TABLE OF CONTENTS

15.  Conclusions.. 15-1

15.1     Introduction.. 15-1

15.2     Air Quality.. 15-1

15.3     Noise.. 15-2

15.4     Water Quality.. 15-2

15.5     Waste Management Implications.. 15-2

15.6     Land Contamination.. 15-2

15.7     Ecology.. 15-3

15.8     Hazard to Life.. 15-3

15.9     Landscape and Visual. 15-3

15.10   Cultural Heritage.. 15-4

15.11   Overall Conclusion.. 15-4

 

 

15.                    Conclusions

 

15.1                 Introduction

15.1.1.1        This EIA Report has provided an assessment of the potential environmental impacts associated with the construction and operation of the proposed Sai O Trunk Sewer SPS, based on the engineering design information available at this stage.  The assessment has been conducted, in accordance with the EIA Study Brief (No. ESB-281/2014) under the EIAO for the Project and EIAO-TM, covering the following environmental issues:

·         Air Quality Impact

·         Noise Impact

·         Water Quality Impact

·         Waste Management Implication

·         Land Contamination

·         Ecological Impact

·         Hazard to Life

·         Landscape and Visual Impact

·         Cultural Heritage Impact

 

15.1.1.2        The findings of this EIA report have determined the likely nature and extent of environmental impacts predicted to arise from the construction and operation of the Project.  During the EIA process, environmental control measures have been identified and incorporated into the planning and design of the Project, to achieve compliance with environmental legislation and standards during both the construction and operational phases.  The Implementation Schedule listing the recommended mitigation measures is presented in Section 13.  An environmental monitoring and audit (EM&A) programme has also been developed.  Details of the EM&A requirements are provided in a standalone EM&A manual.

 

15.1.1.3        The assessment results for each environmental aspect are summarised in the following sections. 

 

15.2                 Air Quality

15.2.1.1        Potential air quality impact during construction phase would be fugitive dust generated from wind erosion of the excavated areas and stockpiles, and dusty construction activities.  With implementation of regular site watering and good construction practices for dust minimisation, construction dust impacts are not expected to be significant on the surrounding sensitive receivers.  Requirements of Air Pollution Control (Construction Dust) Regulation and EPD’s Recommended Pollution Control Clauses for Construction Contracts are proposed to be incorporated into the contract.

 

15.2.1.2        Odour emission from the proposed Sai O Trunk Sewer SPS would be the main concern during the operational phase.  Air ventilated from the enclosed structure of the proposed SPS should be treated by deodorising unit with odour removal efficiency of at least 99.5% in terms of target odour species, i.e. H2S before discharge to the atmosphere.  The exhaust outlet of the deodorising unit would be located away from the nearby air sensitive receivers as far as practicable, i.e. facing east of the Sai O Trunk Sewer SPS.  With incorporation of the proposed odour control measures in the design of the SPS, quantitative assessment indicated the predicted odour concentrations at representative ASRs would comply with respective EIAO-TM criterion of 5 OU, no adverse air quality impact would be anticipated from the operation of the SPS.

 

15.3                 Noise

15.3.1.1        The assessment for the potential construction noise impact from the proposed Sai O Truck Sewer SPS has been conducted. The assessment result indicated that the mitigated noise levels at all NSRs would comply with the noise criteria set out in the EIAO-TM with proper implementation of the proposed mitigation measures, including adoption of good site practices, use of quiet PME, movable noise barriers / acoustic mats and proper scheduling of noisy construction activities.  No adverse noise impact is anticipated during construction phase of the Project.

 

15.3.1.2        The noise impact associated with the operation of the Project has been assessed based on the plant inventory provided by the Project engineer at the time of the assessment.  The assessment result indicated that the predicted fixed plant noise levels at all representative NSRs would comply with the noise criteria with proper implementation of the proposed mitigation measures.  No adverse noise impact is anticipated during operational phase of the Project. 

 

15.4                 Water Quality

15.4.1.1        Key concerns of water quality issues would be mainly related to the potential of construction run-off during construction phase, and emergency sewage overflow / bypass from the SPS during the operational phase. With incorporation of the precautionary design of the SPS, proper implementation of the proposed mitigation measures and good site practices, adverse water quality impact would not be expected during the construction and operational phases.

