TABLE OF CONTENT
List of Tables
Table 13.1 Summary of Key
Environmental Outcomes and Benefits
List of
Appendices |
|
Key Assessment Assumptions, Limitations of Assessment Methodologies
and Prior Agreements with the Director |
|
Summary of Environmental Impacts |
· Air Quality Impact
· Noise Impact
· Water Quality Impact
· Waste Management Implications
· Land Contamination
· Ecological Impact (Terrestrial)
· Landscape and Visual Impact
· Impact on Cultural Heritage
Table 13.1 Summary of Key
Environmental Outcomes and Benefits
Environmental Issue |
Description |
Environmental / Social Benefits of
the Project |
·
Eastbound alignment shifted away from Tung Lo Wan Village
and residential buildings of Sha Tin Central and placed in front of Tai Wai
industrial buildings, less noise and quality impacts to the residents of the
buildings close to the bridges during operation stage. ·
Depressed road / underpass sections at the south of Shing
Mun River Channel (SMRC) reduces the air quality and noise impact to the
residents of Sha Tin Tau Village (STTV) and Tsang Tai Uk
Village (TTUV) during operation stage. ·
Avoid conflicting with existing Old and Valuable Trees (OVTs)
along Chung Ling Road ·
Eastbound alignment shifted away from Tung Lo Wan Village
and residential buildings in Sha Tin Central with less visual impact. ·
Depressed road / underpass sections at the south of SMRC
would have insignificant visual impact during operation stage, particularly
for the residents of the Riverpark, STTV and TTUV and Fung Shing Court. ·
Additional road connections between the T4 and local road
network in Sha Tin Central which help to relieve traffic congestion in Sha
Tin Central and provide convenience to road users. |
Environmentally
Friendly Design and Options |
·
The operation traffic noise from existing at-grade roads,
e.g. Lion Rock Tunnel Rock is identified to be the main source of nuisance to
the nearby NSRs of residential buildings in Sha Tin Central, application of
advance low noise road surfacing (LNRS) to the carriageways of the existing
at-grade roads to reduce the traffic noise is recommended. ·
No noise semi-enclosure will be required to be installed
on the bridge structures of the T4 fronting the HKHM with the application of
the advance LNRS on existing roads and LNRS at new roads, the visual impact
to the LCA of the Hong Kong Heritage Museum (HKHM) and nearby residents is
reduced. ·
No noise barrier/enclosure is proposed to be erected on
the northern portion of the T4 bridge deck across SMRC within the flight path
of ardeids to avoid bird collision. ·
Avoid having ventilation buildings/shafts for the
underpasses, large size openings will be provided on the rooftop of the two underpasses
at STTV to adopt natural ventilation. ·
Avoid significant environmental and ecological impacts to
the habitats of the Lion Rock Country Park (LCRP), the proposed soil nailing
works within LRCP will be replaced by a rigid barrier to be erected at the
edge of the widened Sha Tin Road (outside the boundary of LRCP). ·
Recommend to adopt precast
concrete construction method for construction of viaduct which is a more
environmentally friendly approach. ·
Implementation of Environmental Monitoring and Auditing
System. |
Air
Quality Impact |
Construction Phase: ·
Potential dust impact
generated from construction activities, such as site clearance, utilities
protection and diversion works, slope work,
excavation, piling and roadworks, and wind erosion of exposed work area, and
emission from PMEs would be minor. With the implementation of mitigation
measures specified in the Air Pollution Control (Construction Dust)
Regulation together with the recommended dust suppression measures and good
site practices, no adverse dust impact at ASRs is anticipated due to the
construction activities of the Project. Operation Phase: ·
Cumulative air quality impact
arising from the operation of the Revised Trunk Road T4 such as vehicular
emission from open roads and nearby chimneys within 500 m study area has been
assessed for the operation phase of the Project. The results conclude that the predicted
cumulative NO2, RSP and FSP concentration at all ASRs would comply
with AQOs. No adverse air quality
impact is anticipated arising from the operation of the revised Trunk Road
T4. |
Noise
Impact |
Construction Phase ·
The NSRs
are protected with the implementation of quiet PME, movable barriers and full
enclosure as well as good site practices during construction phase. The
predicted mitigation noise levels comply with the noise standards at all NSRs
during non-restricted hours and restricted hours except during examination
