TABLE OF CONTENT

 

2............. Consideration of alternative alignment options. 2-1

2.1.......... History and Background of the Project 2-1

2.2.......... Consideration of Alignment Options. 2-2

2.3.......... Selection of Preferred Alignment 2-9

2.4.......... Key Design Elements. 2-12

2.5.......... Consideration of Different Construction Methods for Viaduct 2-15

2.6.......... Consideration of Different Construction Methods for Underpass. 2-17

2.7.......... Construction Programme. 2-19

2.8.......... Public Consultation. 2-19

 

List of Tables

 

Table 2.1                   Summary of Environmental Considerations of Alignment Options

Table 2.2                   Comparison of Different Construction Methods for Viaduct

Table 2.3                   Comparison of Different Construction Methods for Underpass

Table 2.4                   Summary of Concerns Raised by STDC T&TC Members and the Public and Follow Up Actions

 

 

List of Figures

Figure 2.1

Alignment Options for Trunk Road T4

Figure 2.1.1

Alignment Base Scheme for Trunk Road T4

Figure 2.1.2

Alignment Option 1 for Trunk Road T4

Figure 2.1.3

Alignment Option 2 for Trunk Road T4

Figure 2.1.4

Alignment Option 3 for Trunk Road T4

Figure 2.3.1

Revised Trunk Road T4 General Layout Plan (Sheet 1 of 4)

Figure 2.3.2

Revised Trunk Road T4 General Layout Plan (Sheet 2 of 4)

Figure 2.3.3

Revised Trunk Road T4 General Layout Plan (Sheet 3 of 4)

Figure 2.3.4

Revised Trunk Road T4 General Layout Plan (Sheet 4 of 4)

Figure 2.4.1

Construction Method at Shing Mun River Channel

Figure 2.4.2

Construction Method at Shing Mun River Channel - Section

 

List of Appendices

Appendix 2.1

Tentative Construction Programme


2                    Consideration of alternative alignment options

2.1                History and Background of the Project

2.1.1            In 2006, a Trunk Road T4 scheme was gazetted under the Roads (Works, Use and Compensation) Ordinance.  Owing to substantial number of objections received during the road gazettal objection period, the Traffic and Transport Committee (T&TC) of Sha Tin District Council (STDC) withdrew their support on the Trunk Road T4 and passed the motions for the Government to monitor and review the traffic situations in Sha Tin District after the commissioning of Route 8 in order to determine the need of the Trunk Road T4 (the T4).  In this connection, the implementation of the T4 was then on hold and the scheme was not adopted.  

2.1.2            A traffic review study under CEDD’s Agreement No. CE 71/2015 (HY) – Traffic Review on Major Roads in Sha Tin – Feasibility Study (the TR Study) was conducted with the aim to review the existing traffic situations in Sha Tin, identify the existing traffic problems and recommend mitigation measures to improve the situation.  The result of the TR Study demonstrated that due to the missing direct road link in the existing local road network between north-eastern portion and south-western portion of Sha Tin District, traffic travelling between Ma On Shan area and Tsuen Wan/West Kowloon areas relies mainly on existing at-grade roads in Sha Tin area, in particular, Tai Po Road (Sha Tin Section) (TPR-ST) and Tai Chung Kiu Road (TCKR), which add extra traffic loading to these heavily trafficked roads.  It was revealed from the TR Study that the need of the T4 as one of the medium-term mitigation measures for alleviating the traffic congestion in Sha Tin District was fully justified since it provides a direct connection to divert the traffic from using the local road network.  

2.1.3            Sha Tin District has been developed since 1970s and are fully urbanized new town. The road network of Sha Tin District was well-planned at the beginning of the development. There is not much room available for introducing additional new corridor for the T4 due to various constraints such as avoidance of impacts to existing buildings, civil infrastructures, and community recreation and leisure facilities etc. within the well-developed community. 

2.1.4            Having investigated thoroughly on the possible routes for the T4 under the TR Study, it was found that the corridor of previously gazetted road scheme is the only available corridor with sufficient space and surmountable constraints for the construction of the T4.  Provisions for future road connections (the reserved connections) to Shing Mun Tunnel Road (SMTR), Tsing Sha Highway (TSH) and Sha Tin Road (STR) have been allowed and reserved in these existing roads within this corridor.

2.1.5            Road scheme of Revised Trunk Road T4 was then proposed for alleviating the traffic congestion in Sha Tin District.  Based on the conceptual design established in the TR Study as a framework, the alignment of the T4 is further reviewed and refined taking into account the site constraints and requirements from stakeholders under Agreement No. CE 8/2018 (HY) – Revised Trunk Road T4 and Associated Improvement Works in Sha Tin – Investigation. Meanwhile, the public concerns and requirements received during the objection period of the last gazettal of road scheme in 2006 has been addressed. 

2.2                Consideration of Alignment Options

2.2.1            Although the need of the T4 has been established under the TR Study, different alignment options should be developed in compliance with the design requirements for further investigation to determine which alignment option would be the best solution for the T4. In the course of the traffic review under the TR Study and as required in the Project, 10 alignment options for the T4 were proposed.  These alignment options were then further  narrowed down to 4 options for option evaluation, which are considered satisfying the predetermined functional requirement of providing a direct connection for through traffic between Ma On Shan area and Tsuen Wan/West Kowloon areas without the need of travelling along the existing busy major roads in Sha Tin area such as TPR-ST and TCKR. The design and layout of 4 alignment options are shown in Figure 2.1, Figure 2.1.1, Figure 2.1.2, Figure 2.1.3 and Figure 2.1.4 and described below. In view of the other 6 options could not fulfil the predetermined functional requirements such as the start or end points connecting with existing road were deviated from proposed T4, and the road schemes still need to travel through traffic controlled junctions which did not fulfil the purpose of proposed T4 to provide a direct connection route bypassing the road network in Sha Tin Central. Therefore, these options were not selected for comparison.

2.2.2            Base Scheme

2.2.2.1         Base scheme is the road scheme gazetted in 2006, which was also studied under the EIA Report No. AEIAR-084/2005.  It comprises the construction of 1.6 km dual 2-lane elevated carriageways with connections to TSH, SMTR and STR.  The layout of the Base Scheme is shown in Figure 2.1.1.

2.2.2.2         For the T4 eastbound traffic, the elevated carriageway diverges from SMTR eastbound (EB) and runs along and to the north of SMTR above Chung Ling Road. It merges with another elevated carriageway which starts at the reserved connection of TSH northbound (NB) near Tung Lo Wan Village forming the T4(EB). The T4(EB) will be in form of viaduct and runs in parallel and above Lion Rock Tunnel Road (LRTR), across Shing Mun River Channel (SMRC) and TCKR, in front of Sha Tin Tau Village (STTV) and then connects to and merge with the at-grade section of STR (EB) near Tsang Tai Uk Village / Pok Hong Estate.

