Table 13.1 Implementation
Schedule of the Proposed Mitigation Measures for Air Quality Impact
Table 13.2 Implementation Schedule
of the Proposed Mitigation Measures for Noise Impact
Table 13.3 Implementation
Schedule of the Proposed Mitigation Measures for Water Quality Impact
Table 13.5 Implementation
Schedule of the Proposed Mitigation Measures for Land Contamination Issues
Table 13.6 Implementation
Schedule of the Proposed Mitigation Measures for Ecological Impact
Table 13.7 Implementation
Schedule of the Proposed Mitigation Measures for Hazard to Life
Table 13.9 Implementation Schedule
of the Proposed Mitigation Measures for Cultural Heritage Impact
Table 13.1 Implementation Schedule of the Proposed Mitigation Measures for Air Quality Impact
EIA
Ref. |
Environmental
Protection Measures |
Location
/ Duration of measures/ Timing of completion of measures |
Implementation
Agent |
Implementation
Stages** |
Relevant
Legislation and Guidelines |
||
Des |
C |
O |
|||||
Construction Phase |
|||||||
3.7.1.1 |
Sufficient dust suppression
measures as stipulated under the Air
Pollution Control (Construction Dust) Regulation (Cap. 311R), as well as good
site practices and good housekeeping of the site should be properly
implemented in order to minimise the construction dust generated. These measures include the followings:
a)
Use of regular watering, to reduce dust emissions
from exposed site surfaces and unpaved roads particularly during dry weather; b)
Use of frequent watering of particular dusty
construction areas close to ASRs; c)
Use of frequent watering or water sprinklers for
major haul roads, material stockpiling areas and other dusty activities within
the construction site; d)
Side enclosure and covering of any aggregate or
dusty material storage piles to reduce emissions. Where this is not practicable owing to
frequent usage, watering should be applied to aggregate fines; e)
Provide hoarding of not less than 2.4 m high from
ground level along the site boundary except for site entrance or exit; f)
Open temporary stockpiles should be avoided or
covered. Prevent placing dusty
material storage plies near ASRs; g)
Tarpaulin covering of all dusty vehicle loads transported
to, from and between site locations; h)
Establishment and use of vehicle wheel and body
washing facilities at the exit point of the site; i)
Imposition of speed control for vehicles on
unpaved site roads. 8 km/hr is the
recommended limit; and j)
Routing of vehicles and positioning of
construction plant should be at the maximum possible distance from ASRs; k)
Avoid position of material stockpiling areas,
major haul roads and dusty works within the construction site close to
concerned ASRs; and l)
Avoid unnecessary exposed earth. |
All construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- Air Pollution Control Ordinance (APCO); - Hong Kong Air Quality Objectives (HKAQO); - Air Pollution Control (Construction Dust)
Regulation; and - Technical Memorandum on Environmental Impact
Assessment Process (EIAO-TM) |
3.7.1.2 |
Guidelines
stipulated in EPD’s Recommended Pollution
Control Clauses for Construction Contracts should be incorporated in the
contract documents to abate dust impacts.
The clauses include: · The contractor shall observe and comply with
the Air Pollution Control Ordinance
and its subsidiary regulations, particularly the Air Pollution Control (Construction Dust) Regulation. · The contractor shall undertake at all times to
prevent dust nuisance as a result of the construction activities. · The contractor shall ensure that there will be
adequate water supply / storage for dust suppression. · The contractor shall devise, arrange methods
of working and carrying out the works in such a manner so as to minimise dust
impacts on the surrounding environment, and shall provide experienced
personnel with suitable training to ensure that these methods are
implemented. · Before the commencement of any work, the contractor may
require to submit the methods of working, plant,
equipment and air pollution control system to be used on the site for the
engineer inspection and approval. |
All construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- Recommended
Pollution Control Clauses for Construction Contracts - APCO - Air
Pollution Control (Construction Dust) Regulation |
3.4.1.4 |
Control on fuel
combustion from the use of PMEs · Legal control on the types of fuel allowed for use and
their sulphur contents in commercial and industrial processes should be
observed. · Only approved or exempted non-road mobile machinery should
be allowed to be used in construction sites. · All construction plants are required to use
ultra-low-sulphur diesel (ULSD) (defined as diesel fuel containing not more
than 0.005% sulphur by weight). |
All construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- Air Pollution Control (Fuel Restriction)
Regulation - Air Pollution control (Non-road Mobile
Machinery) (Emission) Regulation - ETWB-TC(W) No. 19/2005 |
Operational Phase |
|||||||
3.7.2.1 |
Air ventilated from the enclosed structure of the proposed
SPS should be treated by deodorising units with odour removal efficiency of
at least 99.5% in terms of target odour species, i.e. H2S, before
discharging to the atmosphere. The exhaust
outlet of the deodorising units should be located away from the nearby air
sensitive receivers as far as practicable, i.e. facing east of the Sai O
Trunk Sewer SPS.