 

15.5                 Waste Management Implications

15.5.1.1        The main waste types generated from the construction phase would be C&D materials, chemical waste and general refuse. Waste management would be the contractor’s responsibility to ensure that all wastes produced during the construction of the Project are handled, stored and disposed of in accordance with good waste management practices and EPD’s regulations and requirements.  The recommended mitigation measures should form the basis of the site’s Waste Management Plan to be developed by the Contractors at the construction stage.  The main waste types generated from the operation of the Project would be screenings.  Small quantities of chemical wastes are also anticipated.  With implementation of the recommended mitigation measures, adverse environmental impacts would not be anticipated during construction and operational phases.

 

15.6                 Land Contamination

15.6.1.1        Based on the findings of desktop review and site walkover, no current or historical potentially contaminating land uses / activities were identified within the Project site and therefore adverse land contamination impact arising from the construction and operation of the Project is not anticipated. No mitigation measure is deemed necessary.

 

15.7                 Ecology

15.7.1.1        A total of 12 habitat types were identified within the assessment area, including woodland, mixed woodland, plantation, shrubland, grassland, developed area / wasteland, natural watercourse, modified watercourse, mangrove, rocky shore, sandy shore and intertidal mudflat. The woodland, mixed woodland and the intertidal habitats within the assessment area are considered to have moderate ecological value while the other habitats are of low or low to moderate ecological value.  6 flora and 19 fauna species of conservation importance were recorded in the assessment area.  The Project area is a shrubland of low ecological as it is derived by recolonization of weedy vegetation and under frequent disturbance.  While a mammal species of conservation importance was identified within the Project area in the previous survey, no species of conservation importance was recorded in the recent survey.   

 

15.7.1.2        A total of approximately 0.35 ha shrubland within the Project area would be permanently lost.  Given the small size and low ecological value of the affected habitat, the direct impact is considered minor. Construction site runoff, deterioration of water quality and other disturbance impacts resulting from the construction works would have potential indirect impact on nearby natural habitats (e.g. intertidal, mangrove, shrubland, etc.).  With the implementation of good site practice and control / mitigation measures for water quality impacts and other construction disturbance (e.g. dust, noise), no adverse residual ecological impact would be anticipated from the Project. 

 

15.8                 Hazard to Life

15.8.1.1        The proposed sewage pumping station will be an unmanned station during operation.  The risks in the construction and operation of the proposed Project associated with two high pressure town gas pipelines and an offtake and pigging station were assessed.  The societal risk level was in the ALARP region. The results showed that both the individual risks and societal risks comply with the Risk Guidelines given in Annex 4 of the EIAO-TM. 

 

15.8.1.2        The risks in the construction and operation of the proposed Project associated with the Ma On Shan Water Treatment Works (MOSWTW) was reviewed. The proposed development is relatively far away from the MOSWTW, and it was concluded that risk to life from the MOSWTW was insignificant which is not a key issue with respect to EIAO-TM.

 

15.9                 Landscape and Visual

15.9.1.1        During the construction phase, the key sources of landscape and visual impacts would mainly due to the construction of the proposed Sai O Trunk Sewer SPS including associated temporary works and removal of existing vegetation.  During construction, 21 nos. of existing trees would be retained in-situ.  Nevertheless, 65 nos. of existing trees within the proposed works boundary would be felled. To compensate the loss of greenery, 65 nos. of new trees are proposed on-site for compensation.  To replenish the loss of greenery, vertical green wall and green roof are also proposed.  The scale of development is considered medium as the works are localized and at low level.  Generally, there would not be any potential blockage of view during construction.  With the implementation of mitigation measures including preservation of trees, compensatory tree planting, control of night-time lighting glare, erection of decorative screening hoarding, careful management of construction activities and facilities, as well as reinstatement of temporarily disturbed landscape areas, no unacceptable residual landscape and visual impacts from the construction of the Project would be anticipated.  

 

15.9.1.2        During the operational phase, the operation of the proposed Sai O Trunk Sewer SPS would be the key sources of landscape and visual impacts. With the recommended mitigation measures including proposed tree and shrub planting to soften the proposed SPS, aesthetically pleasing design of the proposed SPS, as well as provision of green roof and vertical greening, no unacceptable residual landscape and visual impacts from the operation of the Project would be anticipated.

 

15.10              Cultural Heritage

15.10.1.1    Based on detailed assessment, there is no direct or indirect impact to cultural heritage from the construction or operation of the Project.  Thus, no mitigation measure is required. 

 

15.11              Overall Conclusion

15.1.1.1        Overall, the EIA Report has predicted that the Project would be environmentally acceptable with the implementation of the recommended mitigation measures for construction and operational phases. An EM&A programme has been recommended to ensure the effectiveness of recommended mitigation measures.