2.2.2.3         For the T4 westbound traffic, it starts ascending from Sha Tin Road westbound (WB) near Pok Hong Estate. After diverging from STR (WB), the T4(WB) will also be in form of viaduct travelling along the alignment similar to that of the T4(EB), which runs over and in front of STTV, across TCKR and SMRC, and then splits into two elevated slip roads with one connecting to SMTR (WB) while the other connecting to TSH southbound (SB). The followings are the key characteristics of Base Scheme:

·         Design speed of 80 km/h which is a desirable standard for trunk road is adopted for the design of both vertical and horizontal alignments of the trunk road;

·         Mainly in form of viaduct along its alignment with the road level of the bridge across SMRC at about +31mPD;

·         Viaduct structure along eastbound alignment in conflict with 5 existing old and valuable trees (OVTs) along Chung Ling Road;

·         3 layers of viaduct structures in front of Scenery Court, Hilton Plaza and Sha Tin New Town Plaza Phase 3 - with the minimum horizontal distance between the viaduct and building tower of Scenery Court of 74m approximately; and

·         No connection to existing local road network of Sha Tin Central – road users heading to Sha Tin Central cannot enjoy the benefits of the T4.

 

2.2.3            T4 Option 1

2.2.3.1         T4 Option 1 also satisfies the predetermined functional requirements, which can provide a direct connection for through traffic between Ma On Shan area and Tsuen Wan/West Kowloon and deal with the future traffic demand and traffic growth.  The horizontal alignment of Option 1 runs along the same corridor as of Base Scheme, which connects to both SMTR and TSH and STR at its western end and eastern end respectively.  The two slip roads connecting SMTR(EB) and TSH(NB) are merged to form the T4(EB) and then travels along the southern side of TSH in front of the industrial buildings of Tai Wai area and adjacent to the Hong Kong Heritage Museum (HKHM).

2.2.3.2         The T4(EB) then turns south running almost in parallel with and at the immediate west of LRTR such that the T4 alignment will be away from Scenery Court albeit close to the HKHM and fronting the Riverpark.  The T4(WB) runs alongside with the T4(EB) in front of the HKHM and descends together at maximum allowable gradient across SMRC before reaching the southern riverbank.

2.2.3.3         T4 Option 1 changes from elevated carriageway to depressed carriageway/underpass for the section at the south of SMRC.  After crossing SMRC, the T4 Option 1 alignment will start to descend below ground in front of the Riverpark and then goes in form of underpass beneath the existing carriageway of TCKR and between piers of Tuen Ma Line rail tracks.  The T4 underpass continues to travel in front of and below the farmland of STTV and across LRTR.  The T4 then ascends after crossing LRTR and merges with the existing STR.

2.2.3.4         In order to avoid the need of ventilation buildings/shafts for the underpass section of the T4 which would induce additional environmental impacts such as air quality, noise and visual impacts, the rooftop of a section of the T4 underpass fronting STTV will be provided with large scale openings in order to allow natural ventilation for the underpass through these rooftop openings.

2.2.3.5         A slip road is proposed as part of the Project connecting from LRTR (SB) to STR (EB) near Tsang Tai Uk Village (TTUV) so that road users originated from Sha Tin Central can enjoy the convenience brought from the Project as a short cut route for traveling to Shek Mun and Ma On Shan (MOS) areas.

2.2.3.6         Another slip road is proposed connecting the T4(WB) with LRTR (NB) at Lion Bridge such that traffic from MOS area heading to Sha Tin Central can use the T4 as an alternative route by exiting at LRTR. The layout of the T4 Option 1 is shown in Figure 2.1.2 and the followings are the key characteristics of T4 Option 1: 

·         Owing to various site constraints and spatial limitation, design speed of 70 km/h which is a less desirable standard for trunk road can only be adopted for the design of vertical and horizontal alignments;

·         The T4(EB) alignment is shifted and situated near Tai Wai industrial area which can avoid conflicting with the existing OVTs along Chung Ling Road;

·         3 layers of viaduct structures sandwiched between the HKHM and Scenery Court, with the minimum horizontal distance between the T4(WB) viaduct and building tower of Scenery Court of 105m approximately while the horizontal separation between the T4(EB) viaduct and the HKHM building structure is around 7.4m;

·         No elevated carriageway after reaching the southern riverbank of SMRC - depressed road / underpass section starts in front of the Riverpark with the minimum horizontal separation between the Riverpark boundary and depressed road structure of 4m approximately; and

·         With additional road connections between the T4 and local road network in Sha Tin Central – help to relieve traffic congestion in Sha Tin Central and provide convenience to road users.

2.2.4            T4 Option 2

2.2.4.1         The T4 Option 2 also satisfies the predetermined functional requirements and its horizontal alignment runs along the same corridor as of Base Scheme and T4 Option 1.  The two slip roads connecting SMTR(EB) and TSH(NB) are merged to form the T4(EB) and then travels along the southern side of TSH in front of the industrial buildings of Tai Wai area.  After passing the HKHM, both of the eastbound and westbound carriageways run across LRTR, turn southward and continue to run along and at the east to LRTR. 

2.2.4.2         The T4 Option 2 alignment descends at maximum allowable gradient across SMRC before reaching the southern riverbank.  After crossing SMRC, the T4 starts to descend below ground in front of the Hong Kong Bible Research and Education Centre (HKBREC) and then goes in form of underpass beneath the existing carriageway of TCKR and between piers of Tuen Ma Line rail tracks.  The T4 underpass continues to travel in front of and below the farmland of STTV and across LRTR.  The T4 then ascends after crossing LRTR and merges with the existing STR.

2.2.4.3         Under the T4 Option 2, the viaducts will encroach into the boundaries of Sha Tin Park, Tsang Tai Uk Recreation Ground (TTURG) and HKBREC.  Occupation of government land allocation of Sha Tin Park and TTURG and resumption of land of HKBREC are necessary.  The layout of the T4 Option 2 is shown in Figure 2.1.3.

2.2.4.4         The followings are the key characteristics of T4 Option 2: 

·         Owing to various site constraints and spatial limitation, design speed of 70 km/h which is a less desirable standard for trunk road can only be adopted for the design of vertical and horizontal alignments;

·         3 layers of viaduct structures sandwiched between LRTR and Scenery Court, with the minimum horizontal distance between the T4(WB) viaduct and building tower of Scenery Court of 65m approximately;

·         No elevated carriageway after reaching the southern riverbank of SMRC - depressed road / underpass section starts at the HKBREC with the minimum horizontal separation between the Riverpark boundary and depressed road structure of 74m approximately;

·         With additional road connection between the T4(EB) and STR – provide convenience to road users heading to Ma On Sha area;

·         With encroachment into the boundary of HKBREC – additional land resumption and relocation of the existing premises are required; and

·         With encroachment into Sha Tin Park and TTURG – temporary closure of leisure facilitates and significant impacts to the existing trees and ecology of Sha Tin Park.