|
Sai O Trunk Sewer SPS / Design and Operational phases |
Project Proponent |
P |
|
P |
EIAO-TM |
3.6.2.2 & 3.7.2.1 |
In addition to the deodorising units, the following
measures should be implemented to minimise the odour impacts from the
proposed SPS:
· The odour sources including
inlet chamber, coarse screen channels, distribution chamber and wet wells
should be enclosed with air- and water-tight lids at all times except during
checking, maintenance and cleaning; · Negative pressure should be
maintained within the facilities; · Screening wastes should be stored
in a covered container or sealed plastic bag and handled carefully inside the
screen houses before transporting outside the SPS building;
· Screening wastes should be
regularly removed from the proposed SPS by a reputable waste collector. They should be transported in an enclosed
type carrier or vehicle and disposed of on the same working day; and · The deodorising units
should be regularly checked and maintenance to maintain the odour removal
efficiency. |
Sai O Trunk Sewer SPS/ Design and Operational phases |
Project Proponent |
P |
|
P |
|
** Des – Design, C – Construction,
and O – Operation
Table 13.2 Implementation Schedule of the Proposed Mitigation Measures for Noise Impact
EIA Ref. |
Environmental Protection Measures |
Location / Duration of measures /
Timing of completion of measures |
Implementation Agent |
Implementation Stages** |
Relevant Legislation and Guidelines |
||
Des |
C |
O |
|||||
Construction Phase |
|||||||
4.8.1.2 |
Good Site Practice
The
site practices listed below should be followed during construction works:
· Only well-maintained PME to be operated on
site and should be serviced regularly during construction; · Silencers or mufflers on construction
equipment should be utilised (if appropriate) and should be properly
maintained during the construction; · Mobile plant, if any, should be sited as far
away from NSRs as possible; · Machines and plant (such as trucks) that may
be in intermittent use should be shut down between work periods or should be
throttled down to a minimum; · Plant known to emit noise strongly in one
direction should, wherever possible, be orientated to direct noise away from
the nearby NSRs; and · Material stockpiles and other structures
should be effectively utilised, wherever practicable, in screening noise from
on-site construction activities |
All
construction sites / construction phase / upon completion of all construction
activities |
Contractor |
|
P |
|
- |
4.8.1.3 – 4.8.1.4 & Table 4.7 |
Use of
Quiet PME
The
Contractors may adopt alternative quiet PME as long as it can be demonstrated
that they would not result in construction noise impacts worse than those
predicted in this EIA Report. Use of
quiet plant should be made reference to the Powered Mechanical Equipment
(PME) listed in the Technical Memorandum or the Quality Powered Mechanical
Equipment (QPME) / other commonly used PME listed in Environmental Protection
Department (EPD) web pages as far as possible which includes the Sound Power
Level (SWLs) for specific quiet PME.
|
All
active construction sites / construction phase / upon completion of all
construction activities |
Contractor |
|
P |
|
- EIAO-TM -
Noise Control Ordinance (NCO) |
4.8.1.5 |
Use of Movable Noise Barriers/Acoustic Mats
Movable
noise barriers that can be placed close to the construction equipment and
moved along with the PME are effective for screening noise from NSRs. A typical design which has been used
locally is a wooden framed barrier with a cantilevered upper portion of
superficial density no less than 10 kg/m² on a skid footing with internal
sound absorptive lining. This measure
is particularly effective for low level zone of NSRs. A longer cantilevered top cover would be
required to achieve screening benefits at upper floors of NSRs. The Contractor shall
be responsible for the design and actual position of the movable noise
barriers with due consideration given to the position and size of the PME,
and the requirement of intercepting the line-of-sight from the NSRs to the
PME, as well as ensuring that the barriers should have no opening and gap. It is anticipated that properly designed
noise barriers would achieve a 5 dB(A) reduction for mobile PME and a 10
dB(A) reduction for static PME.
