TABLE OF
CONTENTS
7. Land contamination.. 7-1
7.1 Introduction.. 7-1
7.2 Environmental Standards and Guidelines.. 7-1
7.3 Assessment Methodology.. 7-1
7.4 Description of the Environment. 7-2
7.5 Site Appraisal. 7-2
7.6 Prediction and Evaluation of Land Contamination
Impacts.. 7-3
7.7 EM&A Requirements.. 7-3
7.8 Conclusion.. 7-4
List of
Table
Table 7.1 Aerial Photographs Reviewed
List of
Figure
Figure 7.1 Photographic
Records of Site Walkover
List of
Appendices
Appendix 7.1 Aerial
Photographs
Appendix 7.2 EPD’s
Reply on Land Contamination Records
Appendix 7.3 FSD’s
Reply on Land Contamination Records
Appendix 7.4 Site
Walkover Checklist
7.
Land contamination
7.1.1.1 This section presents the potential implications of land
contamination associated with the Project. The land contamination assessment
was conducted in accordance with requirements given in Section 3.4.4 and
Appendix F of the EIA Study Brief, as well as Annex 19 of the Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM).
7.2.1.1 The relevant environmental guidelines and standards on land
contamination aspect include the following:
·
Annex 19 of Technical Memorandum
on Environmental Impact Assessment Process (EIAO-TM)
·
Guidance Note for Contaminated Land
Assessment and Remediation (Guidance Note) – The Guidance
Note sets out the requirements for proper assessment and management of
potentially contaminated sites such as oil installations (e.g. oil depots,
petrol filling stations), gas works, power plants, shipyards / boatyards,
chemical manufacturing / processing plants, steel mills / metal workshops, car
repairing / dismantling workshops and scrap yards. In addition, this Guidance Note provides guidelines on how site assessments should be
conducted and analysed and suggests practical remedial measures that can be
adopted for the clean-up of contaminated sites.
·
Practice Guide for Investigation and
Remediation of Contaminated Land (Practice Guide) – The Practice
Guide outlines typical investigation methods and remediation strategies for
the range of potential contaminants typically encountered in Hong Kong.
·
Guidance Manual for Use of Risk-based
Remediation Goals for Contaminated Land Management (Guidance Manual) – The Guidance Manual introduces the risk
based approach in land contamination assessment and present instructions for
comparison of soil and groundwater data to the Risk-Based Remediation Goals
(RBRGs) for 54 chemicals of concern commonly found in Hong Kong. The RBRGs were derived to suit Hong Kong
conditions by following the international practice of adopting a risk-based
methodology for contaminated land assessment and remediation and were designed
to protect the health of people who could potentially be exposed to land
impacted by chemicals under four broad post restoration land use
categories. The RBRGs also serve as the
remediation targets if remediation is necessary.
7.3.1.1 Land contamination assessment was
carried out according to the abovementioned EIAO-TM,
Guidance Note, Practice Guide and Guidance Manual.
7.3.1.2 A site appraisal, including site walkover
and desktop review, was conducted to identify the potentially contaminating
land uses that may pose adverse impact to the Project. Site walkover was conducted within the
Project site to review the general site conditions and to identify any source
of land contamination (or ‘hotspots’).
For the desktop review, the following information was reviewed:
·
Aerial photographs from Survey
and Mapping Office of Lands Department;
·
Records (if any) on dangerous
goods (DGs), chemical wastes, chemical spillage / leakage and fire incidents
from Environmental Protection Department (EPD) or Fire Services Department
(FSD);
·
Site Investigation Report
Volume 1 of 3, EDD Contract No.
8/GCO/1983 Pumping Stations in Plover Cove Reservoir and Aqueducts in Tolo
Channel Phase II, Enpack (H.K.) Ltd., 1983; and
·
Site Investigation Report
Volume 2 of 4 Appendix D, Agreement
CE/31/82 Pumping Stations at Plover Cove Reservoir & Tolo Channel Aqueduct,
Binnie & Partners (Hong Kong), 1984.
