TABLE
OF CONTENTS
3.2 Monitoring Parameters for
Construction Noise
3.10 Commissioning Test for Fixed Plant
Noise Sources
5. Waste
management implication
11.2 Compliance with Legal and
Contractual Requirements
12.2 Electronic Reporting of EM&A
Information
12.3 Baseline Monitoring Report
12.5 Final Summary EM&A Report for
Construction Phase
12.6 EM&A Reports for Operation Phase
12.8 Interim Notifications of
Environmental Quality Limit Exceedances
List of Tables
Table 2.1 Proposed Construction
Dust Monitoring Station
Table 2.2 Summary of Construction Dust
Monitoring Programme
Table 2.3 Action and Limit Levels for Air
Quality (Construction Dust)
Table 2.4 Event and Action Plan for Air
Quality (Construction Dust)
Table 2.5 Odour Intensity Levels
Table 2.6 Action and Limit Levels for Air
Quality (Odour)
Table 2.7 Event and Action Plan for Air Quality
(Odour)
Table 3.1 Proposed Noise Monitoring
Stations during Construction of the Project
Table 3.2 Action and Limit Levels for
Construction Noise
Table 3.3 Event and Action Plan for
Construction Noise
Table 9.1 Landscape and Visual Impacts
Mitigation Measures for Construction Phase
Table 9.2 Landscape and Visual Impacts
Mitigation Measures for Operational Phase
List of Figures
Figure 1.1 Location of the Proposed Sai O Trunk
Sewer Sewage Pumping Station
Figure 1.2 Project Organisation
Figure 2.1 Location of Proposed Dust Monitoring
Point
Figure 3.1 Location of Proposed Noise Monitoring
Point
List of Appendices
Appendix A Tentative Construction Programme
Appendix B Implementation Schedule of Mitigation
Measures
Appendix C Sample Record Sheet
Loading/unloading bay
Inlet chamber
Coarse screen channel
Distribution chamber
Wet wells
Valve chamber
Emergency storage tank
Deodorizing unit
Switch room
Transformer room
·
Responsibilities
of the Contractor, the Engineer or Engineer’s Representative (ER),
Environmental Team (ET) and Independent Environment Checker (IEC) with respect
to the environmental monitoring and audit requirements during the course of the
Project;
·
Project
organisation for the EM&A works;
·
The
basis for, and description of the broad approach underlying the EM&A programme;
·
Details
of the methodologies to be adopted, including all field laboratories and
analytical procedures, and details on quality assurance and quality control
programme;
·
The
rationale on which the environmental monitoring data will be evaluated and
interpreted;
·
Definition
of Action and Limit levels;
·
Establishment
of Event and Action plans;
·
Requirements
for reviewing pollution sources and working procedures required in the event of
non-compliance with the environmental criteria and complaints; and
·
Requirements
for presentation of environmental monitoring and audit data and appropriate
reporting procedures.
Engineer or Engineer’s Representative (ER)
·
Supervise
the Contractor’s activities and ensure that the requirements in the
Environmental Permit (EP), the approved EIA Report, EM&A Manual are fully
complied with;
·
Inform
the Contractor when action is required to reduce environmental impacts in
accordance with the Event and Action Plans;
·
Participate
in joint site inspection undertaken by the ET; and
· Adhere to the procedures for carrying out
complaint investigation.
The Contractor
·
Work
within the scope of the contract and other tender conditions with respect to
environmental requirements;
· Operate and strictly adhere to the
guidelines and requirements in this EM&A programme and contract
specifications;
· Provide assistance to ET in carrying out
monitoring and auditing;
· Participate in the site inspections
undertaken by ET as required, and undertake correction actions;
· Provide information / advice to ET
regarding works activities which may contribute, or be continuing to the
generation of adverse environmental conditions;
· Submit proposals on mitigation measures in
case of exceedance of Action and Limit levels in accordance with the Event /
Action Plans;
· Implement measures to reduce impact where
Action and Limit levels are exceeded; and
· Adhere to the
procedures for carrying out complaint investigation.