Acoustic mat with surface mass of not less than 7kg/m2 would be used
for plant items such as piling, oscillator and a 10 dB(A) noise reduction is
anticipated.
|
All
active construction sites / construction phase / upon completion of all construction
activities |
Contractor |
|
P |
|
- EIAO-TM -
NCO |
4.8.1.7 |
Scheduling
of Noisy Activities to outside Examination Period of N2
To
minimise the construction noise impact on N2, the use of piling (oscillator)
in ELS and concurrent use of concrete lorry mixer with other PMEs in steel
fixing and concreting of structure should be avoided during the examination
period of N2.
Contractor
should keep close communication with the operator of HKBTS to obtain the
updated schedule of examination at the time conducting of the relevant
construction works.
|
All
active construction sites / construction phase / upon completion of all
construction activities |
Contractor |
|
P |
|
- EIAO-TM |
Operational Phase |
|||||||
4.8.2.1 |
Install silencers or other acoustic treatment equipment at
the outlet of the ventilation fans and exhaust fan of the deodorizing unit,
which openings would be facing away from the nearest NSRs, i.e. towards to
the eastern side of the SPS, with reference to “Good Practices on Ventilation
System Noise Control” published by EPD.
|
Sai O
Trunk Sewer SPS / Design and Operational Phases |
Project Proponent |
P |
|
P |
- EIAO-TM - NCO - Good Practices on Ventilation System Noise Control |
4.8.2.3 |
The following best practices be implemented as
far as practicable to further minimise any potential impacts: · Quieter plant should be chosen as far as practical; · Include noise levels specification when
ordering new plant items; · All openings, including louvres for
ventilation and machine room doors should be oriented away from the NSRs as
far as practicable; · Silencers, acoustic louvres
or acoustic doors should be used where necessary; and · Develop and implement a regularly scheduled plant
maintenance programme so that plant items are properly operated and
serviced. The programme should be
implemented by properly trained personnel. |
Sai O
Trunk Sewer SPS / Design and Operational Phases |
Project Proponent and Operator. |
P |
|
P |
- |
**
Des – Design, C – Construction, and O – Operation
Table 13.3 Implementation Schedule of the Proposed Mitigation Measures for Water Quality Impact
EIA
Ref. |
Environmental
Protection Measures |
Location/Duration
of measures/ Timing of completion of measures |
Implementation
Agent |
Implementation
Stages** |
Relevant
Legislation and Guidelines |
||
Des |
C |
O |
|||||
Construction Phase |
|||||||
5.8.1.1 |
Construction
Site Runoff
Proper site management measures should be implemented
to control site runoff and drainage, and thereby prevent high sediment
loadings from entering nearby watercourses.
The contractor should follow the practices, and be responsible for the
design, construction, operation and maintenance of
all the mitigation measures as specified in ProPECC
PN 1/94 “Construction Site Drainage”. The design of the mitigation measures
should be submitted by the contractor to the engineer for approval. These mitigation measures should include the
following practices: · At the start of site establishment, perimeter
cut-off drains to direct off-site water around the site should be constructed
with internal drainage works and erosion and sedimentation control facilities
implemented. Channels (both temporary
and permanent drainage pipes and culverts), earth bunds or sand bag barriers should be provided on site to direct storm water to
silt removal facilities. · Sand / silt removal facilities such as sand /
silt traps and sediment basins should be provided to remove sand / silt
particles from runoff to meet the requirements of the TM standard under the WPCO.