7.4.1.1 The proposed Sai O Trunk Sewer Sewage Pumping Station (SPS) is
located at the north of Sai O and situated adjacent to the Sai O Offtake and
Pigging Station with Hong Kong Baptist Theological Seminary located to the
south. The location of the Project site
is shown in Figure 2.1.
7.5.1
Review of Historical Land Use
7.5.1.1 A review of aerial photographs has been undertaken to evaluate the
likelihood of potential contamination associated with past land uses within the
Project site. The development history of
the Project site is summarised below and the list of aerial photographs
reviewed is shown in Table
7.1. The aerial photographs reviewed are provided
in Appendix 7.1.
Table 7.1 Aerial Photographs Reviewed
7.5.1.2 The Project site had been used for cultivation since 1963 and till
1985 when the site was vacated. In 1990,
the Project site was entirely covered with vegetation and no significant change
in land uses was observed since then. No
historical potentially contaminating land uses were identified based on the
review of the aerial photographs.
7.5.2
Site Geology
7.5.2.1 Based on the reports mentioned in Section 7.3, the Project site is
majorly underlain by 7.5 m to 9 m thick of alluvium / fill / gravel overlaying
a layer of mudstone (Grade V rock) / siltstone / sandstone encountered between
-4.60 mPD and -5.33 mPD.
7.5.3
Acquisition of Information from
Government Departments
7.5.3.1 The EPD and FSD have been contacted for (i) records on any leakage /
spillage of chemicals and chemical waste, (ii) records of DGs, (iii) records of
Chemical Waste Producer(s) (CWP) and (iv) records of reported fire incidents
within the Project site. EPD’s and FSD’s
replies on the requests have been received and attached in Appendix
7.2 and Appendix
7.3 respectively. Replies are summarized below.
Environmental
Protection Department
7.5.3.2 According to the replies from EPD, there are no spillage / leakage
of chemicals at the Project site.
Following to the replies from EPD, records of CWP were reviewed on
14 October 2020 at EPD Southorn Centre Office. According to the records reviewed, there are
no records of registered CWP within the Project site.
Fire
Services Department
7.5.3.3 According to the replies from FSD, there are no records of DGs
license, DGs spillage / leakage incidents and fire incidents at the Project
site.
7.5.4
Site Walkover
7.5.4.1 Site walkover was conducted on 23 July and 21 November 2020 to
ascertain any contaminative issues associated with current land uses and
activities within the Project site.
7.5.4.2 The Project site is currently fenced off and inaccessible for
detailed site walkover. The Project site is currently owned by the Lands
Department and change of land use at the site is not expected prior to
commencement of the Project. Based on peripheral site observation, the Project
site is a piece of vacant / vegetated land.
No potentially contaminating land uses / activities have been identified
and no oil stains and / or stressed vegetation have been observed.
7.5.4.3 Photographic records illustrating the current land uses and
activities observed during site walkover are provided in Figure
7.1.
7.5.4.4 Site walkover checklist, providing information on site condition and
details on site observation, is enclosed in Appendix 7.4.
7.6
Prediction and Evaluation
of Land Contamination Impacts
7.6.1.1 Based on the findings of the desktop review and site walkover, no
current or historical potentially contaminating land uses / activities were
identified within the Project site and therefore, no land contamination impact
associated with the Project is anticipated.
7.6.1.2 No further land contamination assessment, including intrusive site
investigation (SI) works and submission of Contamination Assessment Plan (CAP),
Contamination Assessment Report (CAR) and Remediation Action Plan (RAP), is
therefore considered necessary for the Project.
7.7.1.1 Since land contamination impact is not anticipated, no EM&A
requirements are considered necessary for the Project.
7.8.1.1 Based on the findings of desktop review and site walkover within the
Project site, no current or historical potentially contaminating land uses /
activities were identified within the Project site and therefore adverse land
contamination impact arising from Project is not anticipated. No further land contamination assessment
(including SI works and submission of CAP, CAR and RAP) or EM&A
requirements are considered necessary for the Project.