Environmental Team (ET)
·
Monitor
various environmental parameters as required in this EM&A Manual;
·
Analyse
the EM&A data and review the success of EM&A programme to confirm the
adequacy of mitigation measures implemented and the validity of the EIA
predictions, and to identify any adverse environmental impacts arising;
·
Carry
out regular site inspection to investigate and audit the Contractors' site
practice, equipment and work methodologies with respect to pollution control
and environmental mitigation, and effect proactive action to pre-empt problems;
carry out ad hoc site inspections if significant environmental problems are
identified;
·
Audit
and prepare monitoring and audit reports on the environmental monitoring data
and site environmental conditions;
·
Report
on the EM&A results to the IEC, Contractor, the ER or its delegated
representative and EPD;
·
Recommend
suitable mitigation measures to the Contractor in the case of exceedance of
Action and Limit levels in accordance with the Event and Action Plans;
·
Advice
to the Contractor on environmental improvement, awareness, enhancement matters,
etc. on site;
·
Timely
submission of the EM&A report to the Project Proponent and the EPD; and
· Adhere to the procedures for carrying out
complaint investigation in accordance with Section
11.3 of this EM&A Manual.
Independent Environmental Checker (IEC)
·
Validate
and confirm the accuracy of monitoring results, appropriateness of monitoring
equipment, monitoring locations with reference to the locations of the nearby
sensitive receivers, and monitoring procedures;
·
On an
as needed basis, verify and certify the environmental acceptability of the
permanent and temporary works, relevant plans and submissions required in the
EM&A manual and/or under the EP;
·
Review
and verify the EM&A works performed by the ET (at least at monthly
intervals);
·
Carry
out random sample check and audit the monitoring activities and results (at
least at monthly intervals);
·
Conduct
random site inspection;
·
Review
the EM&A reports submitted by the ET;
·
Review
the effectiveness of environmental mitigation measures and project
environmental performance;
·
Review
the proposal on mitigation measures submitted by the Contractor in accordance
with the Event and Action Plans;
·
Check
the mitigation measures that have been recommended in the EIA and this Manual,
and ensure they are properly implemented in a timely manner, when necessary;
and
·
Adhere
to the procedures for carrying out complaint investigation, and verify
investigation results of complaint cases and the effectiveness of corrective
measures..
Monitoring Parameters
Monitoring Equipment
· 0.6 - 1.7 m3 per minute (20 - 60 standard cubic feet per minute) adjustable flow range;
· equipped with a timing / control device with ± 5 minutes accuracy for 24 hours operation;
· installed with elapsed-time meter with ± 2 minutes accuracy for 24 hours operation;
· capable of providing a minimum exposed area of 406 cm2;
· flow control accuracy: ± 2.5% deviation over 24-hour sampling period;
· equipped with a shelter to protect the filter and sampler;
· incorporated with an electronic mass flow rate controller or other equivalent devices;
· equipped with a flow recorder for continuous monitoring;
· provided with a peaked roof inlet;
· incorporated with a manometer;
· able to hold and seal the filter paper to the sampler housing at horizontal position;
· easy to change the filter; and
· capable of operating continuously for 24-hour period.
· The wind sensors shall be installed on masts at an elevated level 10m above ground so that they are clear of obstructions or turbulence caused by the buildings;
· The wind data shall be captured by a data logger. The data recorded in the data logger shall be downloaded periodically for analysis at least once a month;
· The wind data monitoring equipment shall be re-calibrated at least once every six months; and
· Wind direction should be divided into 16 sectors of 22.5 degrees each.
Laboratory Measurement / Analysis
Monitoring Location
Table 2.1 Proposed Construction Dust Monitoring Station
Monitoring Station ID |
EIA ASR ID |
Location |
CA_M1 |
A1 |
In front of Hong Kong Baptist Theological Seminary (HKBTS) Staff
& Students Quarters |
i.
at the
site boundary or such locations close to the major dust emission source;
ii. close to the air sensitive receivers as
defined in the EIAO-TM;
iii. proper position/sitting and orientation of
the monitoring equipment; and
iv. take into account the prevailing meteorological
conditions.
i.
a
horizontal platform with appropriate support to secure the samplers against
gusty wind shall be provided;
ii. two samplers shall be placed less than 2 meters
apart;
iii. the distance between the sampler and an
obstacle, such as buildings, must be at least twice the height that the
obstacle protrudes above the sampler;
iv. a minimum of 2 metres of separation from
walls, parapets and penthouses is required for rooftop samplers;
v. a minimum of 2 metres of separation from
any supporting structure, measured horizontally is required;
vi. no furnace or incinerator flue is nearby;
vii. airflow around the sampler is unrestricted;
viii. the sampler is more than 20 metres from the
dripline;
ix. any wire fence and gate, to protect the
sampler, shall not cause any obstruction during monitoring;
x. permission must be obtained to set up the
samplers and to obtain access to the monitoring stations; and
xi. a secured supply of electricity is needed
to operate the samplers.
