TABLE
OF CONTENTS
1............ Introduction.. 1
1.1 Project Background. 1
1.2 Purpose of this Executive Summary. 1
2............ Project
description.. 2
2.1 Purpose and Scope of Project 2
2.2 Need and Benefits of the Project 2
2.3 Consideration of Alternative Options. 3
2.4 Construction Method and
Sequence. 8
2.5 Construction Programme. 8
2.6 Concurrent
Project 8
3............ Key Findings of the
environmental impact Assessment. 8
3.1 Air Quality Impact 8
3.2 Noise Impact 9
3.3 Water Quality Impact 9
3.4 Waste Management
Implication. 10
3.5 Land Contamination. 11
3.6 Ecological Impact
(Terrestrial and Aquatic) 11
3.7 Hazard to Life. 12
3.8 Landscape and Visual Impact 12
3.9 Cultural Heritage. 13
4............ Environmental monitoring
and audit (EM&A) 13
5............ Conclusion.. 13
LIST OF TABLE
Table
2.1 Comparison of Alternative
Location Options
LIST OF Figure
Figure
2.1 Location Plan of the Project
LIST OF Appendices
Appendix
2.1 Alternative
Locations of the Proposed Sai O Trunk Sewer Sewage Pumping Station
Appendix
2.2 Alternative
Design of the Proposed Sai O Trunk Sewer Sewage Pumping Station
1.1.2
The short-term measures were
implemented under the project entitled “Tolo Harbour Catchment – first-aid
measures” and comprised the interception and diversion of pollution flows into
the existing sewerage system at seven locations in Sha Tin and Tai Po. These
measures are completed and in operation. The long-term measures include the
provision of sewerage facilities to collect pollution discharges from 165
unsewered areas within the Tolo Harbour Catchment.
1.1.3
Since the completion of the
SMP, the projected populations in the region have increased significantly. To
assess whether the existing sewerage system has the capacity for the future
need, EPD completed another study, the Review of North District and Tolo
Harbour Sewerage Master Plans (the Review) in November 2002. The Review
recommended, amongst others, construction of sewers and pumping stations with
associated rising mains for provision of sewerage to the unsewered areas in Sha
Tin and Tai Po and also the extension of existing trunk sewer in Ma On Shan
along Sai Sha Road with construction of a pumping station at the downstream of
this trunk main. Based on the findings and recommendations of the Review, the
scope of works under Stage II has been repackaged. To tackle the local
pollution issues at Shing Mun River and the proposed Lung Mei Artificial Beach,
the proposed village sewerage works under Stage I Phase IIC and Stage II have
also been re-prioritised.
1.1.5
In accordance with the
requirements of Section 5(1)(a) of the EIAO,
an application for an Environmental Impact Assessment (EIA) Study Brief for the
proposed sewage pumping station was submitted on 30 October 2014 under EIAO with a Project Profile (PP) (No.
PP-517/2014). An EIA Study Brief
No.ESB-281/2014 for “Sai O Trunk Sewer Sewage Pumping Station” (hereafter referred
to as “the Project”) was issued on 10 December 2014.
1.2.1
This Executive Summary (ES) summarizes
the key findings, recommendations and conclusions of
the EIA Report for the Project. The ES contains the following information:
·
Section 2 presents purpose and
nature of the Project, consideration of alternative options and construction
methods for the Project;
·
Section 3 presents the key
findings of the environmental impact assessment;
·
Section 4 describes the proposed
environmental monitoring and audit for the Project; and
·
Section 5 presents the
conclusions.
2.1
Purpose and Scope of Project
2.1.1
The proposed Sai O Trunk Sewer
SPS, as part of “Public Works Programme
Item 4125DS - Tolo Harbour Sewerage of Unsewered Areas, Stage II” that originated from the findings of
the Study “Review of North District and Tolo Harbour Sewerage Master Plans”
completed by Environmental Protection Department (EPD) in 2002, is a core component of the proposed trunk sewerage system in Ma On
Shan along Sai Sha Road. It is required to receive all sewage flows along Sai
Sha Road from Kei Ling Ha Lo Wai to Cheung Muk Tau
and the adjacent residential development, health care and education institutions,
and then convey the sewage to Ma On Shan Sewage Pumping Station and ultimately
to Sha Tin Sewage Treatment Works. Location of the proposed Sai O Trunk Sewer
SPS is shown in Figure
2.1.