period for Hong Kong Bible Research and Education Centre and Christ College. ·
It is recommended that the works area of these critical
construction activities shall be restricted during the examination period of
these schools. Minimum separation distance between the critical construction
activities and the schools has been recommended. Operation Phase ·
Although there is still
predicted exceedance of the noise criteria at some of the NSRs under the
mitigated scenario, with the implementation of noise mitigation measures
including LNRS, vertical noise barriers/cantilever noise barriers and semi/
full enclosures on some Project roads, the exceedances were dominantly
contributed by the nearby existing roads. The contributions from the Project
roads at all NSRs are less than 1.0 dB(A) and the predicted noise levels at
NSRs due to the Project roads would comply with the noise criteria. Thus, no adverse road traffic noise impacts
arising from the Project would be anticipated. ·
The Project itself is not a
fixed noise source. No fixed noise impact would arise from the Project. |
Water
Quality Impact |
Construction Phase: ·
The construction of bridge structures across Shing Mun
River Channel would require the installation of new bridge piers in Shing Mun
Main River. The excavation and pilling
works will only be carried out in a confined dry working environment by
phases and only one cofferdam would be installed in each period. With
implementation of mitigation measures including installation of watertight steel
casing and cofferdam at the pier site, provision of appropriate desilting or
sedimentation device for treatment of water from dewatering process and deployment
of silt curtains for construction works, no unacceptable water quality impact
was expected due to construction of the bridge piers. ·
Besides, the construction activities would be conducted by
phases and only one cofferdam would be installed in each period. With
consideration of the cross-section area of the rive
channel to be blocked by the pier installation, no unacceptable impact on
hydrodynamic of Shing Mun River was anticipated. ·
Excavation and construction works
for the diversion of Sha Tin Tau Nullah have potential to create water
quality impact at the downstream area if unmitigated. As such, the nullah
diversion works should be scheduled in dry season as far as practicable when
the flow is low. Temporary drainage or permanent drainage at most downstream
should first be established to intercept and divert the upstream flow. Good site practices as described in ETWB TC(Works) No. 5/2005 “Protection of natural streams/rivers from
adverse impacts arising from construction works” and ProPECC
PN1/94 “Construction Site Drainage”
should be adopted where applicable to avoid adverse water quality impact from
arising. ·
Potential water quality impacts from the land-based
construction works are associated with the general construction activities,
construction site run-off, accidental spillage, and sewage effluent from
construction workforce. With
implementation of site practices as outlined in ProPECC
Note PN 1/94, no adverse water quality impact was expected due to the
land-based construction works. Operation Phase: ·
Potential hydrodynamic impact due to the presence of the
permanent bridge pier structure in Shing Mun River was predicted to be
localised and transient with consideration of the cross-section area of the
river channel to be blocked by the pier.
No unacceptable change in flow regime at the river channel was
anticipated. ·
Surface runoff generated from the additional paved areas
was identified as an alternate source of potential water quality impact. The
associated water quality impact was expected to be minimal and acceptable,
provided that the recommended mitigation measures for the drainage system are
properly implemented. |
Waste
Management Implications |
Construction Phase: ·
Waste types generated by the construction of this Project
are likely to include C&D materials, chemical waste from maintenance of
construction plant and equipment, general refuse and
excavated sediment. Provided that
these wastes are handled, transported and disposed
of according to the recommended good site practices, adverse environmental
impacts are not expected. ·
The excavated sediment generated from the project
comprised of marine-based sediment. The excavated
marine-based sediment will be treated using S/S technique and will be reused
on site (e.g. as backfilling materials). No adverse environment
impacts would be expected from the excavation and handling of sediment. Operation Phase: ·
It is expected
that no waste will be generated during the operational phase of the Project.
