6.        Water Quality. 6-1

6.1       Introduction. 6-1

6.2       Water Quality Parameters. 6-1

6.3       Monitoring Equipment 6-1

6.4       Measurement and Laboratory Analysis. 6-3

6.5       Monitoring Locations. 6-4

6.6       Baseline Water Quality Monitoring. 6-4

6.7       Impact Water Quality Monitoring. 6-5

6.8       Event and Action Plan. 6-5

 

 

List of Appendices

Appendix 1           Implementation Schedule of Recommended Mitigation Measures

 

 

List of Figures

Figure 6.1            Water Sensitive Receivers at Sung Shan New Village

Figure 6.2            Water Sensitive Receivers at Tai Wo

Figure 6.3            Water Sensitive Receivers at Lin Fa Tei

Figure 6.4            Water Sensitive Receivers at Ha Che

Figure 6.5            Water Quality Monitoring Location at Sung Shan New Village

Figure 6.6            Water Quality Monitoring Location at Tai Wo

Figure 6.7            Water Quality Monitoring Location at Lin Fa Tei

Figure 6.8            Water Quality Monitoring Location at Ha Che

 

6.           Water Quality

6.1         Introduction

6.1.1    The water quality assessment in the EIA Report identified that the key issue would be related to excavation works for the construction phase of the proposed drainage improvement works. To minimize potential impacts on water quality during the drainage construction, the excavation would be carried out in dry condition (even in wet season) by diverting the stream flow from upstream by a temporary drainage channel with a temporary sheet piles, earth bund or barrier, so that the works area will remain dry for later excavation and widening works. The locations of the representative WSRs are shown in Figures 6.1 to 6.4.

6.1.2    A monitoring programme is recommended for both baseline conditions and during the construction phase to detect any deterioration of water quality, as well as to ensure the performance of the proposed mitigation measures.

6.2         Water Quality Parameters

6.2.1    The water quality parameters, as presented in Table 6.1 shall be monitored to ensure the drainage water quality and to detect any water quality deterioration situations in order to take actions on time.

Table 6.1        Water Quality Parameters to Be Monitored

Parameter

Type of Analysis

Dissolved Oxygen (DO)

In situ measurement

(mg L-1 and % saturation)

Temperature ()

pH value

Turbidity (NTU)

Salinity (ppt)

Water Depth (m)

Suspended Solids (SS) (mg L-1)

Laboratory analysis

6.2.2    These parameters are selected for monitoring on the following basis:

·        To reflect the background water quality near and within the working area; and

·        To reflect the nature of the construction activities.

6.2.3    In addition to the water quality parameters, relevant data shall also be measured, such as monitoring location / position, time, saturation, weather conditions and any special phenomena and work underway at the construction site.

6.3         Monitoring Equipment

6.3.1    Water quality monitoring equipment with the following specifications shall be supplied and maintained by the ET.

Dissolved Oxygen and Temperature Measuring Equipment

6.3.2    The instrument should be portable, weatherproof dissolved oxygen measuring instrument with cable, sensor, comprehensive operation manuals, and applicable to use a DC power source. It should be capable of measuring:

·        DO level in the range of 0 – 20 mg /L and 0 – 200% saturation; and

·        Temperature of 0-45.

6.3.3    It should have a membrane electrode with automatic temperature compensation connected with a cable. Sufficient stocks of spare electrodes and cables should be available for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

pH

6.3.4    pH meter (e.g. Hanna - HI 9024 or equivalent) should be used to measure pH value of water samples in situ. It should be readable to 0.1 pH in a range of 0 to 14. Standard buffer solutions of at least pH 7 to pH 10 shall be used for calibration of the instrument before and after use.

Turbidity Measurement Instrument

6.3.5    The instrument should be a portable, weatherproof turbidity-measuring instrument with a comprehensive operation manual. The equipment should use a DC power source. It should have a photoelectric sensor capable of measuring turbidity between 0-1000 NTU and be equipped with a cable (e.g. Hach model 2100P or an approved similar instrument).

Suspended Solids

6.3.6    A water sampler should comprise a transparent PVC cylinder, with a capacity of not less than 2 litres, and should be effectively sealed with latex cups at both ends. The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (e.g. Kahlsico Water Sampler or an approved similar instrument).

6.3.7    Water samples for suspended solids measurement shall be collected in high density polythene bottles, packed in ice (chilled to 4°C without being frozen), and delivered to the laboratory as soon as possible after collection.

Water Depth detector

6.3.8    A portable, battery-operated echo sounder should be used for determining water depth at each designated monitoring station. This unit can either be hand held or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.