Baseline Monitoring
Impact Monitoring
Table 2.2 Summary of Construction Dust Monitoring Programme
Monitoring Period |
Duration |
Sampling Parameter |
Frequency |
Baseline
Monitoring |
Consecutive days of at least 2 weeks before commencement of major
construction works |
1-hour TSP |
3 times per day |
Impact
Monitoring |
Throughout the construction phase |
1-hour TSP |
Event and Action Plan
Table 2.3 Action and Limit Levels for Air Quality (Construction Dust)
Parameter |
Action Level [1] |
Limit Level |
TSP
(1-hour average) |
BL
<= 384 µgm-3, AL = (BL * 1.3 + LL)/2 BL
> 384 µgm-3, AL = LL |
500
µgm-3 |
Note: [1] BL = Baseline level, AL = Action level, LL = Limit level
Table 2.4 Event and Action Plan for Air Quality (Construction Dust)
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action level being exceeded by one sampling |
1.
Identify
source, investigate the causes of complaint and propose remedial measures; 2.
Inform
Contractor, IEC and ER; 3.
Repeat
measurement to confirm finding; and 4.
Increase
monitoring frequency to daily. |
1.
Check
monitoring data submitted by ET; 2.
Check
Contractor’s working method; and 3.
Review
and advise the ET and ER on the effectiveness of the proposed remedial
measures. |
1.
Notify
Contractor. |
1.
Identify
source(s), investigate the causes of exceedance and propose remedial
measures; 2.
Implement
remedial measures; and 3.
Amend
working methods agreed with the ER as appropriate. |
Action level being exceeded by two or more
consecutive sampling |
1.
Identify
source; 2.
Inform
Contractor, IEC and ER; 3.
Advise
the Contractor and ER on the effectiveness of the proposed remedial measures; 4.
Repeat
measurements to confirm findings; 5.
Increase
monitoring frequency to daily; 6.
Discuss
with IEC and Contractor on remedial actions required; 7.
If
exceedance continues, arrange meeting with Contractor, IEC and ER; and 8.
If
exceedance stops, cease additional monitoring. |
1.
Check
monitoring data submitted by ET; 2.
Check
Contractor’s working method; 3.
Discuss
with ET, ER and Contractor on possible remedial measures; 4.
Advise
the ET and ER on the effectiveness of the proposed remedial measures; and 5.
Supervise
Implementation of remedial measures. |
1.
Confirm
receipt of notification of exceedance in writing; 2.
Notify
Contractor; 3.
Ensure
remedial measures properly implemented. |
1.
Identify
source and investigate the causes of exceedance; 2.
Submit
proposals for remedial measures to the ER with a copy to ET and IEC within
three working days of notification; 3.
Implement
the agreed proposals; and 4.
Amend
proposal as appropriate. |
Limit level being exceeded by one sampling |
1.
Identify
source, investigate the causes of exceedance and propose remedial measures; 2.
Inform
Contractor, IEC, ER, and EPD; 3.
Repeat
measurement to confirm finding; 4.
Increase
monitoring frequency to daily; and 5.
Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results. |
1.
Check
monitoring data submitted by ET; 2.
Check
Contractor’s working method; 3.
Discuss
with ET and Contractor on possible remedial measures; 4.
Advise
the ER on the effectiveness of the proposed remedial measures; and 5.
Supervise
implementation of remedial measures. |
1.
Confirm
receipt of notification of exceedance in writing; 2.
Notify
Contractor; 3.
Ensure
remedial measures properly implemented. |
1.
Identify
source(s) and investigate the causes of exceedance; 2.
Take
immediate action to avoid further exceedance; 3.
Submit
proposals for remedial measures to ER with a copy to ET and IEC within three
working days of notification; 4.
Implement
the agreed proposals; and 5.
Amend
proposal if appropriate. |
Limit level being exceeded by two or more
consecutive sampling |
1.
Notify
IEC, ER, Contractor and EPD; 2.
Identify
source; 3.
Repeat
measurement to confirm findings; 4.
Increase
monitoring frequency to daily; 5.
Carry
out analysis of Contractor’s working procedures to determine possible
mitigation to be implemented; 6.
Arrange
meeting with IEC and ER to discuss the remedial actions to be taken; 7.
Assess
effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER
informed of the results; and 8.
If
exceedance stops, cease additional monitoring. |
1.
Check
monitoring data submitted by the ET; 2.
Discuss
amongst ER, ET, and Contractor on the potential remedial actions; 3.
Review
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise the ER accordingly; and 4.
Supervise
the implementation of remedial measures. |
1.
Confirm
receipt of notification of exceedance in writing; 2.