The design of efficient silt removal facilities should be based on the
guidelines in Appendix A1 of ProPECC PN 1/94, which
states that the retention time for silt / sand traps should be 5 minutes
under maximum flow conditions. · All drainage facilities and erosion and
sediment control structures should always be regularly inspected and
maintained to ensure proper and efficient operation and particularly during
rainstorms. Deposited silt and grit
should be regularly removed, at the onset of and after each rainstorm to
ensure that these facilities are functioning properly at all times. · Measures should be taken to minimise the
ingress of site drainage into excavations.
Water pumped out from foundation excavations should be discharged into
storm drains via silt removal facilities. · If surface excavation works cannot be avoided
during the wet season (April to October), temporarily exposed slope / soil
surfaces should be covered by a tarpaulin or other means, as far as
practicable, and temporary access roads should be protected by crushed stone
or gravel, as excavation proceeds.
Interception channels should be provided (e.g. along the crest / edge
of the excavation) to prevent storm runoff from washing across exposed soil
surfaces. Arrangements should always
be in place to ensure that adequate surface protection measures can be safely
carried out well before the arrival of a rainstorm. Other measures that need to be implemented
before, during and after rainstorms are summarised in ProPECC
PN 1/94. · All vehicles and plant should be cleaned
before leaving a construction site. An
adequately designed and sited wheel washing facility should be provided at
every construction site exit where practicable. Wash-water should have sand and silt
settled out and removed at least on a weekly basis. The section of access road leading to, and
exiting from, the wheel-wash bay to the public road should be paved with
sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of
soil and silty water to public roads and drains. · Open stockpiles of construction materials or
construction wastes on-site should be covered with tarpaulin or similar
fabric during rainstorms. |
All construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- EIAO-TM - Water Pollution Control Ordinance (WPCO) - Technical Memorandum on Standards for
Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal
Waters (TM-DSS) - The Practice Note for Professional Persons on
Construction Site Drainage (ProPECC PN 1/94) |
5.8.1.2 – 5.8.1.3 |
General
Construction Activities
· Debris and refuse generated on-site should be
collected, handled and disposed of properly to avoid
entering any nearby water bodies and public drainage system. · Stockpiles of cement and other construction
materials should be kept covered when not being used. · Oils and fuels should only be used and stored
in designated areas, which have pollution prevention facilities. · All fuel tanks and storage areas should be
provided with locks and be sited on sealed areas, within bunds of a capacity
equal to 110% of the storage capacity of the largest tank. Rainwater in the bunds should be cleared
after each rain event. Waste oils,
fuels and solvents collected within the bund should be handled and treated as
chemical waste. |
All construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- EIAO-TM - WPCO - ProPECC PN 1/94 - Waste Disposal Ordinance (WDO) |
5.8.1.4 |
Sewage
Effluent
|
All construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- WPCO - EIAO-TM - TM-DSS - WDO |
5.8.1.5 |
Construction Works in Close Proximity of
Inland Waters The practices outlined in ETWB TC (Works) No.
5/2005 “Protection of natural
streams/rivers from adverse impacts arising from construction works”
should be adopted where applicable to minimise the water quality impacts upon
any natural streams or surface water systems.
|
All construction sites / construction phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- WPCO - EIAO-TM - ETWB TC (Works) No. 5/2005 |
Operational Phase |
|||||||
5.7.2.5 |
(i) Designs to safeguard the normal operation
of the SPS (a) Secure
Electrical Power Supply at SPS · Backup power supply in the form of dual-transformer
and switchgear, and dual / ring circuit power supply by CLP Power Hong Kong Ltd.