Monitoring Position Equipment

6.3.9    A hand-held or boat-fixed digital Global Positioning System (GPS) or other equivalent instrument of similar accuracy shall be provided and used during water monitoring to ensure the water sampling locations are correct during water quality monitoring work.

Water Sampling Equipment

6.3.10  A transparent PVC or glass cylinder, which has a volume of not less than 2 litres and can be sealed at both ends with cups, should be equipped with a positive latching system. During the water sampling, a messenger is released to trigger the closure of the water sampler at suitable water depth.

6.3.11  All in-situ monitoring instruments should be checked, calibrated and certified by a laboratory accredited under HOKLAS or another international accreditation scheme before use, and subsequently re-calibrated at 3-monthly intervals throughout all stages of the water quality monitoring. Responses of sensors and electrodes should be checked with certified standard solutions before each use. Wet bulb calibration for a DO meter should be carried out before measurement at each monitoring location.

6.3.12  For the on-site calibration of field equipment, the BS 127:1993, Guide to Field and On-Site Test Methods for the Analysis of Water should be observed.

6.3.13  Sufficient stocks of spare parts should be maintained for replacements when necessary. Backup monitoring equipment shall also be made available so that monitoring can proceed uninterruptedly even when some equipment is under maintenance, calibration, etc.  

6.4         Measurement and Laboratory Analysis

6.4.1    Analysis of suspended solids shall be carried out in a HOKLAS or another international accredited laboratory. Water samples of about 1,000 ml shall be collected at the monitoring stations for carrying out the laboratory SS determination. The detection limit shall be 1mg/L or better. The SS determination shall follow APHA 17ed 2540D or equivalent methods subject to approval of EPD.

6.4.2    If a site laboratory is set up or a non-HOKLAS and non-international accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment, analytical procedures, and quality control shall be approved by EPD. The ET Leader shall provide the ER with one copy of the relevant chapters of the “Standard Methods for the Examination of Water and Wastewater” updated edition and any other relevant document for his reference.

6.4.3    For the testing methods of other parameters as recommended by EIA or required by EPD, detailed testing methods, pre-treatment procedures, instrument use, Quality Assurance/Quality Control (QA/QC) details (such as blank, spike recovery, number of duplicate samples per batch, etc.), detection limits and accuracy shall be submitted to EPD for approval prior to the commencement of monitoring programme. The QA/QC shall be in accordance with the requirement of HOKLAS or international accredited scheme. The QA/QC results shall be reported. EPD may also request the laboratory to carry out analysis of known standards provided by EPD for quality assurance. Additional duplicate samples may be required by EPD for inter laboratory calibration. Remaining samples after analysis shall be kept by the laboratory for 3 months in case repeat analysis is required. If in-house or non-standard methods are proposed, details of the method verification may also be required to submit to EPD. In any circumstance, the sample testing shall have comprehensive quality assurance and quality control programmes. The laboratory shall prepare to demonstrate the programmes to EPD or his representatives when requested.

6.5         Monitoring Locations

6.5.1    The proposed monitoring locations are shown in Figure 6.5 to Figure 6.8, and Table 6.2. These stations were chosen based on the following criteria:

·         At locations close to and at the boundary of the major site activities as indicated in the EIA report, which are likely to have water quality impacts;

·         Close to the sensitive receivers which are directly or likely to be affected;

·         For monitoring locations located in the vicinity of the sensitive receptors, care should be taken to cause minimal disturbance during monitoring.

6.5.2    Control stations are necessary to compare the water quality from potentially impacted sites with the ambient water quality. The monitoring stations are proposed to monitor the impacts from the construction site. Control monitoring stations would be located upstream of the construction section of the river, while impact monitoring stations would be located downstream of each river.

6.5.3    The monitoring locations could be adjusted by the ET Leader to suit the exact location of the construction work site but need to obtain agreement from EPD in advance.

Table 6.2        Water Quality Monitoring Locations

Stream

Station

Easting

Northing

Remarks

SSNV

C1

821893

831782

Impact Monitoring Point

C2

822459

831470

Control Monitoring Point

C3

822422

831413

Control Monitoring Point

TW

C4

825497

830664

Control Monitoring Point

C5

825486

830716

Impact Monitoring Point

LFT

C6

827232

831713

Control Monitoring Point

C7

827044

832143

Control Monitoring Point

C8

826513

832075

Impact Monitoring Point

HC

C9

828304

835029

Control Monitoring Point

C10

827919

834271

Impact Monitoring Point

6.5.4    Due to a shallow water depth with low flowrates in rivers, all the monitoring could be located at mid-depth level.

