TABLE OF CONTENTS

 

1          INTRODUCTION. 1-1

1.1              Project Background. 1-1

1.2              Purpose, Objective and Benefits of the Project 1-2

1.3              Designated Projects. 1-3

1.4              Material Changes to Exempted Designated Project 1-4

1.5              Individual Work Not Constitute Material Change to an Environmental Impact 1-4

1.6              Purpose of the EIA Study. 1-4

1.7              Objectives of the EIA Study. 1-5

1.8              Need of the Project 1-7

1.9              Scenario “with” and “without” Project 1-7

1.10            Consequences of Not Proceeding with the Project 1-9

1.11            Implementation Programme. 1-9

1.12            Concurrent Projects. 1-9

1.13            Structure of the EIA Report 1-12

 

List of Tables

 

Table 1.1 Summary of the Other Projects in the Vicinity of the Project Site

 

List of Figures

 

Figure 1.1

Location Plan of The Project

Figure 1.2

Location of Concurrent Projects

 

 

 

 

                                                                                                                                                                       


1                      INTRODUCTION

1.1                  Project Background

1.1.1              The title of the Project is “Revised Trunk Road T4 in Sha Tin” (hereafter referred to as the Project).

1.1.2              The proposed Revised Trunk Road T4 is part of the strategic road network connecting Sha Tin Road with Tsing Sha Highway (TSH) and Shing Mun Tunnel Road (SMTR).  Traffic between Ma On Shan area and Tsuen Wan / West Kowloon areas have to travel through Tai Po Road (Sha Tin Section) (TPR-ST) and other local roads in Sha Tin area currently.  The Project, as a strategic route, would serve as a bypass route providing a direct connection for through traffic between Ma On Shan area and Tsuen Wan / West Kowloon areas without the need of travelling along the existing major roads in Sha Tin Central, for example, TPR-ST, Tai Chung Kiu Road, etc., which are already very busy especially in peak hours.  The Project will not only help to relieve traffic congestion on TPR-ST and other major roads in Sha Tin area but it also improve the capacity of major local road junctions by directing traffic between Ma On Shan area and Tsuen Wan / West Kowloon areas away from the local road network.

1.1.3              An Environmental Impact Assessment (EIA) Study Brief for the Trunk Road T4 project (Study Brief No. ESB-094/2001) was issued in January 2002 by the Director of Environmental Protection in respect of a previous road alignment option. Based on this study brief, the EIA report for Trunk Road T4 (EIA Report No. AEIAR-084/2005) was approved by Environmental Protection Department (EPD) under the Environmental Impact Assessment Ordinance (EIAO) in May 2005. 

1.1.4              In October 2006, upon receipt of support from the Traffic and Transport Committee (T&TC) of the Sha Tin District Council (STDC), Trunk Road T4 was gazetted under the Roads (Works, Use and Compensation) Ordinance.  However, during the objection period, considerable number of public objections to the gazetted scheme were received.  In view of the substantial received objections, the originally proposed alignment was not adopted.  STDC T&TC withdrew the support on the Trunk Road T4 project and passed the motions that the Government should monitor and review the traffic condition of Sha Tin area after the commissioning of Tsing Sha Highway to determine whether Trunk Road T4 is still needed.  The Trunk Road T4 project was therefore put on hold.

1.1.5              In March 2016, CEDD appointed a consultant to carry out a traffic review study under Agreement No. CE 71/2015 (HY) Traffic Study on Major Roads in Sha Tin – Feasibility Study to review the traffic situations in Sha Tin, identify the traffic problems and recommend mitigation measures.  The feasibility study recommended, amongst other things, that Trunk Road T4 should be regarded as a medium-term measure to relieve traffic congestion in Sha Tin.  To address the objections received during previous gazettal, an alternative alignment of Trunk Road T4 (“Revised Trunk Road T4”) is proposed, under which the eastbound viaducts will be shifted away from the Scenery Court avoiding the conflict with existing Old and Valuable Trees (OVTs) along Chung Ling Road and the originally proposed viaducts in front of Sha Tin Tau Village (as well as the Riverpark, which did not exist during previous gazettal) will be converted to depressed roads and underpass.  In January 2018, STDC T&TC gave the support on the Revised Trunk Road T4 scheme.  The location plan of the Project is shown in Figure 1.1.