(CLP) will be provided to secure electrical power supply. According to CLP’s performance standard and
track records, their supply reliability reaches 99.99% and electricity
provision will be restored within 2 hours after any unlikely fault
outage. The backup as mentioned above
further enhanced the security and reliability. (b) Designs
to Avoid / Minimise Equipment Failure · Two
(2) duty and two (2) standby pumps will be
provided to prevent interruption of normal operation of the SPS during
breakdown or maintenance of the duty pumps; · Mechanically raked bar screen will be
provided to remove large object,
stones, debris, etc. and thus, protecting the downstream equipment of the SPS against
physical damage. One
duty and one standby screen will be designed to secure the reliability and
redundancy of the operation; · Provision of twin rising mains system to
maintain normal operation of the proposed SPS during maintenance works
by eliminating single point of failure and to minimise the chance of
emergency overflow; and · Regular inspection and preventive maintenance
of plant equipment to minimise equipment failure. |
Sai O Trunk Sewer SPS / Design and Operational Phases |
Project Proponent |
P |
|
P |
- WPCO |
5.7.2.5 |
· Provision of a telemetry system with alarms connecting
the proposed
Sai O Trunk Sewer SPS to Sha Tin Sewage Treatment Works (Sha Tin
STW) to allow close monitoring of the operation of the unmanned SPS. Alarm signal for any malfunction of SPS
(such as power failure, abnormal shut down of pumps, etc.) will be sent to
the control centre at Sha Tin STW so that immediate actions can be taken in
case of irregularities or operation problems of the unmanned facilities. Any failure would be promptly repaired by
the operator / its contractor as soon as practicable in advance before sewage
bypass to the emergency storage tank. |
Sai O Trunk Sewer SPS / Design and Operational Phases |
Project Proponent |
P |
|
P |
- WPCO |
5.7.2.5 |
· Emergency
storage tank, which would provide a holding capacity of approximately 1,717
m3 – equivalent to approximately 2 hours’ average dry weather flow (ADWF),
will be provided for the proposed Sai O Trunk Sewer SPS to cater for failure
of all pumps or complete outage of power supply. · If
all the above measures to safeguard and recover normal operations of the SPSs
are exhausted, sewage will be tanked away as necessary as a last resort to
maximise buffer for emergency storage as far as practicable in case the power
outage / plant failure cannot be recovered in time to delay the outflow of
raw sewage. Sewage tankers would be
mobilised within one hour since plant failure to tank away the sewage from
the Sai O Trunk Sewer SPS as much as possible. |
Sai O
Trunk Sewer SPS / Design and Operational Phases |
Project
Proponent |
P |
|
P |
- WPCO |
5.8.2.2 |
Any incident of emergency bypass from the SPS
would follow EPD’s “A Guide on Reporting
Sewage Bypass Incidents in Sewage Pumping Stations and Sewers” and DSD’s “Contingency Plan for Incidents Possibly
Encountered in Sewage Treatment Facilities having a Potential of Generating
an Environmental Nuisance”
(“Contingency Plan”). The Contingency Plan details the
procedures to promptly notify relevant Government Departments [e.g.
Environmental Protection Department (EPD),] in the event of emergency
overflow that may pollute water sensitive receivers close to the proposed SPS
or cause other environmental nuisance as soon as possible within 24 hours of
the incident and to conduct joint investigation with EPD to assess the
impacts as well as to work out mitigation measures to reduce impact to the
environment and public health and to interact with the community if
necessary. |
Sai O Trunk Sewer SPS / Operational Phase |
Project Proponent |
|
|
P |
- WPCO |
5.8.2.3 |
Best Management Practices (BMPs), e.g. good
housekeeping practices, should be implemented to ensure that the operation of
the SPS would not pollute the runoff. |
Sai O Trunk Sewer SPS / Operational Phase |
Project Proponent |
|
|
P |
- WPCO |
** Des – Design, C – Construction, and O – Operation
EIA
Ref. |
Environmental
Protection Measures |
Location/Duration
of measures/ Timing of completion of measures |
Implementation
Agent |
Implementation
Stages** |
Relevant
Legislation and Guidelines |
||
Des |
C |
O |
|||||
6.5.1.3 |
Good Site Practices Recommendations for good site practices during
the construction phase include: · Nomination
of approved personnel, such as a site manager, to be responsible for
implementation of good site practices, arrangements for waste collection and
effective disposal to an appropriate facility; · Training
of site personnel in site cleanliness, concepts of waste reduction, reuse and
recycling, proper waste management and chemical waste handling procedures; · Provision
of sufficient waste reception / disposal points, and regular collection of waste; · Adoption
of appropriate measures to minimise
windblown litter and dust during transportation of waste by either
covering trucks or by transporting wastes in enclosed containers;
· Provision
of regular cleaning and maintenance programme for drainage systems, sumps and oil interceptors; · Adoption
of a recording system for the amount of wastes
generated, recycled and disposed (including the disposal sites); and · Preparation
of Waste Management Plan (WMP), as part of the Environmental Management Plan
(EMP). |
All construction sites / Construction Phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- Waste Disposal Ordinance (WDO) - ETWB TC(W) No. 19/2005 - Waste Disposal (Chemical Waste) (General)