As such it is considered that there should be no adverse environmental
impacts. |
Land
Contamination |
·
Based on the findings of the site appraisal, no adverse
land contamination impact arising from Project is anticipated. |
Ecology
(Terrestrial) |
Construction Phase: · No direct impact to the ardeid night roost site between HKHM and Man Lai Court. · Over 58% of the proposed works areas are situated within developed area along/near the existing roads. · Only very small area of woodland (about 13 m2) and mixed woodland (about 153 m2) within LRCP would be affected by the potential slope stabilization works (flexible barrier). The extent of flexible barrier should be carefully designed to avoid or minimized the potential ecological impacts (e.g. tree felling, impact to flora species of conservation) as far as possible. · For the two flora species of conservation importance (Butulang Canthium and Ailanthus) recorded with the Project footprint, and six flora species of conservation importance (Butulang Canthium, Incense Tree, Luofushan Joint-fir, Small Persimmon, Rhododendron spp. and Hairy-fruited Ormosia) recorded in the vicinity of the Project footprint, a detailed vegetation survey should be conducted at the potentially impacted area to ascertain the presence and condition of the above species prior to site clearance. A Plant Preservation and Transplantation Proposal should be prepared and submitted to AFCD for approval to recommend suitable mitigation measures on flora species of conservation importance recorded within and near the Project footprint, including both within LRCP and outside LRCP. · With the implementation of the recommended mitigation measures, no unacceptable ecological impacts are anticipated during construction phase. Operation Phase: |
Landscape
and Visual Impacts |
Construction Phase: ·
There are 6 nos. of registered OVTs in the vicinity of the project
boundary will be retained in-situ and not be affected by the Project. ·
Based on the broad-brush tree estimate with approximately
3,685 nos. of trees including 176 nos. of trees of particular interest
surveyed, approximate 1,051 nos. of existing trees including 13 nos. of trees
of particular interest will be unavoidably affected by the Project. ·
One tree of particular
interest Ficus benjamina with high amenity
value and large size outside the Hong Kong Heritage Museum will be
unavoidably affected and tree transplanting is proposed, subject to the
review on technical feasibility and sensitivity analysis in detail design
stage and further advice from the existing and future tree maintenance
departments. ·
For the remaining approximate 1,050 nos. of affected
trees, tree felling will be proposed. ·
With implementation of mitigation measures during
construction phase, the residual landscape and visual impact is acceptable. Operation Phase: ·
A
minimum of 250 heavy standard trees will be proposed at roadside flat areas,
at the re-provided Sha Tin Tau Village Sitting-out Area and at the planting
areas of elevated roads with shade-tolerant tree species. ·
Total
area of approximate 11,300m2 will be proposed as compensatory woodland mix
planting with approximately 3,400 nos. of tree whips to be planted. ·
With
mitigation measures implemented during operation phases, the residual
landscape impacts would be further reduced to insubstantial when the proposed
compensatory planting, buffer planting and woodland mix planting become
mature in year 10 of operation. ·
For
those VSRs (i.e. R-03, I-03, I-04 and O-01) viewing to the proposed bridge
with noise semi-enclosure at Shing Mun River Channel of VP3, VP4 and VP11,
and the two VSRs (i.e. R-05 and T-06) viewing to the full noise enclosure
along Sha Tin Road of VP8, there are still slight residual visual impacts
upon day 1 of operation and year 10 of operation. ·
There
would be insubstantial residual impact on other VSRs within the visual
envelope during operation of the Project. In sum, it is considered that the residual
landscape and visual impact is acceptable with mitigation measures
implemented during operation phases. |
Impact
on Cultural Heritage |
Construction Phase: ·
Potential direct impacts due to damages through contacting with
heavy construction machineries and site negligence would be anticipated for Tsang Tai Uk, Gatehouse of Pok Ngar Villa, Li Cottage, Ng Yuen, and OLD26. Indirect impacts including ground-borne vibration, tilting and settlement, would be anticipated
for Tsang Tai Uk, Gatehouse of Pok
Ngar Villa, Li Cottage, Lau Ancestral Hall, Ng
Yuen, High Rock Christian Camp, No. 1, 2 and 3 First Street, OLD1, OLD9, OLD11-21, OLD26-28. ·
Pre and post condition
survey of Tsang Tai Uk, Gatehouse of Pok Ngar Villa, Li Cottage and
Ng Yuen. ·
Monitoring of vibration, settlement and tilting
incorporated with a set of Alert, Alarm and Action (3As) system for Tsang Tai
Uk, Gatehouse of Pok Ngar Villa, Li Cottage, Lau Ancestral Hall, Ng Yuen, High
Rock Christian Camp, No. 1, 2 and 3 First Street, OLD1,
OLD9, OLD11-21, OLD26-28. ·
To ensure the stability of historic buildings, foundation information of the historic buildings shall be verified
on site if needed, sufficient lateral support should be provided and
de-watering (if required) should be carried out with great cautions to control ground movement and change of ground water regime at the
heritage site. ·
Buffer zones with physical
barriers should be employed for Tsang Tai Uk, the
Gatehouse of Pok Ngar
Villa, and OLD26. Substantial physical
barriers, such as hoarding or water-filled barriers, should be set up between
the project site and each of the two built heritage resources, Li Cottage, Ng
Yuen, OLD26.
·
Protective covering of plastic sheets shall be provided for Tsang
Tai Uk, Gatehouse of Pok Ngar Villa, Li Cottage and Ng Yuen during construction to
avoid impacts of dust nuisance. ·
With the implementation of
mitigation measures, impact on cultural heritage would be acceptable. ·
No archaeological impact would be anticipated. Thus, no mitigation
measure would be required. Operation Phase: ·
No impact to cultural heritage would be anticipated from the
operation of the Project. Hence, no mitigation measure would be required for
the operation phase. |