In
consultation with the ET and IEC, agree with the Contractor on the remedial
measures to be implemented; 3.
Supervise
the implementation of remedial measures; and 4.
If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated. |
1.
Identify
source(s) and investigate the causes of exceedance; 2.
Take
immediate action to avoid further exceedance; 3.
Submit
proposals for remedial measures to the ER with a copy to the IEC and ET
within three working days of notification; 4.
Implement
the agreed proposals; 5.
Revise
and resubmit proposals if problem still not under control; and 6.
Stop
the relevant portion of works as determined by the ER until the exceedance is
abated. |
Prior to SPS Operation
· Data logger (to allow the instrument to operate unattended);
· Interface cable and interface software; and
· Data download and graphics services.
Upon SPS Operation
· Participate in a set of screening tests
using a certified n-butanol gas with their individual thresholds (n-butanol)
complied with the requirement of European Standard Method (EN13725) in the
range of 20 to 80 ppb with a R value of <2.3 within 2 weeks before
commencement of the odour sampling;
· Be at least 18 years of age and have
experience in olfactometry analysis for at least two odour sampling projects;
· Be free from any respiratory illnesses and
do not normally work near the Project;
· Not be allowed to smoke, eat, drink (except
water) or use chewing gum or sweets 30 minutes before and during olfactometry
analysis;
· Take great care not to cause any
interference with their own perception or that of others by lack of personal
hygiene or the use of perfumes, deodorants, body lotions or cosmetics;
· Not communicate with each other about the
results of their choices; and
· Calibrated their noses within 2 weeks before the olfactometry analysis.
· Have their individual odour threshold of n-butanol in nitrogen gas in the range of 20 to 80 ppb/v required by the European Standard Method (EN 13725);
· Be at least 16 years of age and willing and able to follow instructions;
· Be free from any respiratory illnesses;
· Be engaged for a sufficient period to build up and monitor/detect at several monitoring location;
· Not be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30 minutes before and during odour patrol;
· Take great care not to cause any interference with their own perception or that of others by lack of personal hygiene or the use of perfumes, deodorants, body lotions or cosmetics; and
· Not communicate with each other about the results of their choices.
Table 2.5 Odour Intensity Levels
Level |
Odour Intensity |
0 |
Not detected. No odour
perceived or an odour so weak that it cannot be easily characterised or
described |
1 |
Slight identifiable odour, and slight chance to have odour nuisance |
2 |
Moderate identifiable odour, and moderate chance to have odour
nuisance |
3 |
Strong identifiable, likely to have odour nuisance |
4 |
Extreme severe odour, and unacceptable odour level |
Table 2.6 Action and Limit Levels for Air Quality (Odour)
Parameter |
Action Level |
Limit Level |
Odour Nuisance |
Odour
intensity of 2 is measured from odour patrol |
Odour
intensity of 3 or above is measured from odour patrol |
Table 2.7 Event and Action Plan for Air Quality (Odour)
EVENT |
ACTION |
|
Person-in-charge of Odour Patrol |
Operator |
|
ACTION
LEVEL |
||
Action level from Odour Patrol
is reached |
1. Identify source / reason of exceedance; 2. Repeat odour patrol to confirm finding |
1. Carry out investigation to identify the source/reason of exceedance; 2. Rectify any unacceptable practice; 3. Implement further mitigation measures if necessary. |
LIMIT
LEVEL |
||
Limit level from Odour Patrol is reached |
1. Identify source / reason of non-compliance; 2. Repeat odour patrol to confirm findings; 3. Assess effectiveness of remedial action and keep EPD informed of the results |
1. Carry out investigation to identify the source/reason of non-compliance; 2. Rectify any unacceptable practice; 3. Amended working methods if required; 4. Formulate remedial actions; 5. Ensure amended working methods and remedial actions properly implemented; 6. If non-compliance continues, consider what portion of the work is responsible and stop that portion of the work until the non-compliance is abated; and 7. Correspond to the complainant within 10 days to inform the cause of the nuisance and action taken. |
Table 3.1 Proposed Noise
Monitoring Stations during Construction of the Project
Noise
Monitoring Point |
Location |
CN_M1 |
In front of the HKBTS Staff
& Students Quarters |
CN_M2 |
In front of the HKBTS
Administration and Education Block |
i. at locations close to the major site activities which are likely to have noise impacts;
ii. close to the NSRs; and
iii. for monitoring locations located in the vicinity of the sensitive receivers, care shall be taken to cause minimal disturbance to the occupants during monitoring
Table 3.2 Action and Limit Levels for Construction Noise
Time Period |
Action Level |
Limit Level |
0700
– 1900 hours |
When
one documented complaint is received |
75 dB(A) for residential premises; |
70 dB(A) for schools and 65 dB(A) during
school examination periods |
Notes:
· If works are to be carried out during restricted hours and/or percussive piling is be carried out, the monitoring requirements and the conditions stipulated in the Construction Noise Permit (CNP) issued by the Noise Control Authority have to be followed.