1.1.6              Due to the major changes in road alignment, revision in form of structures, provision of additional slip roads, introduction of new sensitive receivers and new assessment requirements on the Revised Trunk Road T4 scheme, the findings and recommendations in the EIA Report (Report No. AEIAR-084/2005) are no longer valid. Therefore, it is considered a fresh EIA study for the Revised Trunk Road T4 will be required.


 

1.2                  Purpose, Objective and Benefits of the Project

1.2.1              The Project is designed to provide a direct connection for through traffic between Ma On Shan area and Tsuen Wan / West Kowloon areas bypassing the busy at-grade road network of Sha Tin Central.  Road users can be benefited from this direct connection route travelling between different districts such as Tai Wai, Ma On Shan, Tsuen Wan and West Kowloon etc.  It is also identified as a medium-term mitigation measure to alleviate the traffic congestion in Sha Tin District, in particular, Tai Po Road (Sha Tin Section) and some major road junctions.

1.2.2              The scope of the Project mainly comprises:

·         Construction of dual two-lane elevated carriageways of approximately 1.4km long connecting Shing Mun Tunnel Road and Tsing Sha Highway to the proposed at-grade carriageways fronting the Riverpark;

·         Construction of dual two-lane at-grade carriageways and underpasses of approximately 600m long between the Riverpark and Tsang Tai Uk;

·         Construction of a slip road of approximately 80m long near the Riverpark connecting at-grade carriageway northbound and Lion Rock Tunnel Road northbound across Shing Mun River Channel;

·         Construction of a slip road of approximately 300m long near Tsang Tai Uk connecting Lion Rock Tunnel Road southbound and Sha Tin Road eastbound;

·         Widening of a section of Sha Tin Road of approximately 150m long from a dual two-lane carriageway to a dual four-lane carriageway;

·         Modification of a section of the elevated carriageway of Shing Mun Tunnel Road eastbound near Chung Ling Lane of approximately 200m long to provide extra space for improved merging of traffic;

·         Modification and realignment of a section of Tung Lo Wan Hill Road, Chung Ling Road, Chung Ling Lane, Tai Po Road (Tai Wai Section), Shing Chuen Road, Shing Wan Road, Man Lam Road and Man Lai Road;

·         Construction of an at-grade and an elevated footpath of approximately 50m long across the proposed underpass near Sha Tin Tau Village;

·         Construction of an elevated cycle track and an elevated footpath of approximately 100m long across Shing Mun River Channel;

·         Demolition of the existing subways across Lion Rock Tunnel Road fronting the Riverpark and construction of an elevated cycle track and an elevated footpath with lifts and staircases across Lion Rock Tunnel Road fronting the Riverpark;

·         Demolition of the existing pedestrian subway across Che Kung Miu Road and Lion Rock Tunnel near MTR Che Kung Temple Station and construction of an elevated footpath with lifts and staircases across Che Kung Miu Road;

·         Ancillary works including geotechnical, drainage, sewerage, water, utilities, lighting, landscaping, electrical and mechanical works, construction/reconstruction of noise barriers, retaining walls, slope improvement, mitigation works for natural terrain hazard near Shing Mun Tunnel Road and within Lion Rock Country Park and installation of street furniture and traffic aids; and

·         Modification of Existing Noise Barrier/Enclosure at Tsing Sha Highway (Trunk Road T3).

 


 

1.3                  Designated Projects

1.3.1              A Project Profile (No. PP-578/2019) was submitted to the EPD on 21 March 2019 for application for an EIA Study Brief under section 5(7)(a) of the EIAO and the EIA Study Brief No. ESB-315/2019 for the Project was issued on 24 April 2019 under the EIAO.