2.1.2
Based on the latest design, the
installed capacity per day of the proposed Sai O Trunk Sewer SPS is about
20,600m3 for coping with the sewerage needs of both existing and
future developments, with the following main components:
Loading/unloading
bay
Inlet
chamber
Coarse
screen channel
Distribution
chamber
Wet wells
Valve
chamber
Emergency
storage tank
Deodorizing
unit
Switch room
Transformer
room
2.2
Need and Benefits of
the Project
2.2.1
At present, the sewage from the
existing village houses at Sai Sha is preliminarily
treated by private treatment facilities, i.e. septic tanks / and soakaway systems, the performance of which could be
affected by high development density, poor design and inadequate maintenance
and could cause pollution of the environment and poor hygiene. While the
sewage from existing residential developments is treated by local private
treatment plants, the nearby residents are suffering from the nuisance from the
aging treatment plants.
2.2.2
The Sai Sha trunk sewerage
system together with the proposed Sai O Trunk Sewer SPS is designed to serve
the existing and planned developments in the Sai Sha area, by collecting and
conveying the sewage generated from these developments to Shatin Sewage
Treatment Works for proper treatment. The proposed trunk sewerage system
is generally supported by the local communities. As an
essential component for the operation of the proposed trunk sewerage system,
the Project plays an important role to improve the environment and hygiene
conditions of the area.
2.2.3
Without the Project, the whole
sewerage system along Sai Sha Road could not be functioned. Without proper collection of sewage generated from the existing developments to Shatin Sewage Treatment Works for
treatment, the environmental and hygiene nuisance resulting from the potential
inadequate performance of the private treatment facilities / plants due to
aging, increasing village density, poor maintenance etc. could not be rectified
or improved. Moreover, the planned developments cannot be implemented and potential supply of housing units within
the catchment, e.g. the “Comprehensive Development Area” (“CDA”) zone on the
approved Shap Sz Heung Outline Zoning Plan No.
S/NE-SSH/11, will be seriously affected, which will aggravate the shortage of housing
supply in Hong Kong.
Site Selection and
Optimisation
2.3.2
Eight possible locations were
identified and considered in the site selection process.
The possible locations are listed
below and their indicative positions are shown in Appendix 2.1.
·
Location 1: On footpath next to existing public toilet
and Nai Chung Bus Terminus
·
Location 2: Vacant land in between Nai Chung Bus Terminus
and Nai Chung Village
·
Location 3: Vacant land at the east of Hong Kong Baptist
Theological Seminary (HKBTS)
·
Location 4: Vacant land at the east of Nai Chung Village
and opposite to Nai Chung Barbecue Site
·
Location 5: Open area at Lok Wo Sha Lane and on the west
of The Entrance
·
Location 6: Nai Chung Barbecue Site
·
Location 7: Chek Kok
·
Location 8: Vacant land next to Sai O Offtake and Pigging
Station
·
Conservation and Ecology: Avoidance of recognised sites
of conservation importance and natural habitats with higher ecological values in
order to avoid any irreversible adverse impact on ecology and conservation;
·
Air Quality and Noise: Minimisation of air and / or noise
sensitive receivers to be affected;
·
Visual: Lower Visibility to Public;
·
Better Environmental
Performance: higher
energy efficiency, less waste generation, impact on less sensitive receivers);
and
·
Minimisation of septic sewage
and the associated odour issue due to long retention time.