6.5.5    The ET could review the monitoring stations and the monitoring period in light of the actual construction activities. However, the ET Leader should report and seek agreement form IC(E), ER and approval then from EPD for the actual monitoring periods for each station.

6.6         Baseline Water Quality Monitoring

6.6.1    Baseline conditions of water quality shall be established and agreed with EPD prior to the commencement of works. The purposes of the baseline monitoring are to establish ambient conditions prior to the commencement of the construction works and to demonstrate the suitability of the proposed impact and control monitoring stations. The baseline conditions should normally be established by measuring the water quality parameters specified in Table 6.1. The measurements shall be taken at all designated monitoring stations including control stations for 3 days per week for 4 consecutive weeks, applicable with a period of four weeks prior to commencement of the works.

6.6.2    There shall not be any construction activities in the vicinity of the stations during the baseline monitoring. In the exceptional case when insufficient baseline monitoring data or questionable results are obtained, the ET should seek approval from EPD for an appropriate set of data to be used as baseline reference. Baseline monitoring schedule shall be sent to EPD 1 week prior to the commencement of baseline monitoring. The interval between 2 sets of monitoring shall not be lesser than 36 hours.

6.7         Impact Water Quality Monitoring

6.7.1    During the construction process, impact monitoring shall be carried out 3 days per week. If no exceedances are recorded during the three-month’s period, the monitoring frequency can then be reduced to once per week, with sampling /measurement at the designated monitoring stations. The interval between two sets of monitoring shall not be less than 36 hours except where there are exceedances. However, the ET Leader should report and seek agreement form IC(E), ER and approval then from EPD before changing the monitoring frequency.

6.7.2    All monitoring information including date and time, weather conditions, operator, identification and description of monitoring locations, works, progress and construction activities, method, analytical data and calculation etc., shall be recorded in the monitoring data sheet. The water quality monitoring schedule shall be sent to EPD on or before the first day of the monitoring month, EPD shall be notified immediately of any changes in schedule in written format.

6.8         Event and Action Plan

6.8.1    The Action and Limit levels for the water quality monitoring are shown in Table 6.3. These thresholds shall be applied to ensure that any water quality deterioration can be readily detected. If the monitoring results at any designated monitoring stations indicate that the water quality thresholds are exceeded, appropriate actions in accordance with the Event and Action Plan in Table 6.4 shall be carried out.

Table 6.3        Action and Limit Levels for Water Quality

Parameters

Action Level

Limit Level

DO in mg/L

< 5%-ile of baseline data

< 4mg/L or < 1%-ile of baseline data

SS in mg/L

> 95%-ile of baseline data or >120% of upstream control station of the same day

> 99%-ile of baseline data or 130% of upstream control station of the same day

Turbidity in NTU

> 95%-ile of baseline data or >120% of upstream control station of the same day

> 99%-ile of baseline data or > 130% of upstream control station of the same day

Notes:

1. For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

2. For SS and turbidity, non-compliance of the water quality limits occurs when monitoring result is higher than the limits

3. All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.

Table 6.4          Event and Action Plan for Water Quality Monitoring

EVENT

ACTION

ET(1)

IEC(1)

ER(1)

Contractor

Action Level being exceeded by one sampling day

1. Repeat in-situ measurement to confirm findings;
2. Identify source(s) of impact;
3. Inform the IEC and the Contractor;
4. Check monitoring data, all plant, equipment and the Contractor’s working methods;
5. Discuss mitigation measures with the IEC and the Contractor;
6. Repeat measurement on next day of exceedance.

1. Discuss with the ET and the Contractor on the mitigation measures;
2. Review proposals on mitigation measures submitted by the Contractor and advise the ER accordingly;
3. Access the effectiveness of the implemented mitigation measures.

1. Discuss with the IEC on the proposed mitigation measures;
2. Make agreement on the mitigation measures to be implemented.

1. Inform the ER and confirm notification of the non-compliance in writing;
2. Rectify unacceptable practice;
3. Check all plant and equipment;
4. Consider changes of working methods;
5. Discuss with the ES and the IEC and propose mitigation measures to the IEC and the ER;
6. Implement the agreed mitigation measures.

Action Level being exceeded by more than one consecutive sampling days

1. Repeat in-situ measurement to confirm findings;
2.
Identify source(s) of impact;
3.
Inform the IEC and the Contractor;
4. Check monitoring data, all plant, equipment and Contractor’s working methods;
5.
Discuss mitigation measures with the IEC and the Contractor;
6. Ensure mitigation measures are implemented;
7. Prepare to increase the monitoring frequency to daily;
8. Repeat measurement on next day of exceedance.