1.3.2              The Project comprises the following which are classified as a Designated Project (DP) under Part I, Schedule 2 of the EIAO:

1.3.3              Item A.1 - A road which is an expressway, trunk road, primary distributor road or district distributor road including new roads, and major extensions or improvements to existing roads

The new road sections under the Revised Trunk Road T4 comprise of expressway, trunk road and primary distributor road.  Besides, the following items under the scope of works also constitute a DP item under A.1:

·         Construction of a slip road near the Riverpark connecting at-grade carriageway northbound and the existing northbound of Lion Rock Tunnel Road (between Tai Po Road – Tai Wai and Che Kung Miu Road) crossing Shing Mun River Channel via Lion Bridge which is a primary distributor road (PD);

·         Construction of a slip road near Tsang Tai Uk connecting existing at-grade carriageway of Lion Rock Tunnel Road southbound which is a primary distributor road (PD) to Sha Tin Road eastbound;

·         Widening of a section of Sha Tin Road fronting Pok Hong Estate which is an expressway; and

·         Modification of a section of the elevated carriageway of Shing Mun Tunnel Road eastbound near Chung Ling Lane which is an urban trunk road (UT).

1.3.4              Item A.8 - A road or railway bridge more than 100 m in length between abutments

The construction of dual two-lane elevated carriageways which is approximately 1.4km long connecting Shing Mun Tunnel Road and Tsing Sha Highway across Shing Mun River Channel to the proposed at-grade carriageways fronting the Riverpark and hence is a DP under Item A.8 of Schedule 2, Part 1 of the EIAO.

1.3.5              Item Q.1 - All projects including new access roads, railways, sewers, sewage treatment facilities, earthworks, dredging works and other building works partly or wholly in an existing country park

Additional traffic lanes of the depressed road section of the Revised Trunk Road T4(EB) & (WB) and the proposed slip road SR6-1 will be merged with existing carriageway of Sha Tin Road. As such, existing slope along Sha Tin Road is required to set back from the carriageway in order to accommodate the additional traffic lanes sandwiched between Pok Hong Estate at the north and Lion Rock Country Park at the south.  Natural terrain hazard mitigation works including the erection of rigid and flexible barriers etc. are necessary to enhance the stability of the existing natural slopes in order to protect road users along Sha Tin Road when the Project is in operation. As some of the natural terrain hazard mitigation works will be carried out within the catchment of the affected slope where they are situated within the boundary of Lion Rock Country Park, such natural terrain hazard mitigation works fall within the meaning of Item Q.1 of Schedule 2, Part 1 of the EIAO.


 

1.4                  Material Changes to Exempted Designated Project

1.4.1              The EIA Ordinance comes into operation on 1 April 1998.  Since Shing Mun River Channel (SMRC) has been completed before the EIA Ordinance was in force, SMRC is classified as an exempted DP under Item I.1(a), Part I, Schedule 2 of the EIAO.  It is confirmed that the Project will not have changes to the SMRC that may constitute material changes with following explanation.

1.4.2              No river training or diversion works is required at SMRC for the construction of the Revised Trunk Road T4 vehicular bridges and an elevated cycle track and an elevated footpath across SMRC.  The works at SMRC includes construction of a new bridge piers in bullet shape which will be placed aligning to the existing piers of the Lion Bridge, in order to minimize the impediment of water flow at SMRC. With reference to Section 3 to Section 10, with the implementation of the proposed environmental mitigation measures during construction and operation phase of the Project, adverse environmental impacts are not anticipated.  Thus, it is confirmed that such construction activities will not constitute material changes which are defined in Section 6.1 of the EIAO-TM, to an exempted DP. 

 

1.5                  Individual Work Not Constitute Material Change to an Environmental Impact

1.5.1              In accordance with Section 6.2 of the EIAO-TM, the environmental impact of a designated project, for which an environmental permit has been issued, is considered to be materially changed if the environmental performance requirements set out in the EIA report for the project may be exceeded or violated even with the mitigation measures in place.  The elevated section of Tsing Sha Highway (Trunk Road T3) between Mei Tin Road and Lion Rock Tunnel Road is an urban trunk road. Being a designated project under Part I of Schedule 2 of the EIAO, it is controlled by an existing environmental permit (No. EP-135/2002/J) for construction and operation.