Table 2.1 Comparison of
Alternative Location Options
Environmental Consideration
|
Alternative Location Options
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
Conservation & Ecology
|
Preferable
No encroachment on or in close
proximity to any recognized sites of conservation importance and habitats
with high ecological value.
|
Not Preferable
Encroachment on and in close
proximity to natural habitats of higher ecological value, including woodland,
mudflat and mangrove.
|
Less Preferable
While no encroachment on any
recognized sites of conservation importance and habitats with high ecological
value, it is located close to habitats of higher ecological value, including
mangrove, mudflat and woodland.
|
Not Preferable
Encroachment on woodland of higher
ecological value.
|
Preferable
No encroachment on or in close
proximity to any recognized sites of conservation importance and habitats
with high ecological value.
|
Not Preferable
Encroachment on Ma On Shan Country Park and woodland.
|
Not Preferable
Encroachment on Tseng Tau Coast
SSSI.
|
Preferable
No encroachment on or in close
proximity to any recognized sites of conservation importance and habitats
with high ecological value.
|
Air Quality &
Noise
|
Less Preferable
Affects more nearby existing or planned air /
noise sensitive receivers within 150 m* of the location including HKBTS, Sai
O Village, Nai Chung Village, Sai Sha Villa, planned sitting
out area and playground, and Zessa Vista.
|
Less Preferable
Affects more existing or planned air / noise sensitive receivers
within 150 m* of the location, including Sai O Village, Nai Chung Village, Zessa Vista, HKBTS and Sai Sha Villa
|
Preferable
Affects not as many nearby air / noise sensitive receivers within 150 m* of the location,
including the planned sitting out area and playground, HKBTS, Zessa Vista and Nai Chung Village.
|
Preferable
Affects not as many nearby existing or planned air / noise sensitive receivers within 150
m* of the location, including Nai Chung
Village, Kwun Hang Village, Nai Chung
barbecue area and the “CDA” zone on the approved Shap Sz Heung OZP No. S/NE-SSH/11.
|
Less Preferable
Affects more nearby existing or planned air / noise sensitive receivers within 150
m* of the location, including the Entrance,
Double Cove, Li Po Chun United World College, Lake Silver and
“Residential (Group A)” zone on the draft Ma On Shan OZP No. S/MOS/23.
|
Preferable
Affects
not as many
existing or planned nearby air / noise sensitive receivers within 150
m* of the location, including Nai Chung barbeque area, Kwun Hang Village, Nai
Chung Village and “CDA” zone on the approved Shap Sz Heung OZP No.
S/NE-SSH/11.
|
More Preferable
Far away from air and
noise sensitive receivers (over 500m).
|
Preferable
Affects not as many nearby existing or
planned air / noise sensitive receivers within 150 m* of the location,
including HKBTS, the planned school with recreational area under approved
planning application no. A/MOS/125 and planned sitting
out area and playground.
|
Visual
|
Less Preferable
High visibility to public
|
Less Preferable
Medium to high visibility to
public
|
Preferable
Medium visibility to public
|
Preferable
Medium visibility to public
|
Less Preferable
High visibility to public
|
More Preferable
Low to medium visibility to public
|
More Preferable
Low visibility to public
|
Preferable
Medium visibility to public
|
Environmental Performance
|
Preferable
Since the
site is located at low point of the catchment, no additional pumping
facilities or deep excavation for the SPS to facilitate connection with
deeper gravity sewerage pipe is required, better environmental performance
could be achieved with less C&D materials generation, higher energy
efficiency in operation, and avoidance of impact on additional sensitive receivers
near the extra pumping facilities.
|
Preferable
Since the
site is located at low point of the catchment, no additional pumping
facilities or deep excavation for the SPS to facilitate connection with
deeper gravity sewerage pipe is required, better environmental performance
could be achieved with less C&D materials generation, higher energy
efficiency in operation, and avoidance of impact on additional sensitive receivers
near the extra pumping facilities.
|
Preferable
Since the
site is located at low point of the catchment, no additional pumping
facilities or deep excavation for the SPS to facilitate connection with
deeper gravity sewerage pipe is required, better environmental performance
could be achieved with less C&D materials generation, higher energy
efficiency in operation, and avoidance of impact on additional sensitive receivers
near the extra pumping facilities.