1. Discuss with the ET and the Contractor on the mitigation measures;
2. Review proposals on mitigation measures submitted by the Contractor and advise the ER accordingly;
3. Access the effectiveness of the implemented mitigation measures.

1. Discuss with IEC on the proposed mitigation measures;
2. Make agreement on the mitigation measures to be implemented;
3. Access the effectiveness of the implemented mitigation measures.

1. Inform the ER and confirm notification of the non-compliance in writing;
2. Rectify unacceptable practice;
3. Check all plant and equipment;
4. Consider changes of working methods;
5.
Discuss with the ES and the IEC and propose mitigation measures to the IEC and ER within 3 working days;
6. Implement the agreed mitigation measures.

Limit Level being exceeded by one consecutive sampling day

1. Repeat in-situ measurement to confirm findings;
2. Identify source(s) of impact;
3. Inform the IEC, the Contractor and the DEP;
4. Check monitoring data, all plant, equipment and the Contractor’s working methods;
5. Discuss mitigation measures with the IEC, the ER and the Contractor;
6. Ensure mitigation measures are implemented;
7. Increase the monitoring frequency to daily until no exceedance of Limit Level.

1. Discuss with the ES and the Contractor on the mitigation measures;
2. Review proposals on mitigation measures submitted by the Contractor and advise the ER accordingly;
3. Access the effectiveness of the implemented mitigation measures.

1. Discuss with the IEC, the ES and the Contractor on the proposed mitigation measures;
2. Request the Contractor to critically review the working methods;
3. Make agreement on the mitigation measures to be implemented;
4. Access the effectiveness of the implemented mitigation measures.

1. Inform the Engineer and confirm notification of the non-compliance in writing;
2. Rectify unacceptable practice;
3. Check all plant and equipment;
4. Consider changes of working methods;
5. Discuss with the ES, the IEC and the ER and propose mitigation measures to the IEC and the ER within 3 working days;
6. Implement the agreed mitigation measures.

Limit Level being exceeded by more than one consecutive sampling days

1. Repeat in-situ measurement to confirm findings;
2. Identify source(s) of impact;
3. Inform the IEC, the Contractor and DEP;
4. Check monitoring data, all plant, equipment and Contractor’s working methods;
5. Discuss mitigation measures with the IEC, the ER and the Contractor;
6. Ensure mitigation measures are implemented;
7. Increase the monitoring frequency to daily until no exceedance of Limit Level for two consecutive days.

1.  Discuss with ET and Contractor on the mitigation measures;
2.  Review proposals on mitigation measures submitted by the Contractor and advise the ER accordingly;
3.  Access the effectiveness of the implemented mitigation measures.

1.  Discuss with the IEC, the ES and the Contractor on the proposed mitigation measures;
2.  Request Contractor to critically review the working methods;
3.  Make agreement on the mitigation measures to be implemented;
4.  Access the effectiveness of the implemented mitigation measures;
5.  Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the works until no exceedance of Limit Level.

1.  Inform the ER and confirm notification of the non-compliance in writing;
2.  Rectify unacceptable practice;
3.  Check all plant and equipment;
4.  Consider changes of working methods;
5.  Discuss with the ES, the IEC and the ER and propose mitigation measures to the IEC and the ER within 3 working days;
6.  Implement the agreed mitigation measures;
7.  As directed by the ER, slow down or stop all or part of the construction activities.
 

Note (1):  ET – Environmental Team, IEC – Independent Environmental Checker, ER – Engineer’s Representative

6.8.2    It is recommended that additional mitigation measures be taken if the monitoring results indicate that the construction works have caused adverse impacts on water quality to identified sensitive receivers to rectify the non-compliance to water quality criteria. Construction programme shall be carefully reviewed to ensure that water quality at locations of identified sensitive receivers is in compliance with criteria. Working schedule and mitigation measures should be reviewed by the Contractor, IC (E), ET Leader and ER. The schedule for construction works may need to be revised until the adverse impacts to water quality are reduced to an acceptable level.

6.8.3    The ET Leader should assess the effectiveness and efficiency of the proposed mitigation measures and/or remedial actions for on-going construction activities.  The performance of the environmental management system (that is, the overall EM&A programme) should be reviewed by the ET Leader on a weekly basis. The findings of this review should be included in the relevant monthly EM&A reports and quarterly summary reports, together with any recommendations to improve the performance of the EM&A programme.