1.5.2              To facilitate the construction of the T4, the following changes to the existing noise barriers and/or semi-noise enclosure at Tsing Sha Highway is required. The potential environmental impacts during both construction and operation phases due to the following changes have been reviewed and addressed in this EIA report. Based on the findings described in Section 3 and Section 4 for air quality assessment and noise impact assessment respectively, potential air quality and noise impacts due to the following changes to the existing noise mitigation measures at Tsing Sha Highway are not expected to be adverse.  Besides, no other adverse environmental impacts would be anticipated.  Hence, according to Section 6.2 of the EIAO-TM, the following changes to the existing noise mitigation measures would not constitute a material change to the environmental impact of the Tsing Sha Highway.

·         Temporary removal of a 5m vertical noise barrier of approximately 10m in length;

·         Temporary removal of a 6m vertical noise barrier of approximately 5m in length;

·         Temporary removal of a 5.8m with 3m cantilever noise barrier of approximately 20m in length;

·         Temporary removal of a semi-enclosure of approximately 55m in length;

·         Permanent removal of a 3m vertical noise barrier of approximately 60m in length.

 

1.6                  Purpose of the EIA Study

1.6.1              The purpose of the EIA study is to provide information on the nature and extent of environmental impacts arising from the construction and operation of the Project and the associated works that take place concurrently.  This information will contribute to decisions on:

·         the overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project;

·         the conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences wherever practicable; and

·         the acceptability of residual impacts after the proposed mitigation measures are implemented.

1.7                  Objectives of the EIA Study

1.7.1              The objectives of the EIA study as defined in Section 2 of the EIA Study Brief are as follows:

(i)         to describe the Project and associated works together with the requirements and environmental benefits for carrying out the proposed Project;

(ii)        to identify and describe the elements of the community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including both the natural and man-made environment and the associated environmental constraints;

(iii)       to provide information on the consideration of alternative options of the alignment, design, layout, location, scale and extent of the Project and the construction methods with a view to avoiding or minimising potential environmental impacts to environmentally sensitive areas and sensitive uses; to compare the environmental benefits and dis-benefits of different options; to provide reasons for selecting the preferred option(s) and to describe the part environmental factors played in the selection of preferred option(s);

(iv)       to identify and quantify emission sources (including air quality, noise, water quality and waste, etc. as appropriate) and determine the significance of impacts on sensitive receivers and potential affected uses;

(v)        to identify and quantify potential waste management issues and impacts arising as a result of the construction activities of the Project;

(vi)       to identify and quantify contaminated land within any project area for development works, and to propose measures to avoid disposal in the first instance;

(vii)      to identify, assess and quantify any potential ecological impacts arising from the Project, including potential losses or damage to flora, fauna and natural habitats; and to propose measures to mitigate these impacts;

(viii)     to identify any potential landscape and visual impacts and to propose measures to mitigate these impacts;

(ix)       to identify any negative impacts on cultural heritage and to propose measures to mitigate these impacts;

(x)        to propose the provision of infrastructure or mitigation measures so as to minimise pollution, environmental disturbance and nuisance during construction and operation of the Project;

(xi)       to investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;

(xii)      to identify, predict and evaluate the residual (i.e. after practicable mitigation) environmental impacts and the cumulative effects expected to arise during the construction and operation phases of the Project in relation to the sensitive receivers and potential affected uses;

(xiii)     to identify, assess and specify methods, measures and standards, to be included in the detailed design, construction and operation of the Project which are necessary to mitigate these environmental impacts and cumulative effects and reduce them to acceptable levels;

(xiv)     to identify within the scope of the EIA study as defined in Section 3.2 of the EIA Study Brief, any individual works that constitute material change(s) to exempted project(s) or other designated projects(s) under the EIAO; to ascertain whether the EIA Study has adequately addressed the environmental impact of these change(s) to exempted project(s); and where necessary, to identify the outstanding issues that need to be addressed;

(xv)      to design and specify the environmental monitoring and audit requirements; and

(xvi)     to identify any additional studies necessary to implement the mitigation measures of monitoring and proposals recommended in the EIA report.


 

1.8                  Need of the Project

1.8.1              As described in Section 1.1, the Project is designed to provide a direct connection for through traffic between Ma On Shan area and Tsuen Wan / West Kowloon areas bypassing the busy at-grade road network of Sha Tin Central.  Road users can be benefited from this direct connection route travelling between different districts such as Tai Wai, Ma On Shan, Tsuen Wan and West Kowloon etc.  It is also identified as a medium-term mitigation measure to alleviate the traffic congestion in Sha Tin District, in particular, Tai Po Road (Sha Tin Section) and some major road junctions.