|
Less Preferable
Since the
site is located at high point of the catchment, additional pumping facilities
or deep sewer/SPS would be required, poorer environmental performance would be
anticipated with more C&D materials generation, lower energy efficiency
in operation and impact on additional sensitive receivers near the extra
pumping facilities.
|
Less Preferable
Since the
site is located at high point of the catchment, additional pumping facilities
or deep sewer/SPS would be required, poorer environmental performance would be
anticipated with more C&D materials generation, lower energy efficiency
in operation and impact on additional sensitive receivers near the extra
pumping facilities.
|
Less Preferable
Since the
site is located at high point of the catchment, additional pumping facilities
or deep sewer/SPS would be required, poorer environmental performance with more
C&D materials generation, lower energy efficiency in operation and impact
on additional sensitive receivers near the extra pumping facilities.
|
Preferable
Since the
site is located at low point of the catchment, no additional pumping
facilities or deep excavation for the SPS to facilitate connection with
deeper gravity sewerage pipe is required, better environmental performance
could be achieved with less C&D materials generation, higher energy
efficiency in operation, and avoidance of impact on additional sensitive receivers
near the extra pumping facilities.
|
Preferable
Since the
site is located at low point of the catchment, no additional pumping
facilities or deep excavation for the SPS to facilitate connection with
deeper gravity sewerage pipe is required, better environmental performance
could be achieved with less C&D materials generation, higher energy
efficiency in operation, and avoidance of impact on additional sensitive receivers
near the extra pumping facilities.
|
Septic Sewage & Odour
|
Preferable
Medium pumping distance that
decrease the likeliness of septic sewage and hence causing odour problems
|
Preferable
Medium pumping distance that
decrease the likeliness of septic sewage and hence causing odour problems
|
Preferable
Medium pumping distance that
decrease the likeliness of septic sewage and hence causing odour problems
|
Preferable
Medium pumping distance that
decrease the likeliness of septic sewage and hence causing odour problems
|
More Preferable
Short pumping distance that
decrease the likeliness of septic sewage and hence causing odour problems
|
Preferable
Medium pumping distance that
decrease the likeliness of septic sewage and hence causing odour problems
|
Less Preferable
Long pumping distance that
increase the likeliness of septic sewage and hence causing odour problems
|
Preferable
Medium pumping distance that
decrease the likeliness of septic sewage and hence causing odour problems
|
Note:
* – As described
in Section 1.1.4, the proposed SPS is considered as a DP by virtue of
Item F.3(b) of Part I, Schedule 2 of EIAO as it has
an installed capacity of more than 2 000 m3 per day and a boundary of which is less than 150 m from existing or
planned uses that would be potentially affected by development of SPS
(including residential area, place of worship, and educational institution).
2.3.4
As shown in the Table 2.1, Locations 2, 4, 6 and 7 are not recommended for the proposed SPS
as all of them would encroach on recognised sites of
conservation importance and / or natural habitats with higher ecological values
that irreversible adverse impact on ecology and conservation could not be
avoided. While Location 3 would not
encroach on these valuable sites/habitats, it is less preferable due to its
relatively close proximity to habitats with higher
ecological values (including woodland, mudflats and mangrove). For the
remaining 3 locations (Locations 1, 5 and 8), they are all considered
preferable with respect to conservation and ecology aspects as they would not
encroach on or in the close proximity to any recognised
sites of conservation importance and/or natural habitats with higher ecological
values.
2.3.5
In regard to air quality and noise
aspects, amongst the remaining 3 locations (Locations 1, 5 and 8), Location 8 is
considered more preferable as the proposed SPS at this location would affect
relatively less nearby air and noise sensitive receivers.
2.3.6
In regard to visual aspect, Location 8 is also comparatively less visible to public than
Locations 1 and 5.
2.3.7
In regard to environmental performance and septic sewage
and odour aspect, Location 8 is also considered preferable. Extra pumping
facilities or deep gravity sewer/SPS would not be required and hence would
result in less C&D materials generation, higher energy efficiency in
operation, and avoidance of impact on additional sensitive receivers near the
extra pumping facilities. In addition, the likeliness of
septic sewage that cause odour problem would be reduced.