2.2.5            T4 Option 3

2.2.5.1         T4 Option 3 also satisfies the predetermined functional requirements which can provide a direct connection for through traffic between Ma On Shan area and Tsuen Wan/West Kowloon and deal with the future traffic demand and traffic growth but its horizontal alignment does not run within the same corridor of Base Scheme, T4 Option 1 and T4 Option 2.

2.2.5.2         The majority of the T4 Option 3 alignment will be in form of tunnels except for the approaching road sections connecting to the existing elevated carriageways of SMTR and TSH, which are in form of viaducts.  The slip road of T4(EB) after branching out from the at-grade SMTR(EB) will be in form of tunnel running underneath Tung Lo Wan Village, Villa Maria and Pineridge before crossing the East Rail tracks. Another T4(EB) slip road will branch out from TSH(NB) and runs in a form of tunnel around and underneath Lai Chi Yuen before crossing East Rail tracks.  Then, these two underground slip roads will join together forming the T4(EB) tunnel and go beneath and across East Rail track.  The T4(EB) tunnel will continue to run below ground towards the south passing through Sha Tin Park, SMRC, HKBREC, STTV and LRTR.  The T4(EB) then ascends after crossing LRTR and daylights near TTUV before merging with the STR(EB) at grade near Pok Hong Estate.  

2.2.5.3         The T4(WB) starts from the at-grade section of STR(WB) and travels westward and then northward after crossing LRTR in form of underground road tunnel. The T4(WB) tunnel then branches off into two slip roads, which are still in tunnel form at STTV.  One of the slip road tunnels serves for the traffic from T4(WB) heading to SMTR and continues to travel in a form of underground tunnel in north-western direction passing through TCKR, HKBREC, SMRC, Tai Po Road – Tai Wai Section, MTR East Rail, Pineridge, Tin Liu, Tung Lo Wan Villa, On Ting Terrance, Tung Lo Wan Village, The Church of Jesus Christ of Latter-Day Saints, Villa Le Parc and Villa Viva. Then the slip road tunnel daylights near Mei Lam Estate, changes to bridge structure and runs almost in parallel with SMTR until it reaches sufficient level for merging with SMTR(WB) near Mei Chung Court.

2.2.5.4         Another slip road tunnel serves for the traffic of T4(WB) heading to TSH, it climbs up quickly to achieve sufficient level for daylighting at the Riverpark and changes into bridge structure before crossing SMRC. The bridge runs in front of the HKHM and connects with the existing bridge deck of TSH(SB) at the reserved connection point. The layout of the T4 Option 3 is shown in Figure 2.1.4 and the followings are the key characteristics of T4 Option 3:

·         Mainly in form of underground tunnel along its alignment (eastbound and westbound tunnels are around 1800m and 1600m long respectively) with only limited bridge structures for connections between T4 tunnel portals and the reserved connections at existing bridges / at-grade roads;

·         Owing to various site constraints and spatial limitation, design speed of 70 km/h which is a less desirable standard for trunk road, can only be adopted for the design of vertical and horizontal alignments of this tunnel option;

·         Several tunnel buildings including administration building, ventilation buildings /shafts and evacuation staircases/adits are required for the operation of the T4 tunnels;

·         Proposed tunnels go beneath a lot of private developments and villages – encroach upon underground stratum of private lands;

·         With additional road connection between the T4(EB) and STR – provide convenience to road users heading to Ma On Shan area; and

·         More resources required for operation and maintenance of the T4 owning to the maintenance for necessary tunnel signaling and lighting system, tunnel ventilation system, and tunnel evacuation adits etc.

2.2.6            Environmental Considerations for Each Alignment Options

2.2.6.1         The environmental considerations for the alignment options have been compared and presented in Table 2.1 below:

Table 2.1    Summary of Environmental Considerations of Alignment Options

Alignment Options

Environmental Considerations

Environmental Benefits

Environmental Disbenefits

Base Scheme

Noise and Air Quality

·         Mainly viaduct construction using precast bridge segment and erection by launching gantry method. Less construction noise impacts and dust emission as large portion of works to be carried out off site in precasting yards and the construction duration is the shortest among other options

·         Adoption of quiet piling method to minimise the construction noise impact

 

Landscape and Visual

·         Sha Tin Park has been avoided.

·         The bridge structures situated away from the HKHM, hence the visual impact to the recreational users in the museum which is a visual sensitive receiver (VSR) is reduced. 

 

Cultural Heritage

·         Less underground excavation works near historic buildings, e.g. Tsang Tai Uk Village and less vibration / settlement effect is envisaged

 

Waste

·         Less excavated C&D materials will be generated comparing other options with certain amount of tunnel construction

 

 

Noise and Air Quality

·         Higher air quality and noise impacts to the residents at Tung Lo Wan Village, residential buildings in Sha Tin Central and STTV close to the elevated carriageways during operation stage; substantial noise barriers/enclosures may be required to reduce road traffic noise levels

 

Landscape and Visual

·         Viaducts conflicting with the existing OVTs along Chung Ling Road

·         3 layers of bridge structure with noise barriers in different levels create wall effect and cause intrusive/adverse visual impacts to the VSRs in Sha Tin Central

·         Viaduct across Shing Mun River Channel and Sha Tin Tau Village is massive and induces significant and intrusive visual impacts on environment during operation

 

Ecological

·         Potential impact to the ardeid night roosting site at SMRC during construction and operation stages

 

T4 Option 1

Noise and Air Quality

·         Eastbound alignment shifted away from Tung Lo Wan Village and residential buildings of Sha Tin Central and placed in front of Tai Wai industrial buildings, less noise and quality impacts to the residents of the buildings close to the bridges during operation stage

·         Depressed road / underpass sections at the south of SMRC reduces the air quality and noise impacts to the residents of STTV and TTUV during operation stage

·         Adoption of quiet piling method to minimise the construction noise impact

 

Landscape and Visual

·         Avoid conflicting with existing OVTs along Chung Ling Road

·         Eastbound alignment shifted away from Tung Lo Wan Village and residential buildings in Sha Tin Central with less visual impact

·         Depressed road/underpass section at the south of SMRC would have insignificant visual impact during operation stage, particularly for the residents of the Riverpark, STTV, TTUV and Fung Shing Court

Noise and Air Quality

·         Some air quality and noise impacts to the residents of the Riverpark, STTV and TTUV during construction of the depressed road/underpass section by open excavation

·         Some noise and quality impacts to the residents of the buildings close to elevated carriageway; noise barrier is required to reduce noise levels during operation stage