Existing Traffic Condition

1.8.2              Tai Po Road (Sha Tin Section) (TPR-ST) is a major trunk road in Sha Tin area providing direct connection for traffic from North District via Tolo Highway to West Kowloon and Tsuen Wan areas.  Heavy traffic flow and traffic congestion are observed during morning and evening peak hours in both traffic bounds of this trunk road.  From the traffic flow data collected in 2019, both traffic bounds of TPR-ST between Fo Tan Road and Sha Tin Rural Committee Road (STRCR) were observed to be under manageable degree of traffic condition during morning peak hours(Volume/Capacity (V/C)[1] ratio between 1.0 and 1.2).  Traffic condition in the evening peak hour was even worse for the TPR-ST northbound which indicates more serious congestion with traffic speed progressively deteriorating due to further increase in traffic flow (V/C ratio > 1.2).  A manageable degree of traffic condition was identified for the section of TPR-ST to the south of STRCR for both traffic bounds (V/C ratio between 1.0 and 1.2).

1.8.3              Other than TPR-ST, traffic congestions were also found during morning peak hours in Lion Rock Tunnel southbound, Tate’s Cairn Tunnel and Tai Wai Tunnel heading to the urban area of Kowloon (V/C ratio between 1.0 and 1.2).

1.8.4              Heavy traffic movements were also observed along Tai Chung Kiu Road and STRCR and their associated road junctions (J/Os) resulting traffic congestion during peak hours.  From the traffic flow data collected, the road junction of STRCR/Slip Roads of TPR-ST, the road junction of STRCR/Yuen Wo Road and the road junction of Sha Tin Wai Road/Tai Chung Kiu Road were operating with capacity problems during peak periods.

Provision of Revised Trunk Road T4

1.8.5              The Project introduces the implementation of the Revised Trunk Road T4.  Upon completion of the Revised Trunk Road T4, traffic between Ma On Shan area and Tsuen Wan / Western Kowloon areas will no longer require to pass through those congested at-grade road sections in Sha Tin area such as TPR-ST, Tai Chung Kiu Road and STRCR but can travel on a dedicated road link at design speed of 70 km/hr bypassing the at-grade road traffic of Sha Tin Central.  It can provide a direct link between the southeast to northwest vehicular movements within Sha Tin.  Thus, the journey time of traffic between Ma On Shan and Tsuen Wan / West Kowloon areas can be shortened.

1.9                  Scenario “with” and “without” Project

Scenario “without” Project

1.9.1              Without the implementation of the Project, even with the completion of Widening and Reconstruction of TPR-ST project scheduled tentatively in 2023, capacity problem is anticipated to be experienced in 2028 and beyond at the following major road links and road junctions in Sha Tin area which include:

·         Tolo Highway (between Pak Shek Kok and Ma Liu Shui)

·         Tai Po Road – Sha Tin (between Ma Liu Shui and Fo Tan)

·         Tai Po Road – Sha Tin (near Fo Tan Road)

·         Tai Po Road – Sha Tin (between Fo Tan Road and Sha Tin Rural Committee Road)

·         Tai Po Road – Sha Tin (south of Sha Tin Rural Committee Road)

·         Tate’s Cairn Highway (T6 Bridge)

·         Tate’s Cairn Highway (between T6 Bridge and Shek Mun Interchange)

·         A Kung Kok Street near Sha Tin Hospital

·         Tate’s Cairn Tunnel

·         Lion Rock Tunnel

·         Tai Wai Tunnel

·         J/O Chak Cheung Street / Slip Roads of Tolo Highway & Tate's Cairn Highway

·         J/O Chak Cheung Street / Science Park Road

·         J/O Fo Tan Road / Off Ramp from Tai Po Road - Sha Tin / Lok King Street