2.3.9
In the process of developing
the preferred design option for the SPS (Section 2.3.10 refers), the site footprint and
location of the proposed SPS building have been modified from Location 8 into
Location 8A as indicated in Appendix 2.1. In order to optimise the preferred location, the SPS building has been moved further away from Nin Ming Road and
sit alongside the aboveground structures of Sai O Offtake and Pigging Station
at the corner of the preferred vacant land.
Location 8A allows the SPS
building to be positioned in such a way that is most compatible with the
surrounding landscape and visual context and greater room for landscape planting to enhance the landscape quality
and block the view from the main road as detailed in Section 2.3.11,
which could in turn minimise the landscape and visual
impact to the maximum practicable extent. Location 8A has therefore
been selected as the preferred location for the Sai O Trunk Sewer SPS that
could best avoid impacts on area of conservation importance and natural
habitats of higher ecological value, and avoid / minimise
the potential adverse environmental impacts associated with the SPS (e.g.
noise, odour, visual) while achieving a comparatively better environmental
performance.
Design
Options
2.3.10
The major environmental impacts
associated with the Sai O Trunk Sewer SPS would be odour and fixed plant noise
impacts from its operation and visual impact from the aboveground structures. Different design
features (e.g. underground plant facilities, minimising the building bulk, appropriate façade and
boundary treatments, etc.) were
considered in the process of developing the preferred design option for the SPS
from the original design option presented in the Project Profile submitted for
the Application for EIA Study Brief (Application No. ESB-281/2014) (Appendix 2.2), with an aim to avoid / minimise the potential impacts on the nearby sensitive receivers to the maximum practicable
extent without compromising operational requirements of the proposed SPS. The preferred design option adopted was optimised from the original design that it has retained
beneficial features of the original design that could improve the overall environmental
performance of the SPS and also incorporated other advantageous features in
order to minimise the potential environmental impacts
on the nearby sensitive receivers to the maximum practicable extent.
2.3.11
Similar to the original design option, the preferred design option has adopted
the typical design of submersible type pumping station to reduce the scale and
size of above-ground structure of the SPS. To
avoid adverse odour and fixed plant noise impacts, all the underground and
aboveground equipment / components of the SPS will be enclosed within
reinforced concrete structure with soundproof door and ventilated via
deodorization unit and equipped with silencers or other acoustic treatment equipment
at ventilation openings. Similar to landscape and aesthetic design of the original design option,
the preferred design option has been designed to blend into the existing
environment of the Project site and screen the view of the proposed SPS from
the public path with aesthetically designed fence wall treated with planters
and vegetation. Building façades, roof slab and
fence walls would be treated with planters and vegetation while the surface of
the SPS would be covered with wall tiles to harmonize with the earthy landscape
to echo with the surrounding natural environment.
·
Apart from the enclosed design
of SPS, the loading/unloading area in the alternative scheme has been enclosed
to confine any potential environmental nuisances
from the loading and unloading activities during the SPS operation.
·
Building bulk of the SPS has
been reduced by about 16% with the adoption of submersible type pumping station
together with the compacted design and thereby minimising the potential visual
impact from the new superstructure.
·
Site footprint has been
modified and compacted design of SPS has been adopted to
allow the SPS building
to be moved further away from Nin Ming Road and sited alongside the aboveground
structures of Sai O Offtake and Pigging Station at the corner of the vacant
land, and be positioned in such a way that is most compatible with the
surrounding landscape and visual context, hence minimising the potential
landscape and visual impact from the new superstructure. .
·
The area of excavation works
required for the underground wells/chambers would be reduced as compared to the
original design since deeper underground structures with smaller plan area
would be adopted in the design, hence minimising the potential visual impact
from the excavation works.
·
With the whole SPS building
being moved to the northern part of the site (alongside to
the northern boundary wall of the existing Sai O Offtake
and Pigging Station), the southern part of the site (next to Nin Ming Road) could therefore be preserved for landscape planting to
improve the existing landscape quality and provide screen planting to block the
view of the SPS from the main road.