Regulation - Project Administration Handbook (PAH) for Civil
Engineering Works, Section 4.1.3 of Chapter 4 |
6.5.1.4 |
Waste Reduction Measures Recommendations to achieve waste reduction are
discussed as follow: · Segregate and store
different types of construction related waste in different containers, skips
or stockpiles to enhance reuse or recycling of materials and their proper disposal; · Provide separate labelled
bins to segregate recyclable waste such as aluminium cans from other general
refuse generated by the work force, and to encourage collection by individual
collectors; · Recycle any unused
chemicals or those with remaining functional capacity; · Maximise the use of
reusable steel formwork to reduce the amount of C&D materials; · Adopt proper storage and
site practices to minimise the potential for damage to, or contamination of
construction materials; · Plan the delivery and stock
of construction materials carefully to minimise the amount of waste
generated; and · Minimise over ordering and
wastage through careful planning during purchasing of construction materials. |
All construction sites / Construction Phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- WDO |
6.5.1.6 – 6.5.1.7 |
Reducing and Reuse of C&D Materials
· Careful design, planning together
with good site management can reduce over-ordering and generation of C&D
materials such as concrete, mortar and cement grouts. Formwork should be designed to minimise the
use of standard wooden panels, so that high reuse levels can be
achieved. Alternatives such as steel
formwork or plastic facing should be considered to increase the potential for
reuse. · To minimise off-site
disposal of inert C&D material, the excavated inert materials with
suitable characteristics / size should be reused on-site as fill material as
far as practicable, such as for backfilling of the box culvert and drainage
pipe works. · Prior to disposal of
non-inert C&D materials, wood, steel and other
metals should also be separated for reuse and / or recycle where practicable
so as to minimise the quantity of waste to be disposed of to landfill. |
All construction sites / Construction Phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- WDO - DEVB TC(W) No.6/2010 - ETWB TC(W) No. 19/2005 Project Administration
Handbook (PAH) for Civil Engineering Works, Section 4.1.3 of Chapter 4 |
6.5.1.8 |
Storage of C&D Materials
Suitable areas should be designated within the
works site boundaries for temporary stockpiling of C&D material. Within stockpile areas, the following measures
should be taken to control potential environmental impacts or nuisance: · cover material during heavy
rainfall; · locate stockpiles to
minimise potential visual impacts; and · minimise land intake of stockpile
areas as far as possible. |
All construction sites / Construction Phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- WDO - ETWB TC(W) No. 19/2005 Project Administration
Handbook (PAH) for Civil Engineering Works, Section 4.1.3 of Chapter 4 |
6.5.1.9 |
Disposal of C&D Materials · In order to monitor the
disposal of C&D materials at the designated public fill reception
facility and landfill and to control fly-tipping, a trip-ticket system should
be included. · When disposing inert
C&D materials at a public filling reception facility, the material shall
only consist of soil, rock, concrete, brick, cement plaster / mortar, inert
building debris, aggregates and asphalt. The material shall be free from marine mud,
household refuse, plastic, metals, industrial and chemical waste, animal and
vegetable matter, and other material considered to be unsuitable by the
Filling Supervisor. |
All construction sites and Transportation Route of Waste /
Construction Phase / upon completion of all construction activities |
Contractor |
|
P |
|
- WDO - DEVB TC(W) No.06/2010 - Land (Miscellaneous Provisions) Ordinance
(Cap. 28) |
6.5.1.10 & 6.5.2.2 |
Chemical Wastes ·
Good
quality containers compatible with the chemical wastes should be used, and
incompatible chemicals should be stored separately. ·
Appropriate
labels should be securely attached on each chemical waste container
indicating the corresponding chemical characteristics of the chemical waste,
such as explosives, flammable, oxidizing, irritant, toxic, harmful,
corrosive, etc. ·
The
contractor shall use a licensed collector to transport and dispose of the
chemical wastes at the CWTC or other licensed facility in accordance with the Waste Disposal (Chemical Waste) (General)
Regulation. |
Construction and Operational Phase |
Contractor |
|
P |
P |
- WDO - Waste Disposal (Chemical Waste) (General)
Regulation - Code of Practice on the Packaging, Labelling
and Storage of Chemical Wastes |
6.5.1.11 &
Table 6.2 |
General Refuse ·
A
reputable waste collector should be employed by the contractor to remove
general refuse / screenings from the site on a regular basis to minimise
odour, pest and litter impacts. · Clearly labelled recycling
bins should be provided on site to encourage segregation and recycling of
aluminium and plastic wastes, and wastepaper to reduce general refuse
production. · The contractor should carry
out an education programme for workers in avoiding, reducing, reusing and recycling of materials generation. Posters and leaflets advising on the use of
the bins should also be provided in the site as reminders. The recyclable waste materials should then
be collected by reliable waste recycling agents on a regular basis. · The collected general
refuse will be disposed of at NENT landfill.