·         J/O Fo Tan Road / Tai Chung Kiu Road / Slip Roads of Sha Tin Road

·         J/O Sha Tin Rural Committee Road / Slip Roads of Tai Po Road - Tai Wai

·         J/O Sha Tin Rural Committee Road / Yuen Wo Road

·         J/O Sha Tin Wai Road / Tai Chung Kiu Road

·         J/O Tai Chung Kiu Road / Siu Lek Yuen Road

·         J/O Tai Chung Kiu Road / On King Street/ On Lai Street

·         J/O Lion Rock Tunnel Road / Che Kung Miu Road/ Tai Chung Kiu Road

1.9.2              The southbound of Lion Rock Tunnel (LRT) and Tate’s Cairn Tunnel (TCT) heading to Kowloon are anticipated to experience serious congestion with traffic speed progressively deteriorating with further increase in traffic during morning peak hours (V/C ratio > 1.2). 

1.9.3              Road junction of Sha Tin Rural Committee Road (STRCR) / Yuen Wo Road (YWR) and road junction of Sha Tin Wai Road (STWR) / Tai Chung Kiu Road (TCKR) are anticipated to be overloaded and highly saturated, with vehicles likely to wait for more than one traffic light cycle for passing through the junction during peak periods (Reserve Capacity (R.C.)[2] < 0%).

1.9.4              In case the Project could be completed and operated in 2028, capacity problem on traffic flow of the major road links and junctions mentioned in Section 1.8.2 to Section 1.8.4 will be relieved or even resolved.

1.9.5              In addition, both traffic bounds of TPR-ST between Fo Tan Road and STRCR are anticipated to have sufficient capacity to cope with the anticipated vehicular traffic volume during both morning and evening peak hours (V/C ratio < 1.0) in 2028 and even up to 2033.  The section of TPR-ST to the south of STRCR for both directions are also anticipated to have sufficient capacity (V/C ratio < 1.0) as well.


 

Scenario “with” Project

1.9.6              With the Project in place, the critical V/C ratio for the southbound of LRT will be reduced during morning peak hours.  Meanwhile, the traffic condition of TCT is anticipated to be improved at its eastbound traffic during morning peak hours.

1.9.7              As the Project will provide a direct link to traffic heading to Tsing Sha Highway and Shing Mun Tunnel, a decrease in traffic volume on STRCR will be expected.  As a result, the reserve capacity of the road junction of STRCR/YWR will be improved during evening peak hours.  Similar to the case of STRCR, a decrease in traffic flow on TCKR will also be expected with the operation of the Project.  Hence, the reserve capacity of the junction of STWR / TCKR will also be improved during morning peak hours. 

1.10                Consequences of Not Proceeding with the Project

1.10.1            In case the Project cannot be proceeded according to the proposed schedule, traffic travelling between Ma On Shan area and Tsuen Wan / Western Kowloon areas will require to pass through those congested at-grade road sections in Sha Tin Central such as TPR-ST, TCKR and STRCR, which will further worsen the traffic conditions of the heavily trafficked roads in Sha Tin results in longer queuing length and longer travelling time.

1.10.2            In addition, the traffic congestion problem in the major road links and junctions as described in Section 1.8.2 to 1.8.4 will unlikely be relieved without the implementation of the Project.

1.11                Implementation Programme

1.11.1            Construction of the Project is scheduled to commence in 2023 Q4 tentatively.  The construction works will take approximately 5 years for completion and the targeted commissioning date of the Project will be in Q3 2028 tentatively.  Details of the construction programme and the measures recommended to be taken during construction are presented in Section 2.7.

1.12                Concurrent Projects

1.12.1            Concurrent projects in the vicinity of the Project site are identified.  The status of these concurrent projects is based on the available information obtained during the course of the EIA Study.  It should be noted that the implementation of individual project would be subject to further development and subsequent actions of the respective project proponent.

Widening and Reconstruction of Tai Po Road (Sha Tin Section)

1.12.2            The existing Tai Po Road (Sha Tin Section) (TPR-ST) is an essential primary distributor road linking Northeast New Territories with Kowloon and Tsuen Wan areas.  The widening of TPR-ST from a dual 2-lane to dual-3 lane carriageway, together with other related traffic improvement and road reconstruction works are needed to cope with the continuous increase of traffic demand due to the existing, committed and planned developments.