 

Waste

·         More excavated materials generated from construction of depressed road / underpass sections at south of SMRC

 

Landscape and Visual

·         The bridge structures situated close to the HKHM, hence the visual impact to the recreational users of HKHM which are visual sensitive receivers, is higher than other options during operation stage

 

Cultural Heritage

·         Underpass close to historic building namely TTUV which is sensitive to construction vibration, settlement and titling

 

Ecological

·         Potential impact to the ardeid night roosting site at SMRC during construction and operation stages

 

T4 Option 2

Noise and Air Quality

·         Eastbound alignment shifted away from Tung Lo Wan Village and residential buildings of Sha Tin Central and placed in front of Tai Wai industrial buildings, less noise and quality impacts to the residents of the buildings close to the bridges during operation stage

·         Depressed road / underpass sections at the south of SMRC reduces the air quality and noise impacts to the residents of STTV and TTUV during operation stage

·         Adoption of quiet piling method to minimise the construction noise impact

 

Landscape and Visual

·         Avoid conflicting with existing OVTs along Chung Ling Road

·         Eastbound alignment shifted away from Tung Lo Wan Village and residential buildings in Sha Tin Central with less visual impact

·         Depressed road/underpass section at the south of SMRC would have insignificant visual impact during operation stage, particularly for the residents of the Riverpark, STTV, TTUV and Fung Shing Court

Noise and Air Quality

·         Some air quality and noise impacts to the residents at residential buildings of Scenery Court, Hilton Plaza and New Town Plaza Phase 3 in Sha Tin Central during construction

·         Higher noise and quality impacts to the residents of the buildings close to elevated carriageway; noise barrier is required to reduce noise levels

 

Landscape and Visual

·         Adverse impacts to trees of Sha Tin Park and Hong Kong Bible Research and Education Centre (HKBREC) during construction and operation stages

·         3 layers of bridge structure with noise barriers in different levels create wall effect and cause intrusive/adverse visual impacts to the VSRs in Sha Tin Central during operation stage

 

Cultural Heritage

·         Depressed road closer to historic building namely Ng Yuen and TTUV which are sensitive to construction vibration, settlement and titling

 

Waste

·         More excavated materials generated from construction of depressed road / underpass sections at south of SMRC

 

Ecological

·         Potential impact to the ardeid night roosting site at Shing Mun River Channel during construction and operation

 

T4 Option 3

Noise and Air Quality

·         Tunnel option would reduce air quality and noise impact during operational stage, especially for the residential buildings along the routing of the T4 (except those from ventilation buildings/shafts)

·         Adoption of quiet piling method to minimise the construction noise impact

 

Landscape and Visual

·         Existing landscape and streetscape could be retained as most of the carriageways are below ground such that the landscape and visual impacts are negligible during operation stage

 

Ecological

·         Impact to the ardeid night roosting site at SMRC during construction and operation is negligible as no elevated structure will be erected across SMRC

Noise and Air Quality

·         Nuisance of noise and exhaust emission from tunnel ventilation buildings / shaft during operation stage may affect the nearby residents close to these tunnel buildings

·         Due to lack of access for the construction of ventilation buildings and mucking out of tunnel excavation at the north of MTR East Rail, haul road construction would induce significant dust emission and noise impact to the environment and the residents close to the haul road

 

Landscape and Visual

·         Haul road construction, tunnel portal excavation and access roads for ventilation buildings at the north of MTR East Rail would impose significant landscape impact to existing trees on natural terrain during construction and operation stages.

·         Some transient visual impact to nearby VSRs during the construction of tunnel portals, haul roads, potential temporary conveyor belt system, etc.

·         Some visual impacts to the residents of Lai Chi Yuen, Villa Maria and Pineridge due to the provision of ventilation buildings during operation stage

 

Waste

·         Substantial excavation materials and waste to be generated due to extensive tunnel excavation and haul road construction

 

Ecological

·         Haul road construction, tunnel portal excavation and access roads for ventilation buildings at the north of MTR East Rail would impose significant impact to existing trees on natural terrain causing consequential ecological impact during construction and operation stages.

 

2.3                Selection of Preferred Alignment

2.3.1            Throughout the evaluation process of the 4 alignment options for the Project, all environmental considerations including air quality, noise, landscape and visual, cultural heritage, waste and ecological during construction and operation stages have been thoroughly reviewed and evaluated.  Apart from the environmental considerations, other engineering aspects such as traffic, land requirement, engineering feasibility as well as public perception, construction time and cost, and maintenance requirements have also been taken into consideration. The following are the main reasons for selecting the preferred option:

2.3.1.1         The Base Scheme is the most straight forward solution for the T4 comparing with the other three options. Since the road geometry is designed using the most desirable standard and parameters, it should be the most preferable option from highway and traffic point of view. Furthermore, the construction and recurrent costs of the Base Scheme would be the lowest among all proposed options in view of its simplicity of design and construction.  However, the proposed viaduct for the eastbound traffic will be in direct conflict with the OVTs along Chung Ling Road.  Moreover, the proposed viaducts run across the town centre of Sha Tin area and SMRC which is considered too high and too close to the existing residential buildings.  It is considered this road scheme for the T4 would not appeal to the public, in particular, the local stakeholders of Sha Tin Central since it does not harmonize with surrounding environment and induces significant visual impacts to the environment.

2.3.1.2         The road scheme of T4 Option 1 is developed based on the public concerns and requirements received during the objection period of the last gazettal of road scheme in 2006 and the public consultations conducted under this Project.  The T4 eastbound carriageway is shifted away from Tung Lo Wan Village and placed at the southern side of TSH in front of the industrial buildings in Tai Wai such that no direct impact to the existing OVTs along Chung Ling Road is resulted and the OVTs can be preserved.  Also, as the future carriageway is further away from Tung Lo Wan Village and other residential buildings in the vicinity, the environmental impacts to the relevant NSRs and ASRs generated from the Project would be reduced.

2.3.1.3         Furthermore, the proposed 3-layers viaducts of T4(EB) and T4(WB) sandwiched between the HKHM and Scenery Court will be located further away from Scenery Court due to the realignment of the T4(EB) under T4 Option 1 albeit they are close to the building façade of the HKHM.  Although there are impacts to the HKHM and the recreational users of the museum during the construction and operation stages of the Project, the impacts are not insurmountable.  However, the environmental impacts to the nearby residents of the residential buildings under T4 Option 1 would be alleviated.  The vertical alignment of the T4 descends at maximum allowable gradient when crossing SMRC such that the height of the bridge structures would be reduced as much as possible.  The substantial reduction in height of the T4 bridge structures across SMRC would significantly reduce the visual impact to the environment and the nearby VSRs.