Table 3.3 Event and Action
Plan for Construction Noise
Event |
Action |
|||
ET |
IEC |
ER |
Contractor |
|
Action Level |
1.
Notify IEC and Contractor; 2.
Carry out investigation; 3.
Report the results of investigation to the
IEC, ER and Contractor; 4.
Discuss with the Contractor and formulate
remedial measures; and 5.
Increase monitoring frequency to check
mitigation effectiveness. |
1.
Review the analyzed results submitted by the
ET; 2.
Review the proposed remedial measures by the
Contractor and advise the ER accordingly; and 3.
Supervise the implementation of remedial
measures. |
1.
Confirm receipt of notification of failure in
writing; 2.
Notify Contractor; 3.
Require Contractor to propose remedial
measures for the analyzed noise problem; and 4.
Ensure remedial measures are properly
implemented. |
1.
Submit noise mitigation proposals to IEC, ET
and ER; and 2.
Implement noise mitigation proposals. |
Limit Level |
1.
Identify source; 2.
Inform IEC, ER, EPD and Contractor; 3.
Repeat measurements to confirm findings; 4.
Increase monitoring frequency; 5.
Carry out analysis of Contractor’s working
procedures to determine possible mitigation to be implemented; 6.
Inform IEC, ER and EPD the causes and actions taken for the
exceedances; 7.
Assess effectiveness of Contractor’s remedial
actions and keep IEC, EPD and
ER informed of the results; and 8.
If exceedance stops, cease additional
monitoring. |
1.
Discuss amongst ER, ET, and Contractor on the
potential remedial actions; 2.
Review Contractors remedial actions whenever
necessary to assure their effectiveness and advise the ER accordingly; and 3.
Supervise the implementation of remedial
measures. |
1. Confirm
receipt of notification of failure in writing; 2. Notify
Contractor; 3. Require
Contractor to propose remedial measures for the analyzed noise problem; 4. Ensure
remedial measures properly implemented; and 5. If
exceedance continues, consider what portion of the work is responsible and
instruct the Contractor to stop that portion of work until the exceedance is
abated. |
1.
Take immediate action to avoid further
exceedance; 2.
Submit proposals for remedial actions to IEC within 3 working
days of notification; 3.
Implement the agreed proposals; 4.
Resubmit proposals if problem still not under
control; and 5.
Stop the relevant portion of works as
determined by the ER until the exceedance is abated. |
Construction Phase
Operational Phase
·
to check the status of the Landscape Resources and
Character Areas within the construction works sites and works areas and the
Visually Sensitive Receivers (VSRs) within the visual envelope;
·
to determine whether any change has occurred to the
status of the Landscape Resources, Character Areas and VSRs since the EIA;
·
to determine whether such change warrants a change
in the design of the landscape and visual mitigation measures; and
·
to recommend any necessary changes to the
recommended landscape and visual mitigation measures in the EIA.
Table 9.1 Landscape and Visual Impacts Mitigation Measures for Construction Phase
ID No. |
Landscape and Visual Mitigation Measures |
Funding Agency |
Implementation Agency |
CM1 |
Preservation of Trees Trees
to be retained in accordance with DEVB TCW No. 4/2020 - Tree Preservation. |
Project Proponent |
Project Proponent via Contractor |
CM2 |
Compensatory Tree
Planting Any Trees to be
felled under the Project shall be compensated in accordance with DEVB TCW No.
4/2020 - Tree Preservation. |
Project Proponent |
Project Proponent via Contractor |
CM3 |
Control of Night-time
Lighting Glare Any lighting
provision of the construction works at night shall be carefully controlled to
prevent light overspill to the nearby VSRs and into the sky in accordance
with “Charter of External Lighting” and “Guidelines on Industry Best
Practices for External Lighting Installations” promulgated by ENB. |
Project Proponent |
Project Proponent via Contractor |
CM4 |
Erection of Decorative
Screen Hoarding Decorative
Hoarding, which is compatible with the surrounding settings, shall be erected
during construction to minimise the potential landscape and visual impacts
due to the construction works and activities.
