hours on normal weekdays; |
When one or
more documented complaints are received |
75dB(A)* |
07:00-23:00
hours on holidays; |
45(1)
dB(A) |
|
23:00-07:00 hours
of the next day |
30(1) dB(A) |
Note: • Between 07:00-19:00 hours, construction noise limit for school
during normal term time is 70dB(A) and 65dB(A) during examination period.
ASR = “A” which is a rural area that are not affected by the IF.
(1) - As stipulated In the Technical Memorandum on Noise from
Construction Work in Designated Areas.
Table 4.4.3 Event /
Action Plan for Construction Noise
Event |
ET |
IEC |
ER |
CONTRACTOR |
Action Level |
1.
Notify ER, IEC and Contractor;
2.
Carry out investigation;
3.
Report the results of investigation to the IEC, ER
and Contractor;
4.
Discuss with the IEC and contractor and formulate
remedial measures; and
5.
Increase monitoring frequency to check the
effectiveness of mitigation measures. |
1. Review the
investigation results submitted by the ET;
2. Review the
proposed remedial measures by the Contractor and advise the ER accordingly;
and
3. Advise the ER
on the effectiveness of the proposed remedial measures. |
1.
Confirm receipt of notification of failure in
writing; 2.
Notify Contractor; 3.
In consolidation with the IEC, agree with the
Contractor on the remedial measures to be implemented; and 4.
Supervise the implementation of remedial
measures. |
1.
Submit noise mitigation proposals to IEC and ER; and
2.
Implement noise mitigation proposals. |
Limit Level |
1. Notify IEC,
ER, EPD & Contractor;
2. Identify
source and investigate the cause of exceedance;
3. Repeat
measurement to confirm findings;
4. Increase
monitoring frequency;
5. Carry out
analysis of Contractor’s working procedures to determine possible mitigation
to be implemented;
6. Discuss with
the IEC, Contractor and ER on remedial measures required;
7. Assess the
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results; and
8. If exceedance
stops, cease additional monitoring. |
1. Discuss
amongst ER, ER and Contractor on the potential remedial actions; and
2. Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly. |
1.
Confirm receipt of notification of failure in
writing; 2.
Notify Contractor; 3.
In consolidation with the EIC, agree with the
Contractor on the remedial measures to be implemented; 4.
Supervise the implementation of remedial measures;
and 5.
If exceedance continues, consider stopping the
Contractor to continue working on that portion of work which causes the
exceedance until the exceedance is abated. |
1. Take
immediate action to avoid further exceedance;
2. Submit
proposals for remedial actions to IEC and ER within 3 working days of
notification;
3. Implement the
agreed proposals;
4. Submit further
proposal if problem still not under control; and
5. Stop the
relevant portion of works as determined by ER, until the exceedance is
abated. |