2.3.1.4         Although the alignment of the T4 after crossing SMRC will be close to and fronting the Riverpark, the T4 will descend quickly and change from elevated carriageway/bridge structure into depressed road and then to underpass before crossing the junction of TCKR/LRTR. Appropriate noise mitigation measures, e.g. noise semi-enclosure will be provided for the depressed road section fronting the Riverpark.  The maximum height of the depressed road together with the proposed noise mitigation measures in front of the Riverpark would be lower than podium of the Riverpark.  It is worth to mention that this section of the T4 under Option 1 between the southern riverbank of SMRC and Che Kung Miu Road (CKMR) will be constructed on existing government lands, neither encroachment nor resumption of private lands is required.      

2.3.1.5         The section of the T4 between CKMR and STR will be in form of underpass with openings to the rooftop at STTV under T4 option 1.  No viaduct structure will be built in front of STTV and TTUV and hence the visual impact is negligible while the noise and air quality impacts to the residents of the nearby villages due to the Project are reduced.  Nevertheless, encroachment and permanent resumption of some private lands are required under T4 Option 1 but the amount of private land (mainly existing farmland) affected is small.    

2.3.1.6         The proposed road alignment of T4 Option 2 is the same as that of T4 Option 1 except the section between Tai Po Road – Tai Wai and STR.  Under T4 Option 2, the proposed 3-layers viaducts of T4(EB) and T4(WB) sandwiched between the HKHM and Scenery Court is the closest to the residential buildings of Scenery Court comparing with the Base Scheme and T4 Option 1 and will encroach into the boundary of Sha Tin Park. Similar to T4 Option 1, the T4 Option 2 descends quickly after crossing LRTR and changes from elevated carriageway/bridge structure to depressed road/underpass after reaching the southern riverbank of SMRC.  However, the depressed road section under this Option is situated and falls within the boundaries of Hong Kong Bible Research and Education Centre (HKBREC) and Tsang Tai Uk Recreation Ground (TTURG).  Some of the existing building structures of HKBREC and existing recreation facilities of TTURG will be affected and need to be demolished to make way for the construction of the Project.  The T4 Option 2 not only affects the existing landscape feature, vegetation and recreation facilities of Sha Tin Park and TTURG, but also causes nuisance and environmental impacts to residents and local stakeholders. In addition, permanent land resumption and demolition of existing buildings of HKBREC are required. 

2.3.1.7         T4 Option 3 comprises mainly underground tunnel running beneath many villages and private developments including Tung Lo Wan Village, Pineridge, Tin Liu, Tung Lo Wan Villa, On Ting Terrance, The Church of Jesus Christ of Latter-Day Saints, Villa Le Parc, Villa Viva, HKBREC, STTV and TTUV.   Substantial amount of private lands will be permanently resumed and/or easement of ground stratum of these private lands will be required.  Tunnel construction underneath these affected lands and developments may affect the stability of the existing building structures and facilities, e.g. movement, settlement, tilting of structures during construction stage.  In addition, the construction of ventilation buildings/shafts and delivery of excavation materials from tunnel mucking out would require construction haul road to be built in the vicinity of residential area, which will induce environmental impacts including noise, air quality (dust emission), ecology and landscape (tree felling). It is envisaged the construction time for the tunnel construction would be much longer than other options in view of the complexity of the tunnel excavation works. The operation of tunnel ventilation buildings/shafts would also create noise and air pollution nuisance to the nearby residents of residential areas during operation stage.    

2.3.1.8         Having thoroughly considered the abovementioned factors and striking the balance between the merits and demerits of each alignment option, T4 Option 1 is concluded to be the most preferred option for the Project to achieve the function of the T4 for alleviating traffic congestion in Sha Tin District without compromising the environmental impacts to nearby residents and relevant stakeholders.

2.3.1.9         The scope of works under the preferred option for the T4, i.e. T4 Option 1 mainly comprises:

(i)      Construction of dual two-lane elevated carriageways of approximately 1.4km long connecting Shing Mun Tunnel Road and Tsing Sha Highway to the proposed at-grade carriageways fronting the Riverpark;

(ii)     Construction of dual two-lane at-grade carriageways and underpasses of approximately 600m long between the Riverpark and Tsang Tai Uk;

(iii)    Construction of a slip road of approximately 80m long near the Riverpark connecting at-grade carriageway northbound and Lion Rock Tunnel Road northbound across Shing Mun River Channel;

(iv)   Construction of a slip road of approximately 300m long near Tsang Tai Uk connecting Lion Rock Tunnel Road southbound and Sha Tin Road eastbound;

(v)    Widening of a section of Sha Tin Road of approximately 150m long from a dual two-lane carriageway to a dual four-lane carriageway;

(vi)   Modification of a section of the elevated carriageway of Shing Mun Tunnel Road eastbound near Chung Ling Lane of approximately 200m long to provide extra space for improved merging of traffic;

(vii)   Modification and realignment of a section of Tung Lo Wan Hill Road, Chung Ling Road, Chung Ling Lane, Tai Po Road (Tai Wai Section), Shing Chuen Road, Shing Wan Road, Man Lam Road and Man Lai Road;

(viii)  Construction of an at-grade and an elevated footpath of approximately 50m long across the proposed underpass near Sha Tin Tau Village;

(ix)   Construction of an elevated cycle track and an elevated footpath of approximately 100m long across Shing Mun River Channel;

(x)    Demolition of the existing subways across Lion Rock Tunnel Road fronting the Riverpark and construction of an elevated cycle track and an elevated footpath with lifts and staircases across Lion Rock Tunnel Road fronting the Riverpark;

(xi)   Demolition of the existing pedestrian subway across Che Kung Miu Road and Lion Rock Tunnel near MTR Che Kung Temple Station and construction of an elevated footpath with lifts and staircases across Che Kung Miu Road;

(xii)   Ancillary works including geotechnical, drainage, sewerage, water, utilities, lighting, landscaping, electrical and mechanical works, construction/reconstruction of noise barriers/enclosures, retaining walls, slope improvement; and installation of street furniture and traffic aids; and

(xiii)  Modification of Existing Noise Barrier/Enclosure at Tsing Sha Highway (Trunk Road T3).

2.3.1.10      The general layout of the preferred option i.e. T4 Option 1 is shown in Figure 2.3.1, Figure 2.3.2, Figure 2.3.3 and Figure 2.3.4.  Detailed environmental impact assessments of the preferred alignment Option 1 are presented in Sections 3 to 10.

 

2.4                Key Design Elements

2.4.1            Road Section at North of Shing Mun River Channel

2.4.1.1         The road section of the T4 at north of SMRC will be mainly in form of bridge structure.  This is because the T4 connects to the existing TSH and SMTR which are all elevated carriageways in nature.  Such connection will utilize the reserved connections at the bridge decks of TSH and SMTR.