1.12.3            Widening of TPR-ST is a designated project under the EIAO and is controlled by an environmental permit (EP-463/2013/B) for construction and operation. A comprehensive review has been conducted to ascertain the validity and acceptability of the environmental impacts assessed in the previously approved EIA report (Register: AEIAR-020/1999) and the EP which covered the current scope of the Project.

1.12.4            Construction works for the Widening of TPR-ST will be completed in Q1 2023 tentatively which is before the commencement of the construction for the Project (i.e. not concurrent project under construction phase) which will commence in Q4 2023 tentatively, and potential cumulative impacts involving this project during the construction of the Project is not anticipated.  Furthermore, as the forecast traffic flow data adopted for the air quality and noise impact assessments in the Project has already included the effect of the completion of Widening and Reconstruction of TPR-ST Project, the cumulative impact during the operation phase of the Project in association with the Widening and Reconstruction of TRP-ST project has been considered. Though cumulative indirect ecological impacts due to dust, noise and glare would be anticipated at the developed area habitats near Tung Lo Wan.  Nevertheless, since this potentially affected habitat is already urbanized and subjected to similar disturbance under current condition, no unacceptable cumulative indirect ecological impacts during the operation phase are expected.  Apart from this, no other cumulative environmental impacts would be anticipated during operation phase of the Widening and Reconstruction of TPR-ST.

Improvement of Lion Rock Tunnel

1.12.5            According to the EIA Study Brief “Improvement of Lion Rock Tunnel” (No. ESB-323/2019), this project is to provide comprehensive rehabilitation to the existing Lion Rock Tunnel (LRT) and enhance the capacity of the LRT and the connecting roads to improve the traffic flow.  

1.12.6            Based on the latest available information, the tentative construction work of the entire Improvement of LRT project will be commenced in 2025 for completion by 2035.  As the road widening works of LRT Road at the section near Sun Tin Wai Estate/Fung Shing Court undertaking by LRT Project will commence in December 2028 while the construction of the Project will be completed in September 2028, no potential cumulative impact due to the construction of the Improvement of  LRT project will be anticipated in this EIA Study.  Furthermore, as the forecast traffic flow data adopted for the air quality and noise impact assessments in the Project has already included the effect of the Improvement of LRT Project, the cumulative impact during the operation phase of the Project in association with the Improvement of LRT project has been considered.

1.12.7            Based on the findings in Section 8, under the proposed footprint of Improvement of LRT project, about 0.16 ha of woodland located within Lion Rock Country Park (LRCP) along the LRT Road and at LRT portal at Shatin would be unavoidably affected. Given only very small area of woodland and mixed woodland (about 166m2 in total) within LRCP at south of Sha Tin Road would be affected under T4 and would only result in minor direct impact to LRCP, it is anticipated this small affected woodland and mixed woodland area would not incur any unacceptable cumulative direct impact to LRCP.  Cumulative indirect ecological impacts such as noise, dust and glare would be likely expected near the developed area habitat near Sha Tin Tau Village, and woodland and mixed woodland habitat located south to Sha Tin Road within LRCP.  Since these affected habitats are already subjected to regular disturbance from the existing Sha Tin Road and LRT Road, the cumulative indirect ecological impacts are expected to be acceptable.  Apart from this, no other cumulative environmental impacts would be anticipated during operation phase of the Improvement of Lion Rock Tunnel.

Revitalisation of Tai Wai Nullah

1.12.8            According to the EIA Study Brief “Revitalisation of Tai Wai Nullah” (No. ESB-320/2019), the project is to revitalise the existing Tai Wai Nullah with an aim to enhance the ecological value of the nullah, provide a greener environment, promote water friendliness and improve the community environment.  The Revitalisation of Tai Wai Nullah also includes necessary drainage improvement works to the nullah, and provision of dry weather flow intercepting devices to improve the water quality.