|
Project Proponent |
Project Proponent via Contractor |
CM5 |
Management of
Construction Activities and Facilities The facilities
and activities at works sites and areas, which include site office, temporary
storage areas, temporary works etc., shall be carefully managed and
controlled on the height, deposition and arrangement to minimise any
potential adverse landscape and visual impacts. |
Project Proponent |
Project Proponent via Contractor |
CM6 |
Reinstatement of
Temporarily Disturbed Landscape Areas All hard and soft landscape areas
disturbed temporarily during construction due to temporary excavations, temporary
works sites and works areas shall be reinstated to equal or better quality,
to the satisfaction of the relevant government departments. |
Project Proponent |
Project Proponent via Contractor |
Table 9.2 Landscape and Visual Impacts Mitigation Measures for Operational Phase
ID No. |
Landscape and Visual Mitigation Measures |
Funding Agency |
Implementation Agency |
Maintenance/ Management Agency |
OM1 |
Tree and Shrub Planting
to soften the proposed SPS Tree and shrub planting shall be proposed
to soften the proposed SPS and enhance the landscape and visual amenity of
the Project. |
Project Proponent |
Project Proponent |
Project Proponent |
OM2 |
Aesthetically pleasing
design of the SPS The design of the proposed SPS in the
regard of layouts, forms, materials and finishes shall be sensitively
designed so as to blend in the structures to the adjacent landscape and
visual context. |
Project Proponent |
Project Proponent |
Project Proponent |
OM3 |
Provision of Green Roof
Green Roof shall be proposed to enhance
the landscape quality of the proposed SPS and mitigate any potential adverse
visual impact on adjacent VSRs. |
Project Proponent |
Project Proponent |
Project Proponent |
OM4 |
Provision of Vertical
Greening Self-climbing species shall be proposed at metal fence wall to soften
the proposed SPS and enhance the landscape and visual amenity of the Project. |
Project Proponent |
Project Proponent |
Project Proponent |
* Remarks: The arrangement of maintenance /
management agencies is subject to agreement with corresponding departments /
parties in accordance with DEVB TCW No. 6 / 2015.
· the EIA and EM&A recommendations on environmental protection and pollution control mitigation measures;
· ongoing results of the EM&A program;
· works progress and programme;
· individual works methodology proposals (which shall include proposal on associated pollution control measures);
· the contract specifications on environmental protection;
· the relevant environmental protection and pollution control laws; and
· previous site inspection results undertaken by the ET and others.
· log complaint and date of receipt onto the complaint database and inform the IEC immediately;
· investigate the complaint to determine its validity, and to assess whether the source of the problem is due to project works;
· if a complaint is valid and due to project works, identify mitigation measures in consultation with the IEC;
· if mitigation measures are required, advise the Contractor accordingly;
· review the Contractor’s response to the identified mitigation measures, and the updated situation;
· if the complaint is a referral from EPD, submit interim report to EPD on status of the complaint investigation and follow-up action within the time frame assigned by EPD;
· undertake additional monitoring and audit to verify the complaint if necessary, and review that any valid reason for complaint does not recur;
· Report the investigation results and the subsequent actions to the complainant (If the source of complain is identified through EPD, the result should be reported within the time frame assigned by EPD); and
· Record the complaint, investigation, the subsequent actions and the results in the monthly EM&A reports.
i.
up to
half a page executive summary;
ii.
brief
project background information;
iii.
drawings
showing locations of the baseline monitoring stations;
iv.
an
updated construction programme with milestones of environmental protection /
mitigation activities annotated;
v.
monitoring
results (in both hard and soft copies) together with the following information:
· monitoring methodology;
· name of laboratory and types of equipment
used and calibration details;
· parameters monitored;
· monitoring locations (and depth);
· monitoring date, time, frequency and
duration; and
· quality assurance (QA) / quality control (QC)
results and detection limits.
vi.
details
on influencing factors, including:
· major activities, if any, being carried out
on the site during the period;
· weather conditions during the period; and
· other factors which might affect results.
vii.
determination
of the Action and Limit Levels (AL levels) for each monitoring parameter and
statistical analysis of the baseline data, the analysis shall conclude if there
is any significant difference between control and impact stations for the
parameters monitored;
viii.
revisions
for inclusion in the EM&A Manual; and
ix.
comments,
recommendations and conclusions.
i.
executive
summary (1-2 pages):
· breaches of AL levels;
· complaint log;
· notifications of any summons and successful
prosecutions;
· reporting changes; and
· future key issues.
ii.
basic
project information:
· project organisation including key
personnel contact names and telephone numbers;
· construction programme with fine tuning of
construction activities showing the inter-relationship with environmental
protection/mitigation measures for the month;
· management structure, and
· works undertaken during the reporting month.