2.4.1.2         The eastbound carriageway of the T4 will be situated at the south of TSH fronting the industrial buildings of Tai Wai area.  This arrangement can avoid the proposed bridge structure in direct conflict with existing OVTs along Chung Ling Road and minimize the environmental impacts including noise, air quality and visual impacts during construction and operation stages.

2.4.1.3         By shifting the eastbound carriageway to the south of TSH, the bridge structures will be further away from the residential buildings of Sha Tin Central, i.e. Scenery Court, Hilton Plaza and New Town Plaza Phase 3 although they will be close to the building structure of the HKHM and partially block the view of its building façade.

2.4.1.4         In order to avoid having high viaducts across SMRC and acquire sufficient cover depth to the underpass structures underneath the junction of TCKR/LRTR, the T4 descends at a maximum allowable gradient of 8% to lower the height of bridge structure above SMRC and  make sure the T4 can pass through the junction of TCKR/LRTR satisfactorily.

2.4.1.5         For the compliance of noise level requirements to the nearby NSRs of residential buildings in Sha Tin Central including Scenery Court, Hilton Plaza, New Town Plaza Phase 3 and the Riverpark, extensive noise barrier/enclosure on the bridge structures of the T4 fronting the HKHM would be anticipated. Nevertheless, the assessment findings revealed that operation traffic noise from existing at-grade roads, e.g. LRTR is the main source of nuisance, and in order to effectively reduce the overall traffic noise, it is recommended to apply low noise road surfacing (LNRS) to the carriageways of the existing at-grade roads so that extensive noise barrier/enclosures on the bridge structure would not be required.  As a result, with the application of the LNRS on existing roads and new roads of T4, the overall noise levels contributing from the new roads of the T4 and existing roads at the nearby NSRs of Sha Tin Central will comply with the noise criteria.  No noise barrier/ enclosure will be required to be installed on the bridge structures of the T4 fronting the HKHM as noise mitigation measures.  This will help to reduce the visual impact to the visual sensitive receivers of the HKHM and nearby residents.

 

2.4.2            Road Section across Shing Mun River Channel

2.4.2.1         This section of the T4 across SMRC will still be in form of bridge structure with the carriageway levels changing approximately from +15mPD to +6mPD at northern riverbank and southern riverbank respectively. No noise barrier/enclosure is proposed to be erected on the northern portion of the T4 bridge deck across SMRC within the flight path of ardeids to avoid bird collision.

2.4.2.2         The bridge deck structures across SMRC will be supported by intermediate piers located at SMRC, the pile caps should be constructed below the riverbed in order to minimize obstruction to the water flow along the river.  Furthermore, streamline shape, e.g. circular or oval shape, bridge piers aligned with the existing piers of Lion Bridge will be adopted in the design to further reduce blocking of water flow of SMRC.

2.4.2.3         For construction of bridge structures across SMRC, concrete block cofferdam will be temporarily installed at the riverbed of SMRC for facilitating the erection of temporary steel platform which provides a working platform for establishing the construction plants/machines to be used for the installation of bridge foundation and piers during dry season.  Concrete block cofferdam will be removed before the coming wet season to allow river flow underneath the temporary steel platform avoiding potential overflow onto the riverbanks of SMRC during wet season.  Watertight steel casing will be used in the design of piling works so that piling excavation can be confined within the steel casing to prevent dispersion of river sediment and its associated odour problem. The watertight steel casing will be lifted up gradually from the riverbed during the concreting process of pile foundations, which will be completely removed once the concrete piles have been hardened for casting the pile cap on top in subsequent construction stage. The temporary steel platform will be demolished, and riverbed will be reinstated during dry season upon completion of pier construction and bridge deck.  The envisaged set up of temporary steel platform is illustrated in Figure 2.4.1 and Figure 2.4.2.

2.4.3            Road Section at South of Shing Mun River Channel

2.4.3.1         Depressed road / underpass design is proposed for this section of the T4.  After reaching the southern riverbank of SMRC, the T4 starts to descend and become a depressed road.  It then changes to two underpasses each for the eastbound and westbound traffic with the northern portal located in front of the Riverpark before going underneath and across the junction of TCKR/LRTR.  The underpasses continue to travel southward beneath the existing farmland of STTV.  The underpasses cross over each other at and beneath LRTR near TTUV, then ascend and connecting the at-grade road at Sha Tin Road.

2.4.3.2         In order to avoid having ventilation buildings/shafts for the underpasses, large size openings will be provided on the rooftop of the two underpasses at STTV such that natural ventilation can be adopted for the underpasses as far as possible to reduce air quality, noise, and visual impact and the amount of electricity consumed for mechanical ventilation. 

2.4.4            Road Section along Sha Tin Road

2.4.4.1         Given the existing man-made Feature 7SE-C/C220 and 7SE-CCR228 along Sha Tin Road are tall and steep slopes, potential landslide hazard, including disperse and rebounce of debris of natural terrain, may occur and cause significant risk to the operation and road users of the T4 and STR.  Such natural terrain hazards that requires mitigation falls within Lion Rock Country Park (LRCP) boundary as well as the boundary of an existing burial ground.  Soil nailing together with debris resisting barriers (e.g. flexible barrier) are primarily proposed as the mitigation measures for mitigating the natural terrain hazard.

2.4.4.2         As the works of the proposed soil nailing for the natural terrain will fall within the boundary of LRCP completely and would have significant environmental and ecological impacts to the habitats of the LRCP, it is recommended to replace the soil nailing works within LRCP by a rigid barrier to be erected at the edge of the widened STR (outside the boundary of LRCP)  together with the flexible barriers as the preventative measures of the potential landslide hazards. The approximate locations of the rigid barrier and flexible are shown in Figure 2.3.4. 

2.4.4.3         The location of the flexible barriers has been carefully studied in order to avoid encroaching within LRCP as far as practicable. In view of the downhill man-made slopes (Feature 7SE-C/C220 and 7SE-C/CR228) are tall and steep in gradient and heavily soil-nailed, as a result it is not feasible to propose the flexible barrier on these slope features outside LRCP otherwise addition loading would significantly affect the stability of these slopes and trigger large scale slope stabilization works within LRCP.  Besides, if the flexible barrier is installed at the toe of these man-made slopes outside LRCP, due to the height and steepness of these slopes, disperse and rebounce of debris of natural terrain from uphill will be a significant safety issue to road users of Sha Tin Road.  