|
All construction sites / Construction Phase / upon
completion of all construction activities |
Contractor |
|
P |
|
- WDO -
Public Health and Municipal Services Ordinance (Cap.132) |
6.5.2.1 |
Screenings from the SPS · The screening filtered by
the mechanical raked bar screen would be collected into container and removed
with covered container or sealed plastic bag at regular time intervals. · A reputable waste collector
should be employed by the operator to remove screenings from the site on a
regular basis to minimise odour, pest and litter
impacts. |
Sai O Trunk Sewer SPS / Operational Phase |
Project Proponent |
|
|
P |
- WDO |
** Des – Design, C – Construction, and O – Operation
Table 13.5 Implementation Schedule of the Proposed Mitigation Measures for Land Contamination Issues
EIA
Ref. |
Environmental
Protection Measures |
Location/Duration
of measures/ Timing of completion of measures |
Implementation
Agent |
Implementation
Stages** |
Relevant
Legislation and Guidelines |
||
Des |
C |
O |
|||||
7.6 |
Since land contamination issue would not be anticipated,
no mitigation measure is considered necessary for the Project. |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
** Des – Design, C – Construction, and O – Operation
Table 13.6 Implementation Schedule of the Proposed Mitigation Measures for Ecological Impact
EIA
Ref. |
Environmental
Protection Measures |
Location/Duration
of measures/ Timing of completion of measures |
Implementation
Agent |
Implementation
Stages** |
Relevant
Legislation and Guidelines |
||
Des |
C |
O |
|||||
Construction Phase |
|||||||
8.8 |
Since the ecological impact is anticipated to be low and adverse
residual ecological impact is anticipated to be nil, no specific mitigation
measures for ecological impact is required. |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
** Des – Design, C –
Construction, and O – Operation
Table 13.7 Implementation Schedule of the Proposed Mitigation Measures for Hazard to Life
EIA
Ref. |
Environmental
Protection Measures |
Location/Duration
of measures/ Timing of completion of measures |
Implementation
Agent |
Implementation
Stages** |
Relevant
Legislation and Guidelines |
||
Des |
C |
O |
|||||
9.7 |
Since hazard to life issue would be insignificant, no mitigation measure is considered necessary for the
Project. |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
** Des – Design, C – Construction, and O – Operation
EIA
Ref. |
Environmental
Protection Measures |
Location/Duration
of measures/ Timing of completion of measures |
Implementation
Agent |
Implementation
Stages** |
Relevant
Legislation and Guidelines |
||
Des |
C |
O |
|||||
Construction Phase |
|||||||
Table 10.9 |
CM1 –
Preservation of Trees Trees to be retained in accordance with DEVB TCW No.
4/2020 - Tree Preservation. |
All active construction
sites / construction phase / upon completion of all construction activities |
Contractor |
|
√ |
|
-
DEVB
TCW No. 4/2020 and the latest Guidelines on Tree Preservation during
Development issued by GLTM Section of DEVB |
Table 10.9 |
CM2 –
Compensatory Tree Planting Any trees to be
felled under the Project shall be compensated in accordance with DEVB TCW No.