iii.
environmental
status:
· works undertaken during the month with
illustrations (such as location of works, daily dredging/filling rates,
percentage of fines in the fill materials used, etc.); and
· drawings showing the project area, any
environmental sensitive receivers and the locations of the monitoring and
control stations (with co-ordinates of the monitoring locations).
iv.
a
brief summary of EM&A requirements including:
· all monitoring parameters;
· environmental quality performance limits
(AL levels);
· Event-Action Plans;
· environmental mitigation measures, as
recommended in the Final EIA report; and
· environmental requirements in contract
documents.
v.
implementation status:
· advice on the implementation status of environmental
protection and pollution control / mitigation measures, as recommended in the
Final EIA report.
vi.
monitoring
results (in both hard and soft copies) together with the following information:
· monitoring methodology;
· name of laboratory and types of equipment
used and calibration details;
· monitoring parameters;
· monitoring locations;
· monitoring date, time, frequency, and
duration;
· weather conditions during the period;
· graphical plots of the monitored parameters;
· major activities being carried out on site
during the period;
· any other factors which might affect the
monitoring results; and
· QA / QC results and detection limits.
vii.
report
on non-compliance, complaints, notifications of summons and successful
prosecutions:
· record of all non-compliance (exceedances)
of the environmental quality performance limits (AL levels);
· record of all complaints received (written
or verbal) including locations and nature of complaints investigation, liaison
and consultation undertaken, actions and follow-up procedures taken, results
and summary;
· record of all notification of summons and
successful prosecutions for breaches of current environmental protection /
pollution control legislations, including locations and nature of the breaches,
investigation, follow-up actions taken, results and summary;
· review of the reasons for and the
implications of non-compliance, complaints, summons and prosecutions including
review of pollution sources and working procedures; and
· description of the actions taken in the
event of non-compliance and deficiency reporting and any follow-up procedures
related to earlier non-compliance.
viii.
others:
· an account of the future key issues as
reviewed from the works programme and work method statements;
· advice on the solid and liquid waste
management status;
· a forecast of the works programme, impact
predictions and monitoring schedule for the next reporting month;
· compare and contrast the EM&A data with
the EIA predictions and annotate with explanation for any discrepancies; and
· comments (for examples, effectiveness and
efficiency of the mitigation measures), recommendations (for example, any
improvement in the EM&A programme) and conclusions.
i.
executive
summary (1 - 2 pages):
· breaches of AL levels;
· complaints log;
· notifications of any summons and successful
prosecutions;
· reporting changes; and
· future key issues.
Basic project information:
· project organisation and management
structure;
· construction programme; and
· works undertaken during the reporting month.
ii.
environmental
status:
· construction programme with fine tuning of
construction activities showing the inter-relationship with environmental
protection / mitigation measures for the month;
· works undertaken during the reporting month
with illustrations (e.g. location of
works, etc.); and
· drawing showing the project area, any
environmental sensitive receivers and the locations of the monitoring stations.
iii.
implementation
status:
· advice on the implementation status of
environmental protection and pollution control / mitigation measures, as
recommended in the Final EIA report, summarised in the updated implementation
schedule.
iv.
monitoring
results (in both hard and diskette copies) together with the following
information:
· monitoring methodology;
· name of laboratory and types of equipment
used and calibration details;
· parameters monitored;
· monitoring locations (and depth);
· monitoring date, time, frequency, and
duration;
· weather conditions during the period;
· graphical plots of the monitored parameters
in the reporting month;
· major activities being carried out on site
during the period;
· any other factors which might affect the monitoring
results; and
· QA / QC results and detection limits.
v.
report
on non-compliance, complaints, and notifications of summons and successful
prosecutions:
· record of all non-compliance (exceedances)
of the environmental quality performance limits (AL levels);
· record of all complaints received (written
or verbal) including locations and nature of complaints investigation, liaison
and consultation undertaken, actions and follow-up procedures taken, results
and summary;
· record of all notification of summons and
successful prosecutions for breaches of current environmental protection /
pollution control legislations, including locations and nature of the breaches,
investigation, follow-up actions taken, results and summary;
· review of the reasons for and the implications
of non-compliance, complaints, summons and prosecutions including review of
pollution sources and working procedures; and
· description of the actions taken in the
event of non-compliance and deficiency reporting and any follow-up procedures
related to earlier non-compliance.
vi.
others:
· an account of the future key issues as
reviewed from the works programme and work method statements;
· advice on the solid and liquid waste
management status;
· a forecast of the works programme, impact
predictions and monitoring schedule for the next reporting months;
· compare and contrast the EM&A data with
the EIA predictions and annotate with explanation for any discrepancies; and
· comments (for examples, effectiveness and
efficiency of the mitigation measures), recommendations (for example, any
improvement in the EM&A programme) and conclusions.
vii.
appendix
· Action and Limit levels;
· graphical plots of trends of monitored
parameters at key stations over the past four reporting periods for
representative monitoring stations annotated against the following:
-
major
activities being carried out on site during the period;
-
weather
conditions during the period; and
-
any
other factors that might affect the monitoring results.