2.4.4.4         Despite the erection of the flexible barriers is unavoidably to be placed at the fringe of LRCP considering public safety concern induced by the effect of disperse and rebounce of debris of natural terrain, the extent of the works of natural terrain mitigation measures would be substantially reduced.  The construction of flexible barrier mainly involves drilling works for anchors installation, footing construction for the supporting steel posts and erection of the flexible barrier which requires less permanent and temporary works area than soil nailing within LRCP.  The location and orientation of anchors and footings would be designed carefully to avoid unnecessary tree felling as far as practicable, and trimming of vegetation would be limited at the location of anchors and footings.  To further minimize the disturbance to the environment and ecology of LRCP, existing maintenance access of the slope features shall be used as the temporary access for the construction of flexible barrier, and the temporary storage area shall be located beyond the LRCP boundary.

2.5                Consideration of Different Construction Methods for Viaduct

2.5.1            The viaduct at north of SMRC can be erected by cast in-place concrete construction method, prefabricated steel structure construction method and precast concrete construction method.  Having considered the scale and site condition of the proposed viaduct, it is recommended to adopt precast concrete construction method which is a more effective and environmentally friendly approach. 

2.5.2            Comparison of the merits and demerits between these three construction methods is shown in Table 2.2 below.

Table 2.2    Comparison of Different Construction Methods for Viaduct

Construction Methods

Cast In-place Concrete

Prefabricated Steel Structure

Precast Concrete

Merits

·      Conventional construction method and require relatively less special skilled labour force and specialists when comparing with other construction methods.

·      Durable and less maintenance cost.

·      Carry out prefabrication works in fabrication yard away from the site.

·      Better control of quality and workmanship for works in fabrication yard.

·      Fabricate the whole bridge deck structure by steel plates / members which does not require formwork, thus less C&D waste/ materials will be generated.

·      Minimise concrete mixing truck travelling in site area, thus minimise potential air and noise impact to the surrounding environment.

·      More efficient construction works as the deck structure can be fabricated off-site concurrently with the substructure works (i.e. allow time overlap of construction activities).

·      Shorten construction time relatively, bridge deck construction can be non-linear (multiple work fronts), with minimising on-site potential environmental impacts and cumulative environmental impacts with concurrent projects.

·      Requires less temporary steel platforms, relatively, for construction of light weight steel structure, thus resulting in smaller area of temporary habitat loss.

·      Carry out precasting works in fabrication yard away from the site.

·      Better control of quality and workmanship for works in fabrication yard.

·      Use steel mould as formworks to maximise the reuse of formworks, thus less C&D waste/ materials will be generated.

·      Minimise concrete mixing truck travelling in site area, thus minimise potential air and noise impact to the surrounding environment.

·      More efficient construction works as the deck segments can be casted off-site concurrently with substructure works (i.e. allow time overlap of construction activities).

·      Shorten construction time, bridge deck construction can be non-linear (multiple work fronts), with minimising on-site potential environmental impacts and cumulative environmental impacts with concurrent projects.

·      Durable and less maintenance cost.

·      Relatively requires less temporary steel platform for construction of precast structure, thus resulting in smaller area of temporary habitat loss.

Demerits

·      Prepare concrete mix at a central concrete batching plant, where control of the materials should be monitored much carefully.

·      For transporting concrete to the site, proper mixing in truck, discharging from the truck and depositing in the forms, and handling for placement, finishing and curing are all subject to the level of responsibility and craft exercised by the workers involved.

·      Site conditions in terms of accessibility and weather can be highly critical to the work, requirement of extreme measures in some situations to control all stages in the production process. Possibility of site run-off might be higher under bad weather conditions.

·      Use of timber formwork,  thus more C&D waste/ materials will be generated.

·      Longer construction time – carry out bridge deck construction only (1) after substructure works is completed and (2) after completion of previous span for cast in-place span by span.

·      Require substantial temporary steel platform / falsework for construction of the bridge deck section over river channel i.e. SMRC.

·      Subject to high risk of steel corrosion.

·      High maintenance cost.

·      Less durable.

·      Require another trade of skilled workers and additional construction equipment for erecting steelwork structures.

·      Require another trade of skilled workers and additional construction equipment for erecting precast segments.

2.5.3            Based on the considerations above, precast concrete construction method is the preferred construction method and the bridge form would be prestressed segmental bridge structure as mentioned in Section 2.4.1.

2.5.4            The bridge deck section will be designed to allow for the use of precast concrete construction method.  The deck will be formed from precast concrete sections which will be manufactured at a casting yard offsite and stitched together at their final positions on-site.  This approach will minimise the quantities of C&D waste/materials to be generated on-site, and also minimise the extent and duration of construction activities required on-site and hence the potential environmental impacts on nearby sensitive receivers during construction.

2.6                Consideration of Different Construction Methods for Underpass

2.6.1            The underpass at south of SMRC can be constructed using various tunnelling method such as cut-and-cover construction method, drill-and-break/drill-and-blast method and tunnel boring machine (TBM) method.  In view of the complexity in the geometry of the T4 alignment, in particular, at LRTR where T4(EB) and T4(WB) crossover each other before connecting to STR as well as the uncertain ground condition and difficulties for construction to be carried out near an existing cultural heritage namely Tsang Tai Uk.  Cut-and-cover construction method is considered a more reliable and controllable approach and is recommended to be adopted as mentioned in Section 2.4.3. 

2.6.2            Comparison of the merits and demerits between these three construction methods is shown in Table 2.3 below.

 

 

Table 2.3  Comparison of Different Construction Methods for Underpass

Construction Methods

Cut-and-Cover

Drill-and-Break/

Drill-and-Blast

Tunnel Boring Machine (TBM)

Merits

·      Conventional construction method and require relatively less special skilled labour force and specialists when comparing with other construction methods considered.

·      Facilitate construction of complex tunnel/underpass geometry.

·      Better control complex geotechnical condition.

·      More flexible for dividing works areas within the site, thus allow flexibility for the contractor to co-ordinate with other concurrent projects in the vicinity for arrangement of respective construction programme to avoid cumulative environmental impacts.

·      Can be used for different tunnel shape.

·      Fast tunnel/underpass construction method.

·      Construction work mainly carried out at underground which can avoid working above ground in some busy urban area

·      Existing trees and vegetations could be retained as construction work will be mainly carried out at underground.

·      Less labour required for construction of tunnel.

·      TBM is usually non-stop working which can speed up construction programme.

·      TBM could deal with mixed ground conditions.

·      Construction work mainly carried out at underground which can avoid working above ground in some busy urban area

·      Less disturbance due to vibration to adjacent building structures.

Demerits

·      Vibration and settlement to adjacent building structures, ground treatment is required to control adverse effect due to excavation

·      Land required for temporary storage of excavated material to be reused on site.

·      Construction work would be affected by adverse weather conditions.

·      Removal of existing trees and vegetations for construction is required, though the affected areas will be reinstated and replanted.

·      Substantial vibration and settlement to adjacent building structures which is not suitable to work near building structures with shallow foundations and sites of cultural heritage.

·      High risk for storage and deliver explosives to work site in urban area.