4/2020 - Tree Preservation. |
All active
construction sites / construction phase / upon completion of all construction
activities |
Contractor |
|
√ |
|
-
DEVB
TCW No. 4/2020 and the latest Guidelines on Tree Preservation during
Development issued by GLTM Section of DEVB |
Table 10.9 |
CM3 –
Control of Night-time Lighting Glare Any lighting provision of the construction works at night
shall be carefully controlled to prevent light overspill to the nearby VSRs
and into the sky. |
All active
construction sites / construction phase / upon completion of all construction
activities |
Contractor |
|
√ |
|
- Charter
of External Lighting issued by ENB -
Guidelines on Industry Best
Practices for External Lighting Installations issued by ENB. |
Table 10.9 |
CM4 – Erection of Decorative Screen
Hoarding Decorative Hoarding, which is compatible with the
surrounding settings, shall be erected during construction to minimise the
potential landscape and visual impacts due to the construction works and
activities. |
All active
construction sites / construction phase / upon completion of all construction
activities |
Contractor |
|
√ |
|
- |
Table 10.9 |
CM5 – Management of Construction
Activities and Facilities The facilities and activities at works sites and areas,
which include site office, temporary storage areas, temporary works etc.,
shall be carefully managed and controlled on the height, deposition
and arrangement to minimise any potential adverse landscape and visual
impacts. |
All active
construction sites / construction phase / upon completion of all construction
activities |
Contractor |
|
√ |
|
- |
Table 10.9 |
CM6 – Reinstatement of Temporarily
Disturbed Landscape Areas All hard and soft landscape areas disturbed temporarily
during construction due to temporary excavations, temporary works sites and
works areas shall be reinstated to equal or better quality, to the
satisfaction of the relevant Government Departments. |
All active
construction sites / construction phase / upon completion of all construction
activities |
Contractor |
|
√ |
|
- |
Operational Phase |
|||||||
Table 10.10 |
OM1 - Tree and Shrub Planting to
soften the proposed SPS Tree and shrub planting shall be proposed to soften the
proposed SPS and enhance the landscape and visual amenity of the
Project. |
Sai O Trunk Sewer
SPS / Design and Operational Phases |
Project
Proponent |
P |
|
P |
DEVB TCW No. 4/2020 and the latest Guidelines on Tree
Preservation during Development issued by GLTM Section of DEVB |
Table 10.10 |
OM2 - Aesthetically pleasing design
of the SPS The design of the proposed SPS in the regard of layouts,
forms, materials and finishes shall be sensitively
designed so as to blend in the structures to the adjacent landscape and
visual context. |
Sai O Trunk Sewer
SPS / Design and Operational Phases |
Project
Proponent |
P |
|
P |
- |
Table 10.10 |
OM3 -
Provision of Green Roof Green Roof shall be proposed to enhance the landscape
quality of the proposed SPS and mitigate any potential adverse visual impact
on adjacent VSRs. |
Sai O Trunk Sewer SPS / Design and Operational Phases |
Project
Proponent |
P |
|
P |
- |
Table 10.10 |
OM4 -
Provision of Vertical Greening Self-climbing species shall be proposed at metal fence
wall to soften the proposed SPS and enhance the landscape and visual amenity
of the Project. |
Sai O Trunk Sewer SPS / Design and Operational Phases |
Project
Proponent |
P |
|
P |
- |
** Des – Design, C – Construction, and O – Operation
Table 13.9 Implementation Schedule of the Proposed Mitigation Measures for Cultural Heritage Impact
EIA
Ref. |
Environmental
Protection Measures |
Location/Duration
of measures/ Timing of completion of measures |
Implementation
Agent |
Implementation
Stages** |
Relevant
Legislation and Guidelines |
||
Des |
C |
O |
|||||
11.8 |
Since cultural heritage impact would not be anticipated,
no mitigation measure is considered necessary for the Project. |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
** Des – Design, C – Construction, and O – Operation