1.12.9            The construction works of Revitalisation of Tai Wai Nullah are tentatively scheduled to commence in Q3 2024 for completion by Q4 2029, which will overlap with the tentative construction programme of the Project. Since a section of Tai Wai Nullah near the existing Shing Mun Tunnel Road falls inside the Study Area of the Project.  There is potential concurrent works between the Revitalisation of Tai Wai Nullah project and the Project.  Although solid information on the construction programme of the Revitalisation of Tai Wai Nullah project is not available at this stage, in accordance with the EIA Study Brief of Revitalisation of Tai Wai Nullah, excavation works within or close to the existing nullah bed would be carried out during dry seasons whenever possible.  Besides, in view that the most dusty and noisy construction works of the Revised Trunk Road T4 within the site area of overlapping with the Revitalisation of Tai Wai Nullah project would be the foundation works for the Revised Trunk Road T4 viaducts, the tentative construction programme and works at the interface area between the two projects could be arranged efficiently, e.g. scheduling works to be carried out during dry season, through close liaison between DSD’s and CEDD’s contractors of the Revitalisation of Tai Wai Nullah project and the Project respectively in order to avoid construction works of respective works contracts to be carried out concurrently at the same interfacing areas and CEDD has agreed to include this requirement in the respective works contract.  With such arrangement in place, cumulative construction environmental impacts, and water quality impacts upon the downstream water body could be minimised. 

1.12.10          Furthermore, due to the nature of the Revitalisation of Tai Wai Nullah project (i.e. a project with no vehicular and traffic noise emission), no cumulative environmental impact is anticipated during operation phase of the Project in association with the Revitalization of Tai Wai Nullah project.

1.12.11          The key details of these identified planned/committed projects are summarized in Table 1.1.  The locations of these projects from which potential cumulative impact may arise are shown in Figure 1.2.  Cumulative impacts from the concurrent projects have been assessed in the individual sections of this EIA Report.


 

Table 1.1 Summary of the Other Projects in the Vicinity of the Project Site

Project

Project Proponent

Construction Programme

Potential Cumulative Impact

Start

Complete

Construction

Operation

Widening of Tai Po Road (Sha Tin Section)

Civil Engineering and Development Department

July 2018

Q1 2023 [1]

Nil

Improvement of Lion Rock Tunnel

Highways Department

2025 [3]

2035

Note [4]

Revitalisation of Tai Wai Nullah

Drainage Services Department

Q3 2024 [2]

Q4 2029 [2]

Nil

Note:

” may have potential cumulative impact;

[1]      Source: CEDD’s website at https://www.cedd.gov.hk/eng/our-projects/major-projects/index-id-71.html

[2]      Source: EPD’s website at https://www.epd.gov.hk/eia/register/profile/latest/esb320/esb320.pdf

[3]      Construction works for the Improvement of Lion Rock Tunnel project at the section near Fung Shing Court will be commenced in December 2028 tentatively

[4]      No potential cumulative impact for air quality, noise, water quality, waste management, land contamination, landscape and visual and cultural heritage; No unacceptable impact for ecology 

 

1.13                Structure of the EIA Report

1.13.1            The background of the Project, description of the Project, objectives and scope of the EIA study are introduced in this section.  Details of considerations of alternative options are provided in Section 2.  Sections 3 to 10 detail the results of the environmental impact assessment of each key subject area, covering relevant legislation, environmental conditions, assessment criteria, methodology, assessment findings, and proposed mitigation measures.

1.13.2            Section 3 to 10 are outlined as follows:

·         Section 3: Air Quality Impact

·         Section 4: Noise Impact

·         Section 5: Water Quality Impact

·         Section 6: Waste Management Implications

·         Section 7: Land Contamination

·         Section 8: Ecology (Terrestrial)

·         Section 9: Landscape and Visual Impact

·         Section 10: Impact on Cultural Heritage

1.13.3            An outline of the requirements for the Environmental Monitoring and Audit (EM&A) is presented in Section 11.  The EM&A programme is presented in detail in a separate EM&A Manual.  A summary of environmental outcomes is provided in Section 12 and a conclusion of the whole assessment is given in Section 13.

 



[1] A preferable v/c ratio is 0.85. A v/c ratio equals to or less than 1.0 is considered acceptable. A v/c ratio between 1.0 and 1.2 indicates a manageable degree of congestion. A v/c ratio above 1.2 indicates more serious congestion.

[2] Reserve Capacity (RC) reflects the traffic condition of a signal-controlled junction.  A positive RC figure suggests that the junction is operating with spare capacity, while a negative RC figure suggests that junction is overloaded, hence resulting in vehicle queues and longer travel time.