2.4.1
The proposed Sai O Trunk Sewer SPS is a single storey building with basement. It would be constructed
using shallow foundation (e.g. footing foundation) and cast in-situ
construction method. The major construction works would involve site clearance,
soil excavation, steel fixing and concreting, backfilling, E&M installations and pipework, finishing and landscape works. The
construction activities would be carried out in phased sequence in conjunction
with the overlapping of some activities such that the construction duration
could be shortened and potential adverse cumulative impacts from concurrent
construction activities would be avoided.
2.5
Construction Programme
2.5.1
The construction of the Project
is planned to commence in year 2021 Q4 for completion, commissioning, and
operation in year 2024 Q2.
2.6.1
Based on the available
information at the time of this EIA preparation, “Sai Sha Road Widening” would
be carried out adjacent to the Project site from Q1 of 2018 to Q4 of 2023, as
such cumulative construction phase environmental impacts are expected.
2.6.2
A school with recreational area
is proposed at various lots in D.D.167 and adjoining government land, Nai Chung
to the north of Nin Ming Road under the approved planning application no.
A/MOS/125. Since no confirmed construction programme of
the planned educational development is available at time of the preparation of
this EIA, potential cumulative environmental impacts associated with this
planned development have not been taken into account.
2.6.3
Comprehensive Residential and
Commercial Development with Government, Institution or Community Facilities is
proposed along Sai Sha Road at Tai Po Town Lot 157 and Various Lots in D.D.
165, D.D. 207 and D.D. 218 and Adjoining Government Land, Sai Sha, Shap Sz Heung under the approved planning
application nos. A/NE-SSH/120 and A/NE-SSH/120-1.
Since no confirmed construction programme of
the planned comprehensive development is available at time of the preparation
of this EIA, potential cumulative environmental impacts associated with this
planned development have not been taken into account.
3
Key Findings of the environmental impact Assessment
3.1
Air
Quality Impact
3.1.1
Potential air quality impacts
associated with the construction and operational phases of the project have
been assessed in accordance with the criteria and guidelines as stated in the
requirements given in Section 3.4.1 and Appendix B of the EIA Study Brief, as well as Annexes 4 and 12 of EIAO-TM. The assessment area for air
quality impact assessment covers the area within 500m from the boundary of the
Project site.
3.1.2
Potential air quality impacts
from the construction works of the Project would mainly be related to fugitive
dust generated from wind erosion of the excavated areas and stockpiles as well
as construction activities such as site clearance,
excavation, backfilling. Given the small scale of the construction works,
with the implementation of sufficient dust suppression measures as stipulated
under the Air Pollution Control (Construction
Dust) Regulation (Cap. 311R) and good site practices, construction dust impacts are not expected to be significant on the
surrounding air sensitive receivers. Requirements of Air Pollution Control (Construction Dust) Regulation and EPD’s Recommended Pollution Control Clauses
for Construction Contracts are proposed to be incorporated into the
contract.
3.1.3
Odour emission from the
proposed pumping station would be the main concern during the operational
phase. Air ventilated from the enclosed structure of the proposed SPS should be
treated by deodorising unit with odour removal efficiency
of at least 99.5% in terms of target odour species, i.e. H2S, before
discharging to the atmosphere. The exhaust outlet of the deodorising unit would
be located away from the nearby air sensitive receivers as far as practicable,
i.e. facing east of the Sai O Trunk Sewer SPS. With incorporation of the
proposed odour control measures in the design of the SPS, no adverse odour
impact would be anticipated during operation of the proposed SPS.
3.2
Noise
Impact
3.2.1
Potential noise impacts
associated with the construction and operational phases of the project have
been assessed in accordance with the criteria and guidelines as stated in the
requirements given in Section 3.4.2 and Appendix C of the EIA Study Brief, as well as Annexes 5 and 13 of the EIAO-TM. The assessment area for noise
impact assessment covers the area within 300m from the boundary of the Project
site.