·      Not suitable for construction work in soft ground.

·      Substantial noise impact during construction.

·      Complex analysis to estimate potential settlement at different geotechnical condition, ground treatment is required to control adverse effect due to excavation.

·      Require another trade of skilled workers and additional construction equipment for launching the TBM.

·      Land required for set up of launching shaft which would impose significant impact to existing trees on natural terrain causing consequential ecological impact.

·      Not suitable for tunnel with shallow ground cover.

·      Not cost effective for short tunnel.

 

2.7                Construction Programme

2.7.1            The construction works of the Project will tentatively commence in 2023 Q4 for completion by 2028 Q3.  A tentative construction programme for the Project is provided in Appendix 2.1.

2.7.2            In order to minimize the adverse impacts to the sensitive receivers during construction of the T4, the construction programme and sequence of works will be carefully planned such that the environmental impacts would be kept to minimum and within acceptable limits.  The followings are the measures recommended to be taken during construction:

·         No works to be carried out from 16:30 to 07:30 during dry season (Oct – Mar) and 17:00 to 07:00 during wet season (Apr – Sep) within 100m from the ardeid night roost site, and to avoid construction works between 18:00 to 08:00 and on Sunday and Public Holidays within country park area;

·         Construction works within the water body of SMRC should be conducted in dry season as far as possible;

·         Avoid noisy construction activities during school examination period and schedule the construction works in the vicinity of schools and kindergartens during summer recess as much as possible if programme allows; and

·         Close liaison with the contractors of other concurrent projects in order to avoid overlapping of construction activities and allow sufficient buffer for works at project interface due to potential delays in the programme so that the cumulative effects of environmental impacts could be minimized.

2.8                Public Consultation

2.8.1            The project profile was submitted to the Environmental Protection Department (EPD) on 21 March 2019 and was exhibited for public inspection between 22 March 2019 to 4 April 2019.  The received comments mainly focused on the ecological impacts and expressed the concerns on the impact of the construction works to the ardeids night roost and the chance of bird collision by the proposed noise barriers and enclosures. This EIA study has addressed the potential impacts to the ardeids night roost and the chance of bird collisions in Section 8.

2.8.2            Several briefing sessions on the latest development of the Project were carried out for members of the STDC in 2019 and 2020.  The Project was also presented in the T&TC Meetings of STDC held on 21 February 2019 and 18 February 2021. In addition, public consultations were also carried out for the residents  of nearby estates and villages in Sha Tin Central who will be affected by the Project, green and concern groups, and cyclist groups between March and June 2021 to obtain the views and concerns from the public and stakeholders.  During the briefing sessions and public consultations, district council members and the public raised the following concerns / issues about the implementation of the Project and the follow-up actions to be taken are summarized in Table 2.4.

 

Table 2.4    Summary of Concerns Raised by STDC T&TC Members and the Public and Follow Up Actions

Concerns / Issues

Follow up Actions to be Taken

·          Concerns on the existing ardeids on the banks of Shing Mun River and Hong Kong Heritage Museum (HKHM).

·          Ecological impact assessment has been conducted in the EIA study under which flight paths and heights of the egrets and herons on the banks of Shing Mun River Channel and on the roof top of the HKHM have been taken into consideration in determining how the impacts can be minimized, i.e. the extent of the proposed noise mitigation measures.

(Please refer to Section 8 for details)

·          Tree removal, bird collision, disturbance and impact on ardeids during construction stage.

·          The glare from construction and operation of the Project should be cut down taking into account the presence of night roosting ardeids near HKHM.

·          Construction works is not allowed to be carried out from 16:30 to 07:30 during dry season (Oct – Mar) and 17:00 to 07:00 during wet season (Apr – Sep) within 100 m from the ardeid night roost site.

·          Dark patterns or strips will be embedded in the noise panels with the use of tinted materials to minimize chance of bird collision.

(Please refer to Section 8 for details)

·          Concerns on blockage of view/vista of the HKHM by the proposed viaducts and noise barriers/enclosure.

·          Noise mitigation measures on viaducts cause visual impact near Scenery Court.

·          Low noise road surfacing (LNRS) will be applied on appropriate section of existing at-grade road to reduce existing road traffic noise (under other/separate project) before the commissioning of the T4. Also, LNRS will be laid on appropriate sections of the new T4 carriageways for reducing the future operating traffic noise. The cumulative noise impact contributed from existing road and the T4 on the nearby NSRs is hence reduced to acceptable level.

·          With the application of the LNRS, the extent of proposed noise mitigation measures for the T4, in particular, the viaducts in front of HKHM which is an identified visual sensitive receiver (VSR) could be reduced and hence alleviate the visual impact caused by the noise mitigation measures.

·          (Please refer to Section 4 for details)

·          Provide full noise enclosure with suitable greening measures in front of the Riverpark.

·          According to the result of noise impact assessment, the predicted noise levels at the nearby NSRs will comply with the road traffic noise criteria with suitable mitigation measures (i.e. semi-enclosure) in place. Details of greening provision for the noise mitigation measures will be designed and agreed with relevant maintenance authorities at the design stage.

·          Provide full noise enclosure or extend the existing noise barriers along Sha Tin Road (Eastbound) near Pok Hong Estate.

·          According to the result of noise impact assessment, the predicted noise levels at the nearby NSRs will comply with the road traffic noise criteria with suitable noise mitigation measures (i.e. full enclosure) along Sha Tin Road in front of Pok Hong Estate in place.

(Please refer to Section 4 for details) 

·          Provide noise barriers/enclosure along Lion Rock Tunnel Road near Fung Shing Court.

·          According to the result of noise impact assessment, the predicted noise levels at the nearby NSRs along Lion Rock Tunnel Road, e.g. Fung Shing Court after mitigation, will comply with the traffic noise criteria.

(Please refer to Section 4 for details)

·          Provide information to compare the height of viaducts and clearance from nearby residential buildings for gazettal of road scheme and Revised Trunk Road T4.

·          The required project information has been provided to the relevant residents’ representatives.  Updated information of the Project will also be provided in future subject to further changes at design stage.

·          Concerns on new pedestrian footbridge adjacent to the Riverpark would cause privacy problem.

·          The Project Proponent will liaise with the maintenance authorities to investigate the feasibility of providing measures on the footbridge to reconcile the privacy issue in design stage.

·          Concerns on noise and air pollution from construction and road traffic affecting the pupils of nearby Zenith Kindergarten during the construction and operation stages.

·          The noise and air quality impact assessments during both construction and operation stages conducted for the Zenith Kindergarten in Sections 3 and 4 have complied with the requirements set out in the EIAO-TM.  Suitable mitigation measures will be implemented during construction and operation stages as recommended in the EIA.

(Please refer to Section 3 and Section 4 for details)