· cumulative statistics on complaints,
notifications of summons and successful prosecutions;
· outstanding issues and deficiencies
i.
executive
summary (1 - 2 pages);
ii.
basic
project information including a synopsis of the project organisation, contacts
of key management, and a synopsis of work undertaken during the course of the
project;
iii.
a
brief summary of EM&A requirements including:
· monitoring parameters;
· environmental quality performance limits
(AL levels); and
· environmental mitigation measures, as
recommended in the Final EIA report.
iv.
A
summary of the implementation status of environmental protection and pollution
control / mitigation measures,
as recommended in the Final EIA report, summarised in the updated
implementation status proformas;
v.
drawings
showing the project area, environmental sensitive receivers and the locations of the monitoring stations;
vi.
graphical
plots of the trends of monitored parameters over the course of the project for
all monitoring stations annotated against:
·
the
major activities being carried out on site during the period;
·
weather
conditions during the period; and
·
any
other factors which might affect the monitoring results.
vii.
a
summary of non-compliance (exceedances) of the environmental quality
performance limits (AL levels);
viii.
a
brief review of the reasons for and the implications of
non-compliance including review of pollution sources and working procedures;
ix.
a
summary description of the
actions taken in the event of non-compliance and any follow-up procedures
related to earlier non-compliance;
x.
a
summary record of all complaints received (written or verbal) for each media,
liaison and consultation undertaken, actions and follow-up procedures taken;
xi.
review
monitoring methodology adopted and with the benefit of hindsight, comment on
its effectiveness (including cost effectiveness);
xii.
a
summary record of notifications of summons and successful prosecutions for breaches
of the current environmental protection/pollution control legislations,
locations and nature of breaches, investigation, follow-up actions taken and
results;
xiii.
review
the practicality and effectiveness of the EIA process and EM&A programme
(for examples, a review of the effectiveness and efficiency of the mitigation
measures and the performance of the environmental management system, that is,
of the overall EM&A programme), recommendations (for example, any
improvement in the EM&A programme); and
xiv. a conclusion to state the return of ambient and / or the predicted scenario as per EIA findings.
i. Executive summary (1-2 pages):
ii. Basic project information including a
synopsis of the project organisation, contacts of key management, and a
synopsis of work undertaken during the course of the project or past twelve
months;
iii. A brief summary of EM&A requirements
including:
·
environmental
mitigation measures for operation stage, as recommended in the project EIA
Report;
·
environmental
impact hypotheses tested;
·
environmental
quality performance limits (Action and Limit levels);
·
all
monitoring parameters;
·
Event
and Action Plans;
iv. A summary of the implementation status of
environmental protection and pollution control / mitigation measures for
operation stage, as recommended in the project EIA Report and summarised in the
updated implementation schedule;
v. drawings showing the project area,
environmental sensitive receivers and the locations of the monitoring stations;
vi. Graphical plots and the statistical
analysis of the trends of monitoring parameters over the course of the project,
including:
·
the
major activities being carried out on site during the period;
·
weather
conditions during the period; and
·
any
other factors which might
affect the monitoring results;
vii.
A
summary of non-compliance (exceedances) of the environmental quality
performance limits (Action and Limit levels);
viii.
A
review of the reasons for and the implications of non-compliance including
review of pollution sources and working procedures as appropriate;
ix.
A
description of the actions taken in the event of non-compliance;
x.
A
summary record of all complaints received (written or verbal) for each media,
liaison and consultation undertaken, actions and follow-up actions taken and
results;
xi.
A
review of the validity of EIA predictions for operation stage and
identification of shortcomings in EIA recommendations;
xii.
Comments
(for example, a review of the effectiveness and efficiency of the mitigation
measures, the performance of the environmental management system, and the
overall EM&A programme for operation stage); and
xiii.
Recommendations
and conclusions (for example, a review of success of the overall EM&A
programme for operational stage to cost-effectively identify deterioration and
to initiate prompt effective mitigatory action when necessary).