3.2.2
Construction noise is expected
from the use of Powered Mechanical Equipment (PME) during various construction
activities, such as site clearance, excavation, substructure works,
superstructure works, fitting out works and landscape works for the proposed
Sai O Trunk Sewer SPS. Noise impact arising from construction activities of the
Project was assessed. With proper implementation of the proposed mitigation
measures, including adoption of good site practices, use of quiet PME, movable
noise barriers/acoustic mats and proper scheduling of noisy construction
activities, the mitigated cumulative construction noise
levels from the Project and nearby concurrent project at all representative noise
sensitive receivers (NSRs) in the vicinity of the Project work site would range
from 59 to 74 dB(A), complying with the noise criteria set out in the EIAO-TM.
3.2.3
The noise impact associated
with the operation of the Project was assessed. Based on the plant design
information, the predicted fixed plant noise levels at all the representative
NSRs would be comply with the criteria with the implementation of mitigation
measures including provision of silencers or other
acoustic treatment equipment at the outlet of the ventilation fans and exhaust
fan of the deodorising unit.
3.3
Water Quality
Impact
3.3.3
Potential water quality impacts
during the operational phase would be mainly associated with emergency discharge from the proposed Sai O Trunk Sewer SPS due to
pumps/parts failure and interruption of the electrical power supply. Precautionary measures and designs to safeguard the normal
operation of the SPS, facilitate immediate actions to recover normal operation
of the SPS in case of irregularities, and temporarily store sewage in case of
complete power outage / plant failure, including provision of dual power
supply, standby pumps, twin rising mains system, mechanically raked bar screen
(which safeguards the equipment downstream from being damaged by large objects),
remote monitoring system, regular
maintenance and inspections, and
2-hour emergency storage, would be provided to avoid the occurrence of any
emergency discharge. Sewage will be tanked away as
necessary as a last resort to maximise
buffer for emergency storage as far as practicable in case the power outage /
plant failure cannot be recovered in time. Any incident of emergency bypass
from the SPS would follow EPD’s “A Guide
on Reporting Sewage Bypass Incidents in Sewage Pumping Stations and Sewers”
and DSD’s “Contingency Plan for Incidents
Possibly Encountered in Sewage Treatment Facilities having a Potential of
Generating an Environmental Nuisance” (“Contingency Plan”). The Contingency Plan
details the procedures to promptly notify relevant Government Departments (e.g.
EPD) in the event of emergency overflow that may pollute water sensitive
receivers close to the proposed SPS or cause other environmental nuisance as
soon as possible within 24 hours of the incident and to conduct joint
investigation with EPD to assess the impacts as well as to work out mitigation
measures to reduce impact to the environment and public health and to interact
with the community if necessary. With the incorporation of the recommended precautionary measures,
emergency discharge of sewage would be prevented to the maximum practicable
extent and the potential impact would be short-term in the unlikely event that
an emergency discharge does occur. No unacceptable water
quality impact would be expected during the operational phase of the Project.
3.4
Waste Management Implication
3.4.2
Construction and Demolition
(C&D) materials will be generated from excavation and demolition activities
during construction phase. A total volume of C&D materials to be
generated from the Project was estimated to be approximately 7,350 m³, with approximately 6,390 m3 of inert C&D materials
and 960 m3 of non-inert C&D materials.
3.4.4
Small quantities of other waste materials, including
general refuse and chemical waste would also be generated throughout
construction. Provided that these identified wastes would be handled, transported and disposed of using the recommended methods
and that good site practices would be strictly followed, adverse environmental
impacts are not expected.
3.4.5
The main waste types to be
generated during the operational phase would be screenings,
which would be similar in nature to general refuse, and the collected screenings
be disposed of at strategic landfill. Provided that proper handling
procedures and disposal method are adopted, adverse environmental impacts are
not expected during the operational phase.
3.5.1
The land contamination
assessment has been conducted in accordance with the criteria and guidelines as
stated in the requirements given in Section 3.4.4 and Appendix F of the EIA Study Brief, as well as Section 3.1
of Annex 19 of the EIAO-TM.
3.5.2
Based on the site appraisal, no
current or historical potentially contaminating land uses / activities were identified
within the Project site and therefore adverse land contamination impact arising
from Project is not anticipated. No further land contamination assessment
(including SI works and submission of CAP, CAR and RAP) as well as EM&A
requirements are considered necessary for the Project.
