9. lANDSCAPE AND VISUAL IMPACT ASSESSMENT
List of Appendices
Appendix
1 Implementation Schedule of
Recommended Mitigation Measures
Table 9.1 - Monitoring
Programme
Stage |
Monitoring Task |
Monitoring Report |
Form of Approval |
Frequency |
Design |
Monitoring
of design works against the recommendations of the landscape and visual
impact assessments within the EIA should be undertaken during detailed design
and tender stages, to ensure that they fulfil the intentions of the
mitigation measures. Any changes to the design, including design
changes on site should also be checked. |
Report by
ER confirming that the design conforms to requirements of EP |
Approved
by Client |
At
Completion of Design Stage |
Construction |
Monitoring
of the contractors operations during the construction period. |
Report on
Contractor's compliance, by ET |
Counter-signature of report by IEC |
Weekly |
Establishment
Works |
Monitoring
of the planting works during the 24-month Establishment period after
completion of the construction works. |
Report on
Contractor's compliance, by ET |
Counter-signature of report by IEC |
3 months |
Table 9.2 - Event and
Action Plan for Landscape and Visual Impact
EVENT |
ACTION |
|||
ET |
IEC |
ER |
Contractor |
|
Design Check |
Check final design conforms to the requirements of EP and prepare
report. |
Check report.
Recommend remedial design if necessary |
Undertake remedial design if necessary |
|
Non-conformity on one occasion |
Identify Source
Inform IEC and ER
Discuss remedial actions with IEC, ER and Contractor
Monitor remedial actions until rectification has been completed |
Check report
Check Contractor's working method
Discuss with ET and Contractor on possible remedial measures
Advise ER on effectiveness of proposed remedial measures.
Check implementation of remedial measures. |
Notify Contractor
Ensure remedial measures are properly implemented |
Amend working methods
Rectify damage and undertake any necessary replacement |
Repeated Non-conformity |
Identify Source
Inform IEC and ER
Increase monitoring frequency
Discuss remedial actions with IEC, ER and Contractor
Monitor remedial actions until rectification has been completed
If non-conformity stops, cease additional monitoring |
Check monitoring report
Check Contractor's working method
Discuss with ET and Contractor on possible remedial measures
Advise ER on effectiveness of proposed remedial measures
Supervise implementation of remedial measures. |
Notify Contractor
Ensure remedial measures are properly implemented |
Amend working methods
Rectify damage and undertake any necessary replacement |