3.6.2
A total of 12 habitat types
were identified within the assessment area, including woodland, mixed woodland,
plantation, shrubland, grassland, developed area / wasteland, natural
watercourse, modified watercourse, mangrove, rocky shore, sandy shore and intertidal mudflat. The woodland, mixed woodland
and the intertidal habitats within the assessment area are considered to have
moderate ecological value while the other habitats are of low or low to
moderate ecological value. 6 flora and
19 fauna species of conservation importance were recorded in the assessment
area. The Project site is a shrubland of low ecological as it is derived by recolonisation
of an abandoned land by weedy vegetation and under frequent disturbance. A
mammal species of conservation importance, Japanese Pipistrelle (Pipistrellus abramus), was identified within the Project site in the previous
surveys conducted in 2015-2016, no species of conservation importance was
recorded in the recent surveys conducted in 2018-2019.
3.7
Hazard
to Life
3.7.2
A review has been conducted to
assess the risk to life associated with the Ma On Shan
Water Treatment Work during the construction stage and operation stage of the
Project. The review showed that the risk to life from the Ma On
Shan Water Treatment Work to the Project was insignificant and therefore not a
key issue with respect to the Risk
Guidelines given in Annex 4 of the EIAO-TM.
3.8.1
A landscape and visual impact
assessment has been carried out in accordance with
Section 3.4.8 and Appendix I of the EIA
Study Brief, Annexes 10 and 18 of the EIAO-TM,
and EIAO Guidance Note No.8/2010.
3.8.2
During the construction phase,
the key sources of landscape and visual impacts would mainly due to the
construction of the proposed Sai O Trunk Sewer SPS including associated
temporary works and removal of existing vegetation. During construction, 21 nos. of existing
trees would be retained in-situ.
Nevertheless, 65 nos. of existing trees within the proposed works
boundary would be felled. To compensate
the loss of greenery, 65 nos. of new trees are proposed on-site for
compensation. To replenish the loss of
greenery, vertical green wall and green roof are also proposed. The scale of development is considered medium
as the works are localized and at low level.
Generally, there would not be any potential blockage of view during
construction. With the implementation of
mitigation measures including preservation of trees, compensatory tree
planting, control of night-time lighting glare, erection of decorative
screening hoarding, careful management of construction activities and
facilities, as well as reinstatement of temporarily disturbed landscape areas,
no unacceptable residual landscape and visual impacts from the construction of
the Project would be anticipated.
3.8.3
During the operational phase,
the operation of the proposed Sai O Trunk Sewer SPS would be the key sources of
landscape and visual impacts. With the
recommended mitigation measures including proposed tree and shrub planting to
soften the proposed SPS, aesthetically pleasing design of the proposed SPS, as
well as provision of green roof and vertical greening, no unacceptable residual
landscape and visual impacts from the operation of the Project would be
anticipated. While some adverse effects
were predicted, these can be eliminated, reduced or
offset to a large extent by specific measures. It is therefore concluded that
the landscape and visual impacts are acceptable with the implementation of the
recommended mitigation measures.
3.9.1
A cultural heritage impact
assessment has been carried out in accordance with Section 3.4.9 of the EIA Study Brief and Annexes 10 and 19 of
the EIAO-TM.
5
Conclusion
5.1.1
The findings of the EIA
provided information on the nature and extent of the environmental impacts
likely to arise from the construction and operation of the proposed Sai O Trunk
Sewer SPS. The EIA has, where appropriate, identified mitigation measures to
ensure compliance with environmental legislation and standards.
5.1.2
Overall, the EIA concluded that
the Project would comply with the requirements of the EIA Study Brief and EIAO-TM
with the implementation of the proposed mitigation measures during the
construction and operational phases of the Sai O Trunk Sewer SPS. The schedule
of implementation of the proposed mitigation measures has been provided in the
EIA Report. An EM&A programme has also been recommended to check the
effectiveness of the